04.A Presentation US 101 Pismo Congestion Relief Project Update 2022-11-15

Pismo Beach City Council
November 15, 2022

Document
04.A Presentation US 101 Pismo Congestion Relief Project Update 2022-11-15
Meeting
November 15, 2022
Body
Pismo Beach City Council
Pages
9
Original file
1 KB
Text extracted from the city's file for reading and search. Open the original on portal.laserfiche.com. That file is the official record.

Five Cities Multimodal
Transportation
Network Enhancement
Project
November 15, 2022
Pismo Beach City Council

Challenges
VMT Due to delay on US 101, vehicles will exit the mainline and drive through the local community instead.

DELAY Existing delay on US 101 negatively impacts commuters, transit travel time and emergency response.

BIKE/PED
GAPS
Poor Level of Traffic Stress
Documented and supported public interest in completing the bicycle and pedestrian network

PHYSICAL
CONSTRAINTS Geographically constrained, the corridor is pushed to explore innovative, context sensitive design solutions.

Project Scope

Outcome of Public Engagement
o This segment of 101 is the highest
level of concern
o Preservation of cultural resources
(including Pismo Rock)
o Maintaining rural coastal aesthetic
through project design
o Priority multimodal project
elements

Corridor Conditions-Local
Bike Level of Traffic Stress
Existing Shared Use Path (LTS 1)
Existing Lane Configuration (LTS 4)
Shell Beach Elementary School

Part-Time Travel Lane Layout

Schedule & Funding
Five Cities Multimodal Transportation Network Enhancement Local Funds TCEP SCCP Total Cost
Project Development $11.4 $508k -$12.1
Right of Way $3.5 --$3.5
Construction $4.8 $3.84 $59.8 $68.4
$19.7 million $4.3 million $59.8 million $84 million