Project Progress Update
Title – Item 3.B

Projects in Progress

Bluff Protection
•Ocean Boulevard Access Project
•Construction to begin March 2022
•Estimated completion September 2023
•DELAY: Up to 25 weeks for epoxy coated rebar which a
major component of the project.
3 Drainage
•Pismo Beach Strom Drain Enhancement Project
•Under construction
•Estimated completion April 2022
•DELAY: Material for Encanto Outfall
•Dolphin Bay Strorm Drain Outfall Repair
•In design
•Anticipated bid date July 2022
4 Parking
•Acquire Parcel for Parking Lot
•330 Main Street Purchased
•Addie Street Parking and Access Improvements
•Estimate completion of plans and specs March 2022
•Estimated start of construction June 2022
•Estimated completion September 2022
5 Parks
•Price Historic Park Signs
•Under construction
•Estimated completion date March 2022
•Rehabilitate Shell Beach Tennis Courts
•Complete
6 Public Facilities
•Corporation Yard Administration Building Addition
•Under construction
•Estimated completion date April 2022
•City Hall Safety Upgrades
•Under construction
•Estimated completion date February 2022
•City Hall Kitchen and Breakroom
•Under construction
•Estimated completion date April 2022
•St. Jude’s Tunnel
•Lighting –Contract issued
•Art –Revising art per Council direction, will return to Council 7

Public Facilities Cont.
•Chapman Estate Improvements
•Roof
•Under construction estimated completion –February/March 2022 •Windows
•Under design
•Estimated construction –April/May 2022
•ADA Bathroom Improvements
•Under design
•Estimated construction –May/June 2022
•Mobil Command Vehicle
•Complete
8 Public Facilities Cont.
•Public Safety Facility construction drawings, owner advisor/ construction management •RFP for three finalists ready to issue
•Study session on 1/25/2022
•Traffic Study and Turn Radius Report in Progress
•Contractor/Architect Selection June 2022
•Demolition Fall 2022
•Tennis and Basketball Court Relocation
•Design Completed; Preparing RFP for Design
•Staff met with DSA Consultant and LMUSD on 1/24/22
•Meeting request for the week of February 7th sent to DSA for Facility Determination •City Project v. School District Project (ADA Issue)
•Aiming for Construction Fall 2022
9 Public Facilities Cont.
•4th Street Affordable Housing
•Contributions ongoing, project under construction, complete Summer 2023 •Shell Beach Road Affordable Housing
•Contribution ongoing, construction permits under review •Dinosaur Caves/Price Historic Park Restroom
•Under construction
•DELAY: Parts (Electrical and Handrail) and Labor at Both Parks •Estimated completion February 2022
•Shell Beach Tennis Court Rehab
•Complete
10 Streets and Transportation
•Price Canyon Slope Repair
•Substantially complete
•Bello Bridge
•Major construction complete
•Estimated completion February 2022
•Experienced 4 month Delay Due to Material
11 Utilities
•Vistal Del Mar Lift Station Upgrades and Backup
Generator
•Complete
•New Chlorine System
•Estimated completion February 2022
•Toucan Terrace Sewer Trestle Rehab
•In design
•Estimated bid date April 2022
•Grit Removal
•Estimated completion May 2022
12 Utilities
•Solids Handling Upgrades
•Belt Press rehab –Complete
•Reconstruction of DAFT –Complete
•Clean Oxidation ditches –Estimated completion May 2022 •Rehab Clarifiers –Anticipated bid June 2023
•Rehab Digester #1 –Anticipated completion April 2022
•Construction of steel building –Anticipated construction December 2023 •Central Cost Blue
•Cost share agreement complete (AG City Council 1/25)
•Ending Leases/Clearing
•Applying for Funding
•Design Work Continuing
13 Utilities
•Shell Beach Reservoir 1 Replacement
•Under construction
•Estimated completion date May 2022
•Pacific Estates Reservoir Maintenance
•On hold pending completion of Shell Beach Reservoir 1
•Charles Street Reservoir Maintenance
•On hold pending completion of Shell Beach Reservoir 1
•Outlet Center Ramp Waterlines (Replace 8” with 12” from 4th St to Outlet Center)
•Anticipated design November 2022
14 Parks
•Beach Swing Replacement
•Estimated completion May 2022
•Chumash Park and Palisades Park Play Structure
•RFP for design due January 2022
•PRBC and Council –February 2022
•Construction –July/August 2022
•May Encounter Material Delay
•South Palisades Park Workout Stations
•Not yet started
15 Parks
•Construct Grassy Event Area at Price Historic Park
•Pending Friends of Price House
•Water Bottle Filling stations
•Estimated completion May 2022
16 Public Facilities
•James Way Beautification
•Pending Council Direction
•Goal to begin Summer 2022
17 Streets and Transportation
•FY 2022 Paving Project
•Received Final Plans
•Engineer’s Estimate $13 million ($7 million over budget and $3 million over anticipated amount) •Anticipated bid date February 2022
•Award contract April 2022
•Anticipated construction May 2022
•Project Will Be of An Extended Duration Due to Size
•Mattie Road and Shell Beach Sidewalk (separate project); Potential Support from Cal Trans Due to New Policy •Sidewalk at Spyglass under US 101
•To be constructed with Paving Project
18 Next Year Projects

Future Projects
•Dog Park at Spyglass
•Construct Pedestrian Path from Hinds to Oceanview
•Signalize Bello/Price Canyon Road Intersection
•Harloe Bluff Stabilization
•Division of Boating and Waterways Grant not funded•Project on hold pending next round of grant funding •New Production Well
•Property purchased (Central Coast Blue site)
•“Treebates” and Tree Planting Program
•Highway 1/Dolliver Paving and Transfer
•Bike Master Plan Update and Improvements
20 Projects Delayed By Labor/Supplies
•Encanto Storm Drain
•Corporation Yard and City Hall
•Dinosaur Caves/Price Park Restrooms
•Bello Bridge
•Ocean Boulevard Bluff Protection and Access
21 Questions