Next Steps in City Capital Planning
The City will complete condition assessment of all the City’s capital assets and identify the funding levels required to maintain these assets. The City will continue to integrate capital planning information into the Long-Term Financial Plan, so City decision makers are aware of the City’s capital needs when they consider allocation of the City’s limited financial resources and consider possibly pursuing additional sources of City revenue.

Project Funding
A variety of funding sources support projects listed in the CIP. The first year’s program in the CIP is adopted by the City Council as the Capital Budget, as a counterpart to the annual Operating Budget. The fiscal resources are appropriated only in the first year, the subsequent four years of the CIP are important for long term planning and subject to further review and modification.

The CIP is funded primarily with funds restricted for specific purposes. The next page descibes various funding sources and their restrictions. Some projects are entirely or partially funded by grants and reimbursements from state and federal government and other agencies.

Page 2 of 66 ends

Funding Sources
Fund # Fund Name
(restriction)
Description
100 General Fund
(unrestricted)
The General Fund is the main operating fund for the City.

It accounts for sources and uses of resources that
(primarily) are discretionary to the City Council in the provision of activities, programs and services deemed
necessary and desirable by the community.
106 Measure S 2014
(unrestricted)
Accounts for 2014 voter-approved half-cent Local Use Tax which levies 0.5% each on all merchandise. Although these are unrestricted General Fund revenues, the 2014 Use
Taxes have been allocated by the City Council to fund
Infrastructure Projects as their highest funding priority. 200
Gas Tax - RMRA
(roads and right-ofway)
Accounts for the Highway Users Tax (HUTA) State imposed excise taxes on gasoline and diesel fuel sales within the City limits. Gas Tax funds are restricted for use in the construction, improvement and maintenance of public
streets. The taxes are allocated to Pinole through the Road Maintenance and Rehabilitation Account (RMRA)
established by the Road Repair and Accountability Act of 2017.
214 Solid Waste
Accounts for special revenue received from Republic
Services from a surcharge assessed on customer rates for solid waste services. These funds are set aside for future solid waste capital and for a rate stabilization fund.
215 Measure J
(roads only)
Accounts for special sales tax revenues collected by Contra Costa Transportation Authority (CCTA) and reapportioned to cities for local street projects. This fund also accounts for return to source funds and grant funds.
276
Growth Impact Fees
(nexus identified
needs)
Accounts for development fees collected to mitigate the impact of new development. Provides funds for nexus
identified needs only.
325
City Street
Improvements
(roads only)
Accounts for funds set aside by the City of Pinole to fund street improvement projects. The Measure S 2014 funding plan allocates $250k annually to this fund.
327 Park Grants
(parks only)
Accounts for grants and reimbursements from the state and federal government and other agencies related to parks. 377
Arterial Street
Rehabilitation
(roads only)
Accounts for funds set aside by the City of Pinole to fund arterial street rehabilitation projects. The Measure S 2014 funding plan allocates $250k annually to this fund.
500 Sewer Enterprise
(sewer only)
Accounts for fees charged to residents and businesses for sewer utilities. Fees are used to operate the PinoleHercules Water Pollution Control Plant which services the Pinole and Hercules areas.

Page 3 of 66 ends

Grants
Certain projects are eligible to receive grant funds from state, federal, or other agencies. Road projects listed in the CIP receive grant funding from a variety of sources such as:
➢ California Department of Transportation (Caltrans)
o Highway Bridge Program (HBP) – funds to improve bridge structural safety. ▪ Project: RO1710
o Highway Safety Improvement Program (HSIP) – funds projects that significantly reduce fatalities and injuries on all public roads.
• Project: IN2104
➢ West Contra Costa Transportation Advisory Committee (WCCTAC) o Subregional Transportation Mitigation Program (STMP) – funds projects that provide congestion relief and mitigate traffic impacts on regional routes through capacity improvements on those routes, improved transit services for subregional and regional travel, and improved facilities that allow West County residents to more efficiently access regional routes and transit service. ▪ Projects: RO2105, RO1902, and RO1710
➢ Metropolitan Transportation Commission (MTC)
o One Bay Area Grant 2 (OBAG2) – policy framework for MTC’s distribution of federal State Transportation Program and Congestion Mitigation and Air Quality Improvement Program funds. The OBAG2 program provides funding for local street and road maintenance, streetscape enhancements, bicycle and pedestrian improvements, Safe Route to School projects, Priority Conservation Areas, and Transportation planning.
▪ Project: RO1714
o Transportation Developlment Act (TDA) Article 3 – funds construction and/or engineering of bicycle or pedestrian capital or quick build projects, maintenance of Class I or Class IV separated bikeways, bicycle and/or pedestrian safety education projects, development of a comprehensive bicycle or pedestrian facilities plans, and restriping Class II bicycle lanes and buffered bicycle lanes. • Project: RO1714
The receipt of certain grants and reimbursements typically follow the award of contracts; therefore, other City funding is programmed for front-end financing of the total estimated project costs.

Page 4 of 66 ends

Overview of Recommended Capital Budget
The FY 2022/23 – 2025/26 CIP contains 43 projects which includes 9 new projects. The CIP also contains information for 25 unfunded and unprogrammed projects. A funded project is one that has identified specific funding, including on-going existing resources to fully implement the project. A partially funded project has funding to accomplish various phases of the project but lacks sufficient funding to complete the project. An unfunded project is one that has been identified in the CIP as a need but no funding secured to implement the project. Should funding become available through grant or other sources, the unfunded list can be reviewed to determine if it is suitable to seek such funding.

CIP projects fall into the following categories: Facilities, Parks, Sanitary Sewer, Stormwater, Streets & Roads, and Infrastructure Assessments. The nomenclature for the project number is derived as follows:

Project numbers begin with the abbreviation of the project category, followed by the year the project was first
programmed, and then a unique sequence number. For
example, FA2001 refers to a facilities project which was first programmed in 2020 with a unique sequence number of 01.

Unfunded projects begin with UF and are followed by a unique sequence number.

In FY2022/23, there are 35 projects programmed for funding, which includes 7 new projects. Below is a summary of the various funding sources based on project category.

FY 2022/23 PROJECT CATEGORIES
FY 2022/23
TOTALS

BY FUND
Funding
Sources
Fund Facilities
FA
Parks
PA
Sanitary
Sewer
SS
Stormwater
SW
Streets &
Roads
RO
Infrastructure
Assessments
IA
General Fund 100 $170,000 $165,000 $335,000
Measure S
2014 106 $776,931 $112,440 $445,000 $149,328 $285,000 $1,768,699 Gas Tax 200 $100,000 $100,000
Solid Waste 214 $425,000 $425,000
Measure J 215 $350,000 $350,000
Growth Impact
Fees 276 $88,000 $88,000
City Street
Improvements 325 $1,666,983 $20,650 $1,687,633
Park Grants 327 $189,758 $189,758
Arterial Street
Rehabiliation 377 $758,624 $758,624
Sewer
Enterprise 500 $2,300,000 $10,382 $89,853 $2,400,235
FY 2022/23 TOTALS

BY PROJECT

CATEGORY
$776,931 $727,198 $2,300,000 $533,000 $3,205,317 $560,503 $8,102,849 Category Abbreviation
Facilities FA
Parks PA
Sewer SS
Stormwater SW
Streets &
Roads
RO
Infrastructure
Assessments
IA
Unfunded UF

Page 5 of 66 ends

CITY OF PINOLE
FY2022-23 THROUGH FY2026-27

FIVE-YEAR CAPITAL IMPROVEMENT PLAN

FUNDING SUMMARY
SOURCES BY FUND FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 5-Year Total 100 – General Fund $ 435,000 $ 310,000 $ 745,000
106 – Measure S 2014 $ 1,668,699 $ 1,528,860 $ 350,000 $ 100,000 $ 3,647,559 200 – Gas Tax $ 100,000 $ 381,082 $ 481,082
200 – Solid Waste $ 425,000 $ 425,000
215 – Measure J $ 350,000 $ 350,000
276 – Growth Impact Fees $ 88,000 $ 320,000 $ 200,000 $ 608,000 325 – City Street Improvements $ 1,687,633 $ 890,000 $ 727,321 $ 890,000 $ 4,194,954 327 – Park Grants $ 189,758 $ 189,758
377 – Arterial Streets Rehabilitation $ 758,624 $ 247,250 $ 1,005,874 500 – Sewer Enterprise Fund $ 2,400,235 $ 2,000,000 $ 906,597 $ 800,000 $ 3,800,000 $ 9,906,832 Sources Total $ 8,102,949 $ 5,296,110 $ 2,565,000 $ 1,790,000 $ 3,800,000 $ 21,554,059 Unfunded Total $ 16,293,235 $ 9,231,700 $ 8,439,200 $ 970,000 $ 34,934,135 Total Sources Required $ 8,102,949 $ 21,589,345 $ 11,796,700 $ 10,229,200 $ 4,770,000 $ 56,488,194

Page 6 of 66 ends

SOURCES BY FUND FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 5-Year Total 100 - General Fund $ 435,000 $ 310,000 $ 745,000
106 - Measure S 2014 $ 1,668,699 $ 1,528,860 $ 350,000 $ 100,000 $ 3,647,559 200 - Gas Tax $ 100,000 $ 381,082 $ 481,082
214 - Solid Waste $ 425,000 $ 425,000
215 - Measure J $ 350,000 $ 350,000
276 - Growth Impact Fees $ 88,000 $ 320,000 $ 200,000 $ 608,000 325 - City Street Improvements $ 1,687,633 $ 890,000 $ 727,321 $ 890,000 $ 4,194,954 327 - Park Grants $ 189,758 $ 189,758
377 - Arterial Streets Rehabilitation $ 758,624 $ 247,250 $ 1,005,874 500 - Sewer Enterprise Fund $ 2,400,235 $ 2,000,000 $ 906,597 $ 800,000 $ 3,800,000 $ 9,906,832 Sources Total $ 8,102,949 $ 5,296,110 $ 2,565,000 $ 1,790,000 $ 3,800,000 $ 21,554,059 Unfunded Total $ 16,293,235 $ 9,231,700 $ 8,439,200 $ 970,000 $ 34,934,135 Total Sources Required $ 8,102,949 $ 21,589,345 $ 11,796,700 $ 10,229,200 $ 4,770,000 $ 56,488,194 PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
FA2201 Public Safety Building Modernization $100,000 $100,000 $100,000 FA2202 Senior Center Modernization $60,000 $100,000 $100,000 106-343-47201 $60,000 Measure S 2014 FA2002 Electric Vehicle Charging Stations $50,000 106-343-47201 $50,000 Measure S 2014 FA1901 Senior Center Auxiliary Parking Lot
formerly known as Fowler House lot reuse $149,120 $588,860 106-343-47201 $149,120 Measure S 2014 FA1902 Energy Upgrades $120,811 106-343-47201 $120,811 Measure S 2014 FA1702 Citywide Roof repairs and replacement $272,000 $140,000 106-343-47201 $272,000 Measure S 2014 FA1703 City Hall Modernization
formerly known as Paint City Hall $125,000 $125,000 106-343-47201 $125,000 Measure S 2014 PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
106-343-47201 $47,440 Measure S 2014
327-345-47203 $189,758 Park Grants
PA2202 Skatepark Rehabilitation $150,000
PA2201 Pocket Park - Galbreth Ave. $65,000 106-343-47201 $65,000 Measure S 2014 PA2101 Installation of high-capacity trash bins $425,000 214-345-47203 $425,000 Solid Waste Fund PA1901 Pinole Valley Park Soccer Field Rehabilitation $200,000 PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
SS2203 Effulent Outfall $150,000 $3,000,000 500-641-47201 $150,000 Sewer Enterprise SS2202 Replacement of Diesel Tank $150,000 500-641-47201 $150,000 Sewer Enterprise SS2201 Sanitary Sewer Rehabilitation $1,500,000 $800,000 $800,000 $800,000 $800,000 500-642-47201 $1,500,000 Sewer Enterprise SS2101 Secondary Clarifier - Center Column Rehabilitation $350,000 500-641-47201 $350,000 Sewer Enterprise SS2102 Air Release Valve Replacements $50,000 500-641-47201 $50,000 Sewer Enterprise SS2002 Water Pollution Control Plant Lab Remodel $100,000 500-641-47201 $100,000 Sewer Enterprise SS1702 Sewer Pump Station Rehabilitation $1,200,000
PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
SW2001 Roble Road Drainage Improvements $30,000 $320,000 276-344-47206 $30,000 Growth Impact Fees SW2002 Adobe Road Repair and Drainage Improvements $30,000 $200,000 106-344-47206 $30,000 Measure S 2014 106-344-47206 $415,000 Measure S 2014
276-344-47206 $58,000 Growth Impact Fees
PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
RO2501 Residential Slurry Seal $890,000
RO2401 Cape Seal $560,000
RO2301 Residential Slurry Seal $890,000
RO2101 Arterial Rehabilitation $758,624 $247,250 377-342-47205 $758,624 Arterial Rehabilitation RO2102 Tennent Ave. Rehabilitation $10,382 $655,000 500-641-47201 $10,382 Sewer Enterprise RO2105 Appian Way Complete Streets $100,000 $970,000 325-342-47205 $100,000 WCCTAC - STMP Fees RO2107 Brandt St. Improvements $170,000 100-342-47205 $170,000 General Fund RO1902 Pedestrian Improvements at Tennent Ave. near R X R $42,976 $800,000 325-342-47205 $42,976 WCCTAC - STMP Fees RO1802 Hazel Street Gap Closure (Sunnyview) $200,000
325-342-47205 $1,223,746 WCCTAC - STMP Fees
325-342-47205 $80,000 CCTA Measure J
325-342-47205 $81,717 Caltrans - HBP
RO1708 Pinole Valley Road Improvements $100,000 200-342-47205 $100,000 Gas Tax - RMRA 325-342-47205 $9,144 City Street Improvements
215-342-47205 $350,000 MTC/OBAG2
325-342-47205 $129,400 MTC/TDA Article 3
106-344-47206 $149,328 Measure S 2014
PRJ # USES BY PROJECT FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Account # FY 2022-23 Funds Funding Source
IN2201 Energy Audit $50,000 106-344-47206 $50,000 Measure S 2014 IN2101 Emergency Power for Critical Facilities $30,000 $170,000 100-343-47201 $30,000 General Fund IN2102 Municipal Broadband Feasibility $60,000 106-118-47201 $60,000 Measure S 2014 IN2103 Recycled Water Feasibility $60,000 $140,000 100-341-42101 $60,000 General Fund IN2104 Local Road Safety Plan $20,650 325-342-47205 $20,650 Caltrans - HSIP IN2106 Active Transportation Plan $75,000 100-341-42101 $75,000 General Fund IN2001 Sanitary Sewer Collection System Master Plan $89,853 500-642-47201 $89,853 Sewer Enterprise IN1703 Storm Drainage Master Plan $75,000 $75,000 106-344-47206 $75,000 Measure S 2014 IN1704 Park Master Plan $100,000 106-344-47206 $100,000 Measure S 2014 Uses by Project Total $8,102,949 $21,589,345 $11,796,700 $10,229,200 $4,770,000

INFRASTRUCTURE ASSESSMENTS

CITY OF PINOLE
PROPOSED PRELIMINARY FY2022-23 THROUGH 2026-27

FIVE-YEAR CAPITAL IMPROVEMENT PLAN

FACILITIES
PARKS

SANITARY SEWER

STORMWATER
SW1901 Hazel Street Gap Closure (Sunnyview) $473,000

STREETS & ROADS
RO1710 San Pablo Ave. Bridge over BNSF Railroad $1,385,463 $16,293,235 $8,431,700 $8,439,200 RO1714 Safety Improvements at Appian Way & Marlesta Rd. formerly known as HAWK at Appian Way and Marlesta $637,872 PA2203 Playground Rubberized Surface Improvements $237,198

Page 7 of 66 ends

CIP FY 2022-23 THROUGH FY 2026-27

PROJECT DESCRIPTION SHEETS

Page 8 of 66 ends

FA2201 - Public Safety Building Modernization

FACILITIES
Initial Project Start: July 1, 2023 Initial Project Completion: June 30, 2026 Revised Project Start: Revised Project Completion: Project Origin: Staff Recommendation Multi-year Project: YesDescription: To extend the useful life of the Public Safety building, there are several items that require attention including but not limited to replacement of the HVAC system, carpet, flooring, water heaters, light fixtures, fans, etc. In addition, the building requires painting (interior and exterior), and the locker rooms also require renovation.

Supplemental Information: Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 100,000 $ 100,000 $ 100,000
Subtotal $ 100,000 $ 100,000 $ 100,000
Total Cost Estimate: $ 300,000

Page 9 of 66 ends

FA2202 - Senior Center Modernization

FACILITIES
Initial Project Start: July 1, 2023 Initial Project Completion: June 30, 2025 Revised Project Start: Revised Project Completion: Project Origin: Council Request Multi-year Project: YesDescription: The project includes a facilities condition assessment and design and construction of improvements to modernize the existing Senior Center building located at 2525 Charles Avenue. Work will include upgrades to energy system, roof replacement, and interior renovations.

Supplemental Information:

Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 60,000 $ 40,000 $ 100,000
Subtotal $ 60,000 $ 40,000 $ 100,000
Total Cost Estimate: $ 200,000

Page 10 of 66 ends

FA2002 - Electric Vehicle Charging Stations

FACILITIES
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: Revised Project Completion: December 30, 2022 Project Origin: Council Request Multi-year Project: Yes
Description: This project will install a level II dual port electric vehicle charging station at the parking lot serving the Public Safety Building. Supplemental Information: City staff continue to assess other public locations throughout Pinole for opportunities to incorporate EV charging infrastructure. An energy audit (Project IN2201) of City owned facilities will inform future installations of electric vehicle charging stations.

Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 106 $ 6,235
Construction 106 $ 50,000
Subtotal $ 6,235 $ 50,000
Total Cost Estimate: $ 56,235

Page 11 of 66 ends

FA1901 - Senior Center Auxiliary Parking Lot

FACILITIES
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: Revised Project Completion: June 30, 2023 Project Origin: Fowler Lot Re-Use Committee Multi-year Project: Yes
Description: On April 16, 1990 City Council adopted Resolution 2380 authorizing the purchase of 2548 Charles Street. At the time of purchase, City Council determined that construction of a Senior Center was necessary, and that this property was needed to provide sufficient parking for the Center. The parcel is surrounded by municipal parking lots which serve the Senior Center and Old Town Pinole. On February 2, 2021 City Council adopted Resolution 2021-07 and awarded a contract to a consultant for the preliminary engineering and design for the parking lot. The parking lot will be designed to be a multi-benefit project that includes pavement structural section, striping, lighting, bicycle parking, electric vehicle charging stations, stormwater capture and retention, and drought tolerant landscaping. The final design will offer the maximum number of parking spaces while allowing access for both vehicles and pedestrians and include aesthetic design components.

Supplemental Information: The Fowler House tenants remained in the properly till 2010 and many discussions took place to determine the best use of the property. It was determined that the house had asbestos and lead paint. On July 17, 2018, City Council adopted Resolution 2018-67 to create the Fowler Lot Re-use Committee to evaluate the reuse and redevelopment of the property. The Committee evaluated uses for the lot and determined the best use of the property is a parking lot. On October 16, 2018, the City Council adopted Resolution No. 2018-93 to approve a contract with a construction company to abate and demolish the Fowler house. The property demolition was completed on March 11, 2019. On July 21, 2020, City Council adopted Resolution 2020–68 to accept the final recommendation of the Committee.

Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 106 $ 42,535 $ 149,120
Construction 106 $ 588,860
Subtotal $ 42,535 $ 149,120 $ 588,860
Total Cost Estimate: $ 780,515

Page 12 of 66 ends

FA1902 - Energy Upgrades

FACILITIES
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: Revised Project Completion: June 30, 2023 Project Origin: End of life cycle Multi-year Project: No
Description: The heating, ventilation, and cooling (HVAC) systems at City Hall and Senior Center have reached the end of their useful life and need to be replaced. A portion of the roof at the Senior Center will also need to be replaced.

Supplemental Information: In October 2020, City staff began working with Marin Clean Energy’s (MCE’s) Energy Efficiency program to explore opportunities for energy conservation and generation at City owned facilities by replacing the HVAC systems and upgrading streetlights. It was determined that the MCE program could not incentivize HVAC replacement project or the upgrade of the streetlights. This project was formerly known as FA1706 and FA1801. In April 2021, the AC unit at City Hall broke down and was replaced.

Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 99,189 $ 120,811
Subtotal $ 99,189 $ 120,811
Total Cost Estimate: $ 220,000

Page 13 of 66 ends

FA1702 - Citywide Roof repairs and replacement

FACILITIES
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2022 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2024
Project Origin: End of life cycle
Multi-year Project: Yes
Description: In 2015, comprehensive visual roof inspections were completed by a contractor on various City owned facilities. The purpose of the inspection was to identify the extent, if any, of moisture intrusion into the existing roof assemblies, document observed roof system deficiencies, determine the overall condition of the existing roof systems and to estimate the service life of the in-place roof assemblies. The roof inspection identified several roofs which need to be repaired or replaced. The roofs at City hall and the Public Safety building need to be replaced.

Supplemental Information: Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 272,000 $ 140,000
Subtotal $ 272,000 $ 140,000
Total Cost Estimate: $ 412,000

Page 14 of 66 ends

FA1703 - City Hall Modernization (formerly known as Paint City Hall)

FACILITIES
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2024
Project Origin: End of life cycle
Multi-year Project: No
Description: To extend the useful life of the City hall building, there are several items that require attention including but not limited to carpet, flooring, window coverings, light fixtures, etc. The interior and exterior surfaces of the building require repainting as the paint system has reached the end of its useful life. Exterior painting is necessary to maintain external protection from the environment. Fading, chipping paint, along with water and mildew damage necessitates the painting project.

Supplemental Information: Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 125,000 $ 125,000
Subtotal $ 125,000 $ 125,000
Total Cost Estimate: $ 250,000

Page 15 of 66 ends

PARKS
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2024 Revised Project Start: Revised Project Completion: Project Origin: Staff Recommendation Multi-year Project: Yes
Description: Replacement of panel rubberized surfaces at Fernandez Park and Pinole Valley Park. Fernandez Park involves replacement of rubberized surface improvements at tot lot and replacement of existing engineered mulch with rubberized surface at older age play equipment. The rubberized surfaces around the play equipment will also be replaced at Pinole Valley Park. These improvements are grant funded through the State of California Department of Parks and Recreation Per Capita funds.

Supplemental Information: Budget:

PA2203 - Playground Rubberized Surface Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 327 $ 189,758 106 $ 7,640 $ 47,440
Subtotal $ 7,640 $ 237,198
$ 244,838
Construction
Total Cost Estimate:

Page 16 of 66 ends

PARKS
Initial Project Start: July 1, 2024 Initial Project Completion: June 30, 2025 Revised Project Start: Revised Project Completion: Project Origin: Council Request Multi-year Project: No
Description: Settling of rampsSupplemental Information: Budget:

PA2202 - Skatepark Rehabilitation
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 150,000
Subtotal $ 150,000
Total Cost Estimate: $ 150,000

Page 17 of 66 ends

PARKS
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: Council Request Multi-year Project: No
Description: Installation of an ADA compliant bench within a pocket park at a suitable location on Galbreth Ave. Supplemental Information: To develop the pocket park, a lot line adjustment may be required. Budget:

PA2201 - Pocket Park - Galbreth Ave.

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 65,000
Subtotal $ 65,000
Total Cost Estimate: $ 65,000

Page 18 of 66 ends

PARKS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: Revised Project Completion: June 30, 2023 Project Origin: Beautification Ad Hoc Committee Multi-year Project: No
Description: Installation of high capacity, solar powered compacting trash bins at City parks. Supplemental Information: In 2019, the City Council established a Beautification Ad Hoc Committee to analyze options for, and to make recommendations to the Council regarding clean-up and beautification projects in Pinole. Among other projects, the Committee recommended the installation of high capacity, solar powered compacting trash bins at City parks.

Budget:

PA2101 - Installation of high capacity trash bins
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 214 $ 425,000
Subtotal $ 425,000
Total Cost Estimate: $ 425,000

Page 19 of 66 ends

PARKS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2023 Revised Project Completion: June 30, 2024
Project Origin: Council Request
Multi-year Project: No
Description: There are two soccer fields at Pinole Valley Park which are utilized on an annual basis, the Wright Avenue Soccer Field at the southerly end, and Savage Avenue Soccer Field at the northern end. Both fields are heavily used by soccer leagues and the general public. The Savage Avenue Soccer Field requires substantial rehabilitation which includes: upgrading the irrigation system and ongoing turf maintenance. Turf maintenance includes mowing, fertilizing, aeration, overseeding, and topdressing.

Supplemental Information: This project has been delayed pending the development of a Park Master Plan (CIP Project# PA1704). Budget:

PA1901 - Pinole Valley Park Soccer Field Rehabilitation Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 106 $ 200,000
Subtotal $ 200,000
Total Cost Estimate: $ 200,000

Page 20 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2027 Revised Project Start: Revised Project Completion: Project Origin: Regulatory Requirement Multi-year Project: Yes
Description: Effluent pumping capacity of the treatment plant is limited by the capacity of the pipe size at the effluent outfall in Rodeo.

Increasing the pipe size at the Effluent Outfall Eductor Station will increase the wet weather effluent pumping capacity and increase the lifespan of the effluent pipe by reducing the pressure in the line during storm events.

Supplemental Information: Project requires coordination with Rodeo Budget:

SS2203 - Effluent Outfall
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 150,000 $ 3,000,000
Subtotal $ 150,000 $ 3,000,000
Total Cost Estimate: $ 3,150,000

Page 21 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: End of life cycle Multi-year Project: No
Description: In-kind replacement of a 4,000 gallon diesel storage tank used to supply fuel to standby generators and City vehicles. The existing tank is compromised.

Supplemental Information: Budget:

SS2202 - Replacement of Diesel Tank
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 150,000
Subtotal $ 150,000
Total Cost Estimate: $ 150,000

Page 22 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2027 Revised Project Start: Revised Project Completion: Project Origin: Master Plan Multi-year Project: Yes
Description: Various improvements to the Sanitary Sewer collection system, as identified in the Sanitary Sewer Collection System Master Plan. Supplemental Information: Budget:

SS2201 - Sanitary Sewer Rehabilitation
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 1,500,000 $ 800,000 $ 800,000 $ 800,000 $ 800,000 Subtotal $ 1,500,000 $ 800,000 $ 800,000 $ 800,000 $ 800,000 Total Cost Estimate: $ 4,700,000

Page 23 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2023
Project Origin: End of life cycle
Multi-year Project: No
Description: The Secondary Clarifier #5 has reached the end of its useful life. The project will involve removal and replacement of catwalk, drive mechanism, center column, and rake arm. Supplemental Information: The City of Hercules will be reimburse the Sewer Enterprise fund for 50% of the total project cost. Budget:

SS2101 - Secondary Clarifier—Center Column Rehabilitation Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 350,000
Subtotal $ 350,000
Total Cost Estimate: $ 350,000

Page 24 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2023 Project Origin: Staff Recommendation Multi-year Project: No
Description: There are four air relief valves at various locations on the WPCP Effluent Pipeline between the WPCP and the Rodeo treated water discharge point. This project includes removal and replacement of the pipe saddle, short pipe section, isolation valve, and air relief valve.

Supplemental Information: The four locations are: 1) across from the WPCP at 11 Tennent Ave., near the entrance of the SF Bay Trail, 2) On the SF Bay Trail near the corner of Santa Fe and Railroad Ave., 3) At the intersection of Mariposa St. and Railroad Ave. (Rodeo), 4) Outside the gate of Rodeo Sanitary District at 800 San Pablo Ave. (Rodeo). The City of Hercules will be reimburse the Sewer Enterprise fund for 50% of the total project cost.

Budget:

SS2102 - Air Release Valve Replacements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 50,000
Subtotal $ 50,000
Total Cost Estimate: $ 50,000

Page 25 of 66 ends

SANITARY SEWER
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2023 Project Origin: Regulatory Requirement Multi-year Project: No
Description: The California Environmental Laboratory Accreditation Program (ELAP) is responsible for accrediting environmental testing labs including the Pinole - Hercules WPCP. The 2019 ELAP inspection results indicated the lab apparatus, countertops, and the fume hood are past their useful life and recommended replacement.

Supplemental Information: The City of Hercules will be reimburse the Sewer Enterprise fund for 50% of the total project cost.

Budget:

SS2002 - Water Pollution Control Plant Lab Remodel
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Construction 500 $ 100,000
Subtotal $ 100,000
Total Cost Estimate: $ 100,000

Page 26 of 66 ends

SANITARY SEWER
Initial Project Start: October 1, 2020 Initial Project Completion: August 31, 2022 Revised Project Start: July 1, 2023 Revised Project Completion: June 30, 2024 Project Origin: End of lifecycle Multi-year Project: No
Description: The City owns and operates two lift stations to convey flow from low lying areas to high elevations where the flow continues by gravity to the wastewater treatment plant. Both pump stations have reached the end of their useful life and need to be rehabilitated.

Supplemental Information: The two pump stations are located on San Pablo Ave. and Hazel St. In FY 2019/20, this project was renamed to include both pump stations. Previously, this project was titled, “Hazel Street Sewer Pump Rehabilitation.” Budget:

SS1702 - Sewer Pump Station Rehabilitation
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 500 $ 22,500
Engineering 500 $ 150,000
Construction 500 $ 884,000 Contingency 500 $ 143,500
Subtotal $ 1,200,000
Total Cost Estimate: $1,200,000

Page 27 of 66 ends

STORMWATER
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2024 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: The existing system appears to have capacity issues at Roble Ave. and Encina Ave. that warrant review and upgrade. This project will assess the collection system for capacity and hydraulic profile and upgrade the system as necessary.

Supplemental Information:

Budget:

SW2001 - Roble Road Storm Drainage Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 276 $ 30,000
Construction 276 $ 280,000 Contingency 276 $ 40,000
Subtotal $ 30,000 $ 320,000
Total Cost Estimate: $ 350,000

Page 28 of 66 ends

STORMWATER
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2024 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: Adobe Road experienced a failure due to drainage impacts. Installation of a culvert will be required to control the drainage in the area. The area will then be regraded and the road surface will be restored. This road serves only as a service access route.

Supplemental Information:

Budget:

SW2002 - Adobe Road Storm Drainage Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 106 $ 30,000
Construction 106 $ 175,000 Contingency 106 $ 25,000
Subtotal $ 30,000 $ 200,000
Total Cost Estimate: $ 230,000

Page 29 of 66 ends

STORMWATER
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: Revised Project Completion: June 30, 2023 Project Origin: Development Driven Multi-year Project: Yes
Description: The existing stormwater collection is an open trench system and needs to be converted to an underground conveyance system to facilitate construction of a through road. This project will include connecting the existing storm drain network within Hazel Street between 1087 Hazel St (eastern limits) and 1081 Hazel St. (western limits). In January 2020, the City contacted with Schaff and Wheeler to prepare the preliminary design which includes plan and profile of the pipe and technical specifications.

Supplemental Information: This conversion also aids in compliance with the MSP4 by reducing the potential of contaminants including litter from entering the stormwater system.

Budget:

SW1901 - Hazel Street Storm Drain Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 106 $ 54,910
106 $ 353,000 276 $ 58,000
Contingency 106 $ 62,000
Subtotal $ 54,910 $ 473,000
Total Cost Estimate: $ 527,910
Construction

Page 30 of 66 ends

ROADS
Initial Project Start: July 1, 2025 Initial Project Completion: June 30, 2026 Revised Project Start: Revised Project Completion: Project Origin: Pavement Management Program Multi-year Project: No
Description: Based on the most current P-TAP report various segments will be recommended for slurry seal treatment. A slurry seal functions as a topcoat to existing asphalt pavement to preserve and protect the pavement. It is best suited for pavements with mild to moderate damage, such as narrow cracks, but not for severe damage such as potholes.

Supplemental Information: Budget:

RO2501 - Residential Slurry Seal
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 325 $ 10,000
Construction 325 $ 800,000
Contingency 325 $ 80,000
Subtotal $ 890,000
Total Cost Estimate: $ 890,000

Page 31 of 66 ends

ROADS
Initial Project Start: July 1, 2024 Initial Project Completion: June 30, 2025 Revised Project Start: Revised Project Completion: Project Origin: Pavement Management Program Multi-year Project: No
Description: Based on the most current P-TAP report, various pavement segments will benefit from a cape seal. A cape seal is applied when a slurry seal or micro-surfacing will not adequately address the pavement deterioration. Cape seals are a multi-layered treatment pavement preservation treatment which can extend the life of a pavement by 6-8 years.

Supplemental Information: Budget:

RO2401 - Cape Seal
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 325 $ 10,000
Construction 325 $ 500,000 Contingency 325 $ 50,000
Subtotal $ 560,000
Total Cost Estimate: $ 560,000

Page 32 of 66 ends

ROADS
Initial Project Start: July 1, 2023 Initial Project Completion: June 30, 2024 Revised Project Start: Revised Project Completion: Project Origin: Pavement Management Program Multi-year Project: No
Description: Based on the most current P-TAP report various segments will be recommended for slurry seal treatment. A slurry seal functions as a topcoat to existing asphalt pavement to preserve and protect the pavement. It is best suited for pavements with mild to moderate damage, such as narrow cracks, but not for severe damage such as potholes.

Supplemental Information: Budget:

RO2301 - Residential Slurry Seal
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 325 $ 10,000
Construction 325 $ 800,000 Contingency 325 $ 80,000
Subtotal $ 890,000
Total Cost Estimate: $ 890,000

Page 33 of 66 ends

ROADS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: Pavement Management Program Multi-year Project: Yes
Description: Based on the 2019 P-TAP report, various segments were recommended for treatment by StreetSaver®. The recommendations will be further validated through a comparative pavement analysis to explore additional treatment options which are not discussed in the P-TAP report. This will allow the City to optimize the available funding. In February 2021, the City selected a consultant to complete the preliminary engineering for this project.

Supplemental Information:

Budget:

RO2101 - Arterial Rehabilitation
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 377 $ 18,606 $ 39,874
Construction 377 $ 625,000 $ 215,000 Contingency 377 $ 93,750 $ 32,250 Subtotal $ 18,606 $ 758,624 $ 247,250
Total Cost Estimate: $1,208,480

Page 34 of 66 ends

ROADS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: Pavement Management Program Multi-year Project: Yes
Description: The construction impacts from the WPCP upgrade project resulted in pavement deterioration. This project will rehabilitate Tennent Ave. from San Pablo Ave. to WPCP. In February 2021, the City selected a consultant to complete the preliminary engineering for this project.

Supplemental Information: In preparation of this project, the City retained a consultant to perform internal CCTV on this section of roadway.

The inspection was completed in early 2021. Coordinating collection system improvements with street resurfacing projects ensures that sewer improvements are made prior to the resurfacing so that manholes and valve covers may be properly realigned, and repairs and replacements are made in a cost-effective manner. This also avoids cutting and patching recently paved streets. The City of Hercules will reimburse $86,430 for this project.

Budget:

RO2102 - Tennent Ave. Rehabilitation
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 500 $ 27,423 $ 10,382
200 $ 381,082 500 $ 74,597 325 $ 167,321
Contingency 500 $ 32,000
Subtotal $ 27,423 $ 10,382 $ 655,000
$ 692,805
Construction
Total Cost Estimate:

Page 35 of 66 ends

ROADS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: Revised Project Completion: June 30, 2023 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: Completion of preliminary engineering and design to provide continuous sidewalks and bike lanes along Appian Way beginning from unincorporated El Sobrante to about 1500 lineal feet north of the City limit within Pinole. In December 2021, City Council approved a Cooperative Funding Agreement with WCCTAC to receive STMP funds to complete preliminary design for this project.

Supplemental Information: This project will connect with the Contra Costa County’s project to provide continuous sidewalks and bike lanes along Appian Way from San Pablo Dam Rd. in unincorporated El Sobrante. This project will involve coordination with Contra Costa County. The construction phase of this project is unfunded and appears in the Unfunded and Unprogrammed list.

Budget:

RO2105 - Appian Way Complete Streets
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 325 $ 100,000 $ 970,000
Subtotal $ 100,000 $ 970,000
Total Cost Estimate: $1,070,000

Page 36 of 66 ends

ROADS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: Council Request Multi-year Project: No
Description: Provide improvements on Brandt St. including application of pavement treatments based on type and severity of distresses on existing pavement.

Supplemental Information: Budget:

RO2107 - Brandt St. Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 100 $ 50,000
Construction 100 $ 120,000
Subtotal $ 170,000
Total Cost Estimate: $ 170,000

Page 37 of 66 ends

ROADS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: Revised Project Completion: June 30, 2025 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: In 2018, the East Bay Regional Park District completed a trail link to connect Pinole Shores Regional Shoreline to Bayfront Park trail. There remains one very small gap on Tennent Ave. from Bayfront Park to Railroad Ave. Improvements to Tennent Ave. at the Railroad Crossing will facilitate safe movement of bicycles and pedestrians. Since project inception, the scope of work has evolved to include improvements that would maximize parking on Railroad Avenue for park users. In February 2021, the City selected a consultant to complete the preliminary engineering for this project.

Supplemental Information: WCCTAC held its STMP Call for Projects in 2018 which committed $100k in funding for preliminary engineering from the 2006 STMP program for this project. This project is eligible to respond to future STMP Call for Projects to compete for funding to advance the project through construction.

Budget:

RO1902 - Pedestrian Improvements at Tennent Ave. near R x R Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 325 $ 37,324 $ 42,976
325 $ 19,700
UF $ 680,000
Contingency UF $ 100,300
Subtotal $ 37,324 $ 42,976 $ 800,000
$ 880,300
Construction
Total Cost Estimate:

Page 38 of 66 ends

ROADS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: Revised Project Completion: July 30, 2025 Project Origin: Development Driven Multi-year Project: No
Description: A developer has proposed to develop on a vacant lot identified as APN 402-013-060 at the end of Hazel Street. The project proposes the subdivision of the lot into four new parcels and development of single family residences on each new parcel, and execution of a development agreement to make public improvements, including the extension of Hazel Street for roadway connection to Sunnyview Drive - West end of Hazel St.

Supplemental Information: Completion of Project SW1901 prior to this project.

Budget:

RO1802 - Hazel Street Gap Closure (Sunnyview)
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 276 $ 50,000
Developer $ 150,000
Subtotal $ 200,000
$ 200,000
Construction
Total Cost Estimate:

Page 39 of 66 ends

ROADS
Initial Project Start: July 1, 2017 Initial Project Completion: Beyond 5 year termRevised Project Start: Revised Project Completion: June 30, 2026 Project Origin: End of life cycle Multi-year Project: Yes
Description: The San Pablo Avenue bridge over the Burlington Northern Santa Fe Railroad is an integral part of the area’s transportation network. The age and condition assessment of the bridge supports replacement. The City was approved for initial funding from the Caltrans Highway Bridge Program (HBP). In February 2020, the City awarded a contract to a consultant for preliminary engineering (PE) to advance the project. The PE will be completed in two phases due to funding limitations. Completion of preliminary design is necessary to develop a final cost estimate for the project. Unfunded portions of this project appear in the Unfunded and Unprogrammed project list as Project UF022.

Supplemental Information: The total budget identified to complete the PE exceeds the amount of funding Caltrans committed to the project of the State’s share in the current HBP. Budget:

RO1710 - San Pablo Avenue Bridge over BNSF Railroad
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 PM 325 $ 257,061 $ 80,000 $ 42,439
325 $ 537,176 $ 1,225,463 $ (42,439) $ (7,500)
STMP $ (91,089) $ (1,223,746) $ (285,165)
HBP $ (708,856) $ (81,717)
UF
STMP
UF $16,578,400 $ 8,439,200 $ 8,439,200
Subtotal $ (5,709) $ - $16,293,235 $ 8,431,700 $ 8,439,200 Planning &
Design
Construction
Total Cost Estimate: $33,158,426

Page 40 of 66 ends

ROADS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2023 Project Origin: Council Request Multi-year Project: No
Description: As part of the high school construction project WCCUSD provided road improvements along the school frontage. Improvements to Pinole Valley Road - from Shea Dr. to Helena Ct. will extend the useful life of the pavement. The existing pavement score is high in this area, so a slurry seal may be the recommended treatment.

Supplemental Information:

Budget:

RO1708 - Pinole Valley Road Improvements
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Engineering 200 $ 5,000
Construction 200 $ 87,000 Contingency 200 $ 8,000
Subtotal $ 100,000
Total Cost Estimate: $ 100,000

Page 41 of 66 ends

ROADS
Initial Project Start: July 1, 2024 Initial Project Completion: June 30, 2025 Revised Project Start: July 1, 2020 Revised Project Completion: June 30, 2023 Project Origin: TAPS Multi-year Project: Yes
Description: The key elements affecting the safety of pedestrians and cyclists at the Appian Way and Marlesta Way intersection is speed and reduced visibility of approaching traffic due to the topography of the project area. Safety improvements are required to improve crossing conditions for pedestrians and bicyclists. In February 2021, the City selected a Consultant to complete the preliminary engineering for this project.

Supplemental Information: The City secured grant funds to install a traffic signal at this intersection instead of a HAWK.

Budget:

RO1714 - Safety Improvements at Appian Way and Marlesta Rd. formerly known as HAWK at Appian Way and Marlesta Rd.

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 325 $ 25,193 $ 9,144
OBAG2 $ 350,000
TDA $ 129,400
106 $ 67,278
Contingency 106 $ 82,050
Subtotal $ 25,193 $ 637,872
$ 663,065
Construction
Total Cost Estimate:

Page 42 of 66 ends

IN2201 - Energy Audit

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: Project Origin: Staff Recommendation Multi-year Project: No Description:

Supplemental Information: Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 106 $ 50,000
Subtotal $ 50,000
Total Cost Estimate: $ 50,000

Page 43 of 66 ends

IN2101 - Emergency Power for Critical Facilities

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2023 Revised Project Start: July 1, 2022 Revised Project Completion: Project Origin: Council Request Multi-year Project: YesDescription: During severe natural hazard events, it is highly likely that utility power will not be available for an extended period of time. Critical facilities will need reliable sources of sustained electrical power to continue operations. This project will: 1) identify critical facilities in need of back-up power in coordination with an Emergency Operations Plan (EOP) , 2) assess power loads in each critical facility that requires back-up power, 3) determine the costs and technology options including solar battery storage, and 4) make any additional recommendations to Council before advancing to construction.

Supplemental Information: The Public Safety Building, Fire Station 74, and the Water Pollution Control Plant have stand by generators. Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 100 $ 30,000
Construction 100 $ 170,000
Subtotal $ 30,000 $ 170,000
Total Cost Estimate: $ 200,000

Page 44 of 66 ends

IN2102 - Municipal Broadband Feasibility

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2024 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2022
Project Origin: Council Request
Multi-year Project: No
Description: A feasibility study will determine a successful deployment strategy and associated costs for implementing municipal broadband service in Pinole.

Supplemental Information: Budget:

Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 106 $ 60,000
Subtotal $ 60,000
Total Cost Estimate: $ 60,000

Page 45 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2022 Initial Project Completion: June 30, 2023 Revised Project Start: Revised Project Completion: June 30, 2024 Project Origin: Council Request Multi-year Project: Yes
Description: A feasibility study will allow the City to plan and phase the construction of future recycled water distribution system infrastructure.

The study will identify potential recycled water customers, evaluate the quantity, quality, and recycled water distribution system options to address the needs of potential users in surrounding areas, seek opportunities to phase the construction of a recycled water delivery system, and develop planning-level cost options for the phased system.

Supplemental Information: Recycled water delays or eliminates the need to construct more potable water facilities, sustains the economy with increased water supply reliability, protects the environment, safeguards investments in parks and landscaping with drought proof or drought resistant water supply, and contributes to a green and healthy environment. In 2019, East Bay Municipal Utility District (EBMUD) prepared an Updated Recycled Waster Plan which considered the potential for potable reuse in EBMUD’s water service area. The development of a new recycled water supply for the Phillips 66 refinery in Rodeo using effluent from the Pinole-Hercules and Rodeo wastewater treatment plants was among the recommended non-potable reuse projects. This project is estimated to deliver up to 3.67 MGD of recycled water to the refinery for use in their boilers and cooling towers. The combined final disinfected effluent from both plants would be pumped at the Rodeo Pump Station to the refinery for treatment a new advanced recycled water treatment plan. This project was recommended by EBMUD because it would deliver a large amount of water to a single customer, with comparatively few pipelines required due to the short distance between the sources of wastewater and the Phillips 66 Refinery
Budget:

IN2103 - Recycled Water Feasibility
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Design 100 $ 60,000
Construction 100 $ 140,000
Subtotal $ 60,000 $ 140,000
Total Cost Estimate: $ 200,000

Page 46 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2022 Revised Project Start: Revised Project Completion: December 30, 2022 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: Development of a Local Road Safety Plan (LRSP) which will include an existing conditions assessment, development of traffic measures in areas of engineering, education, encouragement, enforcement, emerging technologies along with associated evaluation. The LRSP will include a prioritized list of roadway infrastructure improvements.

Supplemental Information: In July 2020, staff submitted a grant application to Caltrans for funding to develop and implement an LRSP for the City of Pinole. LRSP’s allow local governments to identify, analyze, and prioritize roadway safety improvements on roads within their jurisdiction. In the future, an LRSP or its equivalent, will be required for agencies to apply for federal Highway Safety Improvement Plan funds. In October 2020, the City was selected for funding and implementation of an LRSP. In December 2020, the City released a Request for Proposals to seek professional services from licensed engineering firms to develop a LRSP. A contract was awarded to a consultant in April 2021.

Budget:

IN2104 - Local Road Safety Plan
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 325 $ 19,013 $ 20,650
Subtotal $ 19,013 $ 20,650
Total Cost Estimate: $ 39,663

Page 47 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2021 Initial Project Completion: June 30, 2022 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2023 Project Origin: TAPS Multi-year Project: No
Description: Development of an Active Transportation Plan will act as a guide for active mobility within and around Pinole. The Plan will identify an integrated network of walkways and bikeways that connect Pinole neighborhoods and communities to employment, education, commercial, recreational, and tourist destinations. The plan will prioritize a set of connected projects, that when fully implemented, will increase active transportation opportunities and make it safe and more convenient for people to walk, bike, and use non-auto forms of travel.

Supplemental Information: Budget:

IN2106 - Active Transportation Plan
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 100 $ 75,000
Subtotal $ 75,000
Total Cost Estimate: $ 75,000

Page 48 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2022 Revised Project Start: Revised Project Completion: December 30, 2022 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: In September 2020, the City Council awarded a contract to Carollo Engineers, Inc. to develop a Sanitary Sewer Collection System Master Plan (Plan). The Plan will provide a condition assessment of the sewer collection assets to inform capital planning and effectively serve the wastewater needs of residents and businesses. This plan will also provide a capacity analysis to identify pipes that need to be upsized. Master planning is critical to identify when and where infrastructure upgrades or improvements will be needed to accommodate growth.

Supplemental Information:

Budget:

IN2001 - Sanitary Sewer Collection System Master Plan
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 500 $ 359,147 $ 89,853
Subtotal $ 359,147 $ 89,853
Total Cost Estimate: $ 449,000

Page 49 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2023 Revised Project Start: July 1, 2022 Revised Project Completion: June 30, 2024 Project Origin: Staff Recommendation Multi-year Project: Yes
Description: Preparation of a storm drain master plan will provide an analysis of the existing collection system. The plan will identify system deficiencies related to capacity, functionality, and permit compliance. The plan can serve to guide future budget allocations for improvements to the system.

Supplemental Information:

Budget:

IN1703 - Storm Drainage Master Plan
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 106 $ 75,000 $ 75,000
Subtotal $ 75,000 $ 75,000
Total Cost Estimate: $ 150,000

Page 50 of 66 ends

INFRASTRUCTURE ASSESSMENTS
Initial Project Start: July 1, 2020 Initial Project Completion: June 30, 2021 Revised Project Start: July 1, 2021 Revised Project Completion: June 30, 2023
Project Origin: Staff Recommendation
Multi-year Project: No
Description: Preparation of a park master plan will aid the City in developing a strategic approach to park maintenance and operation. The master plan will allow the City to quantify and qualify the existing park system, identify deficiencies, and develop a financial analysis of the cost to maintain and operate park assets.

Supplemental Information: This project was added to the CIP in 2017 as an unfunded project; Council approved funding in 2020. Budget:

IN1704 - Park Master Plan
Fund Prior Funding FY 2022-23 FY 2023-24 FY 2024-25 FY 2025-26 FY 2026-27 Planning 106 $ 100,000
Subtotal $ 100,000
Total Cost Estimate: $ 100,000

Page 51 of 66 ends

CIP FY 2022-23 THROUGH FY 2026-27

UNFUNDED AND UNPROGRAMMED PROJECTS

Page 52 of 66 ends

FIVE-YEAR CAPITAL IMPROVEMENT PLAN: FY 2022-23 THROUGH FY 2026-27

UNFUNDED AND UNPROGRAMMED PROJECTS
# Unfunded/Unprogrammed Projects
UF001 Railroad Avenue Bridge Removal and Replacement
UF002 Electric Vehicle Charging Stations in City lots
UF003 Parking lot resurfacing
UF004 LLAD Landscape Restoration and Improvement
UF005 Dog Park Restroom Replacement
UF006 Dog Park resurfacing and fencing improvements
UF007 Eucalyptus Grove Restoration
UF008 Fernandez Park Baseball grandstand improvement
UF009 Repave Trails
UF010 ADA Ramps
UF011 Appian Complete Streets
UF012 Bridge Maintenance
UF013 Installation of High intensity Activated crossWALK (HAWK) UF014 Pavement Maintenance
UF015 I-80/Pinole Valley Rd. Interchange Improvements
UF016 Shale Hill Retaining wall and sidewalk gap
UF017 Sidewalks gaps
UF018 Signal System Upgrades
UF019 San Pablo Sewer Lift Station Upgrade
UF020 Sewer Collection Systemwide Rehabilitation
UF021 Tree Master Plan
UF022 San Pablo Avenue Bridge over BNSF Railroad
UF023 Installation of Solar at City Facilities
UF024 All weather access roads
UF025 Faria House Renovations

Page 53 of 66 ends

UF001 - Railroad Avenue Bridge Removal and Replacement
Project Information
The Contra Costa County Flood Control and
Water Conservation District has advised
removal of the Railroad Avenue Bridge. The
bridge is a flood barrier. The first step is to
determine if the City of Pinole is the responsible
agency for this project.

UF002 - Electric Vehicle Charging Stations in City lots Project Information
Origin: Staff Recommendation
Budget Unit: Roads/Sanitary Sewer/
Stormwater
Cost Estimate:

Potential Funding Sources:

The City desires to promote and encourage the
use of electric vehicles. With increased adoption
of alternative fuel vehicles, the need for
charging infrastructure is growing. The City
wishes to install charging stations in city owned
parking lots. The first step is to complete a load
study at City owned parking lots to determine
the electrical capacity at each site. There may
be significant electrical upgrades necessary to
install charging stations. Electrical capacity and
siting determine ultimately determine the cost of
each project. There are incentives available for
the charging equipment.

Origin: Council Request
Budget Unit: Facilities
Cost Estimate:

Potential Funding Sources: Bay Area
Air Quality Management District, West
Contra Costa Transportation Authority,
Marin Clean Energy

Page 54 of 66 ends

UF003 - Parking lot resurfacing
Project Information
This project is to maintain and enhance
existing City owned parking facilities and
infrastructure, to increase parking supply,
and to support ongoing multi-modal and
streetscape improvements. Improvements
include saw cutting and demolition,
pavement removal, earthwork, pavement
installation, curb and gutter, striping, and
signage.

UF004 - LLAD Landscape Restoration and Improvement
Project Information
Origin: Staff Recommendation
Budget Unit: Facilities
Cost Estimate:

Potential Funding Sources: Economic
stimulus funding
The Pinole Valley Road Landscape and Lighting
Assessment District was formed in 2008. The
City installed various improvements on Pinole
Valley Road between Henry Avenue and
Ramona Street. The district provides
maintenance to traffic signals, streetlights,
median landscaping, irrigation for landscaping,
electricity to traffic signals and streetlights, and
graffiti removal. This project will maintain and
restore turf, shrubs, plants and trees within the
District.

Origin: LLAD Report
Budget Unit: LLAD
Cost Estimate:

Potential Funding Sources: Fund 345
& 348

Page 55 of 66 ends

UF005 - Dog Park Restroom Replacement
Project Information
The existing restroom located at the Dog
Park is beyond its useful life and requires
replacement.

UF006 - Dog Park resurfacing and fencing improvements
Project Information
Origin: Staff Recommendation
Budget Unit: Parks
Cost Estimate:

Potential Funding Sources: -
Resurfacing and fencing improvements
Origin: Staff Recommendation
Budget Unit: Parks
Cost Estimate:

Potential Funding Sources:

Page 56 of 66 ends

UF007 - Eucalyptus Grove Restoration
Project Information
The open space located between the Old Town
area between John St. and Pinole Valley Road
is forested with Eucalyptus trees. In 2014, a
Safety Inspection was conducted by a
consultant. A total of 8 trees were
recommended for removal, and root crown
excavation was recommended for 3 trees. 2
trees were determined to be hollow and
recommended for further investigation to
evaluate the level of internal decay. In 2018, the
City hired a company to remove 20 Eucalyptus
trees in the area. There are still many trees left
and many of the prior trees were felled with the
trunks remaining on site. This project will
remove the remaining trees, both standing and,
on the ground, and regreen this area with native
trees.

UF008 - Fernandez Park Baseball grandstand improvement
Project Information
Origin: Council Request
Budget Unit: Parks
Cost Estimate:

Potential Funding Sources:

The current grandstand is aging and
requires increased maintenance to
maintain its serviceability.

Origin: Staff Recommendation
Budget Unit: Parks
Cost Estimate:

Potential Funding Sources:

Page 57 of 66 ends

UF009 - Repave Trails
Project Information
The City’s goal is to develop safe,
connected, and comfortable bicycle and
pedestrian facilities for people of all ages
and abilities. Repaving trails will enhance
trail access from the City’s roadway
network to encourage alternative modes of
transportation.

UF010 - ADA Ramps
Project Information
Origin: Staff Recommendation
Budget Unit: Parks
Cost Estimate:

Potential Funding Sources:

This project involves removing barriers to
accessibility for persons using wheelchairs
or other personal assistance devices and
improving pedestrian accessibility and
safety by reconstructing or upgrading curb
ramps at various locations throughout the
City.

Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

Page 58 of 66 ends

UF011 - Appian Complete Streets
Project Information
This project will provide continuous sidewalks and bike lanes along Appian Way from San Pablo Dam Rd. in unincorporated
El Sobrante to about 1500 lineal feet north
of the city limit within the City of Pinole.

The City will seek 2019 STMP funds
from West Contra Costa Transportation
Authority for preliminary design.

UF012 - Bridge Maintenance
Project Information
Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate: $970,000

Potential Funding Sources: -
Maintenance of vehicular and pedestrian
bridges as identified in the Caltrans Bridge
Inspection Reports and Pedestrian Bridge
Inspection Reports completed by Quincy
Engineering, Inc.

Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

Page 59 of 66 ends

UF013 - Installation of High intensity Activated crossWALK (HAWK) Project Information
A High Intensity Activated crossWALK
(HAWK) beacon is a traffic control device
used to stop road traffic and facilitate
pedestrians to cross more safely. HAWKS
are candidate treatments for roads with
three or more lanes and generally have an
annual average daily traffic above 9,000.

HAWKS are considered for all midblock
and intersection crossings where roadway
speed limits are equal or greater than 40
mph. The safety of various crossings can
be improved in Pinole through the
installation of a HAWK.

UF014 - Pavement Maintenance
Project Information
Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

The City uses a pavement management
software known as StreetSaver to
strategize the most cost effective method
to extend the pavement life. Pavement
Maintenance is necessary to maintain the
City’s pavement network. Deferred
maintenance results in increased costs
over time.

Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate: $42,000,000

Potential Funding Sources: Fund 200
and Fund 106

Page 60 of 66 ends

UF015 - I-80/ Pinole Valley Rd. Interchange Improvements Project Information
This project will widen Pinole Valley Road
ramp terminal intersections at I-80 to
provide a dedicated right turn lane to the
eastbound and westbound I-80 on ramps.

This project will also provide crossing
enhancements at the Pinole Valley Road
and I-80 intersection.

UF016 - Shale Hill Retaining wall and sidewalk gap
Project Information
Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate: $10,959,000

Potential Funding Sources:

Shale Hill is located on San Pablo Ave.
near Oak Ridge Road. The cut slope
above the pavement is comprised of shale
which is loose and sloughs onto the road.

There is no sidewalk in this area because
the toe of the embankment is uncontrolled
and there is inadequate space to
accommodate a sidewalk. Staff has not
been successful in securing grant funds for
this project.

Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

Page 61 of 66 ends

UF017 - Sidewalk gaps
Project Information
This project will address sidewalk gaps by
installing public sidewalks where sidewalks
are missing on one or both sides of the
street. This work will be coordinated with
other construction projects. Sidewalk gaps
often exist in places with site constraints
(i.e. right of way, grade/slopes, or utility
conflicts) or are adjacent to properties that
have been required to provide sidewalks in
the past due to land uses or ownerships.

Locations for repair will be selected based
on site conditions, pedestrian safety, and
adjacent property attributes.

UF018 - Signal System Upgrades
Project Information
Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

This project will upgrade various aspects
of the City’s traffic signal system including:
traffic signal controller equipment, vehicle
detection, traffic signal arms and heads,
battery backup systems, and
communications systems to reduce
congestion and improve safety for the
Pinole community.

Origin: Staff Recommendation
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

Page 62 of 66 ends

UF019 - San Pablo Sewer Lift Station Upgrade
Project Information
This project involves upgrading the
structural and electrical needs of the San
Pablo Ave. lift station to address the safety
and operational deficiencies.

UF020 - Sewer Collection Systemwide Rehabilitation
Project Information
Origin: Sanitary Sewer Master Plan
Budget Unit: Sewer
Cost Estimate:

Potential Funding Sources:

In 2020, the City contracted with a
consultant to prepare a sanitary sewer collection system master plan. The Master Plan will provide condition assessment of
sewer collection assets that will inform
capital planning.

Origin: Sanitary Sewer Master Plan
Budget Unit: Sewer
Cost Estimate:

Potential Funding Sources:

Page 63 of 66 ends

UF021 - Tree Master Plan
Project Information
In 2019, the City Council established a
Beautification Ad Hoc Committee to
analyze options for, and to make
recommendations to Council regarding
clean-up and beautification projects in
Pinole. Among other projects, the
Committee recommended the development
of a Tree Master Plan to inventory the
existing trees, and to develop a plan for
managing the tree inventory, including
finding tree planting opportunities.

UF022 - San Pablo Avenue Bridge over BNSF Railroad
Project Information
Origin: Beautification AdHoc Committee
Budget Unit:

Cost Estimate: $375,000

Potential Funding Sources: Cal Fire
Urban and Community Forestry Grant
Program
This project will replace the existing
thirteen span reinforced concrete span
structure over the Burlington Northern
Santa Fe Railroad adjacent to San Pablo
Avenue at the easterly limits of the City.

On 02/18/20, Council awarded a contract
to a Consultant to begin the preliminary
engineering (PE) for this project (CIP
Project RO1710). The PE will be
completed in two phases due to funding
limitations. The first phase was necessary
to develop a final cost estimate to
facilitate pursuing additional funding
required to complete all phases including
construction.

Origin: End of life cycle
Budget Unit: Roads
Cost Estimate: $35,582,665

Potential Funding Sources: Fund 213,
Fund 214, and Economic Stimulus funds.

Page 64 of 66 ends

UF023 - Installation of Solar at City Facilities
Project Information
This project involves procurement and
installation of solar panels at City owned
facilities to offset the City’s electricity
consumption and reduce the greenhouse
gas impacts.

UF024 - All access weather roads
Project Information
Origin: Council Request
Budget Unit: Facilities
Cost Estimate:

Potential Funding Sources:

The General Plan, Chapter 8 discusses
improvement of open space management
to reduce wildfire risks. There is a desire
to have improved, all-weather access
roads through open space to improve access to and from Hercules and El Sobrante to shorten response times and improve
mutual aid.

Origin: General Plan
Budget Unit: Roads
Cost Estimate:

Potential Funding Sources:

Page 65 of 66 ends

UF025 - Faria House Renovations
Project Information
The City has discussed the use and
economic viability of the Faria House.

Significant renovations are required to
utilize the property for any purpose. In
2019, the City awarded a contract to a
consultant to prepare design and
specifications. The scope of work includes
development of drawings and schematics
of interior improvements, specifications for
bidding, an evaluation of the structural engineering for the installation of an elevator for ADA access, and mechanical, electrical, plumbing design as part of the schematics. The consultant will provide the
City with improvement costs.

Origin: Council Request
Budget Unit: Facilities/Economic
Development
Cost Estimate:

Potential Funding Sources:

Page 66 of 66 ends