PISMO BEACH COUNCIL AGENDA REPORT
Agenda Item #12.A
SUBJECT/TITLE:
2022 PAVING PROJECT UPDATE
RECOMMENDATION:
No action required; information only.
BACKGROUND:
One of the City Council’s top goals is to “build on the strength of our local community to preserve the City’s ‘Classic California’ charm and ensure an exceptional quality of life for residents.” One of the several priorities for this goal over the next two years is to “Invest in neighborhoods, including road, sidewalk, and park improvements.”
To achieve this goal, the City Council awarded a contract to CalPortland Construction on April 19, 2022, for the construction of the 2022 Paving Project. This is the largest pavement maintenance project in the City’s modern history and includes:
Repaving of Mattie Road from Price Street to the north end Repaving of Ocean Boulevard from Placentia Avenue to Vista Del Mar Avenue Repaving of Price Street from Dolliver/Highway 1 to US 101 on- and off-ramps including new parking meters and paver median from Bay Street to Pomeroy Avenue
Repaving of streets in the neighborhoods off James Way including:
o Capanna Court
o Capanna Lane
o Cima De Colina
o Clydell Court
o Clydell Way
o Coral Circle
o Coral Court
o El Viento
o Highland Drive
o La Colima
o La Floricita
o La Garza
o La Gaviota
o La Puesta del Sol
o Miguelito Lane
o Morgan Drive
o Princessa Lane
o Rancho Pismo Drive
o Reef Court
o Santos Way
Council Agenda 11-1-2022 12.A-1
o Surf Street
o Valley View Drive
o Ventana Drive
o Villa Court
o Vincente Court
o Wave Avenue
o Whitecap Street
o Irish Way
o Limerick Lane
o Oakwood Drive
o Panorama Drive
o Ridge Road
o Shamrock Lane
o Vista Pacific Circle
o White Oak Boulevard
o Christine Way
o Dugan Drive
o Effie Way
o Elaine Way
o Frances Way
o Houston Way
o Margo Way
o Norma Drive
o Crest Drive
o Skyline Drive
o Summit Drive
Repaving of Wadsworth Avenue from Price Street to the north end New sidewalk on Spyglass Drive underneath US 101 from Shell Beach Road to Mattie Road
Repaving of Solar Way from Bello Street to Price Canyon Road including a new concrete cross gutter at Solar Way and Bello Street
New Sidewalk and ADA curb ramps on James Way at Ventana Drive intersection Repaving of the Bluff Trail in Shell Beach
Repaving of the City Hall Parking Lot
Construction began in May 2022 and the project is estimated to be complete in July 2024.
Conclusion and Recommendation
No action is required. Staff will present a current update at the City Council meeting that includes a full update regarding the project’s progress, including work completed, work in progress, and the revised schedule for the remainder of the project.
FISCAL IMPACT:
There is no direct fiscal impact associated with this report.
Council Agenda 11-1-2022 12.A-2
ALTERNATIVES:
None; for information only.
ATTACHMENTS:
None.
Prepared by: Meeting Date: November 1, 2022
Chad Stoehr, P.E., Engineer
Submitted by: Benjamin A. Fine, P.E., Director of Public Works/City Engineer City Manager Approval:
Council Agenda 11-1-2022 12.A-3