City of Piedmont
COUNCIL AGENDA REPORT
DATE: May 20, 2024
TO: Mayor and Council
FROM: Rosanna Bayon Moore, City Administrator
SUBJECT: Consideration of a Resolution Designating Projects for Senate Bill 1 (SB1) Road Maintenance Project for Fiscal Year 2024-25 and Authorization for the Finance Director to Modify the Budget to Reflect Anticipated SB-1 Revenues (Recommended CEQA Action: Exempt under CEQA Guideline Section15301)
RECOMMENDATION
By a single motion, take the following actions:
1. Adopt the attached resolution designating projects for fiscal year 2024-25 funded by Senate Bill 1: the Road Repair and Accountability Act of 2017; and
2. Authorize the Finance Director to make the changes to the budget reflecting the anticipated revenues from SB-1 as mentioned herein and the expenditures for improvements to the 2024-25 Paving Project as mentioned herein.
BACKGROUND
In accordance with State regulations for California Senate Bill 1 (SB-1) funding, cities must adopt specific budget amendments to account for this specific project. Accordingly, staff is recommending that the Council adopt a specific budget amendment to incorporate the SB-1 funding for FY2024-25.
SB-1, enacted in 2017, provides new revenues for road maintenance projects within the City.
According to the State’s projections, for Fiscal Year 2024-25, the City is projected to receive $288,144 in SB-1 revenues. Regulations contained within SB-1 require that projects funded with SB-1 monies be specifically identified, budgeted for and approved by the City Council. Once approved, paperwork is submitted to the State for approval.
The City’s Pavement Management Program (PMP) has produced a list of proposed roadways for varying degrees of improvement in the upcoming five years as shown in the referenced table below. Five years’ worth of roadways are listed, providing flexibility to maximize the address of roadways for each year’s paving project based on available resources and the bidding environment and allow for coordination with utility providers.
Annual projects also incorporate “Complete Streets” components such as sidewalks, pedestrian ramps and/or bicycle lanes as needed. Complete Streets components typically add up to 25% more to the overall project costs for pavement treatment.
Agenda Report Page 2
Agenda Report Page 3
Bid documents for the 2024-25 Pavement Restoration Project are scheduled for release in Spring 2025. It is anticipated that construction will take place in late spring and summer 2025, spanning two fiscal years.
CALIFORNIA ENVIRONMENTAL QUALITY ACT
Designating the SB 1 project list is exempt under CEQA Guideline Section 15301 (existing facilities) as this action concerns the maintenance and repair of existing streets and roads, “involving negligible or no expansion of existing or former use.”
FISCAL IMPACT
It is anticipated that the overall construction costs including design, construction, construction management and inspection will be approximately $1,600,000. At this time, the funding sources for the project are anticipated to use a combination of SB-1 and Measure BB funding.
By: Daniel Gonzales, Public Works Director
John Wanger, City Engineer
Agenda Report Page 4
Attachments:
A. Resolution
CITY OF PIEDMONT
RESOLUTION NO._______-24
A RESOLUTION DESIGNATING PROJECTS FOR FISCAL YEAR 2024-25 FUNDED BY SENATE BILL 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017 WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of the City of Piedmont are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and WHEREAS, the City will receive an estimated $288,144 in RMRA funding in Fiscal Year 2024- 25 from SB 1; and
WHEREAS, this is the 8th year in which the City is receiving SB 1 funding which will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and WHEREAS, the City has undergone a public process to ensure public input into the City’s community transportation priorities and project list; and WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate numerous roadways, and add active transportation infrastructure throughout the City this year and dozens of similar projects into the future; and
WHEREAS, the 2023 California Statewide Local Streets and Roads Needs Assessment found that City of Piedmont streets and roads are in “Lower Risk” condition and this revenue will help increase the overall quality of the road system and over the next decade will bring streets and roads into a “good” condition; and
Attachment A Agenda Report Page 5
WHEREAS, the SB 1 project list and overall investment in local streets and roads infrastructure with a focus on basic maintenance and safety, complete streets infrastructure, and cutting-edge technology, materials and practices will have significant positive co-benefits statewide; and WHEREAS, designating the SB 1 project list is exempt under CEQA Guideline Section 15301 as this action concerns the maintenance and repair of existing streets and roads, “involving negligible or no expansion of existing or former use.”
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City Council of the City of Piedmont, State of California, as follows:
1. The foregoing recitals are true and correct and incorporated by reference herein.
2. The designation of the project list in Section 3 is exempt under CEQA Guideline Section 15301 as this action concerns the maintenance and repair of existing streets and roads.
3. The Council designates the following list of newly proposed projects to be funded in-part or solely with Fiscal Year 2024-25 Road Maintenance and Rehabilitation Account revenues:
Attachment A Agenda Report Page 6
Attachment A Agenda Report Page 7