2022 Paving Project Update
Agenda Item 12.A
By: Chad Stoehr, P.E.

Engineer
Meeting Date: November 1, 2022

Background
•On April 20,2021 City Council adopted the 2021 Pavement Management Plan (PMP)which included a projected 5-year Pavement Plan
•The 2022 Paving Project is comprised of:
•Year 1 of the 5-year Pavement Plan
•Other street segments added during the budget development process to •Prevent further deterioration
•Address community outreach received
•Fulfill City Council’s goal of providing exceptional quality of life for our residents •On April 19,2022 City Council awarded a contract to CalPortland Construction for construction of the 2022 Paving Project
•The largest pavement maintenance project in the City’s modern history with an overall project cost of approximately $14 million

Work Completed
New Section of sidewalk and ADA curb ramps at the intersection of Ventana Drive and James Way

Work Completed

Work Completed
New ADA curb ramps in neighborhoods above James Way

Work Completed

Work Completed

Work Completed
Concrete cross gutter at intersection of Solar Way and Bello Street

Work in Progress
Construction of new ADA curb ramps at cross street intersections on Mattie Road

Work in Progress

Work in Progress
Repaving of the Bluff Trail at the end of Indio Drive

Work in Progress

Upcoming Work -2022
•Paving of City Hall Parking lot in late November
•Paving of Mattie Road in late December
Schedule is estimated and based on current construction progress,unforeseen circumstances and weather conditions

Upcoming Work -2023
•New sidewalk and ADA curb ramps on Spyglass Drive under HWY 101 in earlyJanuary •Paving of lower Wadsworth Avenue (Price Street to Bello Street)in mid February •Construction of paver median,parking meter poles and paving of Price Street fromDolliver/HWY 1 to US 101 on/off ramp in early March •Completion of concrete work and paving of streets in neighborhoods above JamesWayinlateMay •Paving of Solar Way in October
Schedule is estimated and based on current construction progress,unforeseencircumstancesandweatherconditions

Upcoming Work -2024
•Paving of upper Wadsworth Avenue (Bello Street to the north end)in Winter •Paving of Ocean Boulevard from Vista del Mar Avenue to Placentia Avenue in Spring
Schedule is estimated and based on current construction progress,unforeseen circumstances and weather conditions