City of Piedmont
COUNCIL AGENDA REPORT
DATE: March 18, 2024
TO: Mayor and Council
FROM: Rosanna Bayon Moore, City Administrator
SUBJECT: Update on the Piedmont Community Pool Project
RECOMMENDATION
This is an informational item, no action is required.
CONSTRUCTION PROGRESS
Since the last update on the progress of the Piedmont Community Pool project in December 2023, significant progress has been made.
In the past quarter, the following tasks have
been completed:
• Pool building footings and grade
beams
• Structural steel installation
• Structural steel welding
• Installation of transformer vault and
utility trench on Magnolia Avenue
• Continued off-hauling of soil
• Commencement of CMU wall
installation within the pool building
• Approval of removal of
contaminated soil from the second
underground tank
In the upcoming quarter, the following tasks
are anticipated to be underway:
• Continued grading for pool and deck
• Completion of additional retaining
walls
• Complete installation of building
deck
• Complete installation of CMU walls
within the pool building
• Complete utility trench on Magnolia
Avenue
CONSTRUCTION SCHEDULE
As of February 29, 2024, the project is estimated at 58% complete. As of the same date, the contractor has used 283 out of a revised 490 construction days allocated to the project.
Approximately 52% of the remaining project activities are critical path activities, which indicates that the project remains susceptible to additional delays. The project team continues to work and resolve various items that are impacting the schedule and minimize the overall impact to the project completion date currently estimated as Winter 2024.
BUDGET
With regard to budget, approximately 64% of the contingency has been used as part of approved change order requests to address various unforeseen conditions, as well as clarification of design issues. The project continues to be within the revised budget.
By: Daniel Gonzales, Director of Public Works