CENTRAL COAST BLUE
Joint Council
Meeting

WELCOME

PAGE 3
1 2
3 4
5 6
7 8
9 10
Project Overview
Water Supply Drivers
& Project Benefits
Council Q&A
Costs & Funding
Council Q&A
Project Governance
Project Schedule &
Next Steps
Council Q&A and
Public Comment
Title XVI Grant
Presentation
Project Commitment
Signing
AG
E
N
D
A

PROJECT

OVERVIEW

PAGE 5
Central
Coast Blue
ONE COMMUNITY.

ONE WATER.

ONE FUTURE.

Central Coast Blue is a regional water
reuse project that will create a new, local
water supply and protect the Santa Maria
Groundwater Basin from seawater intrusion.

A partnership between the cities of Arroyo
Grande, Grover Beach, and Pismo Beach,
this collaborative, multi-phase effort will
benefit Southern San Luis Obispo County
for generations to come.

PAGE 6

HOW IT WORKS

PAGE 7
Seawater Intrusion

PAGE 8
Seawater Intrusion Barrier

PAGE 9
Project
Location

PAGE 10
Project
Location

PAGE 11

PAGE 12
Advanced Treatment Process
1 2 3

WATER SUPPLY

DRIVERS &

PROJECT BENEFITS

PAGE 14
South San Luis Obispo
County relies on three water
sources to meet the
community’s diverse needs.

However, prolonged drought and
changing environmental
conditions have dramatically
impacted these sources.

PAGE 15

NORTHERN CITIES

MANAGEMENT AREA
The region receives
30-50%
of its water from
the Northern Cities
Management Area of
basin.

Santa Maria
Groundwater
Basin

PAGE 16
Santa Maria
Groundwater Basin
The NCMA agencies manage
municipal pumping to keep the
Deep Well Index higher than

7.5 feet MSL to maintain a
positive groundwater gradient
and prevent seawater intrusion

PAGE 17
Lopez Reservoir
mandatory cutbacks
triggered for users
%

CAPACITY

PAGE 18
Lopez Reservoir
Lopez Lake Capacity
40K
0 20K
10K
30K
50K
Ac
r
e
-Fe
e
t
1969 2023
11,940
AF

PAGE 19

HISTORIC LOW
State Water Project
%ALLOCATIONS ARE NEAR
with little certainty for
future availability

PAGE 20
Central Coast Blue Provides Many Unique Benefits
Local Control
Drought Resilience Groundwater Protection Water Reuse
Protects the groundwater basin
against seawater intrusion
Provides reliable water supply that
isn’t dependent on rainfall
Reduces reliance on costly
imported water
Recovers valuable local water and
aligns with State priorities
Sustainability
Shares resources to maximize
value for the community
Reduces the amount of water
discharged to the ocean
Regional Collaboration

COUNCIL Q&A

COSTS &

FUNDING

PAGE 23
Project Capital Cost
$93M Implementation
Costs
$18M
Injection Wells,
Monitoring Wells &
Pipelines
$27M
Advanced
Water
Purification
Facility
$40M
Management Reserve/
Program Contingency
$8M9%
19%
29%
43%

PAGE 24
Project Capital Cost
Process Building & Tanks
$8.6M
Site Civil
$2.8M
Process Mechanical
$16.7M
Electrical, Instrumentation
& Controls
$12M

PAGE 25
Project
Capital
Cost
Monitoring Wells
$6M
Injection Wells
$14M
Pipelines
$7M

PAGE 26
25%
50%
25%
Financing Plan
$93M
Planned Low-
Interest Loans
$47M
Planned
Federal Grants
$23M
Central Coast Blue will be
funded by a combination
of grants, low-interest loans
and ratepayer revenues.

Planned State
Grants
$23M

PAGE 27
Funding Update
$14 million
Title XVI WIIN Act Program
$2 million
Proposition 1 Groundwater
Grant Program
$1 million
Proposition 1 IRWM
Grant Program
•Eligible for $9M in
additional funding, or up
to 25% of project cost
•$35.7M in additional
funding requested
•Notification expected
December 2022
•Recommended for award
by RWMG
•Board of Supervisors approval
in December 2022

PAGE 28
Financing Update
•US EPA financing program
•Letter of interest under
development
•49% of project costs
•Five years of deferred debt
service
•Updated application due
December 2022
•Eligibility for up to $15M in
grants through RWFP
•Eligibility for loan
forgiveness through the GPR

PAGE 29
Cost Share
$47M
Grover Beach
$16.9M
Pismo Beach
$18.3M
Arroyo Grande
$11.8M
25%
36%
39%
Following extensive and
collaborative negotiations,
program partners agreed
on a framework to share
program costs and
benefits.

COUNCIL Q&A

PROJECT

GOVERNANCE

PAGE 32

PROJECT GOVERNANCE
Collaborative Partnership
A model for collaborative water
resource management

PAGE 33

PROJECT GOVERNANCE
Cost Share Agreement
Partners agreed to share program
costs and benefits

PAGE 34

PROJECT GOVERNANCE
Joint Powers Authority
Owned, operated, and
maintained by a Joint Powers
Authority (JPA)

PROJECT

SCHEDULE &

NEXT STEPS

PAGE 36
Project Schedule

PAGE 37
Next Steps
•JPA Ratification
•Communications & Outreach
•Funding Pursuits
•Permitting
•Design

COUNCIL Q&A

AND PUBLIC

COMMENT

TITLE XVI GRANT

PRESENTATION

PROJECT

COMMITMENT

SIGNING

THANK YOU

POCKET SLIDES

PAGE 44

SENTRY WELLS

PAGE 45
Lopez Spillway Raise
Dependent on precipitation.

State Water
Challenges with reliability, availability, potential for catastrophic interruption.

Production Well Relocation
Seawater intrusion migrates inland.

Desalination
High cost, permitting and regulatory challenges, environmental consequences.

Alternatives Comparison

PAGE 46
California Environmental Quality
Act (CEQA)
National Environmental Policy Act
(NEPA)
USBR
Division of Drinking Water
Enhanced Source Control Program and Title 22 Engineering Report Regional Water Quality Control
Board
Report of Waste Discharge
Environmental Permitting
Streambed alteration, Clean Water Act 404, Clean Water Act 401, Section 7
Coastal Development and
Construction Permitting
City of Grover Beach, SLO County, California Coastal Commission Permitting Process

PAGE 47
Pismo Beach Grover Beach Arroyo Grande
Capital O&M Debt Service
$X M $X M $X M
Annualized Costs
—Lorem ipsum dolor—

Advanced Water
Purification Facility
Injection &
Monitoring
Wells
Pismo WWTP
Brine

SSLOCSD
WWTP
Ocean

SSLOCSD
Ocean Outfall
Pismo Beach Outfall Pipeline
Pump
Station Pump
Station
Purified
Water
PHASE 2

PAGE 49
Deep Well Index

PAGE 50
Reduction in Municipal Pumping

PAGE 51

UPDATE WITH

MODELING

RESULTS FROM
NCMA
Projected Groundwater Levels

PAGE 52

SWP CONTRACTORS

TABLE A
(Acre-Feet)
(1)

INITIAL

REQUEST
(Acre-Feet)
(2)

APPROVED

ALLOCATION
(Acre-Feet)
(3)

PERCENT INITIAL

REQUEST

APPROVED
(4) = (3)/(2)

CENTRAL COASTAL
San Luis Obispo County
FC&WCD
25,000 25,000 1,250 5%
2022 State Water Project Allocation

PAGE 53
Snowpack Trends

PAGE 54
11,940 AF
0 10,000
20,000
30,000
40,000
50,000
60,000
1969 1972 1975 1978 1981 1984 1987 1990 1993 1996 1999 2002 2005 2008 2011 2014 2017 2020 2023 Lopez Lake Historical Capacity

PAGE 55

PAGE 56
Lopez Lake Reduction Strategy

PAGE 57
Project Capital Cost
$3M $400K $6M
$350K $500K $500K
Monitoring Well Injection Well Pipelines
UV Reactor UF Rack RO Train