SUBJECT: Update on the Piedmont Community Pool Project
RECOMMENDATION
This is an informational item, no action is required.
BACKGROUND
Since the last update on the progress of the Piedmont Community Pool project in April, significant progress has been made.
In the past quarter, the following tasks have
been completed:
• Continued excavation and soils removal
• Shoring at perimeter walls
• Installation and testing of tie-backs
• Removal of underground tank
discovered at site & soils testing
• Commencement of site grading
• Commencement of trenching for
underground utilities
• Layout and digging for grade beams
In the upcoming quarter, the following tasks
are anticipated to be underway:
• Completion of excavation & soils
removal
• Shoring at perimeter walls
• Site grading
• Installation of waterproofing at pit and
retaining walls
• Concrete pour at keyways and footings,
including pit
• Rebar installation for retaining walls
• Continued digging for footings
As of June 30, 2023, 102 out of 495 contract activities have been completed and an additional 45 are in progress, with the project estimated at 28% complete. As of the same date, the contractor has used 120 out of 342 construction days allocated to the project, with a forecasted final completion of late September 2024.
With regard to budget, approximately 12% of the contingency has been used as part of approved change order requests to address various unforeseen conditions, as well as clarification of design issues. The project continues to be within budget.
By: Daniel Gonzales, Director of Public Works