3. Approval of Acceptance of Improvements for the 2024-2025 Annual Sidewalk Repair Program

Piedmont City Council
September 15, 2025

Document
3. Approval of Acceptance of Improvements for the 2024-2025 Annual Sidewalk Repair Program
Meeting
September 15, 2025
Body
Piedmont City Council
Original file
752 KB
Text extracted from the city's file for reading and search. Open the original on piedmont.ca.gov. That file is the official record.

City of Piedmont

COUNCIL AGENDA REPORT
DATE: September 15, 2025
TO: Mayor and Council
FROM: Rosanna Bayon Moore, City Administrator
SUBJECT: Consideration of Acceptance of Improvements for the 2024-2025 Annual Sidewalk Repair Program

RECOMMENDATION
By a single motion, take the following actions regarding the 2024-2025 Annual Sidewalk Repair Program:

1. Accept the improvements as complete.

2. Authorize the release of the Performance and Labor and Material Bonds.

3. Retain the Maintenance Bond until September 15, 2026, and, if there are no warranty items found, authorize the Public Works Director to release the Maintenance Bond at that time.

4. Direct the Public Works Director to file the Notice of Completion for the project.

BACKGROUND
On April 7, 2025, the Council authorized award of the 2024-2025 Annual Sidewalk Repair Program to Villalobos & Associates, Inc. in the amount of $299,012.  The scope of work included the repair of 118 sidewalk locations, totaling approximately 1,800 linear feet of sidewalk replacement. All work associated with this project was recently determined to be complete.

DISCUSSION
Public Works staff have determined that the above-referenced work was completed in accordance with the construction documents and specifications. Staff is recommending that the City Council accept the improvements associated with this project, authorize the release of the Performance and Labor and Material Bonds, retain the Maintenance Bond for a period of one year and direct the filing of the Notice of Completion.  If no issues have been identified with the improvements one year from acceptance, the Maintenance Bond can be released without further action.

FISCAL IMPACT
The overall expenditures associated with this project are:

Original Budget Actual Expenditures Variance
Construction Contract $ 299,012.00 $ 299,012.00 $             0.00 Construction Contingency $   29,091.00 $    2,446.78 $ -26,644.22 Totals $ 328,913.00 $301,458.78 $ -26,644.22
Construction project funding source:

Funding Allocation
Facilities Maintenance Fund – Sidewalk Replacement (#111) $ 301,458.78

CITY ATTORNEY REVIEW
The City Attorney has reviewed the Staff Report.

By: Daniel Gonzales, Public Works Director