Furthermore, with the advent of COVID-19 shelter-at-home orders, traffic demand has been reduced due to many commuters having switched to working from home. With that framework now in place, it is possible that future commuting needs could be greatly reduced from previous projections.

1.5 Comparison of Alternatives
An extensive traffic study was conducted to evaluate various options for their effectiveness in reducing travel delays. A Pismo sub-area cut-out of the Council of Governments’ Traffic Demand Management model was developed to forecast traffic demand. The sub-area Pismo model was developed based on 2018 land use data and validated to 2018 traffic counts. The most recent housing and employment projections for San Luis Obispo County were used as inputs to model future demand.

Several analysis techniques were used to provide the data used to quantify and/or monetize the benefits of each alternative. The performance measures consisted of factors including, but not limited to:
·average travel time
·95th percentile travel time index
·average speed
·travel delay
·number of vehicle trips
·travel distance
·average vehicle occupancy
·average density by segment
·predicted number of collisions by type
Attachment 3
Council Agenda 12-5-2023 12.A-33
Packet Page 284

Chapter 1 Ÿ Proposed Project
Pismo Congestion Relief Pilot Project Ÿ 10
These measures were used to compare and evaluate the operational and safety benefits of each alternative.

Traffic counts and speed data were collected in April 2018 on the southbound mainline and on all on-ramps and off-ramps within the project limits. The data was processed for the weekday (Wednesday and Thursday) and weekend (Friday and Saturday) peak periods from 2:00 p.m. to 7:00 p.m. in 15-minute increments.

Opening year analysis assumed year 2026 conditions; design year was determined to be 2046. Travel demand modeling determined that a 4 percent increase in projected traffic demand would occur with all build alternatives due to traffic diverted from Route 227; therefore, the build alternatives reflect greater traffic volumes than the No-Build Alternative. According to the modeling, freeway operations with all the build alternatives performed better than with the No-Build Alternative. These improvements consist of travel delay reduction, buffer time reduction (a reduction in the additional time a motorist needs to ensure they arrive at their destination at the expected time), improved vehicular flow/speed, and collision reduction through the corridor.

Tables 1-1 through 1-4 show analysis results for expected travel times and speeds for all alternatives for a 6-mile southbound segment from the Avila Beach Drive off-ramp to the Five Cities Drive off-ramp. The information is broken down by opening year (2026) and design year (2046) as well as for weekday and weekend performance. Data on existing conditions is also provided for comparison purposes.

Table 1-1 Year 2026 Weekday Performance Measures
Alternative Average Travel Time
(minutes/vehicle)
Average Speed
(miles/hour)
Buffer Time
(minutes)
Average Level
of Service
Existing 5.9 41.7 11 D
No-Build 6.5 37.4 12.4 E
1 4.8 64.1 9.1 C
1 variation 4.9 64.1 9.4 C
2 4.8 64.5 9.1 C
Table 1-2 Year 2026 Weekend Performance Measures
Alternative Average Travel Time
(minutes/vehicle)
Average Speed
(miles/hour)
Buffer Time
(minutes)
Average Level
of Service
Existing 5.8 39.5 11.6 D
No-Build 6.2 36.9 12.4 E
1 4.6 63.9 9.2 C
1 variation 4.7 63.9 9.5 C
2 4.7 64.3 9.4 C
Attachment 3
Council Agenda 12-5-2023 12.A-34
Packet Page 285

Chapter 1 Ÿ Proposed Project
Pismo Congestion Relief Pilot Project Ÿ 11
Table 1-3 Year 2046 Weekday Performance Measures
Alternative Average Travel Time
(minutes/vehicle)
Average Speed
(miles/hour)
Buffer Time
(minutes)
Average Level
of Service
No-Build 7.1 32.4 13.5 E
1 4.8 63.4 9.2 C
1 variation 4.8 63.4 9.2 C
2 4.8 63.9 9.1 C
Table 1-4 Year 2046 Weekend Performance Measures
Alternative Average Travel Time
(minutes/vehicle)
Average Speed
(miles/hour)
Buffer Time
(minutes)
Average Level
of Service
No-Build 6.5 33.7 13.1 E
1 4.6 62.1 9.3 C
1 variation 4.8 62.1 9.6 C
2 4.7 62.6 9.5 C
Under the No-Build condition, by 2026 motorists can expect severe bottlenecks within the project limits beginning around 2:30 p.m. in the vicinity of Spyglass Drive and the North Price Street off-ramp. Over the next hour, congestion would continue to build, creating backups on the southbound onramps and potentially creating gridlock at adjacent intersections. This can often lead to queue jumping, in which motorists use sequential off-ramps and on-ramps and/or frontage roads to bypass stopped traffic. The congested conditions are predicted to last until about 6:45 p.m.

By 2046, traffic backups within the project limits are predicted to begin by 2:00 p.m. and build continuously throughout the afternoon. Traffic volumes are expected to be so inflated that the freeway and ramps would no longer be able to carry them. Motorists would be forced to use alternative methods to avoid the congestion, which could mean leaving at a different time, taking another route, or cancelling the trip altogether.

Under Alternative 1, at opening year, no bottlenecks are predicted, but there would be some traffic slowing near the end of the existing truck-climbing lane and at the Dolliver Street off-ramp during the weekday between about 4:30 p.m. and 5:00 p.m. On the weekends, traffic slowing would potentially occur only at the end of the truck-climbing lane. The Alternative 1 truck-climbing lane variation would exhibit similar results, but would start about an hour earlier in the day (though for about the same duration). Although this design would extend the truck-climbing lane beyond its current merge point, traffic is still predicted to slow at this location because of the uphill grade. This location also coincides with the first view of the ocean, possibly causing drivers to slow, which could be exacerbating the situation.

Attachment 3
Council Agenda 12-5-2023 12.A-35
Packet Page 286

Chapter 1 Ÿ Proposed Project
Pismo Congestion Relief Pilot Project Ÿ 12
Under Alternative 2, effects on traffic would be similar to that expected with the Alternative 1 truck-climbing variation, with the addition of another brief period of slowing at the Dolliver Street off-ramp beginning around 2:45 p.m. on weekdays.

By year 2046, traffic is still predicted to move relatively smoothly through the project limits with all the build options, but the chance of a bottleneck near Dolliver Street becomes more likely, as does one at the end of the project limits, where Price Street joins US 101.

1.6 Identification of a Preferred Alternative
All of the build options meet the needs and purpose of the project, and the costs for the three are within close range. There was no strong indication by the public for a preferred alternative, but several individuals, as well as the City of Pismo Beach, expressed a desire to eliminate the truck-climbing lane. For the most part, the three build alternatives would have similar environmental impacts. One notable difference is a retaining wall in the median that would be necessary for both Alternative 1 and the truck-climbing lane variation that is not needed for Alternative 2. This wall would create additional hardscape and impact coastal scrub habitat. However, being longer, Alternative 2 would include more lane-use control signals in the median.

Upon completion of the public comment period, and after receiving concurrence from the City of Pismo Beach, the project development team, including the Council of Governments, selected Alternative 2 as the preferred alternative because it provides the longest extent of the part-time travel lane while remaining within the cost range of the other build alternatives. It also would eliminate the truck-climbing lane.

1.7 Alternatives Considered but Eliminated from Further Discussion Prior to the Draft Environmental Impact
Report/Environmental Assessment
Numerous individual traffic management components were evaluated as part of the preliminary design process, either alone or in combination, for their contribution to improving traffic flow. Table 1-5 describes the components that either failed to show an operational improvement or otherwise were rejected.

Attachment 3
Council Agenda 12-5-2023 12.A-36
Packet Page 287

Chapter 1 Ÿ Proposed Project
Pismo Congestion Relief Pilot Project Ÿ 13
Table 1-5 Rejected Design Options
Component Reason for Rejection
Extend existing truck-climbing lane to exit
directly into the Shell Beach Road off-ramp
This would create a “trap lane” and would
maintain truck weaving for those not
wanting to exit the freeway.

Add a third general-purpose full-time travel
lane or a high-occupancy vehicle lane
Traffic demand for additional capacity
occurs during only portions of the day; the
existing configuration manages traffic at an
acceptable level the rest of the time. This
design meets the purpose and need of the
project, but would have excessive cost and
greater community and environmental
impacts.

Reconfigure southbound ramps to add an
on-ramp at Mattie Road, close the
Dinosaur Caves Park on-ramp, and
construct an auxiliary lane between the
new Mattie Road on-ramp and existing
Route 1.

This arrangement would increase commute
times.

End the part-time travel lane just prior to
the Pismo Creek Bridge
This arrangement would increase commute
times and create a bottleneck at the merge
point.

End the part-time travel lane just past the
Pismo Creek Bridge
This arrangement showed no improvement
in traffic management over the proposed
alternatives, but would require widening the
Pismo railroad overhead, with subsequent
added costs and impacts.

Allow continuous entering and exiting of
the part-time travel lane
Most of the traffic using the southbound
lanes in the afternoon is exiting the freeway
south of Pismo Beach. Moving those
vehicles to their own lane reduces the
weaving maneuvers that cause traffic
disturbances.

Build a reversing lane in the median There is insufficient median width for a standard design. It would also adversely
impact Pismo Rock.

1.8 Permits and Approvals Needed
Table 1-6 lists the permits, licenses, agreements, and certifications required for project construction.

Attachment 3
Council Agenda 12-5-2023 12.A-37
Packet Page 288

Chapter 1 Ÿ Proposed Project
Pismo Congestion Relief Pilot Project Ÿ 14
Table 1-6 Permitting and Approving Agencies
Agency Permit/Approval Status
California Department of
Fish and Wildlife
Section 1602 Streambed
Alteration Agreement for
construction within Pismo
Creek
Acquired during final design
of the project.

U.S. Army Corps of
Engineers
Section 404 nationwide permit
for construction within Pismo
Creek
Acquired during final design
of the project.

Central Coast Regional
Water Quality Control
Board
Section 401 Certification for
construction within Pismo
Creek
Acquired during final design
of the project.

U.S. Fish and Wildlife
Service
Section 7 formal consultation
and Biological Opinion for the
tidewater goby and goby critical
habitat, and Programmatic
Biological Opinion for the
California red-legged frog
Complete.

National Marine Fisheries
Service
Section 7 formal consultation
and Biological Opinion for the
Central California Coast
steelhead and steelhead critical
habitat
Complete.

California Transportation
Commission Funding approval
Acquired prior to
advertising project for
contract bids.

City of Pismo Beach Coastal zone development
permit
Acquired during final design
of the project.

County of San Luis
Obispo
Coastal zone development
permit
Acquired during final design
of the project.

California Coastal
Commission
Coastal zone development
permit
Acquired during final design
of the project.

State Historic Preservation
Officer
Programmatic Agreement and
Historic Properties Treatment
Plan
Complete
Attachment 3
Council Agenda 12-5-2023 12.A-38
Packet Page 289

Pismo Congestion Relief Pilot Project Ÿ 15
Chapter 2 Affected Environment,
Environmental Consequences,
and Avoidance, Minimization,
and/or Mitigation Measures
As part of the scoping and environmental analysis done for the project, the following environmental issues were considered, but no adverse impacts were identified. As a result, there is no further discussion of these issues in this document. ·Existing and future land use—The project occurs within the freeway corridor and would not affect land use. It is consistent with the US 101 Comprehensive Multi- modal Corridor Plan, which is the umbrella plan for the US 101 corridor in San Luis Obispo County, as well as the Council of Governments’ 2019 Regional Transportation Plan. The project is not consistent with all policies in the City of Pismo Beach Local Coastal Plan. This topic is discussed in section 2.1.1 Coastal Zone.
·Timberland and farmland—There is no timberland or agricultural land within the project limits.
·Environmental Justice—Adverse impacts from the project will be fairly consistent along its length, but will decrease with increasing distance from the highway, while all residents within the project area would have equal opportunity to benefit from congestion relief. Construction-related impacts from noise, traffic delays, and air quality emissions would be temporary and would be spread out along the corridor, not concentrated in any one location for long periods of time. The 2019 American Community Survey 5-year census data indicate that, relative to the general Pismo Beach population, the population within the project study area does not contain higher-than-average concentrations of traditionally underserved groups. No minority or low-income populations that would be adversely affected by the project have been identified. Therefore, this project is not subject to the provisions of Executive Order 12898. ·Wild and Scenic Rivers—There are no wild or scenic rivers within the project limits. ·Parks and recreation—The project has no impact directly or indirectly on parks or recreational activities.
·Growth—The project uses an existing transportation corridor and does not provide for additional access to planned or existing communities. ·Community character and cohesion—The project expands into the median and therefore does not impact existing communities.
·Utilities and emergency services—No additional services or utilities would be required by the project.

Attachment 3
Council Agenda 12-5-2023 12.A-39
Packet Page 290

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 16
·Traffic and transportation/pedestrian and bicycle facilities—The project is expected to have a beneficial impact on transportation by reducing delay. The freeway does not support pedestrian or bicycle traffic, and therefore there would be no effect on these modes.
·Geology, soils, seismicity and topography—As a standard procedure, the freeway widening would be constructed on a compacted base of imported material. Based on site-specific testing, bridges would be constructed to withstand the maximum credible ground accelerations projected to occur during a seismic event.
·Paleontology—The two geologic formations within the project limits are shown as having a low to zero potential for encountering sensitive paleontological resources in the Paleontological Sensitivity Mapping Project published by Caltrans and California State University, Fresno in June 2000. ·Hazardous waste and materials—The project contains no hazardous waste.

Construction activities could encounter lead paint, lead in the soil, and/or asbestos. These materials would be handled per standard construction specifications and taken to an appropriate facility.
·Air quality—The project is not located in a non-attainment or maintenance area for federal levels of ozone, nitrogen dioxide, carbon monoxide, or small particulate (under 2.5 or 10 microns) per the U.S. Environmental Protection Agency’s Green Book listing of non-attainment areas, therefore air quality conformity does not apply. San Luis Obispo County is non-attainment for state standards for ozone and small particulate under 10 microns, but the project is included in the Council of Governments’ 2019 Regional Transportation Plan and programmed in the 2018 Regional Transportation Improvement Program, both of which are consistent with the 2001 Clean Air Plan.

2.1 Human Envir onment
Coastal Zone
Regulatory Setting
This project has the potential to affect resources protected by the Coastal Zone Management Act of 1972, which is the main federal law enacted to preserve and protect coastal resources. The act sets up a program under which coastal states are encouraged to develop coastal management programs. States with an approved coastal management plan are able to review federal permits and activities to determine if they are consistent with the state’s management plan.

California has developed a coastal zone management plan and has enacted its own law, the California Coastal Act of 1976, to protect the coastline. The policies established by the California Coastal Act are similar to those for the Coastal Zone Management Act. They include the protection and expansion of public access and recreation; the protection, enhancement, and restoration of environmentally Attachment 3
Council Agenda 12-5-2023 12.A-40
Packet Page 291

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 17
sensitive areas; the protection of agricultural lands; the protection of scenic beauty; and the protection of property and life from coastal hazards. The California Coastal Commission is responsible for implementation and oversight under the California Coastal Act.

Just as the federal Coastal Zone Management Act delegates power to coastal states to develop their own coastal management plans, the California Coastal Act delegates power to local governments to enact their own local coastal programs.

The project is subject to the local coastal programs for San Luis Obispo County and the City of Pismo Beach, as well as being within the original jurisdiction of the Coastal Commission. The local coastal programs contain the ground rules for development and protection of coastal resources in their jurisdiction consistent with the California Coastal Act goals. A Federal Consistency Certification will be needed as well. The Federal Consistency Certification process will be initiated prior to the final environmental document and will be completed during final design.

Affected Environment
Most of the project lies within the coastal zone and would require a permit for construction from each of the jurisdictional agencies. The portion of the project alignment within the coastal zone is almost entirely within the limits of the City of Pismo Beach, except for the short northern segment near Avila Beach Drive. The California Coastal Commission has retained original jurisdiction in the area surrounding Pismo Creek. The project is therefore subject to the policies of the California Coastal Act and the local coastal programs of both the County of San Luis Obispo and the City of Pismo Beach.

The County of San Luis Obispo General Plan includes the Land Use Element and Local Coastal Program that was adopted by the County Board of Supervisors and certified by the California Coastal Commission in 1988 and was last updated in 2007. The Land Use Element contains a local coastal program policy document outlining coastal plan policies for the county. The project is within the San Luis Bay Planning Area, which has a separate report describing land use policies and development standards for communities in the planning area. The San Luis Bay Plan was adopted and certified in 1988 with the County General Plan and was last updated in 2009.

The City of Pismo Beach General Plan and Local Coastal Program was adopted by the City Council in 1992 and certified by the California Coastal Commission in 1993; the plan was last updated in April 2014. The City and County local coastal programs generally feature the same themes and principles to allow for coordinated planning efforts.

The following is a list of the policies from Chapter 3 of the California Coastal Act (Resource Planning and Management Policies), the County of San Luis Obispo’s Local Coastal Program and San Luis Bay Area Plan, and the City of Pismo Beach’s General Plan and Local Coastal Program. The relevant policies from each plan Attachment 3
Council Agenda 12-5-2023 12.A-41
Packet Page 292

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 18
have been grouped together by subject. Policies for resources that would not be affected by the project, such as agricultural lands, have not been included.

Public Access and Circulation
California Coastal Act
·30211—Development not to Interfere with Access
·30252—Maintenance and Enhancement of Public Access
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Public Works Chapter
·Policy 2—New or Expanded Public Works Facilities
Coastal Plan Policies, Shoreline Access Chapter
·Policy 8—Minimizing Conflicts with Adjacent Uses
City of Pismo Beach Local Coastal Program
·Principle P-1—Balanced Transportation
·Policy C-1—Street Classification Plan and Design Standards ·Policy C-2—Freeway US 101—6 Lanes
·Policy C-8—Highway System Plan and Traffic Improvements Visual and Scenic Resources
California Coastal Act
·30251—Scenic and Visual Qualities
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Visual and Scenic Resources Chapter ·Policy 1—Protection of Visual and Scenic Resources
·Policy 5—Landform Alterations
·Policy 7—Preservation of Trees and Native Vegetation
San Luis Bay Area Plan
·Land Use, Rural Area Program 2—Viewshed Protection
City of Pismo Beach Local Coastal Program
·Principle P-6—The Big Three
·Principle P-7—Visual Quality is Important
·Policy D-10—Parking Lots and Large Asphalt Areas
·Policy D-13—Freeway Landscaping
Attachment 3
Council Agenda 12-5-2023 12.A-42
Packet Page 293

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 19
·Policy D-14—Public Facilities
·Policy D-17—Native and Drought Tolerant Landscaping
·Policy D-1—View Corridor Protection
·Policy D-20—Special Landscape Features
·Policy D-23—US 101 Freeway
·Policy D-28—Visual Quality
·Policy LU-Q-3—Development Considerations, Minimize Impact on Foothills ·Policy LU-Q-4d—Development Considerations, Vegetation
Archaeological and Paleontological Resources
California Coastal Act
· 30244—Archaeological or Paleontological Resources
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Archaeology Chapter
·Policy 1—Protection of Archaeological Resources
·Policy 4—Preliminary Site Survey for Development within Archaeologically Sensitive Areas
·Policy 5—Mitigation Techniques for Preliminary Site Survey before Construction ·Policy 6—Archaeological Resources Discovered during Construction or through Other Activities
City of Pismo Beach General Plan and Local Coastal Program ·Policy CO-5—Protect Archaeological Resources
·Policy CO-6—Construction Suspension
·Policy LU-9—Chumash Cultural Resources Preservation
·Policy LU-Q-4b—Development Considerations, Archaeology Hazards and Hazardous Waste
California Coastal Act
·30232—Oil and Hazardous Substance Spills
·30253 a, b—Minimization of Adverse Impacts
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Hazards Chapter
·Policy 2—Erosion and Geologic Stability
·Policy 3—Review in Hazards Area
Attachment 3
Council Agenda 12-5-2023 12.A-43
Packet Page 294

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 20
City of Pismo Beach Local Coastal Program
·Principle P-23—Protection of Life and Safety
·Policy S-1—Risk Identification
·Policy S-9—Restrictions on Development Within the 100-Year Floodplain ·Policy S-11—Development Review in Hazardous Overlay Zone Air Quality and Greenhouse Gas
California Coastal Act
·30253 c, d—Minimization of Adverse Impacts: pollution; energy conservation City of Pismo Beach Local Coastal Program
·Principle P-4—Clean Air—A Must
·Policy CO-4—Trip Reduction
Noise
City of Pismo Beach Local Coastal Program
·Principle P-20—Noise Levels
·Policy LU-Q-4c—Development Considerations, Noise
Water Quality and Erosion
California Coastal Act
·30231—Biological Productivity; Water Quality
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Coastal Watersheds Chapter:
·Policy 1—Preservation of Groundwater Basins
·Policy 8—Timing of Construction and Grading
·Policy 9—Techniques for Minimizing Sedimentation
·Policy 10—Drainage Provisions
·Policy 11—Preserving Groundwater Recharge
City /of Pismo Beach Local Coastal Program
·Principle P-24—Maintain Unique Physiographic Characters ·Policy LU-Q-4a—Development Considerations, Water Runoff and Erosion Environmentally Sensitive Habitat Areas; Biological Resources California Coastal Act
·30233—Diking, Filling or Dredging
Attachment 3
Council Agenda 12-5-2023 12.A-44
Packet Page 295

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 21
·30236—Water Supply and Flood Control
·30240—Environmentally Sensitive Habitat Areas; Adjacent Developments County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Environmentally Sensitive Habitats Chapter:
·Policy 1—Land Uses Within or Adjacent to Environmentally Sensitive Habitats ·Policy 3—Habitat Restoration
·Policy 7—Protection of Environmentally Sensitive Habitats ·Policy 13—Diking, Dredging or Filling of Wetlands
·Policy 16—Adjacent Development
·Policy 20—Coastal Streams and Riparian Vegetation
·Policy 21—Development in or Adjacent to a Coastal Stream ·Policy 25—Streambed Alteration
·Policy 26—Riparian Vegetation
·Policy 27—Stream Diversion Structures
·Policy 28—Buffer Zone for Riparian Habitat
City of Pismo Beach Local Coastal Program
·Principle P-2—Natural Resources—Key Foundation of the City ·Principle P-13—Natural Resource Preservation
·Policy CO-13—Oak Tree Protection
·Policy CO-14—Riparian Habitats
·Principle CO-21—Pismo Creek Protection
·Policy CO-28—Natural Drainage Channels
·Policy D-12—Development Considerations, Water Runoff and Erosion ·Policy LU-L2—Pismo Creek
Required Permits
County of San Luis Obispo Local Coastal Program
Coastal Plan Policies, Environmentally Sensitive Habitats Chapter:
·Policy 2—Permit Requirement
·Policy 22—Fish and Game Review of Streambed Alteration ·Policy 23—County Review of Coastal Stream Projects
Attachment 3
Council Agenda 12-5-2023 12.A-45
Packet Page 296

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 22
Coastal Plan Policies, Public Works Chapter:
· Policy 7—Permit Requirements
Environmental Consequences
Caltrans would obtain permits for development within the coastal zone from the County of San Luis Obispo, the City of Pismo Beach, and the California Coastal Commission during final project design, unless a combined permit were agreed upon by one or more of the jurisdictional agencies. The permit process would include a public hearing and comment period; any permit issued could be appealed to the Coastal Commission. Potential inconsistencies with the local coastal plan policies could require a Local Coastal Plan amendment. The jurisdictional agencies would make a determination on consistency during the permitting process.

Public Access and Circulation
By improving traffic flow, the project would improve coastal access to Pismo Beach and the surrounding coastal communities. The added freeway width from the part- time travel lane would accommodate future freeway widening. Widening through this segment is not currently planned, but the project would improve the predicted level of service beyond the No-Build condition through the year 2046. The proposed park-and-ride lot would provide additional parking for the Pismo Preserve.

Visual and Scenic Resources
The project would reduce the visual quality of US 101 through the project limits.

Mitigation measures to reduce impacts have been incorporated, but they would not fully mitigate the anticipated changes to the visual environment. Therefore, the project could be found inconsistent with coastal policies related to visual and scenic resources. As discussed in section 2.1.2 Visual/Aesthetics, the project would further urbanize the corridor through various components, including the installation of new signing and signals, an increase in pavement and other hardscape, and a loss of mature vegetation. Soundwalls, which would reduce freeway noise but also block coastal views, are under consideration for the project. The US 101 corridor through the project limits is eligible for classification as a State Scenic Highway, but the degree of urbanization that has been introduced since obtaining that status has eliminated the potential for official listing. Thus, the project would not change the eligibility status of the highway. The City of Pismo Beach, however, does classify the corridor as a Pismo Beach scenic highway in its Local Coastal Program.

Archaeological and Paleontological Resources
The project has been designed to avoid cultural resources, such as Pismo Rock, where feasible, but the project is still expected to have an adverse impact on cultural resources. Research conducted to date and completion of National Historic Preservation Act Section 106 processes would address the policies noted above. A full discussion on this subject can be found in section 2.1.3, Cultural Resources.

Attachment 3
Council Agenda 12-5-2023 12.A-46
Packet Page 297

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 23
Hazards and Hazardous Waste
Potential hazards for the project have been identified in the hazardous waste study, the Storm Water Data Report, and the Location Hydraulic Study. The project would be constructed using current design standards to minimize hazards from flooding, seismic events, or the release of hazardous substances. Widening the Pismo Creek Bridge would require adding structures within the 100-year flood zone, but this would not be a significant encroachment and would not affect water levels.

Air Quality and Greenhouse Gas
Vehicle miles traveled would increase between 7 and 10 percent for all the build options compared to the No-Build scenario, creating an overall increase in greenhouse gas emissions. The project would partially offset the increase in vehicle miles traveled through construction of a park-and-ride lot. See also section 3.3.4 Greenhouse Gas Reduction Strategies.

Noise
The project is expected to increase the exterior noise level for some residents near the freeway as a result of increased traffic speeds. Anticipated noise levels at these locations are expected to exceed the levels identified by the City of Pismo Beach, therefore the project could be found inconsistent with local policy. Soundwalls would mitigate these noise levels at some of the locations, but would not necessarily be included in the final project design. See section 2.2.3 Noise for more information.

Water Quality and Erosion
The project includes measures to treat storm water runoff and limit erosion; details would be included in the Storm Water Pollution Prevention Plan prepared prior to construction. See section 2.2.1 Hydrology and Floodplain and section 2.2.2 Water Quality and Storm Water Runoff for more information.

Environmentally Sensitive Habitat Areas; Biological Resources Pismo Creek is an environmentally sensitive habitat area within the project limits that hosts newly established riparian vegetation planted as mitigation for the recent project to repair scour under the bridge. The creek bed has been designated as critical habitat for the tidewater goby and south-central California steelhead, and contains habitat for the California red-legged frog and western pond turtle. The project would result in minor permanent impacts to the creek channel as a result of sheet piling. All other creek impacts are temporary. See section 2.3, Biological Environment for more information.

Required Permits
See Table 1-6 Permitting and Approving Agencies for permits that would be acquired during project design.

Attachment 3
Council Agenda 12-5-2023 12.A-47
Packet Page 298

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 24
Avoidance, Minimization, and/or Mitigation Measures
Measures that would avoid, minimize, or mitigate impacts as a result of the project are described in detail in Chapter 2 of this document. No specific measures have been included to address coastal policies, but the coastal development permits could be issued with conditions.

Visual/Aesthetics
Regulatory Setting
The National Environmental Policy Act (NEPA) of 1969, as amended, establishes that the federal government use all practicable means to ensure all Americans safe, healthful, productive, and aesthetically (emphasis added) and culturally pleasing surroundings (42 U.S. Code 4331[b][2]). To further emphasize this point, the Federal Highway Administration, in its implementation of NEPA (23 U.S. Code 109[h]), directs that final decisions on projects are to be made in the best overall public interest taking into account adverse environmental impacts, including among others, the destruction or disruption of aesthetic values.

The California Environmental Quality Act (CEQA) establishes that it is the policy of the state to take all action necessary to provide the people of the state “with…enjoyment of aesthetic, natural, scenic and historic environmental qualities” (California Public Resources Code Section 21001[b]).

California Streets and Highways Code Section 92.3 directs Caltrans to use drought- resistant landscaping and recycled water when feasible and incorporate native wildflowers and native and climate-appropriate vegetation into the planting design when appropriate.

Affected Environment
Reference: Visual Impact Assessment, May 2020.

The region is part of a coastal plateau in the southern coastal area of San Luis Obispo County. The landform of the region is characterized by a narrow marine terrace bordered by the beach and Pacific Ocean to the west and the hills to the east. These landforms are viewed in context with one another within the area. The regional topography produces views for the highway traveler ranging from close-in views of the hillsides to the east, to wide open panoramas of the Pacific Ocean.

Pismo Beach sits along a narrow coastal plateau between low-lying hills and the Pacific Ocean. The inland hills are visible as they rise above the community to the northeast and define the horizon in that direction. The project area through the US 101 corridor is generally well-landscaped, and within the project limits the Pacific Ocean can be seen in the distance from the elevated highway mainline. Throughout the freeway corridor, blue-water ocean views and the inland hillsides play an important role in establishing the visual character and quality of the area. Situated in the median between the Price/Dolliver southbound off-ramp and the North Pismo Attachment 3
Council Agenda 12-5-2023 12.A-48
Packet Page 299

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 25
separation at Mattie Road is a large geographic landmark known locally as the Pismo Rock, seen in Figure 2-1.

Figure 2-1 Pismo Rock as Seen Looking Northeast from Price Street The surrounding area is mostly developed, with commercial, residential, and recreational uses within sight of the project. Visible highway elements include concrete median barrier and metal safety barriers, signs, lighting, call boxes, and markers, as well as the vehicular traffic, at times heavy. Overhead utility poles and wires also contribute to the view along the corridor, mostly seen parallel to the highway on the frontage roads. In this section of US 101, development has a moderately high visual presence in the landscape. Throughout much of this section of the freeway, the scale and frequency of structures and other built amenities, though visible, do not dominate views of the Pacific Ocean when seen in the context of the overall landscape. In addition to buildings, existing vegetation also blocks some of the views of the Pacific Ocean throughout the project area.

Several residences sit on the hillside east of and above the project site. These hillsides and areas to the east of the highway are generally populated by sagebrush and coyote brush, with occasional eucalyptus trees, palm trees, and cypress trees.

Residences also sit to the west and below the freeway, mixed with hotels and commercial developments. In these areas, mature ornamental landscaping is prevalent with palm trees seen along the skyline. Between the southbound outside lane and the local frontage road, there are low mounding shrubs, ornamental trees, and cypress trees.

Although US 101 through the project area is not an officially designated scenic highway, it is on the statutory list of highways eligible for scenic designation in the State Scenic Highway System. An official designation would require nomination by Attachment 3
Council Agenda 12-5-2023 12.A-49
Packet Page 300

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 26
the local jurisdiction, but due to the substantial amount of urban development throughout the corridor, it no longer meets the criteria required to become officially designated. Nevertheless, the quality of the existing visual environment through the project area is still moderately high. The low hills meeting the marine terrace with a view to the Pacific Ocean create an attractive setting for the freeway. The project site contributes to the generally well-landscaped roadside of the freeway corridor and helps establish a vegetated character for the City of Pismo Beach and surrounding coastal communities.

For evaluation purposes, the project area was divided into two landscape units.

These units are based on distinct zones that have certain common visual characteristics. The main unit for this project is the coastal unit, which runs from where US 101 passes over the Coast Range to the southern limits of the project.

Ocean and coastal views are significant scenic elements within this unit, but it is also defined by its urban and semi-urban context through the commercial core and residential areas of Shell Beach and Pismo Beach. The second unit, or inland unit, is the segment between the northern end of the project limits and the Coastal Range pass. There are no coastal views within this unit, rather it is defined by rolling hills east and west of the freeway within a semi-rural context.

Environmental Consequences
Implementation of the project would result in substantial visual changes throughout much of the freeway corridor. The project includes numerous components that would impact the visual character of the area:
·additional lane paving
·additional gore paving
·additional vehicle pull-outs for service vehicles
·paved median and concrete median barrier at a new height ·a park-and-ride lot
·bridge widening at four locations and bridge slope paving ·additional signs and signals
·retaining walls
·loss of skyline trees and freeway landscaping
Each build alternative and variation include additional paving, barriers, retaining walls, slope paving, and other hardscape elements. Collectively, these features would substantially increase the visual scale and engineered urban character of the project corridor. The visual appearance would be of a much larger-scale freeway facility. New lane striping and other lane markings, as well as the new signals and signing, would further draw attention to the uniqueness of the part-time travel lane and increase the visual clutter of the corridor.

Attachment 3
Council Agenda 12-5-2023 12.A-50
Packet Page 301

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 27
To manage the part-time travel lane, 30-foot-tall median overhead lane-use control signals would be installed at approximately 2,300-foot intervals and would be visible to all motorists. (Alternative 1 and the truck-climbing variation would likely need 8 of these signal and pole systems, and 11 for Alternative 2. See Figure 1-3 for a representative example.) The signal poles would support the electronic signal panel, a closed-circuit television camera, and a regulatory sign. Where visible, these signal pole systems, although somewhat narrow in profile, would add visual clutter and adversely affect the quality and character of the view. Additional roadside signs providing advanced notice of the part-time travel lane and the schedule of operation would contribute to the loss of visual character due to the number of signs and signals. Potential vegetation removal or pruning required for placement of roadside signs would further reduce visual quality.

The four existing bridge structures within the project limits would be widened to the inside to accommodate the new part-time travel lane. Current safety standards would require replacing the existing inside bridge rail with new, taller, and bulkier rail. This would result in each of these structures having bridge rails of a different size and shape on opposite sides of the same bridge. The visual effect would be an architectural inconsistency and aesthetic degradation of each bridge structure.

All build options would require a retaining wall between the freeway and Price Street (Route 1) where the lanes are being shifted to the outside to avoid impacts to Pismo Rock. This retaining wall would be approximately 1,200 feet long, varying in height from about 5 feet to about 15 feet. The 36-inch-high safety barrier that would sit atop the wall would further increase the apparent wall height as seen from Price Street. A second retaining wall in the freeway median would be required with Alternative 1, as well as the truck-climbing variation, in the vicinity of Beachcomber Drive, about 0.5 mile north of Spyglass Drive, where widening for the part-time travel lane begins. This wall would be about 500 feet long and about 15 feet tall at its highest level; it would replace a heavily vegetated slope that contains large shrubs and mature trees. When the part-time travel lane is open, there would be only a 2-foot shoulder between the travel lane and the wall, creating an even more imposing structure for motorists.

A dirt lot next to Price Street at the Mattie Road undercrossing, currently being used as an informal parking lot, would be transformed into a formal park-and-ride facility by creating a paved parking and pedestrian area. The lot could also include bike parking and bike boxes, shade trees for parking, vegetative swales to manage stormwater, and new landscaped areas. Because informal parking already occupies the site, the proposed changes would not introduce a new use. However, the other undefined site amenities such as lighting, shade trees, and other elements have the potential to affect views from US 101 to the ocean, and to affect views from Shell Beach Road toward the inland hills.

Some degree of existing freeway landscaping is found throughout much of the project’s length. At certain locations, particularly in the median, the vegetation includes mature and skyline trees and dense shrubs. Along other sections of the Attachment 3
Council Agenda 12-5-2023 12.A-51
Packet Page 302

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 28
freeway corridor, the planting is sparse and at times has a weedy appearance. This, however, still adds to the vegetative character of the corridor as well as reduces views of the freeway from the community. In areas where the existing planting is larger and well-established, the combination of more paving, new walls and barrier, and plant removal would affect the vegetated character and increase the visual scale of the freeway facility. With each of the alternatives and variations, the project would reduce the vegetative character of the corridor, though in some areas removing existing planting could potentially open up views to the coast. The project would include new landscaping, but for safety reasons only wider areas or locations behind safety barrier would accommodate trees or large shrubs. At some of the currently weedy locations, new planting would potentially create a more unified look.

Impacts to visual quality were assessed in terms of the visual resource change that would occur as a result of the project. Three characteristics were used to rate the existing visual quality of the project area to compare it to the expected conditions post-construction: vividness, intactness, and unity. Vividness is the visual power or memorability of the landscape components as they combine in striking and distinctive visual patterns. Intactness is the visual integrity of the landscape and its freedom from non-typical encroaching elements. If all the various elements of a landscape seem to “belong” together, there will be a high level of intactness. Unity is the visual harmony of the landscape considered as a whole. Unity represents the degree to which potentially diverse visual elements maintain a coherent visual pattern.

Evaluations were conducted from the perspective of two viewer groups: those with views from the freeway and those with views of the freeway. The group with views from the freeway would be made up entirely of individuals using motorized transportation at freeway speeds. In general, highway users in motor vehicles will perceive the area as a cumulative sequence of views and may not focus on specific roadway features. In contrast, those with views of the freeway would be experiencing more sustained views from a stationary location or a slower method of travel.

Seven observer viewpoints were considered during the evaluation: 5 from the coastal unit and 2 from the inland unit. Both inland unit observer viewpoints were from US 101; the observer viewpoints within the coastal unit were a combination of views to and from the freeway. These viewpoints are shown in the following photos, first from the existing viewpoint and then from how the same view might look if the project were constructed. It should be noted that the photo simulations are representative images only and not exact views of how the project would appear if constructed. They are included to give a general idea of how the project components might appear in relation to the surrounding landscape.

Observer Viewpoints 2 and 4 are from two of the three locations where a soundwall is being considered. Soundwalls are not a main component of the project; they do not address the purpose of or need for the project, but rather are secondary features being considered to address the adverse noise impacts expected to occur as a result of the project. Therefore, they are discussed at the end of this section.

Attachment 3
Council Agenda 12-5-2023 12.A-52
Packet Page 303

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 29
Observer Viewpoint 1—From US 101 near Pismo Rock, looking southbound Figure 2-2 Existing View
The existing view from US 101 in this area is considered high in visual quality due to several factors. The proximity and visual dominance of Pismo Rock substantially increases the memorability of the view. Views of the Pacific Ocean and distant coastline extending to Point Sal also add to the memorability of the scene. The scale and type of development along the ocean side of the highway help establish a “beach town” character and contribute to a relatively high degree of both visual intactness and unity.

Figure 2-3 Built View, All Alternatives
At this location, US 101 would be widened to the outside, requiring a retaining wall and concrete barrier along Price Street. A new concrete barrier would also be built along the base of Pismo Rock at the edge of the inside shoulder. The added freeway pavement in this area would reduce visual quality and the vividness rating by creating Attachment 3
Council Agenda 12-5-2023 12.A-53
Packet Page 304

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 30
a more urban character in the immediate vicinity of the scenic Pismo Rock. The concrete barrier lining both sides of the freeway would further affect the visual connection to the coastal setting. Visual access to the beach community and ocean would be partially reduced, having a negative result to both visual unity and intactness.

Observer Viewpoint 3—From northbound US 101 north of Spyglass Drive, looking toward Shell Beach
Figure 2-4 Existing View
The high-quality views along the section of US 101 represented by Observer Viewpoint 3 are the result of sweeping ocean and coastal vistas of San Luis Bay and Avila Beach, combined with views of Ontario Ridge and inland hillsides. These visual characteristics combine for a high vividness rating. Roadside development is somewhat less visually dominant through this area, which adds to the higher intactness and unity determinations.

Figure 2-5 Built View, All Alternatives
This image is representative of the project from the northbound lanes. Throughout most of the project limits, the existing 32-inch-high metal median barrier would be replaced with taller, 42-inch concrete barrier. The existing ground below the barrier Attachment 3
Council Agenda 12-5-2023 12.A-54
Packet Page 305

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 31
would likely be raised to meet current cross-slope safety standards, resulting in a cumulative increase of top-of-barrier height of at least 10 inches over what currently exists and reducing views of the Pacific Ocean, San Luis Bay, Avila Beach, and the coastline. Accordingly, the overall memorability of the scene would be reduced, though the existing views of the distant hills would remain largely intact. Lane- control signals, as seen in the photo simulation, would be installed in the median every 2,300 feet at minimum throughout the project limits. Where visible, these signals, though somewhat narrow in profile, would add visual clutter and reduce the intactness and unity rating of the viewshed.

In this area, the Alternative 1 variation would extend the truck-climbing lane. From northbound US 101, views of the coast and/or of the extended truck-climbing lane would depend on the height of the viewer’s vehicle and the lane being traveled.

Viewers in taller vehicles traveling in the inside lane would have minimal view reduction, but would see the added pavement of the southbound extended truck- climbing lane. Alternatively, those in shorter vehicles or those traveling in the outside lane would experience a greater loss of coastal views, but also not readily see the southbound truck-climbing lane. From southbound US 101, the closer proximity of the extended truck-climbing lane would cause a decrease in the visual unity and intactness ratings for the Alternative 1 truck-climbing lane variation.

Observer Viewpoint 5—From Mattie Road near Valencia Drive, looking northwest Figure 2-6 Existing View
This view is from the hills above the freeway. The generally elevated position of Mattie Road provides for scenic vistas of the Pacific Ocean, the coastline from Pecho Hill to Point Sal, and the beach communities below. Although US 101 is a visually detracting element in the mid-ground, the overall visual quality and character are highly rated. Accordingly, the memorability of the vista is high. Along certain sections of Mattie Road, the elevation dips and ocean views are less available, and either vegetation and/or existing development are more dominant.

Attachment 3
Council Agenda 12-5-2023 12.A-55
Packet Page 306

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 32
Views to the east are mostly defined by the adjacent hillsides, although residential and some commercial development blocks lower portions of the slopes. The intactness and unity of the views from Mattie Road are considered above average as they offer a panoramic view of the coastal beachside community.

Figure 2-7 Built View, All Alternatives
At this location, the project would add the part-time travel lane in the southbound direction and replace the existing concrete median barrier with a new, taller one.

The 30-foot-tall lane control signals and camera poles would be seen in the median at between 7 and 10 locations along the freeway. If a soundwall were constructed at this location, this image shows how it could appear from this vantage point.

Generally, because of the lower elevation of US 101, the project elements would be below the main line-of-sight of viewpoints along Mattie Road. The new part-time travel lane, the median barrier, and the soundwall, were it constructed, would appear somewhat more urban than the existing condition. Although the control signals and camera poles would be relatively narrow in visual profile and not block a substantial percentage of the vista, their presence would contribute to an increase of visual clutter and reduction of vividness, unity, intactness, and character.

Attachment 3
Council Agenda 12-5-2023 12.A-56
Packet Page 307

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 33
Observer Viewpoint 6—From US 101 south of Avila Beach Drive, looking southbound
Figure 2-8 Existing View
The visual quality along this section of US 101 is based mostly on the topography rising from both sides of the freeway, the generally sparse development, and its transition to the scenic panorama of the Pacific Ocean and the coastline as it opens up to the south. This sequential viewing experience creates a highly memorable and vivid quality. The visual character of both the natural coastal landscape combined with beach community in the distance allows for a fairly high degree of visual harmony, intactness and unity.

For Alternative 1 and the truck-climbing lane variation, the proposed part-time travel lane would not begin until a point south of this Observer Viewpoint, so the viewpoint after construction would be the same as existing.

Figure 2-9 Built View, Alternative 2
Attachment 3
Council Agenda 12-5-2023 12.A-57
Packet Page 308

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 34
As seen from this Observer Viewpoint, the changes resulting from construction of Alternative 2 would include the part-time lane, replacement of the existing metal median barrier with taller concrete barrier, and added lane control signals.

Alternative 2 would not add any outside barriers or wall at this location, and would leave the scenic vistas of the ocean, coastline, hillsides and community relatively intact. The additional pavement and concrete median barrier would create a more urbanized appearance, and the 30-foot-tall lane control signal and camera pole would increase visual clutter. The electronic nature of the signal would draw attention to the apparatus and its detracting character. As a result, the vividness, intactness and unity of the view would be somewhat diminished.

Observer Viewpoint 7—From US 101 south of San Luis Obispo Creek Bridge, looking southbound
Figure 2-10 Existing View
As seen from Observer Viewpoint 7, the view is dominated by the landform of the ridgeline and hills on each side of the highway. The natural patterns of native vegetation on the surrounding hills and along San Luis Obispo Creek add to the relatively high visual quality, intactness, and unity determinations. Though this type of landscape is somewhat typical of the inland landscape assessment unit, the memorability of this view is increased by the proximity of the dramatic landforms to the highway.

Similar to Observer Viewpoint 6, for Alternative 1 and the truck-climbing lane variation, the proposed part-time travel lane would not begin until a point south of this Observer Viewpoint, so the viewpoint after construction would be the same as existing.

Attachment 3
Council Agenda 12-5-2023 12.A-58
Packet Page 309

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 35
Figure 2-11 Built View, Alternative 2
As seen from Observer Viewpoint 7, Alternative 2 would begin transitioning to the part-time travel lane just south of the bridge. The existing metal median barrier would be replaced with taller concrete barrier, and lane control signals would be added. Other than the lane control signal and camera, this alternative would leave the views of the surrounding hills and vegetation relatively intact. The most noticeable aspects of the project would be the additional pavement in the distance, the concrete median barrier, which would create a more urbanized appearance, and the 30-foot-tall lane control signal and camera pole, which would increase visual clutter. The elevation of the surrounding topography would reduce the extent to which the signal would silhouette above the sky as seen from the highway. As seen from Observer Viewpoint 7, Alternate 2 would result in a minor reduction of the vividness, intactness and unity ratings.

The following two observer viewpoints show how a soundwall could impact the visual quality of the surrounding area, both from the freeway and from the local roads.

Soundwalls
Soundwalls were considered at three locations to mitigate noise impacts from the project. (See section 2.2.3 Noise for more information.) The soundwalls at the two southbound locations were dropped from the project because they would have blocked ocean views and thereby have been inconsistent with the local coastal plan. The soundwall at the northbound location could be designed into the project, depending on the outcome of further discussions with the City of Pismo Beach during the permitting process. (See section 4.1.4 Soundwalls for more information.) Attachment 3
Council Agenda 12-5-2023 12.A-59
Packet Page 310

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 36
Preliminary design shows the soundwalls would likely be between 8 and 12 feet tall and constructed of masonry block. Landscaping or other methods would be used to deter graffiti. Soundwalls that were constructed with the project would not only affect the visual character of the area, but two of the walls would also block high- quality scenic views. Soundwall 6 (south of Wadsworth Avenue) would not reduce scenic views beyond what is currently blocked by existing landscaping and intervening development. It should be noted that the many high-quality ocean and coastal views currently available throughout the project limits would not be affected by the project, and in certain areas quality views are already limited by existing vegetation, development, or both. If constructed, Soundwalls 2 and 3 (both south of Spyglass Drive and on the southbound side of US 101) would cause a direct obstruction of views to the Pacific Ocean, the coastline, and the Shell Beach community as seen from US 101. These two soundwalls, approximately 1,400 feet apart, would block quality coastal views along an approximately one-half mile of US 101. The estimated duration of view blockage would be approximately 30 seconds, traveling at the posted speed limit. For maintenance and potential vandalism reasons, Caltrans District 5 does not allow see-through materials for walls of these heights. As seen from Shell Beach Road and adjacent parts of the community, Soundwalls 2 and 3 would provide a benefit in terms of reducing visibility of the freeway, but would at the same time contribute to a collective increase in urbanized visual character. These soundwalls were dropped from the project due to the impacts they would have on visual resources.

The following observer viewpoints show simulations of how the soundwalls might appear in relation to the surrounding landscape. Aesthetic treatments, such as color and/or texture shown in the photo simulations, are generic representations of possible aesthetic treatments. Actual aesthetic treatments would be determined during the design phase of the project with input from the public and local agency representatives.

Attachment 3
Council Agenda 12-5-2023 12.A-60
Packet Page 311

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 37
Observer Viewpoint 2—From US 101 south of Spyglass Drive, looking southbound Figure 2-12 Existing View
This view represents one of the locations where a soundwall was being considered to mitigate noise impacts from the project. The visual quality along US 101 as represented by Observer Viewpoint 2 is moderately high. The vividness rating is due mostly to the views of the Pacific Ocean, the coastline as it sweeps around to the south to the Oceano Dunes and Point Sal, and because of the inland hillsides rising from the east. The visual unity and intactness ratings are largely positive, though some of the residential development inland from the highway tends to detract from the hillside views and beach community aesthetic character.

Figure 2-13 Built View, All Alternatives
Attachment 3
Council Agenda 12-5-2023 12.A-61
Packet Page 312

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 38
This soundwall has since been removed from the project. If it were constructed, an 8-foot-tall soundwall would be placed along the edge of the southbound freeway shoulder, possibly fronted by a concrete safety barrier. Existing vegetation between US 101 and Shell Beach Road would be removed to accommodate the part-time travel lane, and the existing concrete barrier in the median would be replaced with a taller style.

The most noticeable visual change would be the complete loss of ocean views and reduction of community character because of the new soundwall. The existing vividness or memorability rating would be substantially lowered. The visual unity and intactness provided by views of the Shell Beach community would be reduced.

The inland hills would become the more positive contributor to visual quality, though the type of residential development visible in the mid-ground would moderate that visual benefit.

Observer Viewpoint 4—From Shell Beach Road near Terrace Avenue, looking southeast
Figure 2-14 Existing View
This view from Shell Beach Road is defined mostly by a combination of community elements such as businesses, residences and the frontage road in the foreground, along with the scenic hills rising in the east. From many of the vantage points along Shell Beach Road and other local streets, views of US 101 are somewhat filtered by intervening roadside landscaping. The memorability of this view is considered moderate since it is not particularly unique for the area. The unity and intactness Attachment 3
Council Agenda 12-5-2023 12.A-62
Packet Page 313

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 39
qualities are also in the moderate range because of the variety of competing developed and natural visual elements.

Figure 2-15 Built View, All Alternatives
In this location, a 10-foot-tall soundwall was being considered for construction along the edge of the southbound US 101 outside shoulder, but has since been removed from the project. Existing vegetation between US 101 and Shell Beach Road would be removed to construct the wall and rebuild the associated slope.

As seen from this local roadway, the soundwall would block views of the highway and most associated traffic, but would still allow views of the upper portions of the inland hillsides. The loss of existing vegetation would have an adverse effect on the visual character, including unity and intactness, although replacement landscaping would recreate the vegetated appearance over time. Replacement landscaping as shown in the photo-simulation is expected to take approximately 5 to 7 years to achieve this state of growth.

The main overall visual effect of the project would be an increased urban character.

The inherent visual change associated with an increase in visual scale and additional hardscape would be unavoidable and noticeable. For some casual observers and people traveling through the area, the proposed scale of the facility would not be unexpected in the visual context of this freeway environment. Overall, however, viewer sensitivity and response to change is expected to be high, evidenced largely by the many local coastal planning policies regarding visual character and scenic view protection.

Attachment 3
Council Agenda 12-5-2023 12.A-63
Packet Page 314

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 40
Avoidance, Minimization, and/or Mitigation Measures
The following measures would reduce the project’s potential visual impact as seen from US 101 and the surrounding area; some or all could be included in the project.

Although implementation of these measures would reduce potential impact s, substantial adverse visual impacts would be unavoidable.

Mitigation measures related to the loss of visual quality, character and the scenic vista:
·Retaining walls, concrete median barrier, bridge rail, slope paving, contrast surface treatment, and concrete weed control would include aesthetic treatment such as color and/or texture appropriate for the setting. The specific types of aesthetic treatment would be determined with input from the City of Pismo Beach and the County of San Luis Obispo, per jurisdictional areas. ·Where bridge rail replacement is required on only one side of a structure, the existing rail on the opposite side of the bridge would also be replaced to match the new rail.
·Open-style bridge railing would be used on all bridge rail replacements.

Modifications to existing bridge structures would reflect the visual character of the existing structures in terms of materials, color, style, and the existing human scale of the area.
·All new or replaced median barrier and median guardrail should be placed at the lowest elevation allowable by Caltrans cross-slope safety and drainage standards. If the ground supporting the existing median barrier or guardrail is a higher elevation than the lowest elevation allowable, the ground should be lowered if other environmental resources would not be adversely affected. ·All new, existing, and remaining metal guardrail posts throughout the project limits should be darkened by staining.
·All existing vegetation within the project limits would be protected to the greatest extent possible. Vegetation to be preserved would be delineated by exclusionary fencing and other methods as appropriate.
·All mature trees between proposed soundwalls and frontage roads would be protected. Slope redesign, tree-wells, slope-warping, and/or other techniques would be used to preserve the trees.
·The project would include new and replacement landscaping to the greatest extent possible for the purpose of reducing the urbanizing effect of increased paving, walls and other built project features, as well as for strictly aesthetic attributes.
·New planting would include a combination of trees, shrubs, and ground covers as appropriate.
·New planting would be native or horticulturally appropriate non-native varieties.

Attachment 3
Council Agenda 12-5-2023 12.A-64
Packet Page 315

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 41
·Trees and shrubs would be planted from the largest container size horticulturally appropriate to shorten the amount of time required until they provide substantial visual benefit.
·New planting should not be placed such that it would block views of the Pacific Ocean, the coastline, or the inland hills.
·Existing chain link right-of-way fencing to be replaced adjacent to Shell Beach Road through Shell Beach should match the new ornamental metal fence in- stalled as part of recent Shell Beach Road Improvement project. ·The park-and-ride lot would include landscaping that reduces the visibility of parked vehicles as seen from US 101.
·Drainage structures visible from public areas should be designed to visually blend in with the setting to the extent possible.
·Roadside panel signs, such as those giving advanced “Begin” and “End” notice of the part-time travel lane and the schedule of operation, should be placed so that no tree or large shrub removal or substantial pruning is required. ·Lane-use control signals installed north of Avila Beach Drive should be painted or otherwise colored to visually recede into the setting. Coloring would include poles, arms, cabinets and all attached equipment and connectors (except camera lens and glass covering)
Mitigation measures related to increased light and glare:
·All new and replaced lights and signals would include cut-off shields or other features to limit light trespass beyond the US 101 right-of-way. ·Park-and-ride lot lighting if required would include cut-off shields or other features to limit light trespass beyond the limits of the park-and-ride facility.

Mitigation measures related to soundwalls:

If soundwalls are included in the final project, the following measures would be applied to reduce the visual impact:
·Soundwalls would include aesthetic treatment such as color and/or texture appropriate for the setting.
·Landscaping and irrigation would be installed and maintained on all disturbed areas between the soundwall and the adjacent state right-of-way. ·Soundwalls 2 and 3, which are located at the edge of the freeway, would include cored holes at appropriate intervals to allow for vines to be planted on the back side of the walls so they can migrate through the holes to the front sides.

Attachment 3
Council Agenda 12-5-2023 12.A-65
Packet Page 316

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 42
Cultural Resources
Regulatory Setting
The term “cultural resources,” as used in this document, refers to the “built environment” (structures, bridges, railroads, water conveyance systems, etc.), places of traditional or cultural importance, and archaeological sites (both prehistoric and historic), regardless of significance. Under federal and state laws, cultural resources that meet certain criteria of significance are referred to by various terms including “historic properties,” “historic sites,” “historical resources,” and “tribal cultural resources.” Laws and regulations dealing with cultural resources include:

The National Historic Preservation Act (Preservation Act) of 1966, as amended, sets forth national policy and procedures for historic properties, defined as districts, sites, buildings, structures, and objects included in or eligible for listing in the National Register of Historic Places (National Register). Section 106 of the Preservation Act requires federal agencies to take into account the effects of their undertakings on historic properties and to allow the Advisory Council on Historic Preservation (Advisory Council) the opportunity to comment on those undertakings, following regulations issued by the Advisory Council (Code of Federal Regulations Title 36, Part 800). On January 1, 2014, the First Amended Section 106 Programmatic Agreement (among the Federal Highway Administration, the Advisory Council, the State Historic Preservation Officer (Preservation Officer), and Caltrans went into effect for Caltrans projects, both state and local, with Federal Highway Administration involvement. The Programmatic Agreement implements the Advisory Council’s regulations, Code of Federal Regulations Title 36, Part 800, streamlining the Section 106 process and delegating certain responsibilities to Caltrans. The Federal Highway Administration’s responsibilities under the Programmatic Agreement have been assigned to Caltrans as part of the Surface Transportation Project Delivery Program (U.S. Code Title 23, Section 327).

The California Environmental Quality Act (CEQA) requires the consideration of cultural resources that are historical resources and tribal cultural resources, as well as “unique” archaeological resources. California Public Resources Code Section 5024.1 established the California Register of Historical Resources (California Register) and outlined the necessary criteria for a cultural resource to be considered eligible for listing in the California Register and, therefore, a historical resource. Historical resources are defined in Public Resources Code Section 5020.1(j). In 2014, Assembly Bill 52 added the term “tribal cultural resources” to CEQA, and Assembly Bill 52 is commonly referenced instead of CEQA when discussing the process to identify tribal cultural resources (as well as identifying measures to avoid, preserve, or mitigate effects to them). Defined in P ublic Resources Code Section 21074(a), a tribal cultural resource is a California Register or local register eligible site, feature, place, cultural landscape, or object that has a cultural value to a California Native American tribe. Tribal cultural resources must also meet the definition of a historical resource. Unique archaeological resources are referenced in Public Resources Code Section 21083.2.

Attachment 3
Council Agenda 12-5-2023 12.A-66
Packet Page 317

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 43
Public Resources Code Section 5024 requires state agencies to identify and protect state-owned historical resources that meet the National Register listing criteria. It further requires Caltrans to inventory state-owned structures in its rights-of-way.

Sections 5024(f) and 5024.5 require state agencies to provide notice to and consult with the Preservation Officer before altering, transferring, relocating, or demolishing state-owned historical resources that are listed on or are eligible for inclusion in the National Register or are registered or eligible for registration as California Historical Landmarks. Procedures for compliance with Public Resources Code Section 5024 are outlined in a Memorandum of Understanding between Caltrans and the Preservation Officer, effective January 1, 2015. For most federal-aid projects on the state highway system, compliance with the Section 106 Programmatic Agreement will satisfy the requirements of Public Resources Code Section 5024.

Affected Environment
Resource: Historical Properties Survey Report, May 2020.

Methodology
Record searches were performed at the Central Coast Information Center at the University of California, Santa Barbara in 2017 and 2018. Caltrans conducted Assembly Bill 52 consultation in 2017 and contacted the Native American Heritage Commission to search the Sacred Lands File. Archaeological surveys for much of the study area had already been conducted for prior projects, therefore only small previously unsurveyed sections of the study area were investigated, targeting locations with recorded archaeological sites. Areas surrounding recorded resources along the study area, but outside the Caltrans right-of-way, were also inspected.

Findings
Phase 1 and Extended Phase 1/Phase 2 investigations identified nine previously recorded cultural resources (CA-SLO-801, CA-SLO-1128, CA-SLO-839, CA-SLO- 884, CA-SLO-768, CA-SLO-99, CA-SLO-80/H, CA-SLO-832, CA-SLO-1003/1420) and one new cultural resource (CA-SLO-2885) that are within or extend within the Caltrans right-of-way within the project limits. Of these resources, five (CA-SLO- 80/H, CA-SLO-801, CA-SLO-832, CA-SLO-1003/1420, and CA-SLO-2885) have been recommended or determined eligible for either the National Register or the California Register under criterion D (likely to yield information important to history or prehistory).

CA-SLO-801 is a large, complex, prehistoric shell midden and cemetery dating between 8,000 and 150 years before present. It was first recorded in 1977 and, at that time, portions of the site were under up to 15 feet of imported fill from US 101 construction. To date, it has undergone 46 archaeological investigations. During the early 1980s, Robert Gibson conducted an in-depth analysis of the materials collected during testing and found that the site was continuously occupied between 2 ,000 and 400 years ago. Based on the presence of human remains and the presence of abundant intact shell midden deposits, Gibson recommended CA-SLO-801 as a significant resource for the study of California prehistory. Overall, the site represents Attachment 3
Council Agenda 12-5-2023 12.A-67
Packet Page 318

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 44
multiple occupations spanning 8,000 years and contains numerous house features, thermal features, and abundant data important to prehistory. Also, numerous burials highlight the cultural importance of CA-SLO-801 to the local Chumash as an ancient cemetery. While various authors found that the site contains significant materials under CEQA and the site should be considered eligible under criterion D (for its potential to contain important information about our past), it had not been formally evaluated for the National Register or the California Register.

Construction of US 101, along with other development, has impacted portions of CA-SLO-801. Landform modification within the area is obvious in the form of a series of terraces created for the northbound and southbound lanes of US 101. It is likely that terracing occurred during highway construction in the late 1940s and into the 1960s. However, given the presence of cultural materials on the surface, noted during a recent field visit, there is high potential for pockets of intact buried site de- posits within the study area. Caltrans consulted with the State Historic Preservation Officer for concurrence on the site’s eligibility for the National Register under criteria A and D. The Preservation Officer concurred that the site was eligible under criterion D, but did not concur that it was eligible under criterion A (it makes a contribution to the major pattern of American history.) CA-SLO-1128 was recorded in 1985 as a small marine shell scatter that included one isolated chert flake. Review of previous studies found that no formal testing effort has taken place and the site has not been evaluated for listing in the National Register or California Register. No cultural materials were observed on the surface or within rodent burrows during recent surveys, although visibility was poor due to ground cover. Backhoe trenching performed in 2003 by Clay Singer revealed layers of archaeological deposits. The deposits were highly disturbed down to about 6 feet, after which the intact deposits extended to unknown depth. Without systematic excavations, it is not possible to make an assessment of the potential for cultural resources within the study area, but given the proximity of the deposit at CA-SLO- 801 and the lack of development in the vicinity, there is moderate potential for buried site deposits associated with CA-SLO-1128 within the study area.

CA-SLO-839 was recorded in 1978 as a chert debitage (lithic debris and discards from toolmaking) and shell fragment scatter. The site is defined as a seasonal habitation area with prehistoric artifacts consisting of marine shell fragments, stone tools, debitage, and fire-altered rock. The site might also contain historic-related materials, as a structure of unknown antiquity or function once stood within the boundaries. In 2009, trenching revealed intact subsurface cultural deposits below 3 feet of fill material, but studies also noted that the parcel had been disturbed, and recent fill layers suggested grading activities on the property. It was determined that, with the current level of information, the site could not be recommended eligible for the National Register/California Register. Recent construction, however, uncovered Native American burials, suggesting that CA-SLO-839 contains important archaeological deposits and therefore should continue to be considered eligible for the California Register. The site, however, has not been formally assessed for eligibility for inclusion in the National Register.

Attachment 3
Council Agenda 12-5-2023 12.A-68
Packet Page 319

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 45
CA-SLO-884 was recorded in 1979 as a prehistoric habitation site containing flaked stone and shell. This site, along with two other nearby resources (CA-SLO-768 and CA-SLO -839) could be part of a larger habitation complex. In 1988, two marine shell samples from the site were sent to Washington State University for radiocarbon dating. The results returned a date of 7,250 years before present for one and 8,010 years before present for the other. The area has been highly modified by residential and commercial development, as well as construction of the US 101 on-ramps and off-ramps. Deposits at the site have been described as significant, but the site has not been formally evaluated for inclusion in the National Register or California Register.

CA-SLO-768 was recorded in 1976 as a sparse yet deep and highly disturbed deposit of marine shell and flaked stone. It might be associated with CA-SLO-839 and CA-SLO-884. While the site covers a relatively large section of the coastal terrace, little archaeological information is on file regarding this resource. No record, beyond the site record, is present for this site, therefore it has not been tested or formally evaluated for listing in the National Register/California Register. Overall, these three sites represent an area that appears to contain a higher density of prehistoric sites. Given this density and construction of US 101 using fill rather than excavation, there is a moderate potential for buried materials associated with CA- SLO-768 to be present in the study area.

CA-SLO-99 was recorded in 1950 as a small coastal shell midden (prehistoric trash site) with at least one bedrock mortar. In 1980, a site reconnaissance revealed evidence of a habitation area with dietary remains, burned rock, flaked stone, and bedrock mortars and consequently was noted as significant and important to archaeologists, Native Americans, and the general public. Another site survey in 1980 revealed prehistoric site material mixed with historical and modern refuse, along with evidence of historic-era plowing and other disturbance within the site boundaries. Still later excavations found the site to be a small materiel resource for activities related to milling, shellfish processing, and fishing from the late Middle Period through the Late Period (950 years ago to the time of European settlement.) While several studies have covered CA-SLO-99 and documented “significant” deposits, it has not been formally evaluated for listing in the National Register or California Register. Based on the landform and modern development near CA-SLO- 99, there is a low potential for cultural materials within the study area.

CA-SLO-80/H is a large shell midden with prehistoric cultural materials dating from the Early Archaic to the Late Period (10,000 years ago up to European settlement).

Portions of the midden deposits are mixed due to decades of highway development and maintenance, ranching and agricultural activity, and other uses. Excavation in 1969 produced a broad range of cultural materials, including lithic debitage and flaked stone tools, pitted and battered stone, bone tools, shell beads, fishhooks, and debris from food preparation. Human remains were reported and, although their context was not documented, excavations in 1999 did reveal an intact human burial.

Analysis in 2012 of the material from 1969 indicated the deposit had sustained substantial disturbance, making it impossible to clearly determine the timeline or Attachment 3
Council Agenda 12-5-2023 12.A-69
Packet Page 320

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 46
cultural components; however, two shell beads from the burial indicate it is from the Late Period (700 years ago up to European settlement).

All previous investigations have concluded that CA-SLO-80/H is a significant resource that has potential to yield a substantial amount of important information about local and regional prehistory and history. The site represents as much as 10,000 years of local prehistory and, despite previous disturbance, intact midden deposits are present. Also, the site holds considerable importance for local Native Americans, but it had not been formally evaluated for the National Register or the California Register. Caltrans concluded that CA-SLO-80/H is eligible for the National Register under criterion D because it contains significant archaeological data that retains integrity and is considered an important site in California’s prehistory; the State Historic Preservation Officer concurred with this finding.

CA-SLO-832 and CA-SLO-1003/1420 make up a large prehistoric habitation complex that is bisected by US 101, creating two separate archaeological sites. (Unlike other portions of the study area, highway construction in this area cut down into the natural grade rather than using large amounts of fill to create an elevated roadbed.) CA-SLO-832 was formally recorded in 1976 as a large prehistoric shell midden with occupation episodes dating between 9,800 and 1,000 years before present. The site was disturbed during construction in 1953 without any formal archaeological investigations, but the contractor did note the presence of human remains during grading. It was identified as a significant site in the late 1970s after abundant archaeological resources—consisting of shell, lithic material, animal bone, ground stone, and human remains—were encountered during grading. In 1982, a winter solstice marker was discovered and confirmed as the only identified solstice marker in San Luis Obispo County. CA-SLO-1003/1420 was first identified in 1983 and given the trinomial CA-SLO-1003; CA-SLO-1420 was not identified until 1986.

In 1998, the two sites were combined into CA-SLO-1003/1420.

Excavation was conducted in 2001 to produce preliminary conclusions about the contents and integrity of these two sites. Artifacts recovered included Early Archaic (10,000 to 5,500 years ago) projectile points; shell bead detritus; bone adornments; lithic tools; cores; debitage; milling slabs and other ground stone; and abundant fish and mammal bone. As a result, both CA-SLO-832 and CA-SLO-1003/1420 have been determined eligible for the National Register under criterion D. While disturbances from highway construction are obvious, previous studies have documented that intact deposits associated with the two sites are present in the study area. Overall, these archaeological resources represent an important site complex on both sides of US 101. Therefore, portions of the study area within CA- SLO-839 and CA-SLO-1003/1420 have a high potential for intact archaeological deposits, including midden materials and human remains.

CA-SLO-2885 is a new site discovered during archaeological testing for the project.

The top layer had been disturbed by past construction activity and land-scaping, but below appeared to be an intact cultural midden. Testing produced abundant marine shell, shell beads, small mammal and other vertebrate bones, one obsidian Attachment 3
Council Agenda 12-5-2023 12.A-70
Packet Page 321

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 47
projectile point, flaked stone tools, and toolmaking debris. Use wear indicates the tools were used for daily activities such as processing and scraping bone and wood.

Fire-altered rock was also found, which is an indicator of cultural activity.

Radiocarbon data suggest that the intact portions of the site are between 880 and 535 years old, although one projectile point appeared to be substantially older. The findings demonstrate that though the project area has undergone extensive land- form modification associated with road and highway construction, intact cultural deposits remain that could provide important information about the prehistoric habitation along the Pismo terrace. Caltrans concluded that the tested portion of CA-SLO-2885 is eligible for the National Register under criterion D for its ability to answer regional and local research questions; the State Historic Preservation Officer concurred with this finding.

The following lists the eligibility status of the known archaeological sites within the project limits:
·CA-SLO-801: National Register; California Register
·CA-SLO-1128: unevaluated
·CA-SLO-839: California Register
·CA-SLO-884: unevaluated
·CA-SLO-768: unevaluated
·CA-SLO-99: unevaluated
·CA-SLO-80/H: National Register; California Register
·CA-SLO-832: National Register; California Register
·CA-SLO-1003/1420: National Register; California Register ·CA-SLO-2885: National Register; California Register
Seven historic-period structures within the area of potential effect were also evaluated for eligibility for either the National Register or California Register; none were determined eligible.

Environmental Consequences
The main components of the project have the potential of impacting two recorded archaeological sites eligible for the National Register and where intact human burials have been previously recorded. The fiber optic line proposed to be buried in the median is present on all build alternatives and would cross the recorded edge of CA-SLO-801; however, because of the shallow placement, it is not expected that excavation for the line would encounter intact soil.

Widening for the part-time travel lane as well as other project components for all the build alternatives would bisect a wide segment of CA-SLO-80/H; it is likely that construction excavation would occur only in disturbed soil, but site disturbance is possible. In addition, one of the locations where a soundwall could have been Attachment 3
Council Agenda 12-5-2023 12.A-71
Packet Page 322

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 48
constructed lies within the known boundaries of CA-SLO-2885. Due to the confidentiality of the cultural site locations, the specific soundwall location is not disclosed. Because the footing for a soundwall requires substantial excavation, construction would likely have had severe impacts on this site that could have affected its eligibility status for the National Register in the future. This soundwall has been removed from the project.

Due to safety and access issues within the area of potential effect, the usual practice of preemptive testing and/or data recovery at the cultural sites within the area of potential effect is not feasible. Based on recorded information on the two sites within the area of disturbance, there is a low risk of encountering intact de- posits or cultural artifacts during construction. However, because the potential for significant, unavoidable impacts to cultural resources eligible for the National Register exists, Caltrans is proceeding currently with the Section 106 process of the National Historic Preservation Act under the assumption that the project will result in a Finding of Adverse Effect for both locations and the project as a whole. (A final determination will be made after monitoring activities have been completed and the resultant project impacts evaluated.) To that end, Caltrans has prepared a project- specific Programmatic Agreement pursuant to Stipulation XII.A of the Section 106 Programmatic Agreement and the Code of Federal Regulations Title 36, Part 800.4 (b)(2) and Part 800.14(b) to provide and complete a resolution of adverse effects to cultural resources.

The parties to the project Programmatic Agreement (Parties) consist of the State Historic Preservation Officer, the Tribal Chair for the yak tityu tityu yak tilhini - Northern Chumash Tribe of San Luis Obispo County and Region (Tribe), the Caltrans District 5 Director, and the Caltrans Division of Environmental Analysis Chief. (Pursuant to the Section 106 Programmatic Agreement, Caltrans is deemed to be a federal agency for all highway-aid projects it has assumed [otherwise carried out by the Federal Highway Administration.] In that capacity, Caltrans has assigned the role of federal agency official to the Caltrans Division of Environmental Analysis Chief for compliance with the Code of Federal Regulations Title 36, Part 800 and for oversight of District environmental responsibilities.) In addition to being a signatory on the Programmatic Agreement, the Tribe has also been invited to participate in the implementation of the Programmatic Agreement and the mitigation activities.

If prehistoric or historic-period archaeological resources are discovered during any ground-disturbing activities, the contractor will immediately cease all work activities within 50 feet of the discovery and notify the Caltrans Project Manager. A Caltrans Professionally Qualified Staff Archaeologist will evaluate the significance of the discovery prior to resuming any activities that could impact the resource. If the archaeologist determines that the find embodies significant qualities or offers previously unidentified data potential, the area of concern as determined by the Caltrans Archaeologist will be avoided or a data recovery plan will be implemented.

Any required testing or data recovery will be fully funded by Caltrans and completed by Caltrans prior to construction being resumed in the affected area. Work will not resume until authorization is received from Caltrans.

Attachment 3
Council Agenda 12-5-2023 12.A-72
Packet Page 323

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 49
If potential human remains are discovered, Caltrans will comply with Section 15064.5(e)(1) of the CEQA Guidelines and Public Resources Code Section 7050.5. All work activities will immediately cease in the area (within approximately 50 feet) of the discovery. A Caltrans Professionally Qualified Staff Archaeologist will inspect the remains and confirm that they are human and, if so, will immediately call the county coroner in accordance with Public Resources Code Section 5097.98 and Health and Safety Code Section 7050.5. If the coroner determines the remains are Native American, the coroner will contact the Native American Heritage Commission. As provided in Public Resources Code Section 5097.98, the Native American Heritage Commission will identify the person or persons believed to be most likely descended from the deceased Native American. The most likely descendent, in consultation with Caltrans and other tribal representatives, makes recommendations for means of treating or disposing of, with appropriate dignity, the human remains and any associated grave goods as provided in Public Resources Code Section 5097.98.

Section 4(f) of the Department of Transportation Act of 1966 provides protection for historic properties. It has been determined that none of the historic built- environment properties within the project limits would be affected by the project and none of the archaeological properties within the project vicinity meet the definition of a Section 4(f) resource. For more information, see Appendix A, Resources Evaluated Relative to the Requirements of Section 4(f)—No Use Determination.

Avoidance, Minimization, and/or Mitigation Measures
The Programmatic Agreement includes a Historic Properties Treatment Plan (Treatment Plan) and an Environmentally Sensitive Area Action and Monitoring Plan (Monitoring Plan). The Treatment Plan and the Monitoring Plan detail the measures to avoid, minimize, and mitigate impacts to cultural resources. The Treatment Plan proposes archaeological monitoring of excavation activities, an expedited program of data recovery in the case of a discovery, reporting and documentation of findings, and a timeline for implementation of the Treatment Plan components. The Treatment Plan also includes methods for Native American coordination, public outreach, and curation.

Above and beyond the required actions, the Treatment Plan includes alternative mitigation measures; these measures will be decided on in consultation with the Parties after consideration of the Finding of Effect. The main element of the alternative mitigation entails preparing a synthesis of the current knowledge of the area resources, both individually and in a wider regional context, including the precontact record for the central California coast between Point San Luis and Point Sal. The synthesis will compare this record to data documented for the areas immediately to the north (the Pecho Coast) and immediately to the south (from Vandenberg Air Force Base) of the project vicinity. The summary will demonstrate how sites in the Pismo Beach area contribute to broad patterns of history stretching back more than 8,000 years, allowing for a better understanding of the importance of this region during California’s prehistory. Another element of the alternative mitigation involves a form of public outreach, such as an exhibit or sign, designed in collaboration with the Tribe, to be placed in an easily accessible location. This could Attachment 3
Council Agenda 12-5-2023 12.A-73
Packet Page 324

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 50
be on a website or in a permanent exhibit at The History Center, the San Luis Obispo Public Library, and/or another public location within the City of Pismo Beach.

Preconstruction
Prior to the start of ground-disturbing construction activities:
·Caltrans will initiate formal consultation with the Parties, tribal groups, and other interested parties regarding the archaeological synthesis. It will include family histories, important ethnogeographic sensitivities, and a reference of archaeological studies over time.
·Culturally sensitive locations will be identified as environmentally sensitive areas on the plans and in the field.
·The archaeological monitor will conduct archaeological awareness training (Worker Education Program) for the construction crew, including the Caltrans Resident Engineer and all equipment operators and personnel involved in the mass excavation activities. Caltrans shall also invite the Native American monitors and Native American consulting parties. The archaeological aware- ness training will include:
o A review of archaeology, history, prehistory, and Native American cultures associated with historical resources in the project vicinity. o A review of the types of artifacts and features that may be encountered. o A review of applicable state and local ordinances, laws, and regulations pertaining to historic preservation.
o A discussion of site procedures to be followed if unanticipated cultural resources are discovered during construction activities, including contact information and protocol.
o A statement by the construction contractor or applicable employer agreeing to abide by the Worker Education Program; the policies of Caltrans, the City of Pismo Beach, and the County of San Luis Obispo; and any other applicable laws and regulations.
·Caltrans will notify the Parties at least one week prior to the initiation of ground- disturbing construction activities, unless otherwise determined. ·The Resident Engineer will notify the Caltrans archaeologist and Consultant Project Manager at least 72 hours prior to the start of construction.

Construction Monitoring
·Caltrans will facilitate archaeological and Native American monitoring of ground- disturbing activities within a 100-foot buffer of the known SLO-80/H and SLO- 801/H site boundaries.

Attachment 3
Council Agenda 12-5-2023 12.A-74
Packet Page 325

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 51
·The Monitoring Plan will incorporate detailed project plans, final placement of staging areas, locations for any repaving or lane expansion, and depths of disturbance. The final plan will include the following, as appropriate:
o The types of physical boundaries to be used around environmentally sensitive areas during construction.
o Protocols to follow in the event of a boundary breach. o Specific archaeological monitoring areas, detailed monitoring communication protocols.
o Protocols to follow in the event of unauthorized construction activities within a monitoring area.
·The Resident Engineer will notify the Caltrans archaeologist and Consultant Project Manager at least 48 hours prior to a renewed need for monitoring once construction has begun. The archaeological monitor, in consultation with the Native American monitor, will determine when monitoring is no longer required during construction and communicate the decision to the Caltrans archaeologist.

Post Construction
·Within 30 days of the completion of construction, Caltrans will notify the Parties that construction has concluded. The notice will summarize the results of the monitoring effort and indicate the proposed Finding of Effect. ·Within 12 months of the completion of all archaeological consultant fieldwork, Caltrans will submit to the Parties for review and comment a draft Monitoring Report that details the results of the monitoring effort. The Monitoring Report will include a discussion of all fieldwork, laboratory analysis, an application of the criteria of adverse effect (as set forth in the Code of Federal Regulations Title 36, Part 800.5) for each affected historic property, and a proposed Finding of Effect for the project.
o If construction activities did not encounter historic properties, or if adverse effects to all historic properties were avoided, Caltrans shall notify the Parties that a Finding of No Adverse Effect is appropriate and request comments within 30 days. If no objection is made during the 30-day comment period, Caltrans will finalize the Finding of No Adverse Effect and the project shall not be subject to further review.
o If construction activities encounter historic properties and potential adverse effects were not avoided, Caltrans, in consultation with the Parties, could determine that the mitigation measures did not sufficiently resolve the adverse effects to one or more of the historic properties. In this case, Caltrans shall further consult with the Parties on the alternative mitigation program. Unless determined otherwise through consultation, the preference for alternative mitigation will be towards the development of an interpretive program of physical and/or digital exhibits open to the public. Any additional mitigation or treatment measures would also be documented in the Monitoring Report.

Attachment 3
Council Agenda 12-5-2023 12.A-75
Packet Page 326

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 52
·Within 18 months of the completion of all archaeological consultant fieldwork, Caltrans will submit to the tribal representative(s) a draft technical report that fully documents the results of implementing and completing all components of the Treatment Plan. The Tribe will have 30 days to review the report and submit comments. The final report, along with comments, will be submitted to the State Historic Preservation Officer for approval.
·Caltrans will provide the Parties with an annual update. The update will be due no later than December 31 of each year, beginning December 31, 2022 and continuing annually thereafter throughout the duration of the Programmatic Agreement.

2.2 Physical Environment
Hydrology and Floodplain
Regulatory Setting
Executive Order 11988 (Floodplain Management) directs all federal agencies to refrain from conducting, supporting, or allowing actions in floodplains unless it is the only practicable alternative. The Federal Highway Administration requirements for compliance are outlined in the Code of Federal Regulations Title 23, Part 650, Subpart A. To comply, the following must be analyzed:
·Practicability of alternatives to any longitudinal encroachments. ·Risks of the action.
·Support of incompatible floodplain development.
·Measures to minimize floodplain impacts and to preserve/restore any beneficial floodplain values affected by the project.

The base floodplain is defined as “the area subject to flooding by the flood or tide having a one percent chance of being exceeded in any given year.” An encroachment is defined as “an action within the limits of the base floodplain.” Affected Environment
Resource: Location Hydraulics Study, February 2020.

The project lies within the Estero Bay Hydrological Unit. Pismo Creek originates in the Santa Lucia Range, and its floodplain stretches from Edna Valley north of Route 227 down Price Canyon to the Pacific Ocean. The upper reaches consist of three creeks—East and West Corral de Piedra and Canada Verde—which converge to create Pismo Creek. A floodway is designated on the Federal Emergency Management Agency Flood Insurance Rate Map to the north of US 101 and runs approximately 0.85 mile upstream (Figure 2-16). The Pismo Creek floodplain widens downstream of US 101, where it joins the Meadow Creek floodplain.

Attachment 3
Council Agenda 12-5-2023 12.A-76
Packet Page 327

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 53
Environmental Consequences
The project would widen the southbound Pismo Creek Bridge toward the median by 8 feet. The existing structure is supported by 3 bents, each with two 3.5-foot- diameter columns. Three new 4-foot-diameter columns would be added, one in line with each bent, to support the additional bridge width. This would create a localized increase in water surface elevation under the bridges, but the elevations upstream and downstream would not be affected. In addition, a sheet pile is proposed at the east bank of the channel. The top of the sheet pile would be level with the bottom of the slope and would not impact the existing creek cross-section. Consequently, the project would not result in a significant floodplain encroachment as defined in the Code of Federal Regulations Title 23, Part 650.105.

Figure 2-16 Flood Hazard Map
Avoidance, Minimization, and/or Mitigation Measures
No measures have been proposed.

Attachment 3
Council Agenda 12-5-2023 12.A-77
Packet Page 328

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 54
Water Quality and Storm Water Runoff
Regulatory Setting
Federal Requirements: Clean Water Act
In 1972, Congress amended the Federal Water Pollution Control Act, making the addition of pollutants to the waters of the United States (U.S.) from any point source unlawful unless the discharge complies with a National Pollutant Discharge Elimination System (Pollutant Discharge) permit. This act and its amendments are known today as the Clean Water Act. Congress has amended the act several times.

In the 1987 amendments, Congress directed dischargers of storm water from municipal and industrial/construction point sources to comply with the Pollutant Discharge permit scheme. The following are important Clean Water Act sections:
·Sections 303 and 304 require states to issue water quality standards, criteria, and guidelines.
·Section 401 requires an applicant for a federal license or permit to conduct any activity that may result in a discharge to waters of the U.S. to obtain certification from the state that the discharge will comply with other provisions of the act.

This is most frequently required in tandem with a Section 404 permit request (see below).
·Section 402 establishes the National Pollutant Discharge Elimination System, a permitting system for discharges (except for dredge or fill material) of any pollutant into waters of the U.S. Regional Water Quality Control Boards (Regional Water Boards) administer this permitting program in California.

Section 402(p) requires permits for discharges of storm water from industrial/construction and municipal separate storm sewer systems. ·Section 404 establishes a permit program for the discharge of dredge or fill material into waters of the U.S. This permit program is administered by the U.S.

Army Corps of Engineers.

The goal of the Clean Water Act is “to restore and maintain the chemical, physical, and biological integrity of the Nation’s waters.”
The U.S. Army Corps of Engineers issues two types of 404 permits: General and Individual. There are two types of General permits: Regional and Nationwide.

Regional permits are issued for a general category of activities when they are similar in nature and cause minimal environmental effect. Nationwide permits are issued to allow a variety of minor project activities with no more than minimal effects.

Ordinarily, projects that do not meet the criteria for a Regional or Nationwide Permit may be permitted under one of the U.S. Army Corps of Engineers’ Individual permits. There are two types of individual permits: standard permits and Letters of Permission. For individual permits, the U.S. Army Corps of Engineers’ decision to approve is based on compliance with U.S. Environmental Protection Agency’s Section 404 (b)(1) Guidelines (Code of Federal Regulations Title 40, Part 230), and Attachment 3
Council Agenda 12-5-2023 12.A-78
Packet Page 329

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 55
whether the permit approval is in the public interest. The Section 404(b)(1) Guidelines were developed by the U.S. Environmental Protection Agency in conjunction with the U.S. Army Corps of Engineers and allow the discharge of dredged or fill material into the aquatic system (waters of the U.S.) only if there is no practicable alternative that would have fewer adverse effects. The guidelines state that the U.S. Army Corps of Engineers may not issue a permit if there is a least- environmentally damaging practicable alternative to the proposed discharge that would have lesser effects on waters of the U.S. and not have any other significant adverse environ-mental consequences. According to the guidelines, documentation is needed that a sequence of avoidance, minimization, and compensation measures has been followed, in that order.

The guidelines also restrict permitting activities that violate water quality or toxic effluent standards, jeopardize the continued existence of listed species, violate marine sanctuary protections, or cause “significant degradation” to waters of the U.S. In addition, every permit from the U.S. Army Corps of Engineers, even if not subject to the Section 404(b)(1) Guidelines, must meet general requirements. See Code of Federal Regulations Title 33, Part 320.4. A discussion of the least environmentally damaging practicable alternative determination, if any, for the document is included in section 2.3.2 Wetlands and Other Waters.

State Requirements: Porter-Cologne Water Quality Control Act California’s Porter-Cologne Act, enacted in 1969, provides the legal basis for water quality regulation within California. This act requires a “Report of Waste Discharge” for any discharge of waste (liquid, solid, or gaseous) to land or surface waters that may impair beneficial uses for surface and/or groundwater of the state. It predates the Clean Water Act and regulates discharges to waters of the state. Waters of the State include more than just waters of the U.S., such as groundwater and surface waters otherwise not considered waters of the U.S. Also, it prohibits discharges of “waste” as defined, and this definition is broader than the Clean Water Act definition of “pollutant.” Discharges under the Porter-Cologne Act are permitted by Waste Discharge Requirements and may be required even when the discharge is already permitted or exempt under the Clean Water Act.

The State Water Resources Control Board (State Water Board) and Regional Water Boards are responsible for establishing the water quality standards (objectives and beneficial uses) required by the Clean Water Act and regulating discharges to ensure compliance with the water quality standards. Details about water quality standards in a project area are included in the applicable Regional Water Board Basin Plan. In California, Regional Water Boards designate beneficial uses for all water body segments in their jurisdictions and then set criteria necessary to protect those uses. As a result, the water quality standards developed for particular water segments are based on the designated use and vary depending on that use. In addition, the State Water Board identifies waters failing to meet standards for specific pollutants. These waters are then state listed in accordance with Clean Water Act Section 303(d). If a state determines that waters are impaired for one or more constituents and the standards cannot be met through point source or non- Attachment 3
Council Agenda 12-5-2023 12.A-79
Packet Page 330

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 56
point source controls (water discharge permits), the Clean Water Act requires the establishment of Total Maximum Daily Loads (maximum daily loads). Maximum daily loads specify allowable pollutant loads from all sources (point, non-point, and natural) for a given watershed.

State Water Resources Control Board and Regional Water Quality Control Boards The State Water Board administers water rights, sets water pollution control policy, and issues water board orders on matters of statewide application, and oversees water quality functions throughout the state by approving Basin Plans, maximum daily loads, and Pollutant Discharge permits. Regional Water Boards are responsible for protecting beneficial uses of water resources within their regional jurisdiction using planning, permitting, and enforcement authorities to meet this responsibility.

National Pollutant Discharge Elimination System Program Municipal Separate Storm Sewer Systems
Section 402(p) of the Clean Water Act requires the issuance of National Pollutant Discharge Elimination System (Pollutant Discharge) Program permits for five categories of storm water discharges, including Municipal Separate Storm Sewer Systems. A municipal separate storm sewer system is defined as “any conveyance or system of conveyances (roads with drainage systems, municipal streets, catch basins, curbs, gutters, ditches, human-made channels, and storm drains) owned or operated by a state, city, town, county, or other public body having jurisdiction over storm water, that is designed or used for collecting or conveying storm water.” The State Water Board has identified Caltrans as an owner/operator of a municipal separate storm sewer systems under federal regulations. The Caltrans municipal separate storm sewer systems permit covers all Caltrans rights-of-way, properties, facilities, and activities in the state.

The State Water Board or the Regional Water Board issues Pollutant Discharge permits for five years, and permit requirements remain active until a new permit has been adopted.

The Caltrans Municipal Separate Storm Sewer Systems Permit, Order Number 2012-0011-DWQ (adopted on September 19, 2012 and effective on July 1, 2013), as amended by Order Number 2014-0006-EXEC (effective January 17, 2014), Order Number 2014-0077-DWQ (effective May 20, 2014) and Order Number 2015- 0036-EXEC (conformed and effective April 7, 2015) has three basic requirements:

1. Caltrans must comply with the requirements of the Construction General Permit (see below).

2. Caltrans must implement a year-round program in all parts of the State to effectively control storm water and non-storm water discharges; and

3. The Caltrans storm water discharges must meet water quality standards through implementation of permanent and temporary (construction) Best Management Attachment 3
Council Agenda 12-5-2023 12.A-80
Packet Page 331

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 57
Practices, to the maximum extent practicable, and other measures as the State Water Board determines to be necessary to meet the water quality standards.

To comply with the permit, Caltrans developed the Statewide Storm Water Management Plan to address storm water pollution controls related to highway planning, design, construction, and maintenance activities throughout California.

The plan assigns responsibilities within Caltrans for implementing storm water management procedures and practices as well as training, public education and participation, monitoring and research, program evaluation, and reporting activities.

The plan describes the minimum procedures and practices Caltrans uses to reduce pollutants in storm water and non-storm water discharges. It outlines procedures and responsibilities for protecting water quality, including the selection and implementation of Best Management Practices.

The project will be programmed to follow the guidelines and procedures outlined in the latest Statewide Storm Water Management Plan to address storm water runoff.

Construction General Permit
Construction General Permit, Order Number 2009-0009-DWQ (adopted on September 2, 2009 and effective on July 1, 2010), as amended by Order Number 2010-0014-DWQ (effective February 14, 2011) and Order Number 2012-0006-DWQ (effective on July 17, 2012)—The permit regulates storm water discharges from construction sites that result in a Disturbed Soil Area of 1 acre or greater, and/or smaller sites that are part of a larger common plan of development. By law, all storm water discharges associated with construction activity where clearing, grading, and excavation result in soil disturbance of at least 1 acre must comply with the provisions of the General Construction Permit. Construction activity that results in soil disturbances of less than 1 acre is subject to this Construction General Permit if there is potential for significant water quality impairment resulting from the activity as determined by the Regional Water Board. Operators of regulated construction sites are required to develop Storm Water Pollution Prevention Plans; to implement sediment, erosion, and pollution prevention control measures; and to obtain coverage under the Construction General Permit.

The Construction General Permit separates projects into Risk Levels 1, 2, and 3.

Risk levels are determined during the planning and design phases, and are based on potential erosion and transport to receiving waters. Requirements apply according to the Risk Level determined. For example, a Risk Level 3 (highest risk) project would require compulsory storm water runoff pH and turbidity monitoring, and before-construction and after-construction aquatic biological assessments during specified seasonal windows. For all projects subject to the permit, applicants are required to develop and implement an effective Storm Water Pollution Prevention Plan. In accordance with the Caltrans Statewide Storm Water Management Plan and Standard Specifications, a Water Pollution Control Program is necessary for projects with a disturbed soil area of less than 1 acre.

Attachment 3
Council Agenda 12-5-2023 12.A-81
Packet Page 332

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 58
Section 401 Permitting
Under Section 401 of the Clean Water Act, any project requiring a federal license or permit that may result in a discharge to a water of the U.S. must obtain a 401 Certification, which certifies that the project will comply with state water quality standards. The most common federal permits triggering 401 Certification are Clean Water Act Section 404 permits issued by the U.S. Army Corps of Engineers. The 401 permit certifications are obtained from the appropriate Regional Water Board, de-pendent on the project location, and are required before the U.S. Army Corps of Engineers issues a 404 permit.

In some cases, the Regional Water Board may have specific concerns with discharges associated with a project. As a result, the Regional Water Board may issue a set of requirements known as water discharge permits under the State Water Code (Porter-Cologne Act) that define activities, such as the inclusion of specific features, effluent limitations, monitoring, and plan submittals that are to be implemented for protecting or benefiting water quality. Water discharge permits can be issued to address both permanent and temporary discharges of a project.

Affected Environment
Resources: Water Quality Assessment Report, March 2020; Natural Environment Study, May 2020.

Pismo Beach and the project area sit within the Coast Ranges Geomorphic Province, along a narrow coastal plateau between the low-lying hills of the San Luis Range and the Pacific Ocean. Pismo Creek originates in the Coast Range foothills about 9 miles northeast of the project area. Runoff from various small drainages in the foothills of Edna Valley feed into West Corral de Piedra Creek and East Corral de Piedra Creek, which are tributaries that reach their confluence with Pismo Creek about 4 miles upstream from the project location. During times of extreme rainfall and runoff, Pismo Creek reaches the Pacific Ocean about 0.8 mile downstream of the project area. However, during most of the year, the surface flow ends at a sand barrier on Pismo Beach and the sub-surface flow travels under the sand to make a confluence with the Pacific Ocean.

The project is divided into two Hydrologic Sub-areas: 1) Point Buchon Hydrologic area and San Luis Obispo Creek Hydrologic Sub-Area (HSA) within the Estero Bay Unit (HSA Number 310.24) and 2) Point Buchon Hydrologic area and Pismo Hydro- logic Sub-Area (HSA) within the Estero Bay Unit (HSA Number 310.26). The receiving water bodies for this project are Pismo Creek, San Luis Obispo Creek, and several unnamed drainages that cross the highway, all of which flow to the Pacific Ocean. Both San Luis Obispo Creek and Pismo Creek are on the 2014/2016 303(d) list for sediment.

Environmental Consequences
The disturbed soil area for this project is estimated to be 13.5 acres, which include areas to construct and stage equipment for construction. The net new impervious Attachment 3
Council Agenda 12-5-2023 12.A-82
Packet Page 333

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 59
surface area as a result of the project was calculated at about 5 acres; the project would also replace about 4 acres of existing impervious surface.

Highway storm water runoff has the potential to affect receiving water quality. The nature of these impacts depends on the uses and flow rate or volume of the receiving water, rainfall characteristics, and highway characteristics. Heavy metals associated with vehicle tire and brake wear, oil and grease, and exhaust emissions are the main pollutants associated with transportation corridors. There are no existing treatment best management practices along US 101 within the project limits to treat roadway runoff; therefore, the water quality of the receiving water bodies would still be affected by highway runoff as a result of this project. The project would increase impervious areas and therefore potentially increase the volume and velocity of storm water flow to downstream receiving water bodies. In addition, pollutant loading could also be increased.

Construction Impacts
Short-term surface water quality impacts may result from implementation of the project; no groundwater impacts are expected. Potential surface water quality impacts may include an increase in sediments, turbidity and total dissolved solids and/or toxicity due to chemical substances originating from construction activities.

Avoidance, Minimization, and/or Mitigation Measures
The project would be designed to avoid water resources to the maximum extent practicable, promote infiltration of storm water runoff, maximize the treatment of storm water runoff, and reduce erosion by matching post-project runoff rates to pre- project rates.

Design Pollution Prevention best management practices to reduce permanent water quality impacts could include:
·Limiting work areas to protect as much existing vegetation as possible. ·Reducing impervious surfaces as much as possible.
·Reducing soil disturbance to only areas required for construction of this project. ·Incorporating retaining walls to reduce slope length.
·Including slope rounding to reduce overall slope steepness. ·Reconstructing drainage systems to use open vegetated conveyances wherever feasible.
·Where drainage systems transition from hard to soft systems, incorporating velocity dissipation scour protection.
·Including an aggressive permanent erosion control design, including compost and native plant seed mix to allow slopes to revegetate faster and reduce long- term impacts from erosion.
·Replacing planting where vegetation was removed.

Attachment 3
Council Agenda 12-5-2023 12.A-83
Packet Page 334

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 60
·Incorporating best management practices into the design and operation. ·Preserving existing vegetation outside of the active work area.

A Storm Water Pollution Prevention Plan would be prepared for the project. The following are selected best management practices that could be included in the project:

Temporary Soil Stabilization
·Minimize active disturbed soil areas during the rainy season using scheduling techniques.
·Preserve existing vegetation to the maximum extent feasible. ·Implement temporary protective cover/erosion control on all non-active disturbed soil areas and soil stockpiles.
·Control erosive forces of storm water runoff with effective storm flow management such as temporary concentrated flow conveyance devices, earthen dikes, drainage swales, lined ditches, outlet protection/velocity dissipation devices, and slope drains as determined feasible.

Temporary Sediment Controls
·Implement linear sediment controls such as fiber rolls, check dams, or gravel bag berms on all active and non-active disturbed soil areas during the rainy season.
·To further help prevent sediment discharge stabilized construction site entrances, temporary drainage inlet protection, and street sweeping and vacuuming will be necessary.
·Implement appropriate wind erosion controls year-round.

Temporary Water Quality Controls
·Use pre-disturbed areas, and select appropriately sized equipment for the job. ·Time construction within and near the creek during the dry season. ·When working near streams, implement erosion and sediment controls to keep sediment out of stream channel.
·Minimize disturbance by selecting the narrowest crossing location; limiting the number of equipment trips across a stream during construction; and minimizing the number and size of work areas (equipment staging areas and spoil storage areas).
·Isolate equipment staging and spoil storage areas away from the stream channel using appropriate storm water control barriers. Provide stabilized access to the stream when in-stream work is required.

Attachment 3
Council Agenda 12-5-2023 12.A-84
Packet Page 335

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 61
Streambank Sediment Control and Clear Water Diversion
·Install temporary large sediment barriers to control sediment. Temporary large sediment barriers should be installed only where sediment-laden water can pond, thus allowing the sediment to settle out.
·Install fiber rolls along slope contour above the high-water level to intercept runoff, to reduce flow velocity, and to release the runoff as sheet flow and provide removal of sediment from the runoff. In a stream environment, fiber rolls should be used in conjunction with other sediment control methods. ·Use a gravel bag berm or barrier to intercept and slow the flow of sediment- laden sheet flow runoff.

Noise
Regulatory Setting
The California Environmental Quality Act (CEQA) and the National Environmental Policy Act of 1969 (NEPA) provide the broad basis for analyzing and abating highway traffic noise effects. The intent of these laws is to promote the general welfare and to foster a healthy environment. The requirements for noise analysis and consideration of noise abatement and/or mitigation, however, differ between CEQA and NEPA.

California Environmental Quality Act
CEQA requires a strictly baseline-versus-build analysis to assess whether a proposed project will have a noise impact. If a project is determined to have a significant noise impact under CEQA, then CEQA dictates that mitigation measures must be incorporated into the project unless those measures are not feasible.

The rest of this section will focus on the NEPA/Title 23 Part 772 of the Code of Federal Regulations (23 CFR 772) noise analysis; please see Chapter 3 of this document for further information on noise analysis under CEQA.

National Environmental Policy Act and 23 CFR 772
For highway transportation projects with Federal Highway Administration involvement (and Caltrans, as assigned), the Federal-Aid Highway Act of 1970 and its implementing regulations (23 CFR 772) govern the analysis and abatement of traffic noise impacts. The regulations require that potential noise impacts in areas of frequent human use be identified during the planning and design of a highway project. The regulations include noise abatement criteria (NAC) that are used to determine when a noise impact would occur. The noise abatement criteria differ depending on the type of land use under analysis. For example, the noise abatement criterion for residences (67 A-weighted decibels) is lower than the noise abatement criterion for commercial areas (72 A-weighted decibels).

Table 2-1 lists the noise abatement criteria for use in the NEPA/23 CFR 772 analysis.

Attachment 3
Council Agenda 12-5-2023 12.A-85
Packet Page 336

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 62
Table 2-1 Noise Abatement Criteria
Activity
Category
NAC, Hourly A-
Weighted Noise
Level, Leq(h)
Description of Activity Category
A 57 (Exterior)
Lands on which serenity and quiet are of extraordinary
significance and serve an important public need and
where the preservation of those qualities is essential if the area is to continue to serve its intended purpose.

B 67 (Exterior)Residential.

C 67 (Exterior)
Active sport areas, amphitheaters, auditoriums, camp-
grounds, cemeteries, day care centers, hospitals,
libraries, medical facilities, parks, picnic areas, places of worship, playgrounds, public meeting rooms, public or
nonprofit institutional structures, radio studios, recording studios, recreation areas, Section 4(f) sites, schools, television studios, trails, and trail crossings.

D 52 (Interior)
Auditoriums, day care centers, hospitals, libraries,
medical facilities, places of worship, public meeting
rooms, public or nonprofit institutional structures, radio studios, recording studios, schools, and television
studios.

E 72 (Exterior)
Hotels, motels, offices, restaurants/bars, and other
developed lands, properties, or activities not included in A through D or F.

F
No Noise Abatement
Criteria—reporting
only
Agriculture, airports, bus yards, emergency services, in- dustrial, logging, maintenance facilities, manufacturing, mining, rail yards, retail facilities, shipyards, utilities (water resources, water treatment, electrical, etc.), and warehousing.

G
No Noise Abatement
Criteria—reporting
only
Undeveloped lands that are not permitted.

According to the Caltrans Traffic Noise Analysis Protocol for New Highway Construction and Reconstruction Projects, May 2011, a noise impact occurs when the predicted future noise level with the project substantially (defined as 12 A- weighted decibels or more) exceeds the existing noise level or when the future noise level with the project approaches or exceeds the noise abatement criteria. A noise level is considered to approach the noise abatement criteria if it is within 1 A- weighted decibel of the noise abatement criteria. Figure 2-17 lists the noise levels of common activities to enable readers to compare the actual and predicted highway noise levels discussed in this section with common activities.

Attachment 3
Council Agenda 12-5-2023 12.A-86
Packet Page 337

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 63
Figure 2-17 Noise Levels of Common Activities
If it is determined that the project will have noise impacts, then potential abatement measures must be considered. Noise abatement measures that are determined to be reasonable and feasible and approved to move forward at the time of final design are incorporated into the project plans and specifications. This document discusses noise abatement measures that could be incorporated in the project.

The Caltrans Traffic Noise Analysis Protocol sets forth the criteria for determining when an abatement measure is reasonable and feasible. Feasibility of noise abatement is basically an engineering concern. Noise abatement must be predicted to reduce noise by at least 5 decibels at an impacted receptor to be considered feasible from an acoustical perspective. It must also be possible to design and construct the noise abatement measure for it to be considered feasible. Factors that affect the design and constructability of noise abatement include, but are not limited to, safety, barrier height, topography, drainage, access requirements for driveways, presence of local cross streets, underground utilities, other noise sources in the area, and maintenance of the abatement measure. The overall reasonableness of Attachment 3
Council Agenda 12-5-2023 12.A-87
Packet Page 338

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 64
noise abatement is determined by the following three factors: 1) the noise reduction design goal of 7 decibels at one or more impacted receptors; 2) the cost of noise abatement; and 3) the viewpoints of benefited receptors (including property owners and residents of the benefited receptors).

Affected Environment
Resources: Noise Study Report, February 2020; Noise Abatement Decision Report, February 2020.

The project is classified as a Type 1 by the Federal Highway Administration because it is federally funded and would increase the number of through-lanes.

Freeway traffic is the main source of noise in the project vicinity and can be excessive relative to the surrounding activities. However, the high traffic volumes that occur in the southbound direction during peak hours cause congestion and lower speeds; lower speeds create a quieter environment than a freeway with traffic at the posted speed. Outside of the peak period, when traffic speeds are higher, noise levels exceed the noise abatement criteria at many locations.

As described in Table 2-2, land uses identified in the project area are:
·Activity Category B: residences
·Activity Category C: outdoor park/sports, recreation, churches, day care center, schools
·Activity Category D: churches, day care center, schools ·Activity Category E: restaurants, hotels/motels
For the purposes of the noise study, noise measurements were taken during peak hours between June and August 2016 and simultaneous traffic counts were con- ducted during the measurement period. The purpose of this task was to calibrate the noise modeling software to make accurate predictions for existing peak-period conditions as well as future Build and No-Build scenarios. For the existing peak- period noise model input, actual peak-period traffic speeds were obtained from the count station in Pismo Beach and averaged to 30 miles per hour in the southbound direction and full speed in the northbound. Adjusting for future traffic volumes, future No-Build condition noise levels were based on 27 miles per hour southbound. Traffic noise was evaluated for three scenarios: existing (2016), design year (2046) No- Build condition, and design year (2046) for the Alternative 1 truck-climbing lane alternative. (This alternative is the “maximum” build condition because it includes the most design features and will have the largest impact on the noise environment.) The noise impact from a project is determined by comparing predicted future noise levels with the built project to existing noise levels, as well as to the noise abatement criteria for the applicable land use activity category. The noise abatement criteria are based on interference with speech communication; they are a compromise between noise levels that are desirable and those that are achievable, and they are not design goals. Although all developed land uses were Attachment 3
Council Agenda 12-5-2023 12.A-88
Packet Page 339

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 65
evaluated in the analysis, noise abatement is considered only for areas of frequent human use that would benefit from a lowered noise level. Therefore, the analysis focused on receptor locations with defined outdoor activity areas, such as residential backyards and common-use areas at multi-family residences or outdoor recreation areas. Proximity to the freeway was also considered, as receptors closer to the freeway are more likely to be impacted. All measurements on the northbound side of the freeway were taken at residential receptor locations except for one, taken at the Pismo Beach Sports Complex; on the southbound side, the measurements were taken at receptor locations representing a variety of activity categories. Table 2-2 describes the noise abatement criteria as decibel levels for the activity categories.

The portion of the project where widening for the part-time travel lane would occur was divided into four segments, grouped by similar traffic volumes within each segment. (Noise measurements and modeling were also conducted at four residential locations outside of these segments, where noise levels could still be affected by the project due to increased speeds.)
Segment 1
Located in Shell Beach, this segment extends from the Shell Beach Drive undercrossing at Spyglass Drive to about 2,700 feet northward (across from Beachcomber Drive). Land uses in this segment are mostly residential, but also include tennis courts. Four residential receptor locations were analyzed within this segment. There are no receptors on the northbound side of the freeway within this segment.

Segment 2
This segment extends from Spyglass Drive to the North Pismo separation at Mattie Road; it is a mix of commercial/retail, residential, and recreational uses. It includes Shell Beach Elementary School. A total of 33 receptor locations were analyzed from both sides of the freeway within this segment, including the elementary school and two businesses with outdoor seating areas. The remainder of the receptor locations were residential.

Segment 3
This segment extends from the vicinity of the Dolliver Street off-ramp to Pismo Creek, including the Pismo Beach Sport Complex on the northbound side. Within this segment is a mix of commercial/retail, residential, and recreational uses. A total of 21 receptor locations were analyzed from both sides of the freeway within this segment, including three businesses with outdoor seating areas. The remainder of the receptor locations were residential.

Segment 4
This segment is on the southbound side of the freeway only and contains the area from Pismo Creek to the project’s southern limits. Two receptor locations were analyzed: one from the mobile home park and the other from the RV park.

Attachment 3
Council Agenda 12-5-2023 12.A-89
Packet Page 340

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 66
Environmental Consequences
As a result of reduced congestion and the resulting increase in traffic speeds, noise levels within the project limits are expected to increase with the project. Increased traffic volumes would also increase noise over time, but this is not expected to be a major contributor to the overall noise level. (Traffic noise increases by 3 decibels for every doubling of traffic volumes. Projected traffic volumes are expected to increase by 10 percent by 2046.)
Using predicted traffic volumes, traffic speeds, and travel lane locations, the expected noise level at each receptor location was calculated for the No-Build and for the Alternative 1 truck-climbing lane variation in the year 2046. These levels were then compared to the noise abatement criteria for the applicable activity category.

The noise study modeling indicates that the project would not result in a substantial increase in noise (considered to be 12 decibels or higher) at any of the measured receptor locations. Regardless, some receptor locations within the project limits are predicted to approach or exceed the noise abatement criteria of 67 decibels, so noise abatement measures must be considered.

Further analysis was done to determine the efficacy of soundwalls at strategic locations within the project limits; 13 locations were identified where noise levels could be reduced by a soundwall by 7 or more decibels. Six of these locations were on the southbound side of the freeway where 12 receptor locations were identified as approaching or exceeding the noise abatement criteria; seven were on the northbound side where 15 receptor locations were identified as approaching or exceeding the noise abatement criteria. Of the 13 wall locations evaluated, only three met all the necessary criteria to be carried forward as reasonable and feasible noise abatement measures. These are shown in Table 2-2 and Figure 2-18.

Table 2-2 Soundwalls as Noise Abatement
Soundwall Location Height
(feet)
Length
(feet)
Noise
Reduction
(decibels)
Benefitted
Receptors
SB-2 Segment 2 8 1300 7 46
SB-3 Segment 2 10 1200 8 52
NB-6 Segment 3 12 800 7 25
Segment 1
These receptor locations in Shell Beach, as well as those northward of segment 1, would experience a 3- to 4-decibel increase in the noise levels with the Build condition, which is barely detectable to the human ear, but that increase would cause two residential receptor locations within segment 1 to reach levels that exceed the applicable noise abatement criteria. Within this segment, one soundwall Attachment 3
Council Agenda 12-5-2023 12.A-90
Packet Page 341

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 67
was evaluated but it did not pass the reasonableness criteria due to the low numbers of receptors that would benefit.

Segment 2
These receptor locations would experience noise level increases in the range of 4 to 8 decibels with the Build condition. Of the locations analyzed, six would approach or exceed the applicable noise abatement criteria: four residences on the northbound side and two residences and one outdoor seating area on the southbound side. Within this segment, three soundwalls were evaluated in the southbound direction and four in the northbound. Two of the southbound walls were found to be both reasonable and feasible and therefore are being evaluated further for inclusion in the final project design. The other five walls did not meet the reasonableness criteria due to the low numbers of receptors that would benefit.

Segment 3
Locations in the southbound direction would experience noise level increases in the range of 3 to 8 decibels with the Build condition. Of the locations analyzed, two residences would approach or exceed the applicable noise abatement criteria. The northbound side would experience a maximum increase in noise levels of only 3 decibels but, because the noise levels in that area are already high, three of the residential receptor locations would approach or exceed the applicable noise abatement criteria. Within this segment, one soundwall was evaluated in the southbound direction and three in the northbound. One of the northbound walls was found to be both reasonable and feasible and therefore is being evaluated further for inclusion in the final project design. The other three walls did not meet the reasonableness criteria due to the low numbers of receptors that would benefit.

Segment 4
These receptor locations are expected to experience a 3- to 5-decibel increase in noise levels with the Build condition, but would remain below the applicable noise abatement criteria, so no abatement measures were considered.

Attachment 3
Council Agenda 12-5-2023 12.A-91
Packet Page 342

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 68
Figure 2-18 Potential Soundwall Locations
Attachment 3
Council Agenda 12-5-2023 12.A-92
Packet Page 343

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 69
Locations Evaluated but Rejected for Noise Abatement
Although all locations within the project limits that would experience a substantial increase in noise or that would reach levels that approached noise abatement criteria were evaluated for noise abatement measures, the measures considered (soundwalls) did not meet the reasonableness criteria at many of these locations. As a result, these locations could experience noise impacts as an unavoidable consequence of the project. These areas that could experience noise impacts but that would not receive any abatement measures are described below.

Segment 1
The southbound direction contains residential properties that would not experience a substantial increase in noise levels, but nonetheless the increase is expected to cause an exceedance of the applicable noise abatement criteria.

Segment 2
The southbound direction contains residential and commercial/retail properties, but there would be no exceedances of the applicable noise abatement criteria.

The northbound direction contains residences that would experience noise levels that exceed the applicable noise abatement criteria.

Segment 3
The southbound direction contains residential properties and commercial/retail properties, while the northbound direction contains all residential locations.

Some of these locations on both sides of the freeway would experience noise levels that exceed the applicable noise abatement criteria.

Segment 4
This segment would not experience noise impacts as a result of the project, and there would be no exceedances of applicable noise abatement criteria.

Secondary Impacts
Though mitigating the noise impacts that would result from the project at some locations, the inclusion of soundwalls in the final project would have substantial impacts on the visual quality of the region and on cultural resources. The project would add a considerable amount of additional urbanizing features through the wider freeway lanes, higher median barrier, retaining walls, and the lane-use control signals and signs that would contribute to a decrease in the visual quality. Soundwalls would further this degradation by creating another built feature along the corridor. More substantially, walls built on the southbound side would block the ocean views for which the area is known. As mentioned in section 2.1.2 Visual/ Aesthetics, the soundwalls at the two southbound locations (soundwalls 2 and 3) were dropped from the project because they would have blocked ocean views and therefore would have been inconsistent with the local coastal plan. See section 2.1.2 Visual/ Aesthetics for more information, in particular the discussion on soundwalls. In addition, one of the wall locations Attachment 3
Council Agenda 12-5-2023 12.A-93
Packet Page 344

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 70
under consideration is sited on an archaeological resource. Construction of the wall would likely have severe impacts to the site. (See section 2.1.3 Cultural Resources.) The wall location on the northbound side of the freeway would require removing a substantial amount of heavy vegetation, including mature eucalyptus trees, but otherwise would have minimal adverse impacts, so will be further considered for inclusion in the project in the project design phase.

Construction Noise
During construction of the project, noise from construction activities would add to ambient noise levels in the vicinity and may at times dominate the environment in the area of construction. Caltrans standard specifications restrict construction noise to 86 A-weighted decibels Lmax (the maximum acceptable noise level that can be transmitted from the site when measuring the hourly average using a system in which the decibel values of sounds at low frequencies are reduced) at 50 feet from job site activities from 9:00 p.m. to 6:00 a.m., however the local noise ordinance could be more restrictive. Construction equipment used for road construction typically operates between about 70 and 90 decibels at 50 feet. Most residences along the corridor are at least 120 feet from where construction would be taking place. Based on the formula that noise produced by construction equipment would be reduced at a rate of 6 decibels per doubling of the distance, noise levels at the residences nearest to construction activity could be expected to range between a maximum of 78 and 84 decibels, which is consistent with a noisy, urban, daytime environment.

Bridge widening could periodically be louder during certain activities.

Avoidance, Minimization, and/or Noise Abatement Measures Federal noise abatement measures are restricted to noise barriers; traffic management measures including, but not limited to, prohibition of certain vehicle types, time-use restrictions for certain vehicle types, modified speed limits, and exclusive lane designations; acquisition of a buffer zone; and/or noise insulation. (Noise insulation applies to only specific types of particularly noise-sensitive activities.)
The project could incorporate pavement that reduces some traffic noise, but this is only a temporary measure as the noise-reducing characteristic decreases over time. Solid concrete safety barrier on the outside shoulders would also decrease the noise from tire rotation somewhat, but is not proposed for this project. It also would not address noise from loud engines, truck brakes, or horns.

Soundwalls have been evaluated and could fully mitigate impacts from noise for adjacent residences, but many residents would still experience elevated noise levels as a result of the project. Final recommendations on any federal abatement measure are determined during the public involvement processes and the project’s final design. Based on the studies completed to date and input from the public, Caltrans does not intend to incorporate noise abatement in the Attachment 3
Council Agenda 12-5-2023 12.A-94
Packet Page 345

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 71
form of soundwalls, but the final decision on noise abatement will be made upon completion of the project design.

Limiting construction to daylight hours would eliminate most construction noise concerns. If this cannot be achieved, surrounding residents will be notified in advance of the construction schedule. Notification will include information on upcoming construction activities that are likely to disrupt normal nighttime activities. In addition, noise metering will be conducted and checked regularly to assure activities remain within allowable levels. If necessary, temporary sound barriers could be constructed.

2.3 Biological Environment
Natural Communities
This section of the document discusses natural communities of concern. The focus of this section is on biological communities, not individual plant or animal species. Habitat areas that have been designated as critical habitat under the Federal Endangered Species Act are discussed in section 2.3.4 Threatened and Endangered Species. Wetlands and other waters are discussed in section 2.3.2.

Affected Environment
Resource: Natural Environment Study, May 2020.

Land next to the highway is dominated by disturbed, ruderal roadside vegetation with large patches of ice plant or other ornamental species. Patches of coastal scrub exist on the north side of the highway in the vicinity of Mattie Road, extending into the median near the southbound Highway 1 off-ramp, as well as between Pismo Creek and the railroad. In these regions, the coastal scrub consists of coyote bush, poison oak, California sagebrush, and sticky monkeyflower. There is oak woodland at the northern end of the project near San Luis Obispo Creek, populated mostly by coast live oak trees, with a poorly developed understory. Individual mature trees are scattered throughout the project limits, particularly in the median, where most of the project disturbance would occur. The trees within the project limits are considered more of a scenic resource than a biological one, and therefore are covered in section 2.1.2 Visual/Aesthetics.

Riparian habitat in the form of arroyo willows occurs at San Luis Creek but would not be affected by the project. The vegetative community along Pismo Creek within the project limits is heavily altered and disturbed; arroyo willow habitat was recently established on the west bank of the creek as part of the mitigation plan for the recently completed project to repair scour under the bridge, but would likely be disturbed during construction. Both sides of the channel support mainly ornamental landscaping and/or exotic weedy species, including spider gum and Attachment 3
Council Agenda 12-5-2023 12.A-95
Packet Page 346

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 72
silk oak. Chilean fig is also abundant in patches along the bank slopes. A small patch of native arroyo willow with an understory of California blackberry occurs along the eastern bank downstream from the bridges.

No aquatic vegetation was found growing in the channel within the biological study area, though patches of broadleaf cattail and other emergent species occur within the channel upstream and downstream.

Within the project area, Pismo Creek supports unvegetated open water stream habitat that is often cloudy with visible algal growth, but nonetheless is suitable for fish and other aquatic species. More discussion on Pismo Creek can be found in section 2.3.2 Wetlands and Other Waters.

Environmental Consequences
Alternative 1 and the truck-climbing lane variation would have the greatest impacts to coastal scrub habitat with 506 square feet of permanent impacts.

Alternative 2 would have no impacts on coastal scrub. All build alternatives would temporarily impact about 2.5 acres during construction, which could be restored after construction.

No permanent impacts to arroyo willow riparian habitat are expected with any of the build alternatives, but all would temporarily impact about 3,000 square feet near Pismo Creek. These areas would also be restored after construction completion.

Avoidance, Minimization, and/or Mitigation Measures
Prior to construction, in accordance with CEQA, Caltrans would prepare a Mitigation and Monitoring Plan to track and record actions taken to counter impacts to vegetation and natural habitats. The Mitigation and Monitoring Plan would be modified as necessary to address permit conditions or other changes.

Standard Plans include measures to address hazardous materials spills during construction and erosion control. In addition, the following minimization measures are recommended for inclusion in the Mitigation and Monitoring Plan:

1. Prior to any ground-disturbing activities, fencing will be installed around environmentally sensitive areas and around the dripline of trees to be protected within project limits. These areas will be noted on design plans.

2. Disturbed areas of coastal scrub would be replanted with appropriate native species after construction has completed. Arroyo willows would be replanted at a 3 to 1 ratio.

3. During construction, Caltrans will ensure that the spread or introduction of invasive exotic plant species will be avoided to the maximum extent possible.

When practicable, invasive exotic plants in the project site will be removed and properly disposed of. All vegetation removed from the construction site will be taken to a certified landfill to prevent the spread of invasive species. If soil from Attachment 3
Council Agenda 12-5-2023 12.A-96
Packet Page 347

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 73
weedy areas must be removed off-site, the top 6 inches containing the seed layer in areas with weedy species will be disposed of at a certified landfill.

Wetlands and Other Waters
Regulatory Setting
Wetlands and other waters are protected under a number of laws and regulations. At the federal level, the Federal Water Pollution Control Act, more commonly referred to as the Clean Water Act (33 U.S. Code 1344), is the main law regulating wetlands and surface waters. One purpose of the Clean Water Act is to regulate the discharge of dredged or fill material into waters of the U.S., including wetlands. Waters of the U.S. include navigable waters, interstate waters, territorial seas, and other waters that may be used in interstate or foreign commerce. The lateral limits of jurisdiction over non-tidal water bodies extend to the ordinary high water mark, in the absence of adjacent wetlands.

When adjacent wetlands are present, Clean Water Act jurisdiction extends beyond the ordinary high water mark to the limits of the adjacent wetlands.

To classify wetlands for the purposes of the Clean Water Act, a three-parameter approach is used that includes the presence of: hydrophytic (water-loving) vegetation, wetland hydrology, and hydric soils (soils formed during saturation or inundation). All three parameters must be present, under normal circumstances, for an area to be designated as a jurisdictional wetland under the Clean Water Act.

Section 404 of the Clean Water Act establishes a regulatory program that provides that discharge of dredged or fill material cannot be permitted if a practicable alternative exists that is less damaging to the aquatic environment or if the nation’s waters would be significantly degraded. The Section 404 permit program is run by the U.S. Army Corps of Engineers with oversight by the U.S.

Environmental Protection Agency.

The U.S. Army Corps of Engineers issues two types of 404 permits: general and individual. There are two types of general permits: regional and nationwide.

Regional permits are issued for a general category of activities when they are similar in nature and cause minimal environmental effect. Nationwide permits are issued to allow a variety of minor project activities with no more than minimal effects.

Ordinarily, projects that do not meet the criteria for a regional or nationwide permit may be permitted under one of the U.S. Army Corps of Engineers’ individual permits. There are two types of individual permits: standard permits and Letters of Permission. For individual permits, the U.S. Army Corps of Engineers’ decision to approve is based on compliance with U.S. Environmental Protection Agency’s Section 404(b)(1) Guidelines (Code of Federal Regulations Title 40, Part 230), and whether permit approval is in the public interest. The Section 404(b)(1) Guidelines were developed by the U.S. Environmental Protection Agency in conjunction with the U.S. Army Corps of Engineers, and Attachment 3
Council Agenda 12-5-2023 12.A-97
Packet Page 348

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 74
allow the discharge of dredged or fill material into the aquatic system (waters of the U.S.) only if there is no practicable alternative that would have fewer adverse effects. The guidelines state that the U.S. Army Corps of Engineers may not issue a permit if there is a “least-environmentally-damaging practicable alternative” to the proposed discharge that would have lesser effects on waters of the U.S., and not have any other significant adverse environmental consequences.

The Executive Order for the Protection of Wetlands (Executive Order 11990) also regulates the activities of federal agencies with regard to wetlands.

Executive Order 11990 states that a federal agency, such as the Federal Highway Administration and/or Caltrans, as assigned, cannot undertake or provide assistance for new construction located in wetlands unless the head of the agency finds: (1) that there is no practicable alternative to the construction and (2) the proposed project includes all practicable measures to minimize harm. A Wetlands Only Practicable Alternative Finding must be made.

At the state level, wetlands and waters are regulated mainly by the State Water Resources Control Board, the Regional Water Quality Control Boards and the California Department of Fish and Wildlife. In certain circumstances, the Coastal Commission (or Bay Conservation and Development Commission or the Tahoe Regional Planning Agency) may also be involved. Sections 1600-1607 of the California Department of Fish and Game Code require any agency that proposes a project that will substantially divert or obstruct the natural flow of or substantially change the bed or bank of a river, stream, or lake to notify the California Department of Fish and Wildlife before beginning construction. If the California Department of Fish and Wildlife determines that the project may substantially and adversely affect fish or wildlife resources, a Lake or Streambed Alteration Agreement will be required. The California Department of Fish and Wildlife jurisdictional limits are usually defined by the tops of the stream or lake banks, or the outer edge of riparian vegetation, whichever is wider. Wetlands under jurisdiction of the U.S. Army Corps of Engineers may or may not be included in the area covered by a Streambed Alteration Agreement obtained from the California Department of Fish and Wildlife.

The Regional Water Boards were established under the Porter-Cologne Water Quality Control Act to oversee water quality. Discharges under the Porter- Cologne Act are permitted by Waste Discharge Requirements and may be required even when the discharge is already permitted or exempt under the Clean Water Act. In compliance with Section 401 of the Clean Water Act, the Regional Water Boards also issue water quality certifications for activities that may result in a discharge to waters of the U.S. This is most frequently required in tandem with a Section 404 permit request. See section 2.2.2 Water Quality and Storm Water Runoff for more details.

Affected Environment
Resource: Natural Environment Study, May 2020.

Attachment 3
Council Agenda 12-5-2023 12.A-98
Packet Page 349

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 75
Pismo Creek is considered “other waters of the U.S.” under the Clean Water Act and is defined as the area at or below the ordinary high water mark. Though there is riparian habitat upstream and downstream of the project location, the active channel within the project area is unvegetated and normally flows all year during non-drought periods. The entire creek bed is within the jurisdiction of the California Department of Fish and Wildlife; the active creek channel falls within the jurisdictions of the U.S. Army Corps of Engineers and the Central Coast Regional Water Quality Control Board. A jurisdictional determination from the U.S. Army Corps of Engineers is anticipated during the design phase and would be required before a Section 404 permit is issued.

The creek supports habitat for the south-central California coast steelhead and tidewater goby, as well as other native species such as the western pond turtle and California red-legged frog.

Environmental Consequences
No new piers would be placed within the Pismo Creek channel, but reconstruction of the slope paving would involve placing sheet piling within the creek, creating approximately 9 square feet of permanent impacts. Use of cofferdams would be required during construction to dewater the area, creating about 8,300 square feet of temporary impacts. Figure 2-19 shows the location of these impacts under the southbound bridge over Pismo Creek.

Figure 2-19 Impacts to Other Waters
Avoidance, Minimization, and/or Mitigation Measures
In addition to standard provisions that require actions to control hazardous waste and pollutants, erosion, and the spread of invasive species during Attachment 3
Council Agenda 12-5-2023 12.A-99
Packet Page 350

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 76
construction, the following minimization measures are recommended for inclusion in the Mitigation and Monitoring Plan under CEQA:

1.Prior to any ground-disturbing activities, fencing will be installed around jurisdictional waters, environmentally sensitive habitat areas, and the dripline of trees to be protected within project limits. Caltrans-defined environmentally sensitive areas will be noted on design plans and delineated in the field prior to the start of construction activities.

2.Construction activities in jurisdictional waters will be timed to occur between June 1 and October 31 in any given year, or as otherwise directed by the regulatory agencies, when the surface water is likely to have a low flow rate or at seasonal minimum. Deviations from this work window will be made only with permission from the relevant regulatory agencies.

3.During construction, cleaning and refueling equipment and vehicles will occur only within a designated staging area at least 100 feet from other waters and other aquatic areas. The staging areas will conform to best management practices applicable to attaining zero discharge of stormwater runoff. Equipment and vehicles will be checked and maintained by the contractor daily to ensure proper operation and avoid potential leaks or spills.

4.Stream contours will be restored as close as possible to their original condition.

5.To mitigate for impacts to federal jurisdictional other waters, enhancement plantings are anticipated to be proposed onsite and in-kind. A Caltrans biologist and landscape architect will develop planting specifications to assure survival of planted vegetation. The Pismo Creek corridor is thick with non-native trees and shrubs and could benefit from replacing exotics with native species such as arroyo willow. Impacts to native arroyo willow trees that are larger than 6 inches in diameter at breast height would be offset by replacement planting within the project limits using a 3 to 1 ratio for each arroyo willow tree removed.

Animal Species
Regulatory Setting
Many state and federal laws regulate impacts to wildlife. The U.S. Fish and Wildlife Service, the National Oceanic and Atmospheric Administration’s National Marine Fisheries Service (National Fisheries), and the California Department of Fish and Wildlife are responsible for implementing these laws.

This section discusses potential impacts and permit requirements associated with animals not listed or proposed for listing under the federal or state Endangered Species Act. Species listed or proposed for listing as threatened or endangered are discussed in section 2.3.4 Threatened and Endangered Species. All other special- status animal species are discussed here, including California Department of Fish Attachment 3
Council Agenda 12-5-2023 12.A-100
Packet Page 351

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 77
and Wildlife fully protected species and species of special concern, and the U.S.

Fish and Wildlife Service or National Fisheries candidate species.

Federal laws and regulations relevant to wildlife include the following:
·National Environmental Policy Act
·Migratory Bird Treaty Act
·Fish and Wildlife Coordination Act
State laws and regulations relevant to wildlife include the following:
·California Environmental Quality Act
·Sections 1600–1603 of the California Fish and Game Code ·Sections 4150 and 4152 of the California Fish and Game Code Affected Environment
Resource: Natural Environment Study, May 2020.

White-tailed Kite and Other Nesting Birds
The white-tailed kite is a raptor protected under the Migratory Bird Treaty Act and is fully protected under the California Endangered Species Act. This protection is conveyed on those animals that are rare or face possible extinction; no impacts to the species are permitted. The kite is a year-long resident ranging throughout the valley and coastal lowlands in California and, most commonly, near agricultural areas. Nesting and roosting occur in dense, broad-leafed deciduous groves of trees. Breeding occurs from February to October, peaking from May to August. No white-tailed nesting habitat occurs within the project area, and only marginal foraging habitat is present. However, white-tailed kites have been seen on the coast at Pismo Beach and therefore could be in the project vicinity during foraging activities or while flying to and from nesting sites.

The white-tailed kite was not seen during surveys, and no nesting habitat occurs within the biological survey area, but several individuals were recorded nearby in 2019. Numerous other bird species, both native and non-native, were seen in the project vicinity and could be nesting within the project limits in trees, shrubs, and under the bridges. American cliff swallow mud nests were found under the US 101 southbound bridge over Pismo Creek.

Western Pond Turtle
The western pond turtle is considered a species of special concern by the California Department of Fish and Wildlife. These turtles live where water persists year-round in ponds along foothill streams or in broad washes near the coast. They favor ponds with surfaces such as vegetation mats or floating logs on which they can bask. They are mostly aquatic, leaving the water mainly to Attachment 3
Council Agenda 12-5-2023 12.A-101
Packet Page 352

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 78
reproduce, during summer dormancy, and possibly during the winter. In warmer areas, such as within the project area, pond turtles may be active all year.

The species was not observed during surveys, but suitable aquatic habitat is within the biological study area. During construction of another project in the area—the Pismo Scour Repair Project—a single adult western pond turtle was relocated during dewatering activities. There are other occurrence records for the western pond turtle in Pismo Creek and within ponds in the watershed.

Environmental Consequences
White-tailed Kite and Other Nesting Birds
Project impacts to the white-tailed kite must be fully avoided. In the absence of the kite, however, vegetation removal could impact active bird nests and any eggs or young residing in nests, while construction activities too near active nests could affect nest success.

Western Pond Turtle
If western pond turtles are present onsite, construction activities could result in injury to or death of a western pond turtle during diversion/dewatering. The potential need to capture and relocate this species would subject individuals to stresses that could result in adverse effects. Erosion and sedimentation could also occur, which would directly or indirectly affect water quality. The potential for these impacts is anticipated to be low due to the limited area of impact associated with the project.

Avoidance, Minimization, and/or Mitigation Measures
The following avoidance and minimization measures are recommended for inclusion in the Mitigation and Monitoring Plan under CEQA.

White-tailed Kite and Other Nesting Birds
The following measures apply to all birds protected by the Migratory Bird Treaty Act and California Fish and Game Code. These measures are expected to allow avoidance of all impacts to nesting birds.

1.Tree removal will be scheduled to occur from September 2 to January 31, outside of the typical nesting bird season, to avoid potential impacts to nesting birds. If construction activities are proposed to occur within 100 feet of potential habitat during the nesting season (February 1 to August 31), a nesting bird survey will be conducted by a biologist determined qualified by Caltrans no more than two weeks (14 days) prior to construction. If an active nest is found, Caltrans will determine an appropriate buffer based on the habits and needs of the species. The buffer area will be avoided until a qualified biologist has determined that juveniles have fledged and are no longer dependent upon the nest.

2.Active bird nests will not be disturbed and eggs or young of birds covered by the Migratory Bird Treaty Act and California Fish and Game Code will not be Attachment 3
Council Agenda 12-5-2023 12.A-102
Packet Page 353

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 79
killed, destroyed, injured, or harassed at any time. Readily visible exclusion zones where nests must be avoided will be established by a qualified biologist using fencing. It is recommended that bird nests be excluded from the existing bridge. Nesting bird exclusion methods may include: installing exclusion netting; removing/knocking down nests before they contain eggs; or other methods approved by California Department of Fish and Wildlife.

The proper time for installing bird exclusion netting is outside of the typical nesting season.

3.Trees to be removed will be noted on design plans. Prior to any ground- disturbing activities, fencing will be installed around the dripline of trees to be protected within project limits.

Western Pond Turtle
Prior to construction, a biologist determined qualified by Caltrans will survey the biological study area and, if present, capture and relocate any western pond turtles to suitable habitat upstream. If western pond turtles or other special concern aquatic species are observed during construction, they will likewise be relocated to suitable upstream habitat by a qualified biologist.

Threatened and Endangered Species
Regulatory Setting
The main federal law protecting threatened and endangered species is the Federal Endangered Species Act (Federal Act): 16 U.S. Code Section 1531, et seq. See also Code of Federal Regulations Title 50, Part 402. This act and later amendments provide for the conservation of endangered and threatened species and the ecosystems upon which they depend. Under Section 7 of this act, federal agencies, such as the Federal Highway Administration (and Caltrans, as assigned), are required to consult with the U.S. Fish and Wildlife Service and the National Oceanic and Atmospheric Administration’s National Marine Fisheries Service (National Fisheries) to ensure that they are not undertaking, funding, permitting, or authorizing actions likely to jeopardize the continued existence of listed species or destroy or adversely modify designated critical habitat. Critical habitat is defined as geographic locations critical to the existence of a threatened or endangered species. The outcome of consultation under Section 7 may include a Biological Opinion with an Incidental Take Statement or a Letter of Concurrence. Section 3 of the Federal Act defines take as “harass, harm, pursue, hunt, shoot, wound, kill, trap, capture or collect or any attempt at such conduct.”
California has enacted a similar law at the state level, the California Endangered Species Act (California Act), California Fish and Game Code Section 2050, et seq. The California Act emphasizes early consultation to avoid potential impacts to rare, endangered, and threatened species and to develop appropriate planning to offset project-caused losses of listed species populations and their Attachment 3
Council Agenda 12-5-2023 12.A-103
Packet Page 354

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 80
essential habitats. The California Department of Fish and Wildlife is the agency responsible for implementing the California Act. Section 2080 of the California Fish and Game Code prohibits “take” of any species determined to be an endangered species or a threatened species. Take is defined in Section 86 of the California Fish and Game Code as “hunt, pursue, catch, capture, or kill, or attempt to hunt, pursue, catch, capture, or kill.” The California Act allows for take incidental to otherwise lawful development projects; for these actions, an incidental take permit is issued by California Department of Fish and Wildlife.

For species listed under both the Federal Act and the California Act requiring a Biological Opinion under Section 7 of the Federal Act, the California Department of Fish and Wildlife may also authorize impacts to the California Act species by issuing a Consistency Determination under Section 2080.1 of the California Fish and Game Code.

Another federal law, the Magnuson-Stevens Fishery Conservation and Management Act of 1976, was established to conserve and manage fishery resources found off the coast, as well as anadromous species and Continental Shelf fishery resources of the U.S., by exercising (A) sovereign rights for the purposes of exploring, exploiting, conserving, and managing all fish within the exclusive economic zone established by Presidential Proclamation 5030, dated March 10, 1983, and (B) exclusive fishery management authority beyond the exclusive economic zone over such anadromous species, Continental Shelf fishery resources, and fishery resources in special areas.

Affected Environment
Resource: Natural Environment Study, May 2020.

California Red-legged Frog
The California red-legged frog is federally threatened and a California species of special concern. These frogs breed in permanent or temporary freshwater bodies that will hold water through July, though they require permanent water for hydration. They will move between aquatic sites to breed, forage, or escape drying conditions. Their overland movements can extend more than 2 miles, often in straight lines and without regard to habitat type.

No protocol surveys were conducted for the California red-legged frog, and the species was not seen during recent field surveys. There is no federally designated critical habitat for the California red-legged frog within the project area. The species is not expected to occur within the area of disturbance, but it was seen in a Pismo Creek tributary in 2005. For this reason, its presence during construction cannot be completely ruled out, and presence has been inferred.

Steelhead Trout
Steelhead trout are the anadromous (ocean-going) form of rainbow trout and are federally threatened and a California species of special concern. Adults spawn and juveniles rear in freshwater. The juveniles then either remain in freshwater Attachment 3
Council Agenda 12-5-2023 12.A-104
Packet Page 355

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 81
or migrate to the ocean to mature, subsequently returning to freshwater as adults to reproduce.

Pismo Creek provides migration habitat for adult and juvenile south-central California coast steelhead and is designated critical habitat. In 2019, individuals were relocated from the project area prior to construction on the bridge piers.

Because of the critical habitat designation and the recent presence of these fish, it has been inferred that the project area could contain adult and juvenile steelhead at the time of construction.

Tidewater Goby
The tidewater goby is federally endangered and a California species of special concern. This fish resides in coastal lagoons and the lower reaches of freshwater creeks flowing into coastal lagoons. Pismo Creek is designated critical habitat for this species; in 2019, individuals were relocated from the project area prior to construction on the bridge piers. Because of the critical habitat designation and the recent presence of these fish, it has been inferred that the project area could contain the tidewater goby at the time of construction.

Federally designated critical habitat for the tidewater goby occurs in the western portion of the biological study area at Pismo Creek; the creek bed supports the construction of burrows for reproduction.

Environmental Consequences
California Red-legged Frog
If frogs were present on the project site, construction could result in the injury or mortality of individuals present in aquatic areas or those residing in small mammal burrows within upland habitat. It is possible that frogs would need to be captured and relocated if found within an area needing to be dewatered. Frog habitat would be impacted during construction, but has no specific protection other than as discussed in section 2.3.3 Wetlands and Other Waters.

The Federal Endangered Species Act (Federal Act) Section 7 effects determination is that the proposed project may affect, and is likely to adversely affect, the California red-legged frog. Caltrans requested concurrence on this determination from the U.S. Fish and Wildlife Service on July 2, 2020; concurrence was received on November 3, 2020.

Steelhead Trout
The addition of sheet pile within the riverine habitat (the active channel, below the ordinary high water mark) would result in permanent impacts and could also temporarily alter aquatic habitat quality. However, this activity would be implemented when steelhead are not likely to be present in the project area.

Vegetation removal to allow access to piers could somewhat affect shading and micro-habitat temperature characteristics along the edges of the creek and could alter the stability of the banks. These effects, however, would also be Attachment 3
Council Agenda 12-5-2023 12.A-105
Packet Page 356

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 82
temporary. Vegetation proposed for removal would be replaced by native riparian plantings in a relatively short timeframe.

Diversion, dewatering, and construction in aquatic areas used by migrating steelhead could result in direct impacts to the species through injury or mortality as steelhead stranded in residual wet areas are captured, handled, and relocated. The activities could also impact the structure of the streambed substrate, causing erosion and sedimentation, which could directly or indirectly affect water quality for steelhead. These impacts would likely be temporary and rectified once the pre-construction stream flow conditions are restored. In total, the project would result in approximately 8.8 square feet of permanent impacts and 8,300 square feet of temporary impacts to steelhead critical habitat along about 80 linear feet of the channel.

The Federal Act Section 7 effects determination is that the proposed project may affect, and is likely to adversely affect, the south-central California coast steelhead. The proposed project may affect, and is likely to adversely affect, steelhead critical habitat. Caltrans requested concurrence on this determination from the National Marine Fisheries Service (National Fisheries) on July 8, 2020; a biological opinion was received on December 7, 2020 that the project is not likely to jeopardize the identified population segment of steelhead or destroy or modify its designated critical habitat. National Fisheries staff believe, however, that the project is likely to result in incidental take of steelhead.

Tidewater Goby
The tidewater goby within Pismo Creek would be subject to the same impacts during construction as described for steelhead. Approximately 2,750 square feet of federally designated tidewater goby critical habitat would be temporarily impacted by turbidity during sheet pile installation locally and downstream of the bridges, but there would be no permanent impacts to tidewater goby habitat as a result of the project.

The Federal Act Section 7 effects determination is that the proposed project may affect, and is likely to adversely affect, the tidewater goby. The proposed project may affect, and is likely to adversely affect, tidewater goby critical habitat. Caltrans requested concurrence on this determination from the U.S.

Fish and Wildlife Service on July 2, 2020; a biological opinion was received on November 3, 2020 that the project may adversely affect the tidewater goby and tidewater goby critical habitat during construction and through habitat degradation, however the effects on the tidewater goby would be low with incorporation of the proposed mitigation.

A “no effects” finding was made for all other listed/proposed species and designated or proposed critical habitat on both U.S. Fish and Wildlife Service (U.S. Wildlife Service) and National Fisheries species lists, included in Volume 2.

Attachment 3
Council Agenda 12-5-2023 12.A-106
Packet Page 357

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 83
Avoidance, Minimization, and/or Mitigation Measures
The following avoidance and minimization measures are recommended for inclusion in the Mitigation and Monitoring Plan under CEQA.

California Red-legged Frog
Caltrans anticipates the project will qualify for Federal Act incidental take coverage under the Programmatic Biological Opinion for Projects Funded or Approved under the Federal Highway Administration’s Federal Aid Program.

While all the measures in the California red-legged frog programmatic biological opinion will be adhered to, the following measures are the ones most applicable to this project:

1.Only U.S. Wildlife Service-approved biologists will participate in activities associated with the capture, handling, and monitoring of California red- legged frogs.

2.Ground disturbance will not begin until written approval is received from the U.S. Wildlife Service that the biologist is qualified to conduct the work.

3.A U.S. Wildlife Service-approved biologist will survey the project area no more than 48 hours before the onset of work activities. If any life stage of the California red-legged frog is found and these individuals are likely to be killed or injured by work activities, the approved biologist will be allowed sufficient time to move them from the site before work begins. The U.S. Wildlife Service-approved biologist will relocate the California red-legged frogs the shortest distance possible to a location that contains suitable habitat and will not be affected by the activities associated with the project. The relocation site will be in the same drainage to the extent practicable. Caltrans will coordinate with the U.S. Wildlife Service on the relocation site prior to the capture of any California red-legged frogs.

4.Before any activities begin on a project, a U.S. Wildlife Service-approved biologist will conduct a training session for all construction personnel. At a minimum, the training will include a description of the California red-legged frog and its habitat, the specific measures that are being implemented to conserve California red-legged frog for the current project, and the boundaries within which the project may be accomplished. Brochures, books, and briefings may be used in the training session, provided that a qualified person is on hand to answer any questions.

5.A U.S. Wildlife Service-approved biologist will be present at the work site until all California red-legged frogs have been removed, workers have been instructed, and disturbance of the habitat has been completed. After this time, Caltrans will designate a person to monitor onsite compliance with all minimization measures. The U.S. Wildlife Service-approved biologist will ensure that this monitor receives the training outlined in measure 4 above and in the identification of California red-legged frogs. If the monitor or the U.S. Wildlife Service-approved biologist recommends that work be stopped Attachment 3
Council Agenda 12-5-2023 12.A-107
Packet Page 358

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 84
because California red-legged frogs would be affected in a manner not anticipated by Caltrans and U.S. Wildlife Service during review of the proposed action, he or she will notify the resident engineer immediately. The resident engineer will resolve the situation by requiring that all actions that are causing these effects be halted. When work is stopped, the U.S. Wildlife Service will be notified as soon as possible.

6.During project activities, all trash that may attract predators or scavengers will be properly contained, removed from the work site, and disposed of regularly. Following construction, all trash and construction debris will be removed from work areas.

7.All refueling, maintenance and staging of equipment and vehicles will occur at least 60 feet from the riparian habitat or water bodies and not in a location from where a spill would drain directly toward aquatic habitat. The monitor will ensure contamination of habitat does not occur during such operations.

Prior to the onset of work, Caltrans will ensure that a plan is in place for prompt and effective response to any accidental spills. All workers will be informed of the importance of preventing spills and of the appropriate measures to take should a spill occur.

8.Habitat contours will be returned to a natural configuration at the end of the project activities. This measure will be implemented in all areas disturbed by activities associated with the project, unless U.S. Wildlife Service and Caltrans determine that it is not feasible or modification of original contours would benefit the California red-legged frog.

9.Caltrans will attempt to schedule work for times of the year when impacts to the California red-legged frog would be minimal. For example, work that would affect large pools that may support breeding would be avoided, to the maximum degree practicable, during the breeding season (November through May). Isolated pools that are important to maintain California red-legged frogs through the driest portions of the year would be avoided, to the maximum degree practicable, during the late summer and early fall. Habitat assessments, surveys, and technical assistance between Caltrans and the U.S. Wildlife Service during project planning will be used to assist in scheduling work activities to avoid sensitive habitats during key times of year.

10.To control sedimentation during and after project completion, Caltrans will implement best management practices outlined in any authorizations or permits issued under the authorities of the Clean Water Act received for the project. If best management practices are ineffective, Caltrans will attempt to remedy the situation immediately, in coordination with the U.S. Wildlife Service.

11.If a work site is to be temporarily dewatered by pumping, intakes will be completely screened with wire mesh not larger than 0.094 inch (2.38 mm) to prevent California red-legged frogs, tadpoles, and other aquatic organisms from entering the pump system. Water will be released or pumped down- stream at an appropriate rate to maintain downstream flows during construction. Upon completion of construction activities, any diversions or Attachment 3
Council Agenda 12-5-2023 12.A-108
Packet Page 359

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 85
barriers to flow will be removed in a manner that would allow flow to resume with the least disturbance to the substrate. Alteration of the streambed will be minimized to the maximum extent possible; any imported material will be removed from the streambed upon completion of the project.

12.Unless approved by the U.S. Wildlife Service, water will not be impounded in a manner that may attract California red-legged frogs.

13.A U.S. Wildlife Service-approved biologist will permanently remove any individuals of exotic species, such as bullfrogs, signal and red swamp crayfish, centrarchid fishes (crappies, black bass, bluegills), and catfish from the project area, to the maximum extent possible. The U.S. Wildlife Service- approved biologist will be responsible for ensuring his or her activities are in compliance with the California Fish and Game Code.

14.To ensure that diseases are not conveyed between work sites by the U.S.

Wildlife Service-approved biologist, the fieldwork code of practice developed by the Declining Amphibian Task Force will be followed at all times.

15.Project sites will be revegetated with an assemblage of native riparian, wetland, and upland vegetation suitable for the area. Locally collected plant materials will be used to the extent practicable. Invasive, exotic plants will be controlled to the maximum extent practicable. This measure will be implemented in all areas disturbed by activities associated with the project, unless the U.S. Wildlife Service and Caltrans determine that it is not feasible or practical.

16.Upon completion of the project, Caltrans will ensure that a Project Completion Report is completed and provided to the U.S. Wildlife Service, following the template provided with the Programmatic Biological Opinion. Caltrans will include recommended modifications of the protective measures if alternative measures would facilitate compliance with the provisions of this consultation.

Steelhead Trout
In addition to the previously proposed measures, the following measures will serve to further avoid or minimize impacts to steelhead:

17.Prior to initiation of stream diversion/dewatering, a qualified biologist will conduct an informal worker environmental training program including a description of steelhead, its legal/protected status, proximity to the project site, avoidance/minimization measures to be implemented during the project, and the implications of violating Federal Act and permit conditions.

18.During in-stream work, a National Fisheries-approved biologist will be retained with experience in steelhead biology and ecology, aquatic habitats, biological monitoring (including diversion/dewatering), and capturing, handling, and relocating fish species. During in-stream work, the biological monitor(s) will continuously monitor placement and removal of any required stream diversions to capture stranded steelhead and other native fish species and relocate them to suitable habitat as appropriate. The biologist(s) will capture steelhead stranded as a result of diversion/dewatering and Attachment 3
Council Agenda 12-5-2023 12.A-109
Packet Page 360

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 86
relocate steelhead to suitable in-stream habitat immediately downstream of the work area. The biologist will note the number of steelhead observed in the affected area, the number of steelhead relocated, and the date and time of the collection and relocation.

19.During in-stream work, if pumps are incorporated to assist in temporarily dewatering the site, intakes will be completely screened with no larger than

0.094-inch (2.38 mm) wire mesh to prevent steelhead and other sensitive aquatic species from entering the pump system. Pumps will release the additional water to a settling basin, allowing the suspended sediment to settle out prior to re-entering the stream(s) outside of the isolated area. The form and function of all pumps used during the dewatering activities will be checked daily, at a minimum, by a qualified biological monitor to ensure a dry work environment and minimize adverse effects to aquatic species and habitats.

20.The biological monitor will monitor erosion and sediment controls to identify and correct any conditions that could adversely affect steelhead or steelhead habitat. The biological monitor will be granted the authority to halt work activity as necessary and to recommend measures to avoid/minimize adverse effects to steelhead and steelhead habitat.

21.Dewatering will be limited to the low-flow period between June 1 and October 31, thus avoiding adult steelhead spawning migration and peak smolt emigration.

22.Caltrans will provide National Fisheries a written summary of work performed (including biological survey and monitoring results), best management practices implemented and supporting photographs. Furthermore, the documentation describing listed species surveys and relocation efforts will include name(s) of the Caltrans-approved biologist(s), location and description of area surveyed, time and date of survey, all survey methods used, a list and tally of all sensitive animal species observed during the survey, a description of the instructions/ recommendations given to the applicant during the project, and a detailed discussion of capture and relocation efforts.

Tidewater Goby
In addition to the previously proposed measures, the following measures will serve to further avoid or minimize impacts to the tidewater goby:

23.Prior to initiation of stream diversion/dewatering, a qualified biologist will conduct an informal worker environmental training program, including a description of the tidewater goby, its legal/protected status, proximity to the project site, avoidance/minimization measures to be implemented during the project, and the implications of violating Federal Act and permit conditions.

24.Dewatering will be limited to the low-flow period between June 1 and October 31, thus avoiding storm events that may compromise the cofferdams and water diversion.

Attachment 3
Council Agenda 12-5-2023 12.A-110
Packet Page 361

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 87

25.A U.S. Wildlife Service-approved biologist(s) will install 0.125-inch (3.18 mm) block nets outside of the diversion. The nets will be installed on the first day of work and monitored thereafter for the duration of the work.

26.Once the block nets are secured, the U.S. Wildlife Service-approved biologist will remove as many tidewater gobies as feasible between the block nets using a 0.125-inch (3.18 mm) seine and dip nets, and relocate tidewater gobies to suitable habitat downstream of the proposed project site.

27.All tidewater goby relocation methods will use a clean bucket partially filled with creek water that was collected within or adjacent to the capture site.

Water in the bucket will be maintained at the same temperature as water at the capture site and not contain turbidity greater than current conditions in the creek. Captured tidewater gobies will be placed in the bucket, immediately relocated to suitable habitat downstream, and released. Should the relocation of tidewater gobies require more than 10 minutes from capture to release, the bucket containing tidewater gobies must be placed in the creek to keep the water from heating and harming tidewater gobies contained in the bucket.

28.Once as many tidewater gobies are removed from the block net enclosure as is feasible, the cofferdams may be installed within the block net enclosure.

29.Before dewatering occurs, any pumps being used will be fitted with intake screens no larger than 0.094-inch (2.38 mm) wire mesh to prevent tidewater gobies and other sensitive aquatic species from entering the pump system.

Pumps will release the additional water to a settling basin, allowing the suspended sediment to settle out prior to re-entering the creek outside of the isolated area.

30.Because tidewater gobies often reside on the bottom, the pump intake will be floated near the water surface as long as possible to prevent tidewater gobies from being entrapped on the screen. This can be accomplished with a weight on the intake nozzle (to keep it below the water surface), and a float attached to the hose just above the intake nozzle, that keeps the intake nozzle from going all the way to the bottom. As dewatering proceeds, the U.S. Wildlife Service-approved biologist will remove by hand, dip net, or seine all tidewater gobies found and relocate them to suitable habitat downstream of the proposed project site.

31.A U.S. Wildlife Service-approved biologist will remain onsite and observe for tidewater gobies and turbidity levels within the work areas during all creek dewatering activities, and will capture and relocate tidewater gobies to suitable habitat (downstream) as necessary.

32.Caltrans will provide the U.S. Wildlife Service a written summary of work performed (including biological survey and monitoring results), best management practices implemented and supporting photographs.

Furthermore, the documentation describing listed species surveys and relocation efforts will include the name of the U.S. Wildlife Service-approved Attachment 3
Council Agenda 12-5-2023 12.A-111
Packet Page 362

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 88
biologist, location and description of area surveyed, time and date of survey, all survey methods used, a list and tally of all sensitive animal species observed during the survey, a description of the instructions or recommendations given to the applicant during the project, and a detailed discussion of capture and relocation efforts.

Invasive Species
Regulatory Setting
On February 3, 1999, President William J. Clinton signed Executive Order 13112 requiring federal agencies to combat the introduction or spread of invasive species in the United States. The order defines invasive species as “any species, including its seeds, eggs, spores, or other biological material capable of propagating that species, that is not native to that ecosystem whose introduction does or is likely to cause economic or environmental harm or harm to human health.” Federal Highway Administration guidance issued August 10, 1999 directs the use of the State’s invasive species list, maintained by the California Invasive Species Council, to define the invasive species that must be considered as part of the National Environmental Policy Act analysis for a proposed project.

Affected Environment
Resource: Natural Environment Study, May 2020.

A total of 39 invasive plant species as identified by the California Invasive Plant Council Inventory were found within the biological study area. Nine exotic plant species with an invasiveness rating of “high” were observed in the project area:
red brome, cheatgrass, Australian pine, pampas grass, perennial veldt grass, fennel, French broom, English ivy, and lantana. Seventeen plant species with an invasiveness rating of “moderate” and 13 species with an invasiveness rating of “limited” were also observed. The distribution of these invasive plant species is mostly within the Caltrans right-of-way.

Environmental Consequences
Ground disturbance and other construction activities could spread or introduce invasive species within the project limits.

Avoidance, Minimization, and/or Mitigation Measures
The minimization measures identified under section 2.3.1 Natural Communities would address issues from invasive plant species.

2.4 Construction Impacts
This section contains information related to construction activities that have not been previously addressed.

Attachment 3
Council Agenda 12-5-2023 12.A-112
Packet Page 363

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 89
Affected Environment
Traffic
During bridge widening at the Shell Beach undercrossing, Spyglass Drive under the bridge would need to be closed to vehicular traffic for up to 24 hours while falsework is constructed and again when the falsework is removed. Traffic would likely be detoured to Mattie Road and Shell Beach Road. The North Pismo separation at Mattie Road would also need to be similarly closed for falsework construction and removal. Traffic would likely be detoured to the Spyglass Drive or Hinds Avenue overcrossing. Pedestrian access would likely still be available during these closures. Single lane closures would also be required at times during construction.

Environmental Consequences
Traffic
Traffic detours during temporary road closures would require out-of-direction travel for those individuals who would have used the closed section to cross the freeway. The greatest impact would be to those wishing to visit the Pismo Preserve. For motorists intending to travel south from the preserve, detouring westward to the Shell Beach undercrossing would require a 4-mile diversion.

Construction activities could also delay emergency vehicles if they had to detour.

Avoidance, Minimization, and/or Mitigation Measures
Traffic
Advance notice of road closures would be provided to the public and emergency service providers.

Affected Environment
Subsurface Investigation
For construction of the preferred alternative, widening of the existing bridges and construction of a new retaining wall require a subsurface investigation to determine soil and site conditions. This would occur before starting the project construction phase. This would be done by drilling vertical borings, performing in-situ soil testing (Standard Penetration Tests), collecting soil samples for laboratory testing and soil classification, and developing a subsurface soil profile. Borings would be advanced using standard methods through either paved surfaces or through the unpaved median. Drilling would occur as determined necessary to inform the Preliminary Foundation Reports for 3 bridges and 1 retaining wall. Additional subsurface drilling is planned throughout construction for the installation of deep foundation elements.

One truck mounted rotary core drill rig would be required to conduct the drilling at the approximate boring locations. The drill rig would be accompanied by two support vehicles. No unattended storage of supplies or equipment would occur at the boring locations.

Attachment 3
Council Agenda 12-5-2023 12.A-113
Packet Page 364

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 90
All field work is anticipated to occur during the night, Monday through Thursday of the work week. Shoulder and lane closures are necessary for site safety. The anticipated duration of onsite activities is approximately two to three weeks.

Environmental Consequences
Subsurface Investigation
Subsurface investigations have the potential to affect protected cultural resources located within the highway fill prism and down into the native site material.

Avoidance, Minimization, and/or Mitigation Measures
Subsurface Investigation
Archaeological and Native American monitoring will occur during subsurface investigation activities. Subsurface investigation will be conducted in compliance with the Environmentally Sensitive Area Action and Monitoring Plan and the Historic Properties Treatment Plan. Refer to section 2.1.3 Cultural Resources for discussion of these plans.

2.5 Cumulative Impacts
Regulatory Setting
Cumulative impacts are those that result from past, present, and reasonably foreseeable future actions, combined with the potential impacts of the proposed project. A cumulative effect assessment looks at the collective impacts posed by individual land use plans and projects. Cumulative impacts can result from individually minor but collectively substantial impacts taking place over a period of time.

Cumulative impacts to resources in the project area may result from residential, commercial, industrial, and highway development, as well as from agricultural development and the conversion to more intensive agricultural cultivation. These land use activities can degrade habitat and species diversity through consequences such as displacement and fragmentation of habitats and populations, alteration of hydrology, contamination, erosion, sedimentation, disruption of migration corridors, changes in water quality, and introduction or promotion of predators. They can also contribute to potential community impacts identified for the project, such as changes in community character, traffic patterns, housing availability, and employment.

The California Environmental Quality Act (CEQA) Guidelines Section 15130 describes when a cumulative impact analysis is necessary and what elements are necessary for an adequate discussion of cumulative impacts. The definition of cumulative impacts under CEQA can be found in Section 15355 of the CEQA Guidelines. A definition of cumulative impacts under the National Environmental Policy Act can be found in the Code of Federal Regulations Title 40, Part 1508.7.

Attachment 3
Council Agenda 12-5-2023 12.A-114
Packet Page 365

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 91
Affected Environment
Caltrans has identified eight resources that may be undergoing a change due to cumulative impacts of development or are in poor health within the project area.

The resources, their associated study areas, and a brief description of the historic and current health of the resources are described below.

Visual Resources
The resource study area identified for visual resources for this project is defined as the Avila, Shell Beach, and Pismo Beach visual corridor of US 101. This includes ocean and hill viewsheds, as well as the San Luis Creek valley. See section 2.1.2 Visual/Aesthetics for a detailed description.

Cultural Resources
The resource study area identified for cultural resources is the region encompassing the coastal terraces spanning Avila Beach, Shell Beach, Pismo Beach, and Arroyo Grande in San Luis Obispo County. The area used for analyzing cumulative impacts to archaeological resources is defined based not only on geography, but also by time and shared history. This region contains an interrelated set of archaeological sites connected both ethnographically and temporally. The conditions of cultural resources in this region vary depending on natural and cultural influences, which can impact the integrity of a resource or group of resources.

The most obvious impact to cultural resources in the area is a result of human activities. Human settlement, urbanization, population growth, recreational areas, agriculture, ranching, commercial development and infrastructure are some of the main contributors to cumulative effects on historical resources. After World War 2, the area experienced a rise in tourism, large scale agricultural enterprises, and highway improvements. The communities of Avila Beach, Pismo Beach, Shell Beach and Arroyo Grande have grown exponentially as a result and continue to grow today.

Natural factors affecting cultural resources in the resource study area are erosion, sedimentation, soil deflation and sea level rise. The influence of these effects can be exacerbated by human activities such as increased erosion caused by road construction or agricultural practices.

The Archaeological Survey Report found that 43 archaeological sites exist within the resource study area. Virtually every resource has been affected by one or more of the factors mentioned above, resulting in an overall reduction in archaeological deposits and Northern Chumash sacred sites in the resource study area.

Water Quality
The resource study area identified for water quality impacts is the Pismo Creek watershed. Early water quality impacts in the area were a result of Spanish Attachment 3
Council Agenda 12-5-2023 12.A-115
Packet Page 366

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 92
settlers in the 1800s who mostly relied on agriculture and ranching for their economy. Ranching is the main contributor for several pollutants that are listed constituents in Section 303(d) of the Clean Water Act. Other water quality impairments are listed as unknown origin.

Modern development in the resource study area has altered the health of Pismo Creek. The upper reaches of the Pismo Creek watershed are mostly agricultural land uses such as row crops, vineyards, and ranches. The urban center of the City of Pismo Beach is next to the Pismo Creek Estuary. Other land uses that contribute to water quality impacts in the resource study area include a regional landfill, oil extraction, and a wastewater treatment plant. A reduction in vegetation from urbanization and agricultural land uses contributes to an expansion of impervious surfaces in the area and therefore an increase in erosion and stormwater runoff. Increased stormwater runoff results from the surrounding impervious surfaces contributing to incrementally increased creek flows and causes pollution into the creek. Some of these pollutants are listed constituents regulated in Section 303(d) of the Clean Water Act.

Pismo Creek Habitat
This habitat area is typically identified by the creek channel and includes areas where wet soils, water, and water-loving vegetation are present. (For this analysis, wetlands were not included because there are none present within the project limits.) Riparian habitat is typically characterized by its proximity to other waters of the U.S. and wetlands and includes vegetative habitat of varying types. This resource was identified for inclusion in the cumulative impact analysis due to its sensitive nature and poor health. The resource study area identified for jurisdictional areas is the Pismo Creek watershed.

Historically, riparian and aquatic habitats have been in decline. In California, approximately 90 percent of historic riparian resources have been lost to alternative land uses. According to mapping data from the National Wetlands Inventory, approximately 915 acres of various wetlands and/or riverine habitat have been mapped along the Pismo Creek watershed. It is likely that additional wetlands and/or riparian habitat were present along the watershed prior to the construction of US 101, the Union Pacific Railroad, and the existing Pismo Creek Bridge. Riparian and aquatic habitats are degraded resources within this area due to the reduction in riparian canopy, increased sediment loads, and water runoff from agricultural practices. Current threats to these habitats within the resource study area result from the reduction of riparian vegetation, unsustainable agricultural practices, increased impervious surfaces within the watershed, continued urbanization, and oil development. Regulatory agencies have sought to offset the loss of wetlands and riparian habitat with restoration and revegetation requirements for projects within their respective jurisdictions.

Attachment 3
Council Agenda 12-5-2023 12.A-116
Packet Page 367

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 93
Western Pond Turtle
The resource study area identified for the western pond turtle cumulative impacts analysis is the Pismo Creek watershed. Pismo Creek supports habitat for the western pond turtle, and individuals have been found within the creek and within ponds in the watershed. See section 2.3.3 Animal Species for more information.

California Red-legged Frog
The resource study area identified for cumulative impacts to the California red- legged frog is Pismo Creek and adjacent uplands within 2 miles of Pismo Creek due to the ability of the species to travel over land for about 2 miles regardless of vegetation type. California red-legged frogs face threats such as habitat fragmentation, land conversion for agricultural uses, and the increased development of impervious surfaces.

This resource was identified for inclusion in the cumulative impact analysis due to the likelihood that California red-legged frogs have been substantially impacted over time. California red-legged frog population data from Pismo Creek and surrounding areas is not available from existing literature, but California red- legged frogs face threats such as habitat fragmentation, land conversion for agricultural uses, and the increased development of impervious surfaces. See section 2.3.4 Threatened and Endangered Species for more information.

Steelhead Trout and Steelhead Critical Habitat
The resource study area identified for steelhead trout and steelhead critical habitat cumulative impacts is the Pismo Creek watershed. Historically, steelhead ranged from Alaska southward to the California-Mexico border and were the only abundant salmonid species that occurred naturally within the coast ranges of Southern California. With the increase of the human population in Southern California in the 20th century and the associated land and water development within the coastal drainages (mainly dams and water diversions), steelhead numbers quickly declined, resulting in extinguished populations in many watersheds and sporadic and remnant populations in the remaining watersheds. As a result, the south-central California steelhead was listed as federally endangered under the Federal Endangered Species Act in 1997, with designation of critical habitat in 2005. As a result, according to a 2011 status review, there is little new evidence to suggest that the status of the south -central California coast steelhead unit has changed appreciably since 2005. New information available on anadromous runs since the 2005 review remains limited and does not appear to suggest a change in extinction risk. See section 2.3.4 Threatened and Endangered Species for more information on this species.

Tidewater Goby and Tidewater Goby Critical Habitat
The resource study area identified for the tidewater goby and tidewater goby critical habitat cumulative impacts analysis is the Pismo Creek watershed.

Attachment 3
Council Agenda 12-5-2023 12.A-117
Packet Page 368

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 94
Tidewater gobies have been collected during surveys along Pismo Creek since 1977; no other pertinent population data for the tidewater goby within the research study area was available, but critical habitat for the tidewater goby was first designated in 2008, then again in 2013 due to continued uncertainty for species success. Along the coast of California, critical habitat for the tidewater goby currently remains stable but faces threats from ongoing and future impacts similar to those for steelhead, such as reduced riparian canopy, elevated sediment loads, and runoff carrying sediment and pesticides from agricultural practices. Habitat within the Pismo Creek watershed has suffered degradation from land development, stream channelization, sedimentation, and invasion by exotic frog species.

Table 2-3 lists the projects and resources potentially contributing to cumulative impacts in the resource study areas identified for this analysis. Impact areas were not listed if the project does not reside in the resource study area for the impact or if the project does not potentially impact that resource.

Table 2-3 Projects Potentially Contributing to Cumulative Impacts Project Location Description
Resources Potentially
Impacted in Identified
Resource Study Areas
Pismo Capital
Maintenance
Improvement
Between Garcia
Way and the
South 101/1
Separation in
Pismo Beach
Americans with
Disabilities Act elements
and complete street
elements on Highway 1
None
Avila
Interchange
Improvement
US 101 at Avila
Beach Drive
Roundabout interchange
improvements and park-
and-ride lot
Cultural resources, visual
resources
Pismo Scour
Project
Southbound on-
ramp to US 101
from Price
Street in the City
of Pismo Beach
Improvements to the
banks of Pismo Creek
and piers of Pismo
Creek Bridge to protect
the bridge against
erosion and scour
Jurisdictional areas,
California red-legged frog,
western pond turtle,
steelhead and steelhead
critical habitat, tidewater
goby and tidewater goby
critical habitat, visual
resources, water quality
The Beachwalk
Inn/Vespera on
Ocean
147 Stimson
and 150 Hinds
in Pismo Beach
128-room hotel with
pool, courtyard, deck,
and underground
parking
Cultural resources, visual
resources, water quality
Northeast
Grover Beach
Mixed-Use De-
velopment Plan
North Oak Park
Boulevard in
Grover Beach
New development with 2
hotels and 7 single-
family dwelling units.

Cultural resources, visual
resources, water quality
Spanish Springs East of Pismo
Beach off Price
Canyon Road
Large housing
development
Cultural resources,
jurisdictional areas,
California red-legged frog,
western pond turtle,
steelhead and steelhead
Attachment 3
Council Agenda 12-5-2023 12.A-118
Packet Page 369

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 95
Project Location Description
Resources Potentially
Impacted in Identified
Resource Study Areas
critical habitat, tidewater
goby and tidewater goby
critical habitat, visual
resources, water quality
Pismo Preserve Pismo Preserve
Conservation
area east of
Pismo Beach
Construct two parking
areas, restroom, picnic
facilities, and multi-use
trails
Cultural resources, visual
resources, water quality
Tide Overview
Inn
2121 Price
Street in Pismo
Beach
Demolish existing and
development new hotel
Visual resources
Central Coast
Blue Water
Treatment
Facility
Oceano and
Grover beach
area
Construction of an
advanced treatment
facility
Cultural resources, water
quality
Bello Bridge
Replacement
East of Ocean
View Avenue,
on Bello Street
in City of Pismo
Replace bridge over
Pismo Creek
Cultural resources,
jurisdictional areas,
California red-legged frog,
western pond turtle,
steelhead and steelhead
critical habitat, tidewater
goby and tidewater goby
critical habitat, visual
resources, water quality
Pismo Ranch
Development
Near Price
Canyon Road
and City of
Pismo Beach
Construct 310 single-
family homes, 60 multi-
family units, a 175-room
hotel and 12,000 square
feet of restaurant and
retail space
Cultural resources,
jurisdictional areas,
California red-legged frog,
western pond turtle,
steelhead and steelhead
critical habitat, tidewater
goby and tidewater goby
critical habitat, visual
resources, water quality
Shore Cliff
Lodge
2555 Price
Street in Pismo
Beach
Stabilization of the bluffs
seaward of the Shore
Cliff lodge that are
subject to continuing
erosion
Cultural resources
Avila Beach Golf
Resort
Expansion
Avila Beach golf
course area
Proposal to expand
operations by adding
hotel rooms and
cottages to the property
Cultural resources
The Cottages
Hotel
Near the inter-
section of Avila
Beach Drive and
Ana Bay Drive in
Avila Beach
Proposal to construct 50
cottage-style rentals and
a lodge
Cultural resources
Shell Beach
Road
Streetscape
Downtown Shell
Beach between
Cliff Avenue and
Terrace Avenue
Reconstruct the
roadway, add multi-use
path, and bring
sidewalks into
Americans with
Cultural resources, visual
resources
Attachment 3
Council Agenda 12-5-2023 12.A-119
Packet Page 370

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 96
Project Location Description
Resources Potentially
Impacted in Identified
Resource Study Areas
in City of Pismo
Beach
Disabilities Act
compliance
Price Street
Bluff Projection
Project
2651 Price
Street between
Mattie Road/US
101 underpass
and Cliff Avenue
Emergency construction
of a new drilled pier bluff
wall along an
approximately 90-foot
section of undermined
coastal bluff
Cultural resources, visual
resources, water quality
Gas Station Five Cities Drive
and 4th Street
Construct new gas
station
Visual resources
Vacation Rental 140 Addie Street
in City of Pismo
Vacation rental unit
construction
Jurisdictional areas,
California red-legged frog,
western pond turtle,
steelhead and steelhead
critical habitat, tidewater
goby and tidewater goby
critical habitat, visual
resources
Hotel 2655 Shell
Beach Road in
City of Pismo
Beach
Construction of two-
story, 37-room hotel
Visual resources, water
quality
Grover Beach
Lodge and
Conference
Center
West Grand
Avenue in City
of Grover Beach
Construct 150-room
hotel with conference
center, restaurant, and
other additions
Water quality
Orchard Senior
Living
Near Orchard
Road and US
101 in City of
Arroyo Grande
Construct residential
care facility
Cultural resources
Lopez Bridge
Seismic Retrofit
Lopez Drive in
San Luis Obispo
County near
Arroyo Grande
Seismically retrofit the
existing Lopez Drive
Bridge
Cultural resources
Arroyo Grande
Property
Holdings
Northeast side
of Los Berros
Road, near US
101 and the City
of Arroyo
Grande
Construct a high-density
polyethylene-lined
agricultural reservoir
within the existing El
Campo Ranch
Cultural resources
Brisco-Halcyon
Road
Interchange
Modifications
On US 101 in
the City of
Arroyo Grande
Modifications and im-
provements to the US
101 interchanges at
Brisco-Halcyon Road,
Grand Avenue, and/or
Camino Mercado
Cultural resources
Bridge Street
Bridge
Rehabilitation
Bridge Street,
City of Arroyo
Grande near US
101
Rehabilitate and address
structural deficiencies
associated with the
Bridge Street Bridge
over Arroyo Grande
Creek
Cultural resources
Attachment 3
Council Agenda 12-5-2023 12.A-120
Packet Page 371

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 97
Project Location Description
Resources Potentially
Impacted in Identified
Resource Study Areas
Cherry Avenue
Pipe Bridge
Maintenance
Cherry Avenue,
City of Arroyo
Grande
Removal of existing
paint and debris from the
bridge, followed by re-
placing anti-corrosion
coatings on the bridge
Cultural resources
East Cherry
Avenue Specific
Plan
East Cherry
Avenue, City of
Arroyo Grande
Specific plan with mixed
use and residential uses
for future development
Cultural resources
Village at Pacific
West
Off Oak Park
Boulevard in
City of Pismo
Beach
Recent construction of
37 single-family homes,
36 multi-family units,
including low-income
units, 110 hotel rooms
and a restaurant
Cultural resources, visual
resources
Environmental Consequences
Twenty-nine recent, current, or proposed future projects, including the project considered in this environmental document, are located in one or more of the resource study areas. These projects have been identified as potentially contributing to cumulative impacts on the eight resources in this analysis. The potential environmental consequences of these projects are described below.

Visual Resources
Fifteen other current and reasonably foreseeable projects were identified as having an effect on the visual environment in the resource study area. Visual impacts could include loss of scenic vistas, degradation of visual quality and community character, and increased light and glare. Although the degree of visual change would vary, from low noticeability to substantial, each of these developments would contribute to the overall perception that the region and highway corridor are undergoing a change to a more urban visual environment, causing a cumulative decrease in visual quality.

When seen in the visual context of these other recent and proposed projects, the Pismo Congestion Relief Pilot Project would contribute to cumulative impacts on visual resources in the resource study area. The project contributes to an increase in the urban character and reduction in visual quality along the US 101 corridor through Pismo Beach and a portion of Avila Valley. The noticeability of this visual change would be substantially increased by the scale of this project, including soundwalls, extensive specialized signals, signs, vegetation removal, and other elements. The mitigation measures discussed in section 2.1.2 Visual/Aesthetics of this document will reduce adverse visual impacts, but substantial residual cumulative impacts would remain. Though the visual impacts from the individual projects in the resource study area are mitigable, cumulative impacts for the proposed Pismo Congestion Relief Pilot Project for visual resources are considered significant and unavoidable.

Attachment 3
Council Agenda 12-5-2023 12.A-121
Packet Page 372

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 98
Cultural Resources
Twenty-one other recent, current, and future proposed projects in the resource study area have been identified as contributing to the cumulative impact on cultural resources. Some of these projects include housing developments, hotel developments, road improvements, and the Pismo Preserve recreational area.

The Pismo Preserve is a recent construction project that included two parking areas, restroom, picnic facilities, and multi-use trails in the Pismo Preserve Conservation area and impacted four archaeological resources. All these projects have the potential to impact archaeological resources and add to the cumulative impact on the Chumash resources in this study area. These projects, combined with the general development of this coastal plateau over the decades as the beach communities have expanded, have resulted in a cumulative impact to cultural resources important to the Northern Chumash.

Adverse impacts from these individual projects would be avoided or minimized through the application of specific federal and state regulations, as well as county and city policies, actions, and development standards. These regulations, policies, and standards require avoidance of significant historical resources whenever feasible; if avoidance is not feasible, appropriate mitigation measures would be applied. These actions reduce the number and severity of impacts to historical resources, but an overall loss to the Northern Chumash resource base within this resource study area has occurred and will continue to occur. The projects will cumulatively reduce and degrade the number of these non-renewable resources, thereby contributing to an overall loss of integrity of the resource baseline. Due to adverse impacts that cannot be fully mitigated, the proposed Pismo Congestion Relief Pilot Project would have a significant contribution to cumulative impacts on cultural resources.

Water Quality
Multiple recent, reasonably foreseeable, and current projects within the resource study area for water quality have been identified as contributing to a cumulative impact to this resource. Pismo Creek suffers from poor water quality due to urban development both up and downstream from US 101. Upstream from US 101, a reservoir, agricultural operations, oil production facilities, sewage treatment, and groundwater pumping all affect the downstream flow and quality of water that travels through the project area. Occasional sewage spills from the sewage plant and other water quality issues have impacted water and aquatic life, particularly as a result of high storm flows. Heavy metals such as selenium, iron, and zinc were found to be above Basic Plan Standards at a sampling site upstream of the oilfield during wet and dry sampling events in 2009. The current development projects would increase the area of impervious surface, thereby increasing stormwater runoff volumes and velocities, as well as pollutant loading.

Development can substantially reduce impacts to water quality by implementing avoidance, minimization, and mitigation measures like bio-filtration and detention basins and incorporating stormwater best management practices. Recently, the Attachment 3
Council Agenda 12-5-2023 12.A-122
Packet Page 373

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 99
Pismo Scour Project reduced turbidity and erosion by repairing the failed creek banks. However unregulated activities and historic development prior to the enactment of regulations have created a cumulative adverse impact to water quality within the region. The proposed Pismo Congestion Relief Pilot Project would not make a significant contribution to adverse cumulative impacts to water quality because the project’s impacts to storm water would be fully mitigated.

Pismo Creek Habitat
Projects constructed on or over Pismo Creek can result in temporary and/or permanent impacts to riparian, wetland, and aquatic habitat. Although these impacts are typically required to be mitigated, inadequate or failed mitigation efforts as well as unregulated activities have caused a decrease in these habitat resources over time, causing a cumulative adverse impact. The Pismo Scour Project impacted creek habitat with the addition of concrete and metal structures within the creek channel. The Bello Bridge Replacement Project will replace a bridge over Pismo Creek on Bello Street in the City of Pismo. These projects, among others, have caused or are likely to cause impacts to Pismo Creek that contribute to cumulative impacts to creek habitat.

The Pismo Congestion Relief Pilot Project would have temporary impacts to riparian and aquatic habitat, but these impacts would be fully mitigated.

Therefore, the project would not contribute to the cumulative impact on the habitat within Pismo Creek.

Western Pond Turtle
Western pond turtles were once widely distributed in Central California, but populations have declined and continue to decline over most of their range.

Habitat destruction is attributed to be the major cause of this population decline.

Over 90 percent of the wetland habitat within the historic range of the western pond turtle in California has been eliminated due to agricultural development, flood control, water diversion projects and urbanization. Consequently, there has been a cumulative adverse impact to this species.

The project would cause temporary and permanent impacts to western pond turtle habitat and could directly impact the animal if it is found onsite during construction. Avoidance measures would reduce the likelihood of direct impacts; permanent impacts to habitat are small relative to the available habitat in the resource study area. Therefore, the contribution to cumulative impacts to the western pond turtle is not considered significant.

California Red-legged Frog
Given the historical context and the likelihood that the California red-legged frog population has been substantially impacted over time, it is assumed that this resource has been subjected to cumulative adverse impacts.

Attachment 3
Council Agenda 12-5-2023 12.A-123
Packet Page 374

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 100
The Pismo Congestion Relief Pilot Project would cause permanent and temporary impacts to California red-legged frog habitat and could directly impact the animal if it is found onsite during construction. Avoidance measures would reduce the likelihood of direct impacts. Furthermore, the impacts to California red-legged frog habitat would be relatively small, and compensatory mitigation would offset impacts. Therefore, the contribution to cumulative impacts to the California red-legged frog is not considered significant.

Steelhead Trout and Steelhead Critical Habitat
Though historically there has been an adverse cumulative impact to steelhead and steelhead critical habitat, the population of the south-central California coast steelhead appears currently to be relatively stable. Nonetheless, present-day risks and limiting factors for this population segment continue, including increasing sedimentation; decreasing spawning gravel quality and quantity; fish passage barriers and numerous minor habitat blockages throughout the region; decreased water quality; dewatering and habitat degradation in the form of agricultural and urban development on floodplains and riparian areas; and artificial breaching of estuaries during periods when they are normally closed off from the ocean by a sandbar. Upstream from the ocean about 4.5 miles, a concrete ford crossing Pismo Creek acts as a barrier to upstream movement of juvenile steelhead and a possible impediment to upstream adult movement at lower stream flows. The county bridge crossing of West Corral de Piedra Creek at Righetti Road creates a partial barrier due to an existing steep concrete apron across the stream. Adult steelhead are likely able to pass this partial barrier when water depths are deep enough, but fish passage overall is limited significantly. In addition, canopy cover (required for good quality habitat) in Pismo Creek averaged 59 percent, which is low compared to other local watersheds.

The Pismo Congestion Relief Pilot Project would cause permanent and temporary impacts to steelhead critical habitat and could directly impact the animal if it is found onsite during construction. Avoidance measures would reduce the likelihood of direct impacts. There are 13.7 miles of south-central California coast steelhead critical habitat designated along Pismo Creek; permanent impacts to habitat as a result of the project would be small relative to the available habitat in the resource study area, and minimization measures have been included. Therefore, the contribution to cumulative impacts to steelhead and steelhead critical habitat would not be considered significant.

Tidewater Goby and Tidewater Goby Critical Habitat
Given the historical context and the likelihood that the tidewater goby population has been substantially impacted over time, this resource has been subjected to cumulative impacts.

The available tidewater goby habitat in Pismo Creek encompasses about 18 acres. This area is considered small, but contains an abundant population density and a regular species presence. The Pismo Congestion Relief Pilot Attachment 3
Council Agenda 12-5-2023 12.A-124
Packet Page 375

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 101
Project would cause temporary impacts to tidewater goby critical habitat and could directly impact the animal if it is found onsite during construction.

Avoidance measures would reduce the likelihood of direct impacts. Temporary impacts to habitat as a result of the project would be small relative to the available habitat in the resource study area and minimization measures have been included. Therefore, the contribution to cumulative impacts to tidewater goby and tidewater goby critical habitat would not be considered significant.

Avoidance, Minimization, and/or Mitigation Measures
In addition to the measures identified in sections 2.1.2, 2.1.3, 2.2.2, 2.3.2, 2.3.3, and 2.3.4 to avoid, minimize, and mitigate this project’s potential impacts, the following is a list of potential measures that could be implemented by agencies with jurisdiction over the resources identified in this study to minimize potential cumulative impacts.

Visual Resources
·San Luis Obispo County and the City of Pismo Beach could require placement of existing utilities that degrade ocean views to be moved underground wherever possible in this corridor.
·The City of Pismo Beach could put a moratorium on any further construction that would block ocean views.

Cultural Resources
·Preparation of regional cultural resources overviews and research designs and synthetic analysis and interpretation of cultural resources in regional perspective. This could include ethnographic studies, compilation of previous archaeological data, and oral history interviews from modern descendant communities. Compiling and summarizing this information would help treat effects to this larger cultural landscape by providing a clear chronology of prehistoric habitation and allow for a better understanding of the importance of this region during California’s prehistory.
·Continued efforts at public outreach to keep the public informed and aware of the historical relevance of the area and its importance to the Northern Chumash tribe.
·Local land use plans could add more restrictions to avoid impacts to Northern Chumash archaeological sites.

Water Quality
·In the Pismo Creek Watershed Management Plan (2009) developed by the Pismo Creek/Edna Area Steering Committee, several water quality issues were identified with recommendations to improve water quality in the Pismo Creek watershed. It is recommended for agencies to consider these strategies to improve the health of the watershed:

Attachment 3
Council Agenda 12-5-2023 12.A-125
Packet Page 376

Chapter 2 Ÿ Affected Environment, Environmental Consequences, and Avoidance, Minimization, and/or Mitigation Measures Pismo Congestion Relief Pilot Project Ÿ 102
o Identify areas where sediment is entering the creek by inventorying the road system and then plan to modify structures or initiate Best Management Practices to control erosion and reduce sedimentation. o Provide off-stream sources of water for livestock or fencing livestock to avoid the creek could reduce bacteria entering the creek and improve water quality.
o Implement plan to monitor water quality for selenium and biostimulatory risk. Studies indicate that selenium, iron and zinc are above Basin Plan standards, but additional monitoring should be conducted to assess levels.
o Promote use of low impact development, redevelopment and retrofits to reduce sources of runoff.
·The State of California Water Quality Control Plan for the Central Coastal Basin recommends Best Management Practices to improve water quality by property owners. It is recommended for agencies to encourage property owners to use these practices:
o Preventing discharge by use of recycling used motor oil, fertilizer management, street cleaning, and revegetation.
o Treatment controls such as use of infiltration facilities, oil/water separators, and constructed wetlands to remove pollutants before they reach surface or groundwater.

Aquatic Species and Pismo Creek Habitat
·Protect stream flow from diversions by finding ways to work effectively with the reservoir operator to ensure minimum flow requirements are instituted. It would be imperative to assure that the flow be dedicated to the stream as opposed to other downstream riparian users.
·It is recommended that a program be directed to remove Arundo, Himalayan blackberry, and the other non-native vegetation within the Pismo Creek watershed.
·It is recommended that, where possible, tall, sprawling native trees that are used in more arid conditions be planted along the banks of Pismo Creek in the area from Route 227 to the bridge on Righetti Road. ·Conduct water quality testing to identify the substance causing the turbidity in lower Pismo Creek.
·Remove impediments for fish along Pismo Creek, particularly the concrete blockage. Regulatory agencies could encourage the concrete be removed and the crossing replaced with a railroad flatcar bridge or other structure that accommodates fish passage.

Attachment 3
Council Agenda 12-5-2023 12.A-126
Packet Page 377

Pismo Congestion Relief Pilot Project Ÿ 103
Chapter 3 California Environmental
Quality Act Evaluation

3.1 Determining Significance Under CEQA
The project is a joint project by Caltrans and the Federal Highway Administration and is subject to state and federal environmental review requirements. Project documentation, therefore, has been prepared in compliance with both the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA). The Federal Highway Administration’s responsibility for environmental review, consultation, and any other actions required by applicable federal environmental laws for this project are being, or have been, carried out by Caltrans pursuant to 23 U.S. Code Section 327 (23 USC 327) and the Memorandum of Understanding dated December 23, 2016, and executed by the Federal Highway Administration and Caltrans. Caltrans is the lead agency under NEPA and CEQA.

One of the main differences between NEPA and CEQA is the way significance is determined. Under NEPA, significance is used to determine whether an Environmental Impact Statement, or a lower level of documentation, will be required. NEPA requires that an Environmental Impact Statement be prepared when the proposed federal action (project) as a whole has the potential to “significantly affect the quality of the human environment.” The determination of significance is based on context and intensity. Some impacts determined to be significant under CEQA may not be of sufficient magnitude to be determined significant under NEPA. Under NEPA, once a decision is made regarding the need for an Environmental Impact Statement, it is the magnitude of the impact that is evaluated and no judgment of its individual significance is deemed important for the text. NEPA does not require that a determination of significant impacts be stated in the environmental documents.

CEQA, on the other hand, does require Caltrans to identify each “significant effect on the environment” resulting from the project and ways to mitigate each significant effect. If the project may have a significant effect on any environmental resource, then an Environmental Impact Report must be prepared. Every significant effect on the environment must be disclosed in the Environmental Impact Report and mitigated if feasible. In addition, the CEQA Guidelines list a number of “mandatory findings of significance,” which also require the preparation of an Environmental Impact Report. There are no types of actions under NEPA that parallel the findings of mandatory significance of CEQA. This chapter discusses the effects of this project and CEQA significance.

Attachment 3
Council Agenda 12-5-2023 12.A-127
Packet Page 378

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 104

3.2 CEQA Environmental Checklist
This checklist identifies physical, biological, social, and economic factors that might be affected by the project. Potential impact determinations include Significant and Unavoidable Impact, Less Than Significant Impact With Mitigation Incorporated, Less Than Significant Impact, and No Impact. In many cases, background studies performed in connection with a project will indicate that there are no impacts to a particular resource. A “No Impact” answer reflects this determination. The words “significant” and “significance” used throughout the following checklist are related to CEQA, not NEPA, impacts.

The questions in this checklist are intended to encourage the thoughtful assessment of impacts and do not represent thresholds of significance.

Project features, which can include both design elements of the project and standardized measures that are applied to all or most Caltrans projects such as Best Management Practices and measures included in the Standard Plans and Specifications or as Standard Special Provisions, are considered to be an integral part of the project and have been considered prior to any significance determinations documented below; see Chapters 1 and 2 for a detailed discussion of these features. The annotations to this checklist are summaries of information contained in Chapter 2 to provide you with the rationale for significance determinations; for a more detailed discussion of the nature and extent of impacts, please see Chapter 2. This checklist incorporates by reference the information contained in Chapters 1 and 2.

Aesthetics
CEQA Significance Determinations for Aesthetics
Except as provided in Public Resources Code Section 21099, would the project:
a) Have a substantial adverse effect on a scenic vista? Significant and Unavoidable Impact—The project would add a substantial amount of hardscape within the coastal viewshed, remove skyline trees, and in some locations the new median barrier could briefly block ocean views for some travelers. If soundwalls were constructed, they would create long segments of blocked views for all travelers.
b) Substantially damage scenic resources, including, but not limited to, trees, rock outcroppings, and historic buildings within a state scenic highway? No Impact—This question is not applicable; the section of US 101 within the project area is not an officially designated State Scenic Highway. c) In non-urbanized areas, substantially degrade the existing visual character or quality of public views of the site and its surroundings? (Public views are those that are experienced from a publicly accessible vantage point.) If the Attachment 3
Council Agenda 12-5-2023 12.A-128
Packet Page 379

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 105
project is in an urbanized area, would the project conflict with applicable zoning and other regulations governing scenic quality?
Significant and Unavoidable Impact—Aesthetic treatments may reduce adverse impacts to community character, but because of the inherent visual changes associated with the increased scale and urban appearance of the corridor, substantial impacts to visual quality and character would still occur. d) Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area?
Less than Significant Impact with Mitigation Incorporated—All build alternatives would result in additional light and glare along the highway from the lane-use control signals, but this change would represent a relatively small increase compared to the existing nighttime environment. (See section

2.1.2 Visual/ Aesthetics for more information.)
Agriculture and Forest Resources
CEQA Significance Determinations for Agriculture and Forest Resources In determining whether impacts to agricultural resources are significant environmental effects, lead agencies may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997) prepared by the California Department of Conservation as an optional model to use in assessing impacts on agriculture and farmland. In determining whether impacts to forest resources, including timberland, are significant environmental effects, lead agencies may refer to information compiled by the California Department of Forestry and Fire Protection regarding the state’s inventory of forest land, including the Forest and Range Assessment Project and the Forest Legacy Assessment Project; and the forest carbon measurement methodology provided in Forest Protocols adopted by the California Air Resources Board.

Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use?
No Impact—There is no farmland within the project’s area of impact. b) Conflict with existing zoning for agricultural use, or a Williamson Act contract?
No Impact—The project does not impede on land that is agriculturally zoned or within a Williamson Act contract.

Attachment 3
Council Agenda 12-5-2023 12.A-129
Packet Page 380

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 106
c) Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code section 12220(g)), timberland (as defined by Public Resources Code section 4526), or timberland zoned Timberland Production (as defined by Government Code section 51104(g))? No Impact—There is no forest land or timberland as described within the project limits.
d)Result in the loss of forest land or conversion of forest land to non-forest use? No Impact—There is no forest land as described within the project limits. e) Involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use?
No Impact—There is no agricultural land or forest land as described within the project’s area of impact.

Air Quality
CEQA Significance Determinations for Air Quality
Where available, the significance criteria established by the applicable air quality management district or air pollution control district may be relied upon to make the following determinations.

Would the project:
a) Conflict with or obstruct implementation of the applicable air quality plan? No Impact—Caltrans’ Standard Specification 14-9.02 (Caltrans, 2015) requires compliance with all applicable air quality laws and regulations including local and air district ordinances and rules. The applicable State Implementation Plan for San Luis Obispo County is the 2001 Clean Air Plan.

The project is included in the San Luis Obispo Council of Governments’ 2019 Regional Transportation Plan and programmed in the 2018 Regional Transportation Improvement Program, which are both consistent with the 2001 Clean Air Plan.
b) Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or state ambient air quality standard?
Less than Significant Impact—The project area is not in a non-attainment region under any applicable federal ambient air quality standard. San Luis Obispo County is non-attainment for state standards for ozone and small particulate under 10 microns, however the project is included in the Council of Governments’ 2019 Regional Transportation Plan and programmed in the Attachment 3
Council Agenda 12-5-2023 12.A-130
Packet Page 381

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 107
2018 Regional Transportation Improvement Program, which are both consistent with the 2001 Clean Air Plan. These plans consider cumulative increases in criteria pollutants.
c) Expose sensitive receptors to substantial pollutant concentrations? Less than Significant Impact—There are parks and schools within 500 feet of the project limits, which is the zone of greatest concern near roadways.

Standard specifications are applied to all projects to control air-borne dust and pollutants during construction. The completed project would move some traffic away from the elementary school but closer to the pre-school; the project area is more than 700 feet from the middle school. The project will not have large diesel equipment idling for long periods of time. Also, the project length eliminates the concern that equipment will be operating continuously in one location for long periods. Therefore, exhaust emissions are not expected to exceed acceptable levels.
d) Result in other emissions (such as those leading to odors) adversely affecting a substantial number of people?
Significant and Unavoidable Impact—The project does not cause or contribute to any new localized sources of odors, but it would result in a substantial increase in carbon dioxide emissions. (See section 3.3.3 Project Analysis.) Construction emissions could be unpleasant at times but would not be excessive or affect large numbers of people at any given time.

Biological Resources
CEQA Significance Determinations for Biological Resources Would the project:
a) Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Wildlife or U.S. Fish and Wildlife Service? Less than Significant Impact—Several protected species are present or could be present and temporarily impacted by the project during construction:
white-tailed kite and other birds, western pond turtle, California red-legged frog, steelhead trout, and tidewater goby. Measures have been included in the project to minimize disturbance and return disturbed area to its preconstruction condition.
b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Wildlife or U.S. Fish and Wildlife Service?
Attachment 3
Council Agenda 12-5-2023 12.A-131
Packet Page 382

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 108
Less than Significant Impact—Riparian habitat would be disturbed at Pismo Creek during construction. This is area that was newly planted as mitigation for a recent project to improve scoured areas under the bridge and would be replanted after construction.
c) Have a substantial adverse effect on state or federally protected wetlands (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means? No Impact—There are no state or federal wetlands within the project limits. d) Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites? Less than Significant Impact—Construction activities would restrict the movement of any steelhead trout, tidewater goby, or other aquatic species that were in the vicinity of Pismo Creek Bridge. Resident species would be relocated prior to any disturbance and provisions made to restrict any re-entry into the construction area. This would be a temporary impact; full access would be re-established once construction was completed. e) Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance? No Impact—Most of the project is subject to the local coastal policies of the City of Pismo Beach and the County of San Luis Obispo. Regarding biological resources, the project is consistent with these policies. f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or state habitat conservation plan?
No Impact—There is no such plan active within the project area.

Cultural Resources
CEQA Significance Determinations for Cultural Resources Would the project:
a) Cause a substantial adverse change in the significance of a historical resource pursuant to Section 15064.5?
Significant and Unavoidable Impact—The project would impact a small portion of two known large archaeological sites that are eligible for the National Register. Because excavation would be relatively shallow and mostly in disturbed soil, impacts to these sites are expected to be minimal. Recovery measures have been included as mitigation. One of the soundwalls, if Attachment 3
Council Agenda 12-5-2023 12.A-132
Packet Page 383

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 109
constructed, would severely impact a third site, also eligible; depending on the extent of the impact, the site could be adversely affected to the degree that it would no longer be eligible for the National Register. Impacts to this site could be avoided if the soundwall were not built.
b) Cause a substantial adverse change in the significance of an archaeological resource pursuant to Section 15064.5?
Significant and Unavoidable Impact—See response to a) above. c) Disturb any human remains, including those interred outside of dedicated cemeteries?
Significant and Unavoidable Impact—The project would impact two sites where human remains have been found, so the potential exists that remains could be found during construction. This is not expected, however, because disturbance is not expected to reach intact deposit. As a standard construction practice, measures have been included to address the appropriate and respectful disposition of any unexpected discovery.

Energy
CEQA Significance Determinations for Energy
Would the project:
a) Result in potentially significant environmental impact due to wasteful, inefficient, or unnecessary consumption of energy resources, during project construction or operation?
No Impact—The project would have a beneficial impact on energy use by improving traffic flow and speeds, which improve fuel efficiency. The project design has been limited to include only those components directly impacted during construction.
b) Conflict with or obstruct a state or local plan for renewable energy or energy efficiency?
No Impact—The project is in compliance with all local plans related to energy consumption.

Geology and Soils
CEQA Significance Determinations for Geology and Soils
Would the project:
a) Directly or indirectly cause potential substantial adverse effects, including the risk of loss, injury, or death involving:

Attachment 3
Council Agenda 12-5-2023 12.A-133
Packet Page 384

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 110
i) Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo Earthquake Fault Zoning Map issued by the State Geologist for the area or based on other substantial evidence of a known fault? No Impact—This refers to surface faulting (ground displacement) at a site from an earthquake. Pismo Creek Bridge is not situated within an Earthquake Fault Zone (Alquist-Priolo) as identified by the California Geologic Survey, nor is it located within 1,000 feet of a mapped fault that is of Holocene-Latest Pleistocene age or younger (active within the last 15,000 years). By these definitions, Caltrans considers the bridge site to be free from surface fault rupture potential from known active faulting.
ii) Strong seismic ground shaking?
No Impact—High seismic ground accelerations are the amount (strength and duration) of ground shaking that a site could be subjected to from a local or regional earthquake. Pismo Creek Bridge is in an area that could be subject to high seismic ground accelerations, but site-specific testing would provide data for appropriate design specifications.
iii) Seismic-related ground failure, including liquefaction? Less than Significant Impact—There is a potential for liquefaction at Pismo Creek Bridge due to the high groundwater levels and layers of loose sandy alluvial materials underlying the site and vicinity. Caltrans has performed a site-specific liquefaction and seismically induced settlement analysis to provide project designers with the necessary specifications to design the bridge supports to seismic standards.
iv) Landslides?
No Impact—The likelihood of landslides at this location is low due to the topography and sparse availability of wildfire fuel.
b) Result in substantial soil erosion or the loss of topsoil? Less than Significant Impact—The project would increase the impervious surface area within the project limits by more than 8 acres, which would increase the volume and rate of stormwater flows and thereby increase the risk of erosion, sedimentation, and scour. The project includes erosion control measures per Caltrans’ standard specifications and best management practices to treat a minimum of 9 acres of impervious surface. c) Be located on a geologic unit or soil that is unstable, or that would become unstable as a result of the project, and potentially result in on-site or off-site landslide, lateral spreading, subsidence, liquefaction or collapse? Attachment 3
Council Agenda 12-5-2023 12.A-134
Packet Page 385

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 111
Less than Significant Impact—According to past geologic boring information at Pismo Creek Bridge, there is a layer of medium dense sand and gravel at the toe of the west bank that could be subject to liquefaction, which could cause lateral movement of the west bank. Evaluation results also show the Pismo Creek Bridge site is susceptible to lateral spreading. The potential for seismically induced settlements or instability of the embankment fill and bridge supports site would be evaluated in the Preliminary Foundation Report prepared during project design and the design modified accordingly. d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform Building Code (1994), creating substantial direct or indirect risks to life or property?
No Impact—The road surface is built on base material that prevents impacts from unstable soil beneath it.
e) Have soils incapable of adequately supporting the use of septic tanks or alternative wastewater disposal systems where sewers are not available for the disposal of wastewater?
No Impact—The project does not include the use of septic tanks or disposal systems.
f) Directly or indirectly destroy a unique paleontological resource or site or unique geologic feature?
No Impact—The project has been designed to avoid the geologic feature known locally as the Pismo Rock.

Greenhouse Gas Emissions
CEQA Significance Determinations for Greenhouse Gas Emissions Would the project:
a) Generate greenhouse gas emissions, either directly or indirectly, that may have a significant impact on the environment?
Less than Significant Impact with Mitigation Incorporated—The project would cause higher levels of carbon dioxide emissions than if the project were not constructed. Considering that carbon dioxide accounts for more than 80 percent of total greenhouse gas emissions, the emissions that would result from the project could be considered a significant impact on an individual basis, but certainly contributes to a cumulative significant impact as part of the overall transportation industry. However, carbon dioxide emissions are expected to decrease substantially within the next 20 years as a result of cleaner vehicles and enhanced regulations, resulting in substantially lower carbon dioxide emission rates than are seen today. By implementing Attachment 3
Council Agenda 12-5-2023 12.A-135
Packet Page 386

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 112
available reduction measures and adhering to regulations, the long-term impact from the project would be considered less than significant. b) Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases?
No Impact—The project complies with all applicable plans, policies, and regulations regarding greenhouse gas emissions. The project is included in the San Luis Obispo Council of Governments’ (Council of Governments) 2019 Regional Transportation Plan and 2020 Regional Transportation Improvement Plan. The park-and-ride lot is consistent with the Council of Governments’ Community 2050 Regional Blueprint’s goal of improving multi-modal connectivity, as well as the City of Pismo Beach Climate Action Plan’s goals of encouraging transportation demand management incentives and reducing congestion.

Hazards and Hazardous Materials
CEQA Significance Determinations for Hazards and Hazardous Materials Would the project:
a) Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials? Less Than Significant Impact—The final project would improve the reliability of the highway and thereby reduce potential hazards to the public from the transport of materials. Testing indicates that soil within the top few inches within the project limits contains hazardous levels of aerially deposited lead. Because of the depth and volume of excavation required for construction, the concentration of lead in the excavated soil would not be considered hazardous. Standard dust control measures would prevent substantial amounts of dirt becoming airborne during construction. b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment?
No Impact—Safety requirement and standards would be incorporated into the project design, thereby minimizing the chance of accidents due to traffic collisions.
c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school?
No Impact—Construction could occur within one-quarter mile of Shell Beach Elementary School, Judkins Middle School, and Happy Time Co-op Pre- Attachment 3
Council Agenda 12-5-2023 12.A-136
Packet Page 387

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 113
school. The soil and bridges have been tested for asbestos and lead paint.

Aerially deposited lead was found in the soil, but no asbestos or lead paint was found on the bridges. If lead levels in excavated soil exceed regulatory limits, the materials will be handled according to all applicable regulations.

Caltrans Standard Specifications include measures for handling these substances on all projects as applicable.
d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment? No Impact—There are no hazardous materials sites within the project limits. e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard or excessive noise for people residing or working in the project area?
No Impact—The project is not located within an airport land use plan or within two miles of a public airport.
f) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan?
No Impact—By improving highway operations, the project would be improving any emergency plan that requires highway use. g) Expose people or structures, either directly or indirectly, to a significant risk of loss, injury or death involving wildland fires?
No Impact—The project would reduce the vegetative fuel within the median, which would, to a small degree, reduce the propagation of wildfire.

Hydrology and Water Quality
CEQA Significance Determinations for Hydrology and Water Quality Would the project:
a) Violate any water quality standards or waste discharge requirements or otherwise substantially degrade surface or ground water quality? Less Than Significant Impact—Potential surface water quality impacts may include: an increase in sediments, turbidity and total dissolved solids; and toxicity due to chemical substances originating from construction activities. By incorporating proper and accepted engineering practices and best management practices, the project would not produce significant impacts to water quality during construction.

Attachment 3
Council Agenda 12-5-2023 12.A-137
Packet Page 388

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 114
b) Substantially decrease groundwater supplies or interfere substantially with groundwater recharge such that the project may impede sustainable groundwater management of the basin?
No Impact—There are no water recharge facilities at or downstream of the project location.
c) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river or through the addition of impervious surfaces, in a manner which would:
i)Result in substantial erosion or siltation on-site or off-site; Less than Significant Impact—The project would increase impervious surfaces within the project limits by about 5 acres, which would increase the volume and rate of stormwater flows and thereby increase the risk of erosion, sedimentation, and scour. However, the project design would incorporate permanent storm water treatment best management practices to treat a minimum of 9 acres of impervious surface. The project would also repair damaged slope paving that is currently suffering from erosion, and all disturbed areas would be treated with erosion control or be replanted to prevent runoff that otherwise could cause siltation.
ii) Substantially increase the rate or amount of surface runoff in a manner which would result in flooding on-site or off-site;
Less than Significant Impact—The project would increase impervious surfaces within the project limits by about 5 acres, but this increase is spread out along 4 miles of roadway where the part-time travel lane is proposed. The small increase to each drainage system is insignificant and is not substantial enough to cause flooding.
iii) Create or contribute runoff water that would exceed the capacity of existing or planned stormwater drainage systems or provide substantial additional sources of polluted runoff;
No Impact—The project does not contribute runoff water that would exceed the capacity of existing drainage facilities. The project would increase impervious surfaces within the project limits by about 5 acres, which would increase the volume and rate of storm water flows. However, the project design would incorporate permanent storm water treatment best management practices to treat a minimum of 9 acres of impervious surface, therefore the project would not create substantial additional polluted runoff. iv) Impede or redirect flood flows?
No Impact—The project does not impede flood flows and does not divert any existing drainage systems that would cause redirected flood flows.

Attachment 3
Council Agenda 12-5-2023 12.A-138
Packet Page 389

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 115
d) In flood hazard, tsunami, or seiche zones, risk release of pollutants due to project inundation?
No Impact—No pollutants would be present as part of the roadway prism or bridge structures.
e) Conflict with or obstruct implementation of a water quality control plan or sustainable groundwater management plan?
No Impact—Pismo Creek and the portion of the project south of the creek are within the Santa Maria River Valley—Santa Maria subunit 3-012.01 groundwater basin. Per the Central Coast Regional Water Quality Control Board’s Central Coast Basin Plan, the general water quality objectives for all groundwater in the Central Coast area include tastes, odors, and radioactivity.

A Storm Water Pollution Prevention Plan would be prepared for this project that would include water quality protection measures for construction. No long-term or temporary impacts are anticipated with respect to groundwater.

Land Use and Planning
CEQA Significance Determinations for Land Use and Planning Would the project:
a) Physically divide an established community?
No Impact—The project would not encroach upon or divide any residences or businesses.
b) Cause a significant environmental impact due to a conflict with any land use plan, policy, or regulation adopted for the purpose of avoiding or mitigating an environmental effect?
No Impact—The significant and potentially significant effects associated with the project are not related to land use plans, policies, or regulations.

Mineral Resources
CEQA Significance Determinations for Mineral Resources
Would the project:
a) Result in the loss of availability of a known mineral resource that would be of value to the region and the residents of the state?
No Impact—The project area is not a source of any known mineral resource.

Attachment 3
Council Agenda 12-5-2023 12.A-139
Packet Page 390

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 116
b) Result in the loss of availability of a locally important mineral resource recovery site delineated on a local general plan, specific plan or other land use plan?
No Impact—There is no mineral resource recovery site located near the project limits.

Noise
CEQA Significance Determinations for Noise
Would the project result in:
a) Generation of a substantial temporary or permanent increase in ambient noise levels in the vicinity of the project in excess of standards established in the local general plan or noise ordinance, or applicable standards of other agencies?
Significant and Unavoidable Impact—Traffic noise as a result of the project is expected to be in excess of Caltrans, federal, and local standards. See section 2.2.3 Noise for more discussion on this subject. b) Generation of excessive groundborne vibration or groundborne noise levels?
Less than Significant Impact—Trucks moving at higher speeds can cause groundborne vibrations, but these would be expected in the vicinity of a freeway. c) For a project located within the vicinity of a private airstrip or an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels? No Impact—Oceano County Airport is 2.5 miles from the project location.

Population and Housing
CEQA Significance Determinations for Population and Housing Would the project:
a) Induce substantial unplanned population growth in an area, either directly (for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)? No Impact—The project would support higher traffic volumes that could result from the anticipated future population growth in the region, but there are no components that would induce growth.

Attachment 3
Council Agenda 12-5-2023 12.A-140
Packet Page 391

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 117
b) Displace substantial numbers of existing people or housing, necessitating the construction of replacement housing elsewhere?
No Impact—The project would not impact housing.

Public Services
CEQA Significance Determinations for Public Services
a) Would the project result in substantial adverse physical impacts associated with the provision of new or physically altered governmental facilities, need for new or physically altered governmental facilities, the construction of which could cause significant environmental impacts, in order to maintain acceptable service ratios, response times or other performance objectives for any of the public services:

Fire protection?
No Impact—The project would not induce the need for any new or altered fire protection services.

Police protection?
No Impact—The project would not induce the need for any new or altered police protection services.

Schools?
No Impact—The project would not induce the need for any new or altered school services.

Parks?
No Impact—The project would not induce the need for any new or altered park services.

Other public facilities?
Less than Significant Impact—The project would use the Freeway Service Patrol. (See section 1.4.1 Build Alternatives, “Transportation Demand Management and Transportation System Management Alternatives.”) This service will aid in the project’s purpose to improve traffic flow. Also, the project would use potable water for irrigation of mitigation planting during the plant establishment period. This would likely be discontinued in the case of drought.

Attachment 3
Council Agenda 12-5-2023 12.A-141
Packet Page 392

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 118
Recreation
CEQA Significance Determinations for Recreation
a) Would the project increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated? No Impact—The project would not increase the use of any parks or recreational facilities.
b) Does the project include recreational facilities or require the construction or expansion of recreational facilities which might have an adverse physical effect on the environment?
No Impact—The project does not include recreational facilities.

Transportation
CEQA Significance Determinations for Transportation
Would the project:
a) Conflict with a program plan, ordinance or policy addressing the circulation system, including transit, roadway, bicycle and pedestrian facilities? No Impact—The project would improve traffic circulation; it is not in conflict with applicable plans.
b) Conflict with or be inconsistent with CEQA Guidelines section 15064.3, subdivision (b)?
No Impact—The project is expected to have a draft environmental document submitted for public review prior to the deadline for the requirement to analyze traffic impacts using vehicle miles traveled, therefore level of service has been used.
c)Substantially increase hazards due to a geometric design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)?
No Impact—The project would be designed to include required standards for highway safety.
d) Result in inadequate emergency access?
Less than Significant Impact—Once in operation, the project would improve freeway operations within the project limits and thereby improve emergency access. During construction, travel lanes could be restricted at times to through traffic. If possible, construction would be halted to allow emergency Attachment 3
Council Agenda 12-5-2023 12.A-142
Packet Page 393

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 119
vehicles through. Otherwise, emergency vehicles could cross the median and/or use out-of-direction travel by means of another ramp, which could increase travel times.

Tribal Cultural Resources
CEQA Significance Determinations for Tribal Cultural Resources Would the project cause a substantial adverse change in the significance of a tribal cultural resource, defined in Public Resources Code section 21074 as either a site, feature, place, cultural landscape that is geographically defined in terms of the size and scope of the landscape, sacred place, or object with cultural value to a California Native American tribe, and that is:
a) Listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code section 5020.1(k), or
Significant and Unavoidable Impact—The project would impact a small portion of two known large archaeological sites that are eligible for the California Register. Because excavation would be relatively shallow and primarily in disturbed soil, impacts to these sites are expected to be minimal.

Nonetheless, the full extent of these sites is unknown, and therefore there is potential for the impacts to be severe. Consequently, monitoring and recovery measures have been included as mitigation. One of the soundwalls, if constructed, would severely impact a third site that is also eligible; depending on the extent of the impact, the site could be adversely affected to the degree that it would no longer be eligible for the California Register. Impacts to this site could be avoided if the wall were not built.
b) A resource determined by the lead agency, in its discretion and supported by substantial evidence, to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1. In applying the criteria set forth in subdivision (c) of Public Resource Code Section 5024.1, the lead agency shall consider the significance of the resource to a California Native American tribe.

Significant and Unavoidable Impact—The same information provided in answer a) above applies to this question. The project would avoid direct impacts to Pismo Rock, but Pismo Rock would be encumbered with concrete barrier, which affects its appearance. This would be considered a less than significant impact.

Utilities and Service Systems
CEQA Significance Determinations for Utilities and Service Systems Would the project:

Attachment 3
Council Agenda 12-5-2023 12.A-143
Packet Page 394

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 120
a) Require or result in the relocation or construction of new or expanded water, wastewater treatment or storm water drainage, electric power, natural gas, or telecommunications facilities, the construction or relocation of which could cause significant environmental effects?
Less than Significant Impact—The existing storm water drainage system would be expanded to include the additional lane width created by the project. b) Have sufficient water supplies available to serve the project and reasonably foreseeable future development during normal, dry and multiple dry years?
Less than Significant Impact—The project would not require any water supplies beyond irrigation during the plant establishment period, but the irrigation would be with potable water. During periods of drought, irrigation would likely be discontinued unless the water could be provided from a source that does not deplete the public supply. Discontinuing irrigation could cause mitigation planting to fail, but no new water source would be pursued. c) Result in a determination by the wastewater treatment provider that serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments? No Impact—The project would not affect demand on wastewater treatment facilities.
d) Generate solid waste in excess of state or local standards, or in excess of the capacity of local infrastructure, or otherwise impair the attainment of solid waste reduction goals?
No Impact—The completed project would not generate solid waste. e) Comply with federal, state, and local management and reduction statutes and regulations related to solid waste?
No Impact—The project complies with all statutes and regulations related to solid waste.

Wildfire
CEQA Significance Determinations for Wildfire
If located in or near state responsibility areas or lands classified as very high fire hazard severity zones, would the project:
a) Substantially impair an adopted emergency response plan or emergency evacuation plan?
Attachment 3
Council Agenda 12-5-2023 12.A-144
Packet Page 395

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 121
No Impact—Once active, the project would improve freeway operations within the project limits and thereby improve emergency response and/or evacuation plans. During construction, travel lanes could be restricted, but would reopen during an emergency.
b) Due to slope, prevailing winds, and other factors, exacerbate wildfire risks, and thereby expose project occupants to pollutant concentrations from a wildfire or the uncontrolled spread of a wildfire?
No Impact—The project would not exacerbate wildfire risks. The freeway corridor maintains reduced fuel quantities and few wildfire sources relative to adjacent open areas.
c) Require the installation or maintenance of associated infrastructure (such as roads, fuel breaks, emergency water sources, power lines or other utilities) that may exacerbate fire risk or that may result in temporary or ongoing impacts to the environment?
No Impact—No additional infrastructure is being installed that would increase fire risk.
d) Expose people or structures to significant risks, including downslope or downstream flooding or landslides, as a result of runoff, post-fire slope instability, or drainage changes?
No Impact—The project is not in an area prone to landslides or flooding.

Mandatory Findings of Significance
CEQA Significance Determinations for Mandatory Findings of Significance
a) Does the project have the potential to substantially degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, substantially reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory?
Significant and Unavoidable Impact—The project would result in adverse impacts to the visual quality of the area and to cultural resources important to the Northern Chumash tribe. It would also result in adverse impacts from increased noise levels due to traffic. See the relevant sections in Chapter 2 for more information.
b) Does the project have impacts that are individually limited, but cumulatively considerable? (“Cumulatively considerable” means that the incremental effects of a project are considerable when viewed in connection with the Attachment 3
Council Agenda 12-5-2023 12.A-145
Packet Page 396

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 122
effects of past projects, the effects of other current projects, and the effects of probable future projects.)
Significant and Unavoidable Impact—The project would make a significant contribution to the decline of the visual quality through this portion of the US 101 corridor, as well as to the disturbance of the archaeological resources on the Pismo plateau. See section 2.5 Cumulative Impacts for more information. c) Does the project have environmental effects that will cause substantial adverse effects on human beings, either directly or indirectly? Significant and Unavoidable Impact—The quality of life in San Luis Obispo County has been rated as high in multiple surveys, due in large part to the attractive rural environment, the “small town feel,” and the proximity of quaint, coastal towns with spectacular ocean views. This quality draws people from all over the country, both to visit and to live, which puts a substantial burden on the local infrastructure. In response, urban development has increased, which in turn decreases the characteristics that were the initial draw. A higher density population, expanding development, increased congestion, reduced quality views, reduced connection to area history and culture, poor air quality, and increased noise all contribute to a decrease in the quality of life, which has been shown to have deleterious effects on human health and well-being.

The project would reduce congestion on the freeway for the near future, but the project’s contributions to other degrading factors would result in substantial, long-term adverse effects on human beings in general.

3.3 Climate Change
Climate change refers to long-term changes in temperature, precipitation, wind patterns, and other elements of the Earth’s climate system. An ever- increasing body of scientific research attributes these climatological changes to greenhouse gas emissions, particularly those generated from the production and use of fossil fuels.

While climate change has been a concern for several decades, the establishment of the Intergovernmental Panel on Climate Change by the United Nations and World Meteorological Organization in 1988 led to increased efforts devoted to greenhouse gas emissions reduction and climate change research and policy. These efforts are primarily concerned with the emissions of greenhouse gasses generated by human activity, including carbon dioxide, methane, nitrous oxide, tetrafluoromethane, hexafluoroethane, sulfur hexafluoride, and various hydrofluorocarbons.

Carbon dioxide is the most abundant greenhouse gas; while it is a naturally occurring component of Earth’s atmosphere, fossil-fuel combustion is the main source of additional, human-generated carbon dioxide.

Attachment 3
Council Agenda 12-5-2023 12.A-146
Packet Page 397

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 123
Two terms are typically used when discussing how we address the impacts of climate change: “greenhouse gas mitigation” and “adaptation.” Greenhouse gas mitigation covers activities and policies aimed at reducing greenhouse gas emissions to limit or “mitigate” the impacts of climate change. Adaptation, on the other hand, is concerned with planning for and responding to impacts resulting from climate change (such as adjusting transportation design standards to withstand more intense storms and higher sea levels). This analysis will include a discussion of both.

Regulatory Setting
This section outlines federal and state efforts to comprehensively reduce greenhouse gas emissions from transportation sources.

Federal
To date, no national standards have been established for nationwide mobile- source greenhouse gas reduction targets, nor have any regulations or legislation been enacted specifically to address climate change and greenhouse gas emissions reduction at the project level.

The National Environmental Policy Act (NEPA) (42 U.S. Code Part 4332) requires federal agencies to assess the environmental effects of their proposed actions prior to making a decision on the action or project.

The Federal Highway Administration (FHWA) recognizes the threats that extreme weather, sea-level change, and other changes in environmental conditions pose to valuable transportation infrastructure and those who depend on it. The Federal Highway Administration therefore supports a sustainability approach that assesses vulnerability to climate risks and incorporates resilience into planning, asset management, project development and design, and operations and maintenance practices (FHWA 2019). This approach encourages planning for sustainable highways by addressing climate risks while balancing environmental, economic, and social values—“the triple bottom line of sustainability” (FHWA n.d.). Program and project elements that foster sustainability and resilience also support economic vitality and global efficiency, increase safety and mobility, enhance the environment, promote energy conservation, and improve the quality of life.

Various efforts have been promulgated at the federal level to improve fuel economy and energy efficiency to address climate change and its associated effects. The most important of these were the Energy Policy and Conservation Act of 1975 (42 U.S. Code Section 6201) and the Corporate Average Fuel Economy Standards. This act establishes fuel economy standards for on-road motor vehicles sold in the United States. Compliance with federal fuel economy standards is determined through the Corporate Attachment 3
Council Agenda 12-5-2023 12.A-147
Packet Page 398

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 124
Average Fuel Economy program based on each manufacturer’s average fuel economy for the portion of its vehicles produced for sale in the United States.

Energy Policy Act of 2005, 109th Congress H.R.6 (2005–2006): This act sets forth an energy research and development program covering: (1) energy efficiency; (2) renewable energy; (3) oil and gas; (4) coal; (5) the establishment of the Office of Indian Energy Policy and Programs within the Department of Energy; (6) nuclear matters and security; (7) vehicles and motor fuels, including ethanol; (8) hydrogen; (9) electricity; (10) energy tax incentives; (11) hydropower and geothermal energy; and (12) climate change technology.

The U.S. Environmental Protection Agency in conjunction with the National Highway Traffic Safety Administration is responsible for setting greenhouse gas emission standards for new cars and light-duty vehicles to significantly increase the fuel economy of all new passenger cars and light trucks sold in the United States. Fuel efficiency standards directly influence greenhouse gas emissions.

State
California has been innovative and proactive in addressing greenhouse gas emissions and climate change by passing multiple Senate and Assembly bills and executive orders including, but not limited to, the following:

Executive Order S-3-05 (June 1, 2005): The goal of this order is to reduce California’s greenhouse gas emissions to: (1) year 2000 levels by 2010, (2) year 1990 levels by 2020, and (3) 80 percent below year 1990 levels by 2050.

This goal was further reinforced with the passage of Assembly Bill 32 in 2006 and Senate Bill 32 in 2016.

Assembly Bill 32, Chapter 488, 2006, Núñez and Pavley, The Global Warm- ing Solutions Act of 2006: Assembly Bill 32 codified the 2020 greenhouse gas emissions reduction goals outlined in Executive Order S-3-05, while further mandating that the California Air Resources Board create a scoping plan and implement rules to achieve “real, quantifiable, cost-effective reductions of greenhouse gases.” The Legislature also intended that the statewide greenhouse gas emissions limit continue in existence and be used to maintain and continue reductions in emissions of greenhouse gases beyond 2020 (Health and Safety Code Section 38551(b)). The law requires the California Air Resources Board to adopt rules and regulations in an open public process to achieve the maximum technologically feasible and cost- effective greenhouse gas reductions.

Executive Order S-01-07 (January 18, 2007): This order sets forth the low carbon fuel standard for California. Under this Executive Order, the carbon intensity of California’s transportation fuels is to be reduced by at least 10 percent by the year 2020. The California Air Resources Board re-adopted the low carbon fuel standard regulation in September 2015, and the changes went into effect on January 1, 2016. The program establishes a strong Attachment 3
Council Agenda 12-5-2023 12.A-148
Packet Page 399

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 125
framework to promote the low-carbon fuel adoption necessary to achieve the governor's 2030 and 2050 greenhouse gas reduction goals.

Senate Bill 375, Chapter 728, 2008, Sustainable Communities and Climate Protection: This bill requires the California Air Resources Board to set regional emissions reduction targets for passenger vehicles. The Metropolitan Planning Organization for each region must then develop a “Sustainable Communities Strategy” that integrates transportation, land-use, and housing policies to plan how it will achieve the emissions target for its region.

Senate Bill 391, Chapter 585, 2009, California Transportation Plan: This bill requires the State’s long-range transportation plan to identify strategies to address California’s climate change goals under Assembly Bill 32.

Executive Order B-16-12 (March 2012): This order directs State entities under the direction of the Governor, including the California Air Resources Board, the California Energy Commission, and the Public Utilities Commission, to support the rapid commercialization of zero-emission vehicles. It directs these entities to achieve various benchmarks related to zero-emission vehicles.

Executive Order B-30-15 (April 2015): This order establishes an interim statewide greenhouse gas emission reduction target of 40 percent below 1990 levels by 2030 to ensure California meets its target of reducing greenhouse gas emissions to 80 percent below 1990 levels by 2050. It further orders all state agencies with jurisdiction over sources of greenhouse gas emissions to implement measures, pursuant to statutory authority, to achieve reductions of greenhouse gas emissions to meet the 2030 and 2050 greenhouse gas emissions reductions targets. It also directs the California Air Resources Board to update the Climate Change Scoping Plan to express the 2030 target in terms of million metric tons of carbon dioxide equivalent.

Greenhouse gases differ in how much heat each trap in the atmosphere (global warming potential). Carbon dioxide is the most important greenhouse gas, so amounts of other gases are expressed relative to carbon dioxide, using a metric called “carbon dioxide equivalent.” The global warming potential of carbon dioxide is assigned a value of 1, and the global warming potential of other gases is assessed as multiples of carbon dioxide. Finally, it requires the Natural Resources Agency to update the state’s climate adaptation strategy, Safeguarding California, every three years, and to ensure that its provisions are fully implemented.

Senate Bill 32, Chapter 249, 2016: This bill codifies the greenhouse gas reduction targets established in Executive Order B-30-15 to achieve a mid- range goal of 40 percent below 1990 levels by 2030.

Senate Bill 1386, Chapter 545, 2016: This bill declared “it to be the policy of the state that the protection and management of natural and working lands… is an important strategy in meeting the state’s greenhouse gas reduction Attachment 3
Council Agenda 12-5-2023 12.A-149
Packet Page 400

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 126
goals, and would require all state agencies, departments, boards, and commissions to consider this policy when revising, adopting, or establishing policies, regulations, expenditures, or grant criteria relating to the protection and management of natural and working lands.”
Assembly Bill 134, Chapter 254, 2017: This bill allocates Greenhouse Gas Reduction Funds and other sources to various clean vehicle programs, demonstration/pilot projects, clean vehicle rebates and projects, and other emissions-reduction programs statewide.

Senate Bill 743, Chapter 386 (September 2013): This bill changes the metric of consideration for transportation impacts pursuant to CEQA from a focus on automobile delay to alternative methods focused on vehicle miles traveled, to promote the state’s goals of reducing greenhouse gas emissions and traffic- related air pollution and promoting multimodal transportation while balancing the needs of congestion management and safety.

Senate Bill 150, Chapter 150, 2017, Regional Transportation Plans: This bill requires the California Air Resources Board to prepare a report that assesses progress made by each metropolitan planning organization in meeting its established regional greenhouse gas emission reduction targets.

Executive Order B-55-18 (September 2018): This order sets a new statewide goal to achieve and maintain carbon neutrality no later than 2045. This goal is in addition to existing statewide targets of reducing greenhouse gas emissions.

Executive Order N-19-19 (September 2019): This order advances California’s climate goals in part by directing the California State Transportation Agency to leverage annual transportation spending to reverse the trend of increased fuel consumption and reduce greenhouse gas emissions from the transportation sector. It orders a focus on transportation investments near housing, managing congestion, and encouraging alternatives to driving. This order also directs the California Air Resources Board to encourage automakers to produce more clean vehicles, formulate ways to help Californians purchase them, and propose strategies to increase demand for zero-emission vehicles.

Environmental Setting
US 101 serves as a primary transportation artery for the Central Coast, accommodating interregional, regional, and local traffic. San Luis Obispo Council of Governments’ (Council of Governments) 2014 US 101 Corridor Mobility Master Plan identified the project area as the most congested segment on the US 101 corridor in San Luis Obispo County, as well as “a key goods movement corridor [that] is critical for the economic health and productivity of the Central Coast of California.” It is the dominant thoroughfare through San Luis Obispo County, accommodating over two-thirds of total Attachment 3
Council Agenda 12-5-2023 12.A-150
Packet Page 401

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 127
travel and carrying over twice the daily traffic of any other facility in the county. Much of this is commuter traffic, which causes peak traffic to be heavily one-directional, correlating with the morning and afternoon peak hours, although weekend southbound traffic is also heavy.

The Pismo Congestion Relief Project is included in the Council of Governments’ 2019 Regional Transportation Plan (Regional Plan), which guides transportation and housing development and addresses greenhouse gasses in the project area. A greenhouse gas emissions inventory estimates the amount of greenhouse gases discharged into the atmosphere by specific sources over a period of time, such as a calendar year. Tracking annual greenhouse gas emissions allows countries, states, and smaller jurisdictions to understand how emissions are changing and what actions may be needed to attain emission reduction goals. The U.S. Environmental Protection Agency is responsible for documenting greenhouse gas emissions nationwide, and the California Air Resources Board does so for the state, as required by Health and Safety Code Section 39607.4.

National Greenhouse Gas Inventory
The U.S. Environmental Protection Agency prepares a national greenhouse gas inventory every year and submits it to the United Nations in accordance with the Framework Convention on Climate Change. The inventory provides a comprehensive accounting of all human-produced sources of greenhouse gases in the United States, reporting emissions of carbon dioxide, methane, nitrous oxide, hydrofluorocarbons, perfluorocarbons, sulfur hexafluoride, and nitrogen trifluoride. It also accounts for emissions of carbon dioxide that are removed from the atmosphere by “sinks” such as forests, vegetation, and soils that uptake and store carbon dioxide (carbon sequestration).

The 1990–2016 inventory found that, of 6,511 million metric tons of carbon dioxide-equivalent greenhouse gas emissions, 81 percent consisted of carbon dioxide, 10 percent were methane, and six percent were nitrous oxide; the balance consisted of fluorinated gases (U.S. EPA 2018). In 2016, greenhouse gas emissions from the transportation sector accounted for nearly 28.5 percent of U.S. greenhouse gas emissions, as shown in Figure 3-1.

State Greenhouse Gas Inventory
The California Air Resources Board collects greenhouse gas emissions data for transportation, electricity, commercial/residential, industrial, agricultural, and waste management sectors each year. It then summarizes and highlights major annual changes and trends to demonstrate the state’s progress in meeting its greenhouse gas reduction goals. The 2019 edition of the greenhouse gas emissions inventory found total California emissions for 2017 were 424.1 million metric tons of carbon dioxide equivalent, with the transportation sector responsible for 41 percent of total greenhouse gases. It also found that overall statewide greenhouse gas emissions declined from Attachment 3
Council Agenda 12-5-2023 12.A-151
Packet Page 402

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 128
2000 to 2017 despite growth in population and state economic output (ARB 2019a).

Figure 3-1 U.S. 2016 Greenhouse Gas Emissions
Figure 3-2 California 2016 Greenhouse Gas Emissions
Attachment 3
Council Agenda 12-5-2023 12.A-152
Packet Page 403

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 129
Figure 3-3 Change in California Gross Domestic Product, Population, and Greenhouse Gas Emissions since 2000
Assembly Bill 32 required the California Air Resources Board to develop a Scoping Plan that describes the approach California will take to achieve the goal of reducing greenhouse gas emissions to 1990 levels by 2020, and to update it every five years. The California Air Resources Board adopted the first scoping plan in 2008. The second updated plan, California’s 2017 Climate Change Scoping Plan, adopted on December 14, 2017, reflects the 2030 target established in Executive Order B-30-15 and Senate Bill 32. The Assembly Bill 32 Scoping Plan and the subsequent updates contain the main strategies California will use to reduce greenhouse gas emissions.

Regional Plans
The California Air Resources Board sets regional targets for California’s 18 Metropolitan Planning Organizations to use in their Regional Transportation Plan to plan future projects that will cumulatively achieve greenhouse gas reduction goals. Targets are set at a percent reduction of passenger vehicle greenhouse gas emissions per person from 2005 levels.

The proposed project is included in the 2019 Regional Plan and 2020 Regional Transportation Improvement Program for the Council of Governments. The California Air Resources Board’s reduction targets for Council of Governments are 3 percent by 2020 and 11 percent by 2035, relative to 2005 (ARB 2019c). Table 3-1 lists identified strategies.

Attachment 3
Council Agenda 12-5-2023 12.A-153
Packet Page 404

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 130
Table 3-1 Regional and Local Greenhouse Gas Reduction Plans Title Greenhouse Gas Reduction Policies or Strategies
Council of Governments 2019
Regional Transportation Plan
·Integrated multi-modal network
·Expand public transit network
·Encourage charging stations (EV and e-bike)
·Identify grant opportunities for subsidies for e-bike leasing ·Accelerate deployment of Alternative Fuel Vehicles and infrastructure
·Coordinate efforts to promote flexible work hours, telecommuting, etc. to reduce peak-hour congestion and commute trips
·Collaborate with local public health community to improve public health outcomes through modal investments and the SCS
·Transportation Systems Management measures
·Transportation Demand Management
·Secure funding for and encourage use of Park and Ride lot system
·Fund transportation projects designed to reduce congestion ·Encourage active transportation
·Incorporate complete streets policies
·Provide funding for projects that support land uses that improve jobs-housing balance
·Improve jobs-housing balance across North County, Central County, and South County
·Protect habitat and open space areas
Council of Governments 2020
Regional Transportation
Improvement Plan
·Improve multi-modal connections between communities
·Grow San Luis Obispo Regional Transit Authority ridership by approximately two-thirds
·Reduce congestion
·Increase affordable transportation options
Council of Governments
Community 2050 Regional
Blueprint
·Strengthen and direct development toward existing communities ·Create walkable neighborhoods and towns
·Provide a variety of transportation choices
·Enhance multi-modal and community connectivity
·Increase use of clean, alternative energy
·Advocate development of renewable energy resources
·Prioritize energy efficiency through building code improvements ·Increase average fuel efficiency of fleet vehicles
City of Pismo Beach General
Plan and Local Coastal
Program (adopted 1992;
updated April 2014)
·Principle P-4—Clean Air—A Must: retain consistency with county air pollution control district
·Policy CO-4—Trip Reduction: reduce number of vehicle trips City of Pismo Beach Climate
Action Plan
·Transportation Demand Management incentives
·Electric vehicle network and alternative fueling stations ·Increase transit service frequency/speed
·City government energy efficiency retrofits and upgrades ·Energy efficiency requirements for new city-owned buildings ·Renewable energy systems on city property
·Energy efficiency outreach and incentive programs
·Smart growth
Attachment 3
Council Agenda 12-5-2023 12.A-154
Packet Page 405

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 131
Project Analysis
Greenhouse gas emissions from transportation projects can be divided into those produced during operation of the state highway system and those produced during construction. The main greenhouse gases produced by the transportation sector are carbon dioxide, methane, nitrous oxide, and hydro- fluorocarbons. Carbon dioxide emissions are a product of the combustion of petroleum-based products, like gasoline, in internal combustion engines.

Relatively small amounts of methane and nitrous oxide are emitted during fuel combustion. In addition, a small amount of hydrofluorocarbon emissions is included in the transportation sector.

The CEQA Guidelines generally address greenhouse gas emissions as a cumulative impact due to the global nature of climate change (Public Resources Code, Section 21083(b)(2)). As the California Supreme Court explained, “because of the global scale of climate change, any one project's contribution is unlikely to be significant by itself” (Cleveland National Forest Foundation versus San Diego Association of Governments (2017) 3 California 5th 497, 512). In assessing cumulative impacts, it must be determined if a project’s incremental effect is “cumulatively considerable” (CEQA Guidelines Sections 15064(h)(1) and 15130).

To make this determination, the incremental impacts of the project must be compared with the effects of past, current, and probable future projects.

Although climate change is ultimately a cumulative impact, not every individual project that emits greenhouse gases must necessarily be found to contribute to a significant cumulative impact on the environment.

Operational Emissions
Carbon dioxide accounts for 95 percent of transportation greenhouse gas emissions in the U.S. The largest sources of transportation-related greenhouse gas emissions are passenger cars and light-duty trucks, including sport utility vehicles, pickup trucks, and minivans. These sources account for over half of the emissions from the sector. The remainder of greenhouse gas emissions comes from other modes of transportation, including freight trucks, commercial aircraft, ships, boats, and trains, as well as pipelines and lubricants. Because carbon dioxide emissions represent the greatest percentage of greenhouse gas emissions, it has been selected as a proxy within the following analysis for potential climate change impacts generally expected to occur.

The highest levels of carbon dioxide from mobile sources such as automobiles occur at stop-and-go speeds (0–25 miles per hour) and speeds over 55 miles per hour; the most severe emissions occur from 0–25 miles per hour (see Figure 3-4).

Four main strategies can reduce greenhouse gas emissions from transportation sources: (1) improving the transportation system and operational efficiencies, (2) Attachment 3
Council Agenda 12-5-2023 12.A-155
Packet Page 406

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 132
reducing travel activity, (3) transitioning to lower greenhouse gas-emitting fuels, and (4) improving vehicle technologies/efficiency. To be most effective, all four strategies should be pursued concurrently.

Figure 3-4 Traffic Operations on Carbon Dioxide Emissions The project is included in the Council of Governments 2019 Regional Transportation Plan (Regional Plan), which reflects the region’s strong commitment to building a more sustainable transportation system through long-range planning efforts. The Pismo Congestion Relief Pilot Project is identified in the Regional Plan as one of the priority corridors with the greatest overall anticipated system benefits. The Council of Governments Board of Directors’ endorsed scenario for the 2019 Regional Plan would achieve an 11 percent reduction in per-capita greenhouse gas emissions by 2030 relative to 2005, meeting the California Air Resources Board’s regional target for San Luis Obispo.

The Council of Governments’ US 101 Corridor Mobility Master Plan identifies this section of US 101 as one of the highway’s most congested corridors in San Luis Obispo County. Adding a part-time travel lane is expected to improve traffic operations by reducing travel delay, reducing buffer time, improving vehicle flow and speed, and reducing collisions throughout the corridor. The reduction of existing and predicted future peak-hour congestion would address the 2019 Regional Transportation Plan’s action item aimed at “reducing congestion in highly traveled and highly congested corridors.” In addition to the part-time travel lane, the project would include other Transportation System Management elements: closed-circuit television to Attachment 3
Council Agenda 12-5-2023 12.A-156
Packet Page 407

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 133
monitor real-time operations, a vehicle detection system to monitor traffic flow and speed, and a fiber optic infrastructure network. These features will contribute to the 2019 Regional Transportation Plan’s Transportation System Management goals and contribute to the reduction of greenhouse gases by improving the transportation system and operational efficiencies.

The new park-and-ride lot at Mattie Road and Price Street would contribute to multi-modal system connectivity, aligning with the 2019 Regional Transportation Plan’s goal of maximizing the transportation system’s efficiency through Transportation Demand Management. The park-and-ride lot would provide travelers an alternative mode of travel, which could improve travel time reliability. This section of the US 101 does not support pedestrian or bicycle traffic, therefore there would be no effect on these modes.

Quantitative Analysis
Table 3-2 compares the carbon dioxide emissions and annual vehicle miles traveled by alternative for both the opening year (2026) and the design year (2046), relative to the baseline year (2018). These quantities were computed using CT-EMFAC (2017). Annual carbon dioxide emissions values were derived from daily 5-hour peak-period carbon dioxide values multiplied by 347, per Air Resources Board methodology. “Annual vehicle miles traveled” values were derived from adding daily weekday and weekend 5-hour peak- period vehicle miles traveled values (then multiplying the sum by 347, per Air Resources Board methodology).

Table 3-2 Modeled Annual Carbon Dioxide Emissions and
Vehicle Miles Traveled, by Alternative
Alternative Carbon Dioxide
(tons/year)
Annual Vehicle
Miles Traveled
2018 baseline 36,000 59,718,000
2026 No-Build Alternative 31,300 62,104,000
2026 Alternative 1 (and variation)34,900 65,878,000
2026 Alternative 2 34,900 65,878,000
2046 No-Build Alternative 26,700 63,477,000
2046 Alternative 1 (and variation)29,200 70,931,000
2046 Alternative 2 29,200 70,931,000
The anticipated increase in carbon dioxide tailpipe emissions under the Build Alternatives compared to the No-Build Alternative is tied to the increase in southbound vehicle speeds during peak afternoon hours that would occur as a result of less congestion. Vehicles are typically most efficient between 35 and 55 miles per hour. As vehicle speeds increase above 55 miles per hour, carbon dioxide emissions would also be expected to increase.

Attachment 3
Council Agenda 12-5-2023 12.A-157
Packet Page 408

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 134
However, under all project alternatives, including the No-Build, annual carbon dioxide emissions would decrease in the future compared to 2018 even as vehicle miles traveled increase. This reduction is partially due to the emissions benefits of rulemakings, including on-road diesel fleet rules, Advanced Clean Car Standards, and the Smartway/Phase 1 Heavy Duty Vehicle Greenhouse Gas Regulation. The California vehicle fleet also will become cleaner over time as older engines are phased out and replaced by newer, less-polluting engines.

While CT-EMFAC has a rigorous scientific foundation and has been vetted through multiple stakeholder reviews, its greenhouse gas emission rates are based on tailpipe emission test data. (This analysis does not currently account for the effects of the U.S. National Highway Traffic Safety Administration and Environmental Protection Agency Safer Affordable Fuel-Efficient Vehicles Rule.

Part 1, revoking California’s authority to set its own greenhouse gas emissions standards, was published on September 27, 2019 and effective November 26, 2019. The Safer Affordable Fuel-Efficient Vehicles Rule Part 2 became effective June 30, 2020 and amends existing Corporate Average Fuel Economy and tailpipe carbon dioxide emissions standards for passenger cars and light trucks and establishes new standards covering model years 2021 through 2026. The rule would retain the model year 2020 standards for both programs through model year 2026. The modeling for this project does not include adjustment factors for greenhouse gas emissions that would account for the Safer Affordable Fuel-Efficient Rule. However, modeling these estimates with EMFAC2017 or CT-EMFAC2017 remains the most precise means of estimating future greenhouse gas emissions.) Moreover, the model does not account for factors such as the rate of acceleration and vehicle aerodynamics, which influence the amount of emissions generated by a vehicle. Greenhouse gas emissions quantified using CT-EMFAC are therefore estimates and may not reflect actual physical emissions. Though CT-EMFAC is currently the best available tool for calculating greenhouse gas emissions from mobile sources, it is important to note that the greenhouse gas results are useful only for a comparison among alternatives.

Construction Emissions
Construction greenhouse gas emissions would result from material processing, onsite construction equipment, and traffic delays due to construction. These emissions will be produced at different levels throughout the construction phase; their frequency and occurrence can be reduced through innovations in plans and specifications and by implementing better traffic management during construction phases.

In addition, with innovations such as longer pavement lives, improved traffic management plans, and changes in materials, the greenhouse gas emissions produced during construction can be offset to some degree by longer intervals between maintenance and rehabilitation activities.

Attachment 3
Council Agenda 12-5-2023 12.A-158
Packet Page 409

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 135
The Caltrans Construction Emissions Tool 2018 (CAL-CET 2018) was used to quantify construction greenhouse gas emissions. Carbon dioxide emissions from construction activity for Build Alternatives 1 and 2 were calculated to be approximately 950 and 952 tons, respectively, over a 737-day construction period. This estimate is based on the best information available during preliminary design.

During construction, Caltrans would reduce greenhouse gas emissions whenever feasible. All construction contracts include Caltrans Standard Specifications Section 7-1.02A and 7 1.02C, Emissions Reduction, which require contractors to comply with all laws applicable to the project and to certify they are aware of and will comply with all Air Resources Board emission reduction regulations; and Section 14-9.02, Air Pollution Control, which requires contractors to comply with all air pollution control rules, regulations, ordinances, and statutes. Certain common regulations, such as equipment idling restrictions, that reduce construction vehicle emissions also help reduce greenhouse gas emissions. The traffic management plan would also help reduce greenhouse gas emissions from idling vehicles during construction traffic delays.

CEQA Conclusion
Upon opening, the project would increase carbon dioxide emissions by about 3,600 tons per year as a result of increased vehicle speed. By 2046, the increase in carbon dioxide emissions is expected to be 2,500 more tons per year than if the project were not constructed. Although the project would increase carbon dioxide emissions, the 2046 emissions levels with the project are expected to be approximately 6,800 tons per year lower than 2018 levels.

The improvement in carbon dioxide emissions can be attributed to greenhouse gas reduction strategies and cleaner vehicles rather than to the project itself.

The project could be found to have significant impacts on greenhouse gas emissions. (See section 3.2.8, Greenhouse Gas Emissions.) However, the reduced emissions from 2018 levels indicate substantial progress in meeting statewide emissions reduction goals. To that end, Caltrans is committed to implementing measures to help reduce greenhouse gas emissions. These measures are outlined in the following section.

Greenhouse Gas Reduction Strategies
Statewide Efforts
Major sectors of the California economy, including transportation, will need to reduce emissions to meet the 2030 and 2050 greenhouse gas emissions targets. Former Governor Edmund G. Brown Jr promoted greenhouse gas reduction goals that involved (1) reducing today’s petroleum use in cars and trucks by up to 50 percent; (2) increasing from one-third to 50 percent our electricity derived from renewable sources; (3) doubling the energy efficiency Attachment 3
Council Agenda 12-5-2023 12.A-159
Packet Page 410

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 136
savings achieved at existing buildings and making heating fuels cleaner; (4) reducing the release of methane, black carbon, and other short-lived climate pollutants; (5) managing farms and rangelands, forests, and wetlands so they can store carbon; and (6) periodically updating the state’s climate adaptation strategy, Safeguarding California. See Figure 3-5.

Figure 3-5 California Climate Strategy
The transportation sector is integral to the people and economy of California.

To achieve greenhouse gas emission reduction goals, it is vital that the state build on past successes in reducing criteria and toxic air pollutants from transportation and goods movement. Greenhouse gas emission reductions will come from cleaner vehicle technologies, lower-carbon fuels, and reduction of vehicle miles traveled. A key state goal for reducing greenhouse gas emissions is to reduce today’s petroleum use in cars and trucks by up to 50 percent by 2030 (State of California 2019).

In addition, Senate Bill 1386 (Wolk 2016) established as state policy the protection and management of natural and working lands and requires state agencies to consider that policy in their own decision making. Trees and vegetation on forests, rangelands, farms, and wetlands remove carbon dioxide from the atmosphere through biological processes and sequester the carbon in above-ground and below-ground matter.

Attachment 3
Council Agenda 12-5-2023 12.A-160
Packet Page 411

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 137
Caltrans Activities
Caltrans continues to be involved on the Governor’s Climate Action Team as the California Air Resources Board works to implement Executive Orders S-3- 05 and S-01-07 and help achieve the targets set forth in Assembly Bill 32.

Executive Order B-30-15, issued in April 2015, and Senate Bill 32 (2016), set an interim target to cut greenhouse gas emissions to 40 percent below 1990 levels by 2030. The following major initiatives are underway at Caltrans to help meet these targets.

California Transportation Plan (CTP 2040)
The California Transportation Plan is a statewide, long-range transportation plan to meet our future mobility needs and reduce greenhouse gas emissions.

In 2016, Caltrans completed the California Transportation Plan 2040, which establishes a new model for developing ground transportation systems, consistent with carbon dioxide reduction goals. It serves as an umbrella document for all the other statewide transportation planning documents. Over the next 25 years, California will be working to improve transit and reduce long-run repair and maintenance costs of roadways and developing a comprehensive assessment of climate-related transportation demand management and new technologies rather than continuing to expand capacity on existing roadways.

Senate Bill 391 (Liu 2009) requires the California Transportation Plan to meet California’s climate change goals under Assembly Bill 32. Accordingly, the California Transportation Plan 2040 identifies the statewide transportation system needed to achieve maximum feasible greenhouse gas emission reductions while meeting the state’s transportation needs. While Metropolitan Planning Organizations have primary responsibility for identifying land use patterns to help reduce greenhouse gas emissions, California Transportation Plan 2040 identifies additional strategies in Pricing, Transportation Alternatives, Mode Shift, and Operational Efficiency.

Caltrans Strategic Management Plan
The Strategic Management Plan, released in 2015, creates a performance- based framework to preserve the environment and reduce greenhouse gas emissions, among other goals. Specific performance targets in the plan that will help to reduce greenhouse gas emissions include the following:
·Increasing percentage of non-auto mode share
·Reducing vehicle miles traveled
·Reducing Caltrans’ internal operational (buildings, facilities, and fuel) greenhouse gas emissions
Attachment 3
Council Agenda 12-5-2023 12.A-161
Packet Page 412

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 138
Funding and Technical Assistance Programs
In addition to developing plans and performance targets to reduce greenhouse gas emissions, Caltrans also administers several sustainable transportation planning grants. These grants encourage local and regional multi-modal transportation, housing, and land use planning that furthers the region’s Regional Transportation Plan; contribute to the state’s greenhouse gas reduction targets and advance transportation-related greenhouse gas emission reduction project types/strategies; and support other climate adaptation goals (e.g., Safeguarding California).

Caltrans Policy Directives and Other Initiatives
Caltrans Director’s Policy 30 Climate Change (June 22, 2012) is intended to establish a department policy that will ensure coordinated efforts to incorporate climate change into departmental decisions and activities.

Caltrans Activities to Address Climate Change (April 2013) provides a comprehensive overview of Caltrans’ statewide activities to reduce greenhouse gas emissions resulting from agency operations.

Project-Level Greenhouse Gas Reduction Strategies
The following measures will also be implemented in the project to reduce greenhouse gas emissions and potential climate change impacts from the project.

Construction Emissions Reduction Measures
·The construction contractor must comply with the Caltrans’ Standard Specifications in Section 14-9 (2018), which specifically requires compliance by the contractor with all applicable laws and regulations related to air quality, including air pollution control district and air quality management district regulations and local ordinances.
·Construction equipment and vehicles will be properly tuned and maintained. All construction equipment will use low sulfur fuel as required by California Code of Regulations Title 17, Section 93114. ·A construction traffic management plan will ensure construction traffic will be scheduled and routed to reduce congestion and related air quality impacts caused by idling vehicles along local roads during peak travel times.

Operational Emissions Reduction Measures
·Preserve mature vegetation as a means of mitigating adverse air quality impacts to the maximum degree feasible. The project would be designed to minimize removal of existing trees, especially mature trees. ·Include thick, vegetative plantings and tree canopy where strategically possible to reduce population exposure to existing and future emissions from motor vehicles and to reduce the urban heat island effect.

Attachment 3
Council Agenda 12-5-2023 12.A-162
Packet Page 413

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 139
·Plant disturbed areas with a variety of native and drought-tolerant trees and shrubs to the extent possible to replace the air quality and cooling benefits of trees removed by construction of the project. Trees would be planted from the largest container size horticulturally appropriate to accelerate reestablishment of the greenhouse gas sink and to shade the pavement. Riparian planting would also be included to maintain shade along creek corridors.
·Incorporate landscaping components such as mulch and compost application to improve carbon sequestration rates in soils and reduce organic waste.
·Per Deputy Directive 17 Recycling Asphalt Concrete, incorporate recycling and waste diversion techniques by promoting the reuse of materials such as steel, road base, concrete, and asphalt-concrete to the extent feasible.

Adaptation
Reducing greenhouse gas emissions is only one part of an approach to addressing climate change. Caltrans must plan for the effects of climate change on the state’s transportation infrastructure and strengthen or protect the facilities from damage. Climate change is expected to produce increased variability in precipitation, rising temperatures, rising sea levels, variability in storm surges and their intensity, and in the frequency and intensity of wildfires. Flooding and erosion can damage or wash out roads; longer periods of intense heat can buckle pavement and railroad tracks; storm surges combined with a rising sea level can inundate highways. Wildfire can directly burn facilities and indirectly cause damage when rain falls on bare slopes that landslide after a fire. Effects will vary by location and may, in the most extreme cases, require that a facility be relocated or redesigned. Accordingly, Caltrans must consider these types of climate stressors in how highways are planned, designed, built, operated, and maintained.

Federal Efforts
Under NEPA assignment, Caltrans is obligated to comply with all applicable federal environmental laws and Federal Highway Administration NEPA regulations, policies, and guidance.

The U.S. Global Change Research Program delivers a report to Congress and the president every four years, in accordance with the Global Change Research Act of 1990 (15 U.S. Code Chapter 56A Section 2921 et seq.). The Fourth National Climate Assessment, published in 2018, presents the foundational science and the “human welfare, societal, and environmental elements of climate change and variability for 10 regions and 18 national topics, with particular attention paid to observed and projected risks, impacts, consideration of risk reduction, and implications under different mitigation pathways.” Chapter 12, “Transportation,” presents a key discussion of vulnerability assessments. It notes that “asset owners and operators have Attachment 3
Council Agenda 12-5-2023 12.A-163
Packet Page 414

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 140
increasingly conducted more focused studies of particular assets that consider multiple climate hazards and scenarios in the context of asset- specific information, such as design lifetime” (USGCRP 2018).

The U.S. Department of Transportation Policy Statement on Climate Adaptation in June 2011 committed the federal Department of Transportation to “integrate consideration of climate change impacts and adaptation into the planning, operations, policies, and programs of the U.S. Department of Transportation in order to ensure that taxpayer resources are invested wisely, and that transportation infrastructure, services and operations remain effective in current and future climate conditions” (U.S. DOT 2011).

Federal Highway Administration Order 5520 (Transportation System Preparedness and Resilience to Climate Change and Extreme Weather Events, December 15, 2014) established Federal Highway Administration policy to strive to identify the risks of climate change and extreme weather events to current and planned transportation systems. The Federal Highway Administration has developed guidance and tools for transportation planning that foster resilience to climate effects and sustainability at the federal, state, and local levels (FHWA 2019).

State Efforts
Climate change adaptation for transportation infrastructure involves long-term planning and risk management to address vulnerabilities in the transportation system. California’s Fourth Climate Change Assessment (2018) is the state’s effort to “translate the state of climate science into useful information for action” in a variety of sectors at both statewide and local scales. It adopts the follo wing key terms used widely in climate change analysis and policy documents:
·Adaptation to climate change refers to adjustment in natural or human systems in response to actual or expected climatic stimuli or their effects, which moderates harm or exploits beneficial opportunities. ·Adaptive capacity is the “combination of the strengths, attributes, and resources available to an individual, community, society, or organization that can be used to prepare for and undertake actions to reduce adverse impacts, moderate harm, or exploit beneficial opportunities.” ·Exposure is the presence of people, infrastructure, natural systems, and economic, cultural, and social resources in areas that are subject to harm. ·Resilience is the “capacity of any entity—an individual, a community, an organization, or a natural system—to prepare for disruptions, to recover from shocks and stresses, and to adapt and grow from a disruptive experience.” Adaptation actions contribute to increasing resilience, which is a desired outcome or state of being.
·Sensitivity is the level to which a species, natural system, or community, government, etc. would be affected by changing climate conditions.

Attachment 3
Council Agenda 12-5-2023 12.A-164
Packet Page 415

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 141
·Vulnerability is the “susceptibility to harm from exposure to stresses associated with environmental and social change and from the absence of capacity to adapt.” Vulnerability can increase because of physical (built and environmental), social, political, and/or economic factor(s). These factors include, but are not limited to: ethnicity, class, sexual orientation and identification, national origin, and income inequality. Vulnerability is often defined as the combination of sensitivity and adaptive capacity as affected by the level of exposure to changing climate.

Several key state policies have guided climate change adaptation efforts to date. Recent state publications produced in response to these policies draw on these definitions.

Executive Order S-13-08, issued by then-governor Arnold Schwarzenegger in November 2008, focused on sea-level rise and resulted in the California Climate Adaptation Strategy (2009), updated in 2014 as Safeguarding California: Reducing Climate Risk (Safeguarding California Plan). The Safeguarding California Plan offers policy principles and recommendations and continues to be revised and augmented with sector-specific adaptation strategies, ongoing actions, and next steps for agencies.

Executive Order S-13-08 also led to the publication of a series of sea-level rise assessment reports and associated guidance and policies. These reports formed the foundation of an interim State of California Sea-Level Rise Interim Guidance Document (SLR Guidance) in 2010, with instructions for how state agencies could incorporate “sea-level rise (SLR) projections into planning and decision making for projects in California” in a consistent way across agencies. The guidance was revised and augmented in 2013. Rising Seas in California—An Update on Sea-Level Rise Science was published in 2017 and its updated projections of sea-level rise and new understanding of processes and potential impacts in California were incorporated into the State of California Sea-Level Rise Guidance Update in 2018.

Executive Order B-30-15, signed in April 2015, requires state agencies to factor climate change into all planning and investment decisions. This order recognizes that effects of climate change other than sea-level rise also threaten California’s infrastructure. At the direction of Executive Order B-30-15, the Office of Planning and Research published Planning and Investing for a Resilient California: A Guidebook for State Agencies in 2017, to encourage a uniform and systematic approach. Representatives of Caltrans participated in the multi-agency, multidisciplinary technical advisory group that developed this guidance on how to integrate climate change into planning and investment.

Attachment 3
Council Agenda 12-5-2023 12.A-165
Packet Page 416

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 142
Assembly Bill 2800 (Quirk 2016) created the multidisciplinary Climate-Safe Infrastructure Working Group, which in 2018 released its report, Paying it Forward: The Path Toward Climate-Safe Infrastructure in California. The report provides guidance to agencies on how to address the challenges of assessing risk in the face of inherent uncertainties still posed by the best available science on climate change. It also examines how state agencies can use infrastructure planning, design, and implementation processes to address the observed and anticipated climate change impacts.

Caltrans Adaptation Efforts
Caltrans Vulnerability Assessments
Caltrans is conducting climate change vulnerability assessments to identify segments of the State Highway System vulnerable to climate change effects including precipitation, temperature, wildfire, storm surge, and sea-level rise.

The approach to the vulnerability assessments was tailored to the practices of a transportation agency, and involves the following concepts and actions:
·Exposure—Identify Caltrans assets exposed to damage or reduced service life from expected future conditions.
·Consequence—Determine what might occur to system assets in terms of loss of use or costs of repair.
·Prioritization—Develop a method for making capital programming decisions to address identified risks, including considerations of system use and/or timing of expected exposure.

The climate change data in the assessments were developed in coordination with climate change scientists and experts at federal, state, and regional organizations at the forefront of climate science. The findings of the vulnerability assessments will guide analysis of at-risk assets and development of adaptation plans to reduce the likelihood of damage to the State Highway System, allowing Caltrans to both reduce the costs of storm damage and to provide and maintain transportation that meets the needs of all Californians.

Project Adaptation Analysis
As noted above, it is expected that California may be vulnerable to climate change effects that relate to temperature, precipitation, wildfire, sea level rise, storm surge, and cliff retreat. Given the 20-year design year of 2046, climatic conditions have been considered during project planning and incorporated into project design whenever feasible. Such planning strategies are consistent with the County of San Luis Obispo and the City of Pismo Beach’s Local Coastal Programs and the Council of Governments’ 2019 Regional Transportation Plan.

Attachment 3
Council Agenda 12-5-2023 12.A-166
Packet Page 417

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 143
Although the analysis of climate change risk involves a degree of uncertainty relating to the timing and intensity of potential risks, the construction of the project itself is not expected to locally worsen the effects of climate change.

Sea-Level Rise
The portion of the project within the coastal zone is almost entirely within the limits of the City of Pismo Beach, except for the short segment northward of Avila Beach Drive. The California Coastal Commission has retained original jurisdiction in the area surrounding Pismo Creek. The project is therefore subject to the policies of the California Coastal Act and the local coastal programs of both the County of San Luis Obispo and the City of Pismo Beach.

Within the project limits, US 101 ranges from about 200 feet to 1.3 miles from the ocean and the elevation varies between 25 to 262 feet above sea level.

The State of California 2018 Sea Level Rise Guidance Document provides probabilistic projections for the height of sea level rise along the California coast using the most current data from the Ocean Protection Council.

The freeway lanes are generally planned for a 20-year life span, so the southbound lanes of US 101 would be reconstructed or rehabilitated before 2040. The southbound bridge at Pismo Creek was built in 1960 with an expected life span of 75 years, so the bridge would also likely be replaced by 2040. However, for this analysis, the projection year 2050 was used. Under a high-emissions scenario, there is 0.5 percent probability that sea level rise will meet or exceed 1.0 foot by the year 2050 at the Port San Luis tide gauge, located at the end of the pier; under an extreme climate change (H++) scenario, sea level is predicted to rise 2.6 feet. At this level, the tide would encroach somewhat farther onto the beach area of Pismo Beach and expand the volume at the outlet of Pismo Creek, but creek expansion would stop short of the freeway bridges. Sea level would need to rise by nearly 5 feet before the water level of Pismo Creek at the bridge was affected; this is not expected within the life span of the bridge. Under no predictable scenario would sea level rise encroach upon the freeway lanes. Therefore, the project is not expected to be affected by sea level rise, nor would it exacerbate the effects of sea level rise.

Floodplains
The project limits border a floodway and cross an area inundated by a 1 percent annual chance of flooding for which base flood elevations have been determined (zone AE) at Pismo Creek. As a result of climate change, future rainfall in the project region is expected to be heavier but less frequent. According to the District 5 Climate Change Vulnerability Assessment, by the year 2055, the 100- year storm depth could increase by up to 4.9 percent. Please see section 2.2.2 Water Quality and Storm Water Runoff for more information.

Attachment 3
Council Agenda 12-5-2023 12.A-167
Packet Page 418

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 144
Wildfire
The Caltrans Climate Change Vulnerability Assessment for District 5 integrates three different models that take into consideration factors such as temperature, precipitation, vegetation, population density, and fire history to determine the potential impacts of wildfires on the state highway system.

Most of the project is within the local responsibility area of CalFire’s Fire Hazard Severity Zone map; portions of this area are very high fire hazard severity zones, but otherwise the local responsibility area has no fire hazard rating. (The northern, inland section of the project limits is within a high fire hazard severity zone within the state responsibility area.) The Caltrans Vulnerability Assessment map shows a moderate level of wildfire exposure concern for the project location in the year 2055 based on a scenario with high greenhouse gas emissions continuing to the end of the century. Caltrans 2018 revised Standard Specification 7-1.02M(2) mandates fire prevention procedures during construction, including a fire prevention plan. Once completed, the project will not impair emergency response vehicles or emergency evacuation and is not anticipated to exacerbate the impacts of wildfires intensified by climate change. See section 3.2.20 Wildfire for more information.

Attachment 3
Council Agenda 12-5-2023 12.A-168
Packet Page 419

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 145
Climate Change References
Barth, Matthew and Kanok Boriboonsomsin. 2010. Real-World Carbon Dioxide Impacts of Traffic Congestion. Berkeley, CA: University of California Transportation Center. UCTC-FR-2010-11.
https://www.researchgate.net/publication/46438207 .

Cal-Adapt. Sea Level Rise Tool. http://cal-adapt.org/tools/slr-calflod-3d/ .

Accessed: June 23, 2020.

CalFire Fire and Resource Assessment Program Fire Hazard Severity Zone Viewer, California Department of Forestry and Fire Protection. https://egis.fire.ca.gov/FHSZ/ Accessed: July 17, 2020.

California Air Resources Board (ARB). 2019a. California Greenhouse Gas Emissions Inventory–2019 Edition.
https://ww3.arb.ca.gov/cc/inventory/data/data.htm .

California Air Resources Board (ARB). 2019b. California Greenhouse Gas Emissions for 2000 to 2017. Trends of Emissions and Other Indicators. https://ww3.arb.ca.gov/cc/inventory/pubs/reports/2000_2017/ghg_inventor y_trends_00-17.pdf.

California Air Resources Board (ARB). 2019c. SB 375 Regional Plan Climate Targets.
https://ww2.arb.ca.gov/our-work/programs/sustainable-communities- program/regional-plan-targets.

California Department of Transportation. 2019. Caltrans District 5 Climate Change Vulnerability Assessment. Prepared by WSP. Accessed: June 2020.

Federal Highway Administration (FHWA). 2019. Sustainability. https://www.fhwa.dot.gov/environment/sustainability/resilience/ . Last updated February 7, 2019.

Federal Highway Administration (FHWA). Sustainable Highways Initiative. https://www.sustainablehighways.dot.gov/overview.aspx .

State of California. 2018. California’s Fourth Climate Change Assessment. http://www.climateassessment.ca.gov/ .

State of California. 2019. California Climate Strategy. https://www.climatechange.ca.gov/ .

Attachment 3
Council Agenda 12-5-2023 12.A-169
Packet Page 420

Chapter 3 Ÿ California Environmental Quality Act Evaluation Pismo Congestion Relief Pilot Project Ÿ 146
U.S. Department of Transportation (U.S. DOT). 2011. Policy Statement on Climate Change Adaptation.
https://www.fhwa.dot.gov/environment/sustainability/resilience/policy_and _guidance/usdot.cfm.

U.S. Environmental Protection Agency (U.S. EPA). 2009. Endangerment and Cause or Contribute Findings for Greenhouse Gases under the Section 202(a) of the Clean Air Act.
https://www.epa.gov/ghgemissions/endangerment-and-cause-or- contribute-findings-greenhouse-gases-under-section-202a-clean.

U.S. Environmental Protection Agency (U.S. EPA). 2018. Inventory of U.S.

Greenhouse Gas Emissions and Sinks.
https://www.epa.gov/ghgemissions/inventory-us-greenhouse-gas- emissions-and-sinks.

U.S. Global Change Research Program (USGCRP). 2018. Fourth National Climate Assessment. https://nca2018.globalchange.gov/ .

Attachment 3
Council Agenda 12-5-2023 12.A-170
Packet Page 421

Pismo Congestion Relief Pilot Project Ÿ 147
Chapter 4 Comments and Coordination
Coordination with the general public and appropriate public agencies is an essential part of the environmental process to determine the scope of environmental documentation, the level of analysis, potential impacts and mitigation measures, and related environmental requirements. Agency consultation and public participation for this project have been accomplished through a variety of formal and informal methods, including project development team meetings and interagency coordination meetings, as part of Caltrans’ efforts to identify, address, and resolve project-related issues.

Early Coordination
Project development meetings have been held regularly since January 2017 and have included the Caltrans project team as well as members of the San Luis Obispo Council of Governments (Council of Governments). In addition, Caltrans has presented project updates at the following events:
·Council of Governments board meetings, October 2017 and September 2019
·San Luis Obispo County Mayors monthly meeting, November 2017 ·Council of Governments’ Technical Transportation Advisory Committee meeting, September 2019
·City of Pismo Beach Traffic Safety Committee meeting, October 2019 In September 2017, a Notice of Preparation for the project was circulated to local agencies describing the following project components:
·Extending the existing southbound truck lane near Spyglass Drive. ·Reconstructing the southbound inside shoulder to serve as a left shoulder part-time travel lane during peak periods.
·Reconfiguring the southbound Mattie Road on-ramps and off-ramps, and constructing an auxiliary lane between the relocated southbound Mattie Road on-ramp and Route 1 (Dolliver Street)/Price Street southbound off-ramp. ·Potentially removing the Shell Beach Road on-ramp at Dinosaur Caves Park based on further benefit-cost and design standards analyses.

In response to the Notice of Preparation, the California Highway Patrol expressed concerns over the impact project construction could have on traffic congestion. The agency acknowledged current and continued communication with Caltrans to provide feedback and perspective. In October 2017 and January 2020, Caltrans met with individuals from the California Highway Attachment 3
Council Agenda 12-5-2023 12.A-171
Packet Page 422

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 148
Patrol to discuss impacts during construction and incorporation of the Freeway Service Patrol.

The San Luis Obispo County Air Pollution Control District (District) also responded to the Notice of Preparation with comments including: a request for an air quality assessment to address short-term and long-term emissions impacts; mitigation if the impacts are above the District’s thresholds in the 2012 CEQA Air Quality Handbook; attention to the potential for asbestos- containing material during demolition; recommended dust control measures during construction; attention to diesel emissions near sensitive receptors during construction; consideration of feasible alternatives that would minimize air quality impacts; potential permitting information.

On May 16, 2018, Caltrans held a public meeting at the City of Pismo Beach council chamber. At that time, the project still included consideration of various components: reconfiguring the Mattie Road ramps, extending the truck-climbing lane, constructing an auxiliary lane, constructing a park-and- ride lot, and removing the Shell Beach Road on-ramp, in addition to the widened shoulder. The following is a summary of the comments received from the public:
·Add ramp metering to reduce peak-period congestion.
·Consider a long-term solution to re-route Route 101 inland, roughly following Route 227.
·Replace the post-and-beam outside-shoulder safety barrier with a concrete barrier to help reduce freeway noise and pollution. ·Extend the truck-climbing lane to the off-ramp at Spyglass Drive. ·Do not close either the southbound Spyglass Drive off-ramp or the Dinosaur Caves off-ramp.
·Place a sign directing slower traffic to the truck-climbing lane. ·The Avila Beach Drive/Shell Beach Road/ramps intersection is dangerous, confusing, and congested.
·Route 101 should be six lanes from Paso Robles to Santa Barbara, or at minimum, several three-lane passing areas should be developed within Paso Robles, Atascadero, San Luis Obispo, and Nipomo, in addition to the Avila Beach/Pismo Beach corridor.
·Operate the part-time travel lane between 2:00 p.m. and 6:00 p.m. daily, including weekends.
·Provide three lanes southbound beginning at Spyglass Drive for as far south as possible.
·There is congestion from San Luis Obispo to the Santa Maria River that should be addressed by widening Route 101 to three lanes.

Attachment 3
Council Agenda 12-5-2023 12.A-172
Packet Page 423

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 149
·Traffic speeds vary from 65-70 miles per hour to a full stop at every major on-ramp and off-ramp; closing ramps would only move the existing traffic to the next one.
·Route 101 is a major evacuation route that needs to be fully maintained. ·The truck-climbing lane has caused congested traffic to come to a full stop due to people weaving in and out of the lane. The proposed part-time travel lane will have the same effect, backing up traffic even farther. ·Remove the Price Street off-ramp; lack of sight distance makes left turns difficult.
·On a southbound commute, there is difficulty from the Five Cities Drive on-ramp to the 4th Street exit because drivers are not aware the lane is exit-only and make unexpected lane changes. White arrows directing drivers to the right lane would help.
·On a northbound commute, the congestion and short merge lane from the North Oak Park Boulevard on-ramp to the 4th Street on-ramp results in crashes from impatient drivers who try to pass or tailgate.

To generate public input on the revised project, in March 2020 Caltrans mailed a letter with the updated project scope to residents within close proximity to the project location. The letter discussed the need to evaluate soundwalls as a noise abatement measure as well as the potential for impacts to cultural resources; it also solicited input from the public on other issues to be considered in the draft environmental document.

Tribal Coordination
Throughout 2017 and 2018, Caltrans participated in the early consultation and coordination process as required by Assembly Bill 52. In response to Caltrans’ initial query, in May 2017 the yak tityu tityu yak tilhini - Northern Chumash Tribe of San Luis Obispo County and Region (Tribe) requested consultation on the project. Caltrans met with Tribal members on the project site and provided the Archaeological Survey Report and project mapping.

Subsequently, in September 2018, Caltrans received communication from the Tribe, whose comments are summarized as follows:
·Circles on a map never tell the whole story and are sometimes an incomplete guide for areas that have been tested. Testing could be inadequate and/or the reports could be missing important information. ·All sites within the project limits must be treated carefully, particularly CA- SLO-801, which is highly sensitive. In addition, the on-ramps and off- ramps should be avoided if possible to avoid sites located nearby. ·Cultural soil should stay in place. In the event any cultural soil must be relocated, it must go to a predetermined safe place.

Attachment 3
Council Agenda 12-5-2023 12.A-173
Packet Page 424

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 150
·Any monitoring must be conducted by a Northern Chumash representative. Other monitors must be knowledgeable and experienced in Northern Chumash cultural ways, material culture, and cultural landscape.
·Firm language is needed about protecting Pismo Rock.
·Copies of Applied EarthWorks’ monitoring plan should be provided to the tribe for review prior to implementation.
·Maps from engineers and archaeologists should be to the same scale.

A request to the Native American Heritage Commission for a sacred lands file search in early 2018 was returned as negative (there are no recorded sacred lands in the area).

In June 2019, the Phase 1 Inventory Study Report was provided to the Tribe and the Northern Chumash Tribal Council. In December, Caltrans oversaw extended Phase 1/Phase 2 fieldwork in the presence of monitors from the Tribe. Daily updates, concerns, questions, and requests regarding the project were discussed between Caltrans, the subcontractor, and the Tribe to the satisfaction of all participants.

In July 2020, the Extended Phase 1/Phase 2 Report was provided to Tribal Chair Mona Tucker for review; no edits were requested.

In 2021, during communications with Mona Tucker, Caltrans provided project documentation including the draft Treatment Plan and draft Programmatic Agreement.

Comments on the Draft Document
The Draft Environmental Impact Report/Environmental Assessment was circulated to the public for review and comment from October 2, 2020 to November 17, 2020. The following is a summary of the comments received on the draft document during the public circulation and comment period.

California Coastal Commission
Comment 1:

The park-and-ride lot and highway patrol pullouts are described minimally in the draft document and should be developed in greater detail in future project descriptions.

Response to comment 1:

Additional information has been added to the descriptions of the park-and-ride lot and highway patrol observation areas.

Attachment 3
Council Agenda 12-5-2023 12.A-174
Packet Page 425

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 151
Comment 2:

Regarding the coastal development permit (coastal permit) and the mixed jurisdiction, the Coastal Act allows for a consolidated coastal permit process whereby the Commission evaluates one consolidated coastal permit application. However, the Coastal Act provides for such consolidation only when “public participation is not substantially impaired by […] review consolidation” (Pub. Res. Code Section 30601.3).

Response to comment 2:

The City of Pismo Beach has expressed its intent to permit the portion of the project within its jurisdiction. This will allow for a local hearing, which allows for better public participation. Consolidation efforts will be addressed with the Commission and the County prior to any applications being submitted.

Comment 3:

Regarding the statement on page 14 of the draft document that a Federal Consistency Certification would also be required from the Coastal Commission, a coastal permit issued by the Coastal Commission to Caltrans serves as federal consistency review under the federal Coastal Zone Management Act, and therefore submittal of a separate consistency certification from Caltrans to the Commission is not required. However, a coastal permit issued by a local government does not serve as federal consistency review.

Response to comment 3:

Comment noted.

Comment 4:

Regarding the project being a seven-year pilot, any coastal permit(s) would authorize only the construction and part-time lane use proposed for the pilot period. The Coastal Act defines “development”—the trigger for requiring a coastal permit—broadly, and this includes any “change in the density or intensity of use” (Pub. Res. Code Section 30106). Therefore, at the conclusion of the seven-year pilot period, if Caltrans elects to convert the part-time lane into either a full-time shoulder or a full-time travel lane, either of these changes will require an amendment to the coastal permit(s) to reflect the new intensity of use.

Response to comment 4:

Comment noted.

Comment 5:

Regarding visual resources, the proposed sound walls appear to be fundamentally inconsistent with many, if not all, of Local Coastal Plan and Coastal Act related policies. In addition, the long lag time to establish mature Attachment 3
Council Agenda 12-5-2023 12.A-175
Packet Page 426

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 152
vegetation would reduce the quality of the visual mitigation. Since the freeway lanes have a 20-year life span, the visual mitigation provided by vegetation would not be in place for roughly one-quarter to one-third of the project’s service life.

Response to comment 5:

As explained in further detail in section 2.1.2 Visual/ Aesthetics and section

2.2.3 Noise, the southbound soundwalls (soundwalls 2 and 3), which were noted in the draft environmental document as being inconsistent with coastal policies, will not be included in the final project. The northbound wall (soundwall 6) does not appear to be inconsistent with policies as it does not block views and will mitigate excessive noise. Furthermore, the “20-year life span” of Caltrans projects involving highway lanes is related to general future planning as well as the integrity of the materials. However, this does not mean that the highway itself is expected to last only 20 years. US 101 through Pismo Beach is expected to remain in its current location for the foreseeable future, which would allow the new vegetation to mature well beyond 20 years.

Comment 6:

The project does not currently include the substantial visual mitigation necessary to be found consistent with Coastal Act and Local Coastal Plan policies. Therefore, the soundwalls are not a viable project feature. Caltrans should consider eliminating the soundwalls from the project to ensure compliance with Local Coastal Plan and Coastal Act visual and scenic resource protection policies.

Response to comment 6:

The southbound soundwalls, which were noted in the draft environmental document as being inconsistent with coastal policies, will not be included in the final project. The northbound wall does not appear to be inconsistent with policies as it does not block views and will mitigate excessive noise. See section 2.1.2 Visual/ Aesthetics and section 2.2.3 Noise for further discussion of the northbound soundwall (soundwall 6). Further discussion on the northbound wall, in conjunction with public input, will continue during the permitting process.

Comment 7:

The list of relevant Local Coastal Plan policies on page 16 related to Visual and Scenic Resources does not, but should, include Policy D-28 related to City-designated scenic highways.

Response to comment 7:

The policy has been added to the list.

Attachment 3
Council Agenda 12-5-2023 12.A-176
Packet Page 427

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 153
Comment 8:

The conclusions of Caltrans’ Noise Study Report appear to further call into question the worth of constructing the proposed soundwalls. Based on the noise analysis beginning on page 59, the Noise Study Report indicated that the project would not result in a substantial increase in highway noise at any of the measured receptor locations. In fact, for the majority of the receptor locations, the noise increase resulting from the new highway lane would be at or only slightly above the threshold detectable by the human ear (see page 62). These noise impacts are not proportionate to the described impacts, visual and otherwise, of the proposed soundwalls. Therefore, rather than abating impacts associated with the new lane construction, the proposed soundwalls present a significant net-increase in impacts without adequate justification.

Response to comment 8:

The two southbound soundwalls are no longer being considered for the project. However, please note that consideration of noise abatement is not based entirely on the predicted increase in noise levels with a project, as explained in the Regulatory Setting in section 2.2.3 Noise, and reiterated in the new discussion in section 4.1.4 Soundwalls. It must also be noted that some locations are expected to experience an increase in the noise level of more than 7 decibels as a result of the project. Please refer to Appendix B Predicted Future Noise Levels and Noise Barrier Analysis in the Noise Study Report for this data. The potential impacts of constructing the soundwalls on aesthetics and cultural resources are described and considered in section

2.1.2 Visual/Aesthetics, section 2.1.3 Cultural Resources, section 3.2.1 Aesthetics, and section 3.2.5 Cultural Resources.

Comment 9:

Amending a local coastal plan to render a proposed project approvable is a complex, multi-year process that would require significant coordination between Caltrans, the local government(s), and Commission staff. More fundamentally, we caution that local coastal plan amendments should not be seen as a mechanism for rendering approvable a project feature that is starkly inconsistent with Coastal Act policies. Any amendment to a land use policy must come before the Coastal Commission for approval, where it is judged for consistency with the policies of the Coastal Act. Therefore, if a project feature appears inconsistent with the Coastal Act, it is unlikely that the Commission would approve such an amendment to allow it. Caltrans should bear this point in mind when deciding whether to include soundwalls in the final project proposal.

Response to comment 9:

Comment noted. Caltrans has begun preliminary coordination with San Luis Obispo County, the City of Pismo Beach, and the Coastal Commission.

Attachment 3
Council Agenda 12-5-2023 12.A-177
Packet Page 428

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 154
Caltrans will continue coordination with the jurisdictional authorities through the Coastal Development Permit application process.

Comment 10:

Given that the additional part-time lane is being proposed as a temporary pilot project, the construction of permanent soundwalls in order to abate noise impacts associated with the new lane seems premature. The draft document is clear that the new lane is currently intended to operate for only seven years, at which point Caltrans will determine whether it becomes a full-time travel lane or a full-time shoulder. If Caltrans elects to use the lane as a full- time shoulder, the new soundwalls and their associated impacts will have been unnecessary. Thus, it seems that the logical juncture for deciding whether to construct the soundwalls will be the point at which the pilot is complete and Caltrans knows the permanent disposition of the part-time lane.

Until that time, it is impossible for the Commission or local governments to judge with certainty whether soundwalls are warranted. For this and the other reasons stated above, we strongly advise that the soundwalls not be included as part of the proposed project.

Response to comment 10:

As a point of clarification, the new lane is not expected to operate for only seven years. It is Caltrans’ intent to maintain the part-time travel lane as a permanent feature, although the hours of operation could change in response to need. As explained in the Introduction in Chapter 1, toward the end of the 7-year pilot period, Caltrans will pursue legislative approval to make the lane permanent. Caltrans cannot determine the final disposition of the feature; however, legislative approval is anticipated. Construction of soundwalls must be considered in response to the noise impacts anticipated by this project at the onset of operation. Based on the studies completed to date and input from the public, Caltrans does not intend to incorporate noise abatement in the form of soundwalls, but the final decision on noise abatement will be made upon completion of the project design.

The point regarding timing is noted.

Comment 11:

The policies of the Coastal Act and the Local Coastal Plans require development adjacent to environmentally sensitive habitat areas to be sited and designed to prevent impacts that would significantly degrade those areas.

Additionally, please note that the Commission generally requires any permissible long-term impacts to habitat to be mitigated at a 3:1 ratio by acreage. While temporary impacts may generally be mitigated at a 1:1 ratio, higher ratios may be necessary if such impacts will not be fully mitigated within a reasonably short time after their commencement (e.g., several years).

Attachment 3
Council Agenda 12-5-2023 12.A-178
Packet Page 429

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 155
Response to comment 11:

Comment noted.

Comment 12:

To help minimize impacts to habitat, Caltrans should consider the feasibility of using semi-permeable landscape fabric (e.g., WeedEnder) at ramp gores instead of extended paving. This measure would also help to minimize visual and water quality impacts associated with the project.

Response to comment 12:

Preliminary design included gore treatment to match what has already been used in the area to create a unifying element in the community. Alternative treatments could be considered if they pass the performance and safety testing requirements.

Comment 13:

Caltrans should evaluate any lighting that will be added or modified along the highway corridor and in the park-and-ride lot as part of the project. Caltrans should ensure that all lighting is designed to shine with the minimum necessary brightness and color temperature and is located sufficiently far away from coastal streams and wetlands. Opportunities to replace lighting with reflective signage or other materials should be considered. We also recommend that Caltrans evaluate potential improvements to existing lighting within the highway corridor area as a potential mitigation opportunity for any unavoidable impacts to habitat, streams, or other wetlands.

Response to comment 13:

The only lighting that currently exists is at the on- and off-ramps and the stop/signal at the interchanges; no existing impacts to coastal streams and wetlands due to the existing lighting have been identified by studies completed for this project. Alteration of existing lighting is outside of the scope of this project, and no additional lighting is planned for the corridor. Lighting needs at the park-and-ride lot will be assessed during final design.

Comment 14:

Regarding the proposed bridge widening over Pismo Creek, the Coastal Act and the Local Coastal Plans generally restrict filling in coastal streams and other wetlands, including the placement of bridge piles, foundations, or streambank protective devices such as sheet piling. Bridge widening over Pismo Creek should employ wide spans to clear the creek areas as fully as feasible and to avoid or minimize the placement of piles, foundations, and protective devices in streams and other wetland areas.

Attachment 3
Council Agenda 12-5-2023 12.A-179
Packet Page 430

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 156
Response to comment 14:

As explained under Environmental Consequences in section 2.3.2 Wetlands and Other Waters, no new piers will be placed within the Pismo Creek channel. The only permanent impacts within the channel will be from the sheet piling, which is necessary to minimize impacts to the creek.

Comment 15:

Regarding evaluating unavoidable impacts to wetlands, when applying for the coastal permit(s) for this project, these impacts must be identified and mitigated using a one-parameter wetland delineation, consistent with the Commission’s standards. The Commission generally requires long-term impacts to wetlands to be mitigated at a 4:1 ratio by acreage. While placement of new piles should be minimized or avoided to the greatest extent feasible, any unavoidable pile installation should utilize construction methods or sound attenuating devices that minimize hydroacoustic impacts. Given that there are sensitive species in Pismo Creek, the project should include appropriate best management practices to ensure that negative impacts are avoided/minimized to the greatest extent feasible.

Response to comment 15:

No wetlands impacts from the project have been identified. The project includes measures to minimize creek impacts to the greatest extent practical.

Comment 16:

Future sea level rise analyses included in the final document and in any coastal permit applications should also mention how much the water level of the creek would need to rise by to impact the bridge’s piers and deck.

Additionally, future analyses should note whether such projections factor in future extreme storm events and bridge scour, for clarity. If locating new bridge piles out of the creek is infeasible, future analyses should also note whether sea level rise projections account for increased water levels due to the new piles in the stream.

Response to comment 16:

No further sea level rise analysis is anticipated for this project. Under even the worst-case—though highly unlikely—extreme climate change (H++) scenario, which includes extreme storm events, sea level rise would not affect the bridge. The bridge piers, by design, could withstand creek encroachment, whether from sea level rise or from flooding. As mentioned under “Sea Level Rise” in State Efforts in section 3.3.5 Adaptation, the minimum height of the project, which occurs at Pismo Creek Bridge, is 25 feet. The document also states that sea level would need to rise by nearly 5 feet before the water level of Pismo Creek at the bridge was affected. The water at the creek would therefore have to rise another 25 feet before it reached the bridge deck.

Based on the analysis already performed, the likelihood of this occurring within the life span of the bridge is effectively 0 percent. See “Sea Level Rise” Attachment 3
Council Agenda 12-5-2023 12.A-180
Packet Page 431

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 157
in State Efforts in section 3.3.5 Adaptation for additional details on sea level rise. Furthermore, the use of sheet piling in the creek is necessary to minimize impacts to the creek.

Comment 17:

Because there are archaeological sites within the project area that are eligible for the National Register, we are concerned that the project (specifically, one of the southbound sound walls) has the potential to significantly impact known cultural resources. Caltrans must conduct thorough tribal consultation before any coastal permit applications are submitted. Effective tribal consultation by Caltrans early in the permit process will help ensure that permitting delays do not occur.

Response to comment 17:

As discussed in section 2.1.3 Cultural Resources and the new subheading Tribal Coordination under section 4.1.1 Early Coordination, Caltrans has followed the procedures set forth in Section 106 of the National Historic Preservation Act and has participated in early tribal consultation and coordination as required by Assembly Bill 52. Caltrans will continue to follow the requirements as defined by these regulations and others, if any, identified in the Coastal Act or local coastal plans.

Comment 18:

The mitigation measures for impacts to archaeological resources described on pages 46 to 47 of the draft document are framed in general, hypothetical terms. Coastal permit application(s) for this project should include a more detailed, concrete description of cultural resource mitigation measures to help local government and Commission staff determine the project’s consistency with applicable Local Coastal Plan provisions and Coastal Act Section 30244.

Response to comment 18:

The procedures identified in Section 106 of the National Historic Preservation Act, which includes review and approval of proposed mitigation measures by the State Historic Preservation Officer, must be completed before approving the final environmental document. These measures have been added to section 2.1.3 Cultural Resources.

Air Pollution Control District (Air District)
Comment 1:

Comments were submitted in a letter dated October 18, 2017. These comments were acknowledged in the draft document, but actions items were not addressed. Please address these action items. Air quality analyses and applicable mitigation measures, as well as state and federal air quality regulatory requirements listed in our 2017 letter should be included in the final document.

Attachment 3
Council Agenda 12-5-2023 12.A-181
Packet Page 432

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 158
Response to comment 1:

It is important to note that the action items identified in the 2017 letter in response to the Notice of Preparation are directions for future environmental studies that were to be conducted; they are not comments on the draft environmental document, nor do they take into consideration the revised project description or the actions already taken prior to circulation. The comments are generic and advisory in nature; most of the actions are standard Caltrans practice for preparation of the draft environmental document and design of the final project, and therefore were not specifically described in the document. In addition, the project was down-scoped dramatically since the Notice of Preparation was circulated. The environmental document summarizes the detailed analysis contained in the Air Quality Report, completed in March 2020, which was made available for public review upon request at the time the draft document was published, and which addresses many of the Air District’s points.

Comments from 2017 letter:

Item 1—Contact information.

Response on Item 1—Noted.

Item 2—Permitting and approval authorities.

This comment is summarized as follows: This comment specified requirements for air quality construction phase impact assessment, requirements for diesel equipment information and diesel emissions near sensitive receptors, requirements for asbestos and demolition, dust control measures which must be implemented, construction permit requirements, and construction phase idling limitations.

Response on Item 2— Detailed analysis of the project’s effect on air quality can be found in the Air Quality Report. Requested information that is not already contained within the report is better assessed during final design of the project. Circumstances are not present on the project that would require any permits issued by the Air District. As a state agency, Caltrans is held to the U.S. Environmental Protection Agency’s approved rules and regulations for the San Luis Obispo County Air Pollution Control District portion of the California State Implementation Plan, which is the 2001 Clean Air Plan. The project is consistent with the Clean Air Plan. (Please see section 3.2.3 Air Quality.) The Air District is not a responsible agency on this project under CEQA and therefore has no direct authority over the project and cannot require mitigation. However, the Air District may submit recommendations related to its concerns to the applicable responsible agency during the permitting process.

Item 3—Environmental information
Attachment 3
Council Agenda 12-5-2023 12.A-182
Packet Page 433

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 159
This comment is summarized as follows: A complete air quality analysis should be included in the Draft Environmental Impact Report to adequately evaluate the overall air quality impacts associated with implementation of the proposed project. The required information to be included in the air quality analysis is outlined.

Response on Item 3—The environmental document contains the information required under CEQA and NEPA and is based on the complete air quality analysis contained in the Air Quality Report. This technical report provides the technical details the Air District is requesting. In addition, please refer to section 3.2.3 Air Quality of this document for more information, as well as sections 3.2.8 Greenhouse Gas Emissions, 3.3 Climate Change, and in particular 3.3.3 Project Analysis for information on the greenhouse gas analysis. Please note that the air quality analysis Caltrans performs as part of its standard practice incorporates a cumulative study of the air basin as a whole. Furthermore, as noted in the environmental document, the project is included in the Council of Governments’ 2019 Regional Transportation Plan.

The reduction of existing and predicted future peak-hour congestion would address the 2019 Regional Transportation Plan’s action item aimed at “reducing congestion in highly traveled and highly congested corridors.” Item 4— Permit Stipulations/Conditions
It is recommended reference material include the 2012 version of the “CEQA Air Quality Handbook” (the Handbook). lt can be accessed on the APCD website.

Response on Item 4—Please see response to item 2.

Item 5—Alternatives analysis.

Any alternatives described in the DEIR should involve the same level of air quality analysis as described in section 3 listed above.

Response on Item 5—There was no appreciable difference in the modeled air quality impacts from the various alternatives. Please see Table 3-2 for carbon dioxide emissions estimates by alternative.

Item 6—No reasonably foreseeable projects.

Response on Item 6—Comment noted.

Item 7—Use of CEQA Air Quality Handbook for significance determinations.

Response on Item 7—Please see response to item 2.

Attachment 3
Council Agenda 12-5-2023 12.A-183
Packet Page 434

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 160
California Highway Patrol
Comment 1:

As a result of this project, we anticipate local California Highway Patrol (Highway Patrol) operations will be impacted. The Highway Patrol welcomes the construction of an additional lane of travel at the project location. How- ever, the part-time designation of the travel lane raises safety concerns.

Given the lane weaving that occurs, and tourist unfamiliarity with the area, the installation of lane-use control signals at 2,300-foot intervals may be insufficient to properly protect against errant drivers.

Response to comment 1:

Lane-use control signals will be installed at a minimum of 2,300 feet; intervals will be set such that at least one signal will be visible to drivers at all times.

Comment 2:

Although eliminated from discussion, the addition of a third general-purpose, full-time travel lane or a high-occupancy vehicle lane would eliminate the potential for any travel-lane-versus-shoulder confusion created by the current proposal.

Response to comment 2:

A third general-purpose, full-time travel lane or a high-occupancy vehicle lane is beyond the scope of this project. As identified in Table 1-5 Rejected Design Options, a full-time travel lane or a high-occupancy vehicle lane meets the purpose and need of the project, but would have excessive cost and greater community and environmental impacts. With at least one lane-use control signal visible at all times, there should be no confusion about the operational status of the part-time travel lane.

City of Pismo Beach
Comment 1:

The document should acknowledge Pismo Beach’s designation of US 101 as a scenic highway. Policy D-23 of the City’s Local Coastal Program applies this designation due to the portion of the highway in the project site providing travelers with the only ocean view between the Golden Gate Bridge in San Francisco and Gaviota, which is a distance of over 300 miles. However, this is not the only policy in the City’s Local Coastal Program to highlight how important the views and aesthetics from US 101 are to Pismo Beach and commuters. The document should acknowledge the importance of this distinction to the local community.

Response to comment 1:

A statement to include the City’s classification has been added to the coastal policies discussion under section 2.1.1 Coastal Zone.

Attachment 3
Council Agenda 12-5-2023 12.A-184
Packet Page 435

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 161
Comment 2:

The document should consider soundwalls a Significant and Unavoidable Impact for scenic resources. Southbound travelers would be impacted by the inclusion of soundwalls in the project. While the other components of the project, including retaining walls, increased paving, and lane-use controls, would have impacts to the scenic resources of the project area, those impacts can be minimized. However, construction of soundwalls would have a Significant and Unavoidable Impact for the local community’s scenic resources.

Removal of soundwalls from the project would eliminate this impact.

Response to comment 2:

Caltrans makes significance determinations under CEQA that consider the whole of the action, which includes all project elements, for each environmental resource and topical area. To that end, Caltrans has determined that the project will result in significant and unavoidable impacts to the visual quality of the corridor and surrounding area and has noted the soundwalls as a contributing feature.

Comment 3:

The City supports maintaining the truck-climbing lane through to the Spyglass Drive offramp, also known as the Alternative 1 Truck-Climbing Lane Variation.

This would help reduce issues with local traffic being required to merge with through commuters shortly before exiting the freeway.

Response to comment 3:

Caltrans has noted that as of March 9, 2021, the City has provided an updated statement regarding alternative preference: “Based upon the regional benefits and the promise that the 4pm – 7pm hours of the managed shoulder are a starting point and can be adjusted as needed to relieve congestion we can support that option. We agree that the extension of the managed shoulder that Alt. 2 provides will be a greater regional benefit.” Comment 4:

The City would like to see the installation of an R4-3 “Slower Traffic Keep Right” or similar sign at the point where the truck climbing lane begins.

Response to comment 4:

Alternative 2 will eliminate the truck-climbing lane and thereby the need for vehicles to merge due to a loss of travel lane until the end of the project limits at the railroad overhead.

Comment 5:

The City would encourage consideration of construction phasing to provide the extension of the truck-climbing lane prior to other project components.

Attachment 3
Council Agenda 12-5-2023 12.A-185
Packet Page 436

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 162
This phasing would help mitigate construction-related impacts to both the mainline and the City’s local circulation system.

Response to comment 5:

According to the traffic study, minimal operational benefit would be achieved with a standalone truck-climbing lane extension; the congestion and queuing would be largely unchanged. However, phased construction can be considered in more detail during project design.

Comment 6:

The City of Pismo Beach is looking forward to processing the Coastal Development Permit for the portion of the project located within the City limits.

Response to comment 6:

Comment noted.

Assemblyman Jordan Cunningham
Comment 1:

I am the Assemblymember that represents the 35th district, which includes San Luis Obispo County and the section of US 101 that runs through Pismo Beach. I am pleased to write in support of the full funding of the US 101 San Luis Obispo South County Congestion Relief Project as well as submit 1,698 [sic] signatures from Central Coast residents in support of this project.

The US 101 Corridor Mobility Master Plan, conducted by the San Luis Obispo Council of Governments, identifies US 101 through Pismo Beach as the most congested stretch of highway in the region. The corridor experiences daily southbound commute congestion and seasonal congestion, specifically in the summer months when residents from around the state visit the region’s popular coastal destinations. I fully support the allocation of funds for the US 101 San Luis Obispo South County Congestion Relief Project.

These are improvements that fit our region’s coastal community character, address our long-term highway capacity needs, reduce vehicle emissions, facilitate goods movement, support the region’s tourism economy, alleviate vehicle dependency, and enhance safety for drivers, pedestrians, and bicyclists alike.

Response to comment 1:

Thank you for your support. Information on your petition can be found at the end of this section under Other Public Input. Please note the petition contained 1,687 signatures.

Attachment 3
Council Agenda 12-5-2023 12.A-186
Packet Page 437

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 163
backpacker0509
Comment 1:

I think this option is best: converting the truck climbing lane into the rightmost travel lane, eliminating the merge.

Response to comment 1:

Comment noted.

Bob Schrempp
Comment 1:

I am writing to let you know I support this project. It is a well known that you should not travel south out of San Luis Obispo in the afternoon during "rush hour". Leaving SLO headed south between 4:30 and 6 on a weekday means it will take you an extra 30 to 60 minutes to get past Pismo Beach. On Sunday the traffic starts earlier and runs into the early evening. This project means a lot to the Central Coast.

Response to comment 1:

Comment noted.

Catriona Orosco, Shell Beach
Comment 1:

I strongly believe the truck climbing lane should become an Exit Only lane to Shell Beach Rd. The current merge only contributes to traffic problems. In addition, we need a part-time 3rd lane, or full time, to ease congestion.

Response to comment 1:

The preferred alternative (Alternative 2), which eliminates the truck-climbing lane, will also eliminate the necessity to merge and will provide a third general-use lane during periods of heavy congestion.

Comment 2:

Coming into Pismo Beach from the north, people are often stunned by the amazing view. There’s also a lot of commuter traffic coming from the north.

On a daily basis I see traffic backed up headed south on the 101. Lastly, with the introduction of the path on Shell Beach Rd, I would also like to see a solid wall along the 101 S corridor at Shell Beach. This would provide protection in the event of an accident and reduce noise for the residents.

Response to comment 2:

Metal-beam guardrail currently exists along the outside highway shoulder, which contains most errant vehicles. According to Caltrans’ traffic incident data, there has been only one occasion in which a vehicle crashed through Attachment 3
Council Agenda 12-5-2023 12.A-187
Packet Page 438

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 164
this barrier. This segment of US 101 does not have a safety issue related to errant vehicles.

Cheryl Willey, Arroyo Grande
Comment 1:

As everyone knows who drives the 101 south through Avila to Pismo, the truck lane is used by speeders who want to try to skip ahead of all the backed-up traffic. We need some way to discourage this, by signage and/or additional CHP support to check the people using the lane as such. It's very dangerous, as they can either come upon a slow-moving truck traveling in the lane, or a vehicle entering the freeway and trying to merge into that lane. The speeders then have to quickly slow down and try to merge/cut in on the next lane, which could cause accidents.

Response to comment 1:

The preferred alternative (Alternative 2) will not only reduce backed-up traffic, but also provide a continuous right-hand lane where trucks are most likely to be positioned as they approach the grade. This will reduce the opportunity for others to use the right-hand lane to move around traffic.

Comment 2:

Since the merge area is also a big part of the problem, people need to learn how to merge properly. I’d suggest CalTrans investigate the “zipper” merge method that’s being used successfully in other states and countries. It encourages people to fill up both lanes equally, and then do the “every other one” zipper merge at the end to merge two lanes into one. This will eliminate the issue of having a long line of cars on the left and a shorter line on the right that people run up into and then cut into the left lane.

Response to comment 2:

By providing a continuous right-hand lane, the preferred alternative (Alternative 2) will eliminate the necessary merge movements.

Comment 3:

If you put appropriate signage far enough ahead on the freeway, it would notify people of the upcoming merge, and include a diagram to help show drivers how to do the zipper merge. And I would put the signage overhead as well, as signs on the side of the road can be overlooked or blocked if a big truck is between you and the sign. Maybe put the first signs on the San Luis Bay overpass, and reminder signage near the Avila onramp. I attached a quick mock up of what a sign might look like that could be put over the freeway, with the arrows lined up with the two lanes involved.

Response to comment 3:

The selection of Alternative 2 will eliminate the need for vehicles to merge.

Attachment 3
Council Agenda 12-5-2023 12.A-188
Packet Page 439

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 165
Clare Malone Prichard
Comment 1:

The draft document considers sound walls in only four locations. Private residences in Shell Beach exist adjacent to the highway in a continuous strip along the west side of Highway 101 from Ontario Ridge near the Avila Beach Drive on/off-ramp to Spyglass Drive, with the exception of a small section which is occupied by hotels. Many homes in Pismo Beach on the eastern side of the highway are also in close proximity to the proposed improvements and as such will be negatively impacted by the proposed improvements. The four locations proposed for sound walls do nothing to address the negative noise impacts that all of these homes would be subjected to.

The primary reason stated for not providing the required soundwalls is "the loss of ocean views and reduction of community character.” This is a false assertion, given that Section 1102.6(4) of the July 2020 Caltrans Highway Design Manual provides for transparent noise barriers where view sheds may be affected by highway construction. Such transparent barriers have been allowed by the Coastal Commission in other locations such as Interstate 5 in the San Diego area and in Newport Beach.

Response to comment 1:

As shown in Table 2-1 of the document, the noise abatement criterion level for residential properties is 67 decibels. The results of the noise study indicate that noise levels at the properties at the northernmost end of the project are expected to be around 64 decibels or lower after the project is built; around Silver Shoals Drive and southward, the noise levels are expected to be higher, between 65 and 73 decibels for those closest to the highway. A soundwall was evaluated for this stretch, described as Segment 1 in the document section on noise, but as noted in that section, it did not pass the reasonableness criteria due to the low numbers of receptors that would benefit. (Residences farther from the highway experience lower noise levels from traffic. There are also large gaps of undeveloped property within this segment.) Please see section 4.1.4 Soundwalls for more information.

Comment 2:

In summary, CEQA requires that the impacts of the proposed project must be mitigated to the greatest extent possible. I believe that the draft document’s analyses of the noise impacts and possible mitigations are insufficient.

Solutions exist that would protect the adjacent residences from unacceptable noise levels while still providing views for persons traveling on the freeway, yet these methods have not been explored.

Response to comment 2:

Per section 15126.4 of the Guidelines for Implementation, only feasible mitigation measures must be discussed in the environmental impact report.

Furthermore, these measures must be “fully enforceable through permit Attachment 3
Council Agenda 12-5-2023 12.A-189
Packet Page 440

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 166
conditions, agreements, or other legally binding instruments.” Please see section 4.1.4 Soundwalls for more information.

Dave Daguerre
Comment 1:

I would extend merge past Spyglass. Anything more not really needed as traffic clears up fairly quickly after that point.

Response to comment 1:

The traffic study identifies other areas within the project limits that are expected to experience slow traffic in the near future during the peak afternoon hours.

Please see section 1.5 Comparison of Alternatives for more information.

Comment 2:

Consider a north bound exit off the Price Canyon Road and Price Street.

Traffic of large trucks and campers are causing issues on Bello St where I live. We have two schools, fire department, police department, a church, Vets Hall and overflow parking from tourists. If large trucks coming west on Price Canyon can exit onto freeway there and campers coming east on Hinds can enter there, traffic out of town would flow nicely and be kept out of neighborhood street of Bello. Currently the Hinds off ramp on the north lane of 101 is not used as much because of all traffic from Price Canyon. I do not believe it would be missed as large trucks cannot make sharp turn to get onto Price St. If you put in a north bound off ramp, it will be safer for a lot of people and less congestion for our first responders.

Response to comment 2:

The concerns you raise relate to local traffic issues and are better addressed by the City of Pismo Beach. Caltrans would consider any proposal by the City that affected the state facility (US 101 and roadway infrastructure within the state highway right-of-way).

Dave Payne, Pismo Beach
Comment 1:

I am a homeowner in Pismo Beach and will be impacted by the Pismo Congestion Relief Project. While the construction phase will certainly disrupt traffic in our area, I strongly support moving forward with this project. The congestion in the area on almost every day is a problem for travel and negatively impacts air quality. Addressing this congestion problem is long overdue and I encourage approval of the environmental impact assessment.

Response to comment 1:

Comment noted.

Attachment 3
Council Agenda 12-5-2023 12.A-190
Packet Page 441

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 167
Diana James, Shell Beach
Comment 1:

I live in Shell Beach my partner lives in SLO and I drive back and forth 2 to 3 times a day as I also have a business in Shell Beach. Make the far left lane longer and complete so we as residents of Shell Beach can use that lane to bypass the other two thru traffic lanes. Why does it merge? Response to comment 1:

Presumably the comment is referring to the truck-climbing lane, which is on the far right. That lane was built to allow slow-moving trucks to move out of the main traffic lanes on the incline so they would not slow mainline traffic.

The lane merges at the point where trucks would have regained mainline speed. The preferred alternative (Alternative 2) will convert the truck-climbing lane to a general-use lane and extend it to the Spyglass overhead.

Comment 2:

If you’re going to do this huge project do it fast not during the day or peak times. We as residents of Shell beach JUST GOT DONE with two plus years of Shell Beach Road being torn up and huge delays for me to get to my home on Capistrano Avenue. I’m not looking forward to ANOTHER big huge long traffic road improvement. Make it quick , don’t block or work during peak times, work at night please. Once it’s done I’m sure it will be nice.

Why does the area bottle neck? Looky-loos gazing at the first ocean they see.

Response to comment 2:

Due to project scheduling and funding constraints, Caltrans is limited in its ability to consolidate construction timing between different projects. A traffic management plan will be implemented during construction delays. Project construction will require some night work, which would be outside of peak travel times. Ultimately, in many instances the choice to complete construction during nighttime hours will be at the discretion of the contractor.

Caltrans acknowledges that night work imposes some limitations on visibility and can affect residents’ sleep patterns due to noise and construction lighting.

Diane Clement, San Luis Obispo
Comment 1:

Based on a San Luis Obispo Tribune article, I see you are calling the added right lane a truck lane. One thing to keep in mind is people in regular vehicles like to move to that lane to see the beautiful sudden appearance of the coast after 101 not being near the ocean at all in California southbound. Result is a dangerous mix of trucks, distracted drivers and passengers, and those merging from the Avila onramp. I don’t know what this means for your planning but I think awareness of this should be part of your plans for any changes to that difficult section of 101.

Attachment 3
Council Agenda 12-5-2023 12.A-191
Packet Page 442

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 168
Response to comment 1:

The preferred alternative (Alternative 2) will convert the truck-climbing lane to a continuous, general-use travel lane, eliminating the need for any merge movements between lanes on the mainline until it ends at the Spyglass overhead. Drivers entering the mainline from Avila Beach Drive will still need to merge safely.

Gary Bynum
Comment 1:

This has been a problem area for decades and since we won't see a 3rd lane from SLO to Santa Maria anytime soon, I suggest extending it past the Spyglass exit before merging.

Response to comment 1:

In December 2014, the Council of Governments adopted its 2014 US 101 Corridor Mobility Master Plan (Corridor Plan) after substantial public engagement. The Corridor Plan identified the project area as the most congested segment on the US 101 corridor in San Luis Obispo County. The extent of the part- time travel lane was determined based on the findings of the Corridor Plan and through evaluation of project alternatives, with Alternative 2 being the preferred alternative.

Gary Linquist
Comment 1:

That Caltrans is doing something, anything, about the massive traffic jams on the southbound 101 in Pismo Beach is good news. However, we cannot wait until 2024 for the project to be finished. This project needs to be moved up to #1 on the Caltrans/SLOCOG to do list. These daily traffic jams are the #1 traffic problem in San Luis Obispo county and should have been mitigated 10 years ago. Please move the planning and construction plans up to 2021 and finishing in 2022.

Response to comment 1:

This project is the top priority for the San Luis Obispo Council of Governments, the project’s sponsor. However, prior to beginning construction, Caltrans must complete the project development process, which includes environmental review, final project design, environmental reevaluation of the final design, and contractor selection. In addition, the Council of Governments has yet to secure 100 percent of the funding for project construction. At present, with approved funding, construction is scheduled to begin in the summer of 2024 and be completed in the spring of 2026.

Attachment 3
Council Agenda 12-5-2023 12.A-192
Packet Page 443

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 169
Comment 2:

Instead of starting the project on the southern end, flip it around and start on the northern end and open up sections as they are finished. The traffic jams move from north to south and anything you can do to alleviate them helps.

Response to comment 2:

The traffic congestion within the project limits occurs at several locations. At each of these locations, the traffic backups collect in a northward direction, extending toward the City of San Luis Obispo. There is no prescribed plan for how construction will be carried out; construction progression will be at the discretion of the contractor.

Comment 3:

Do all work on the project from inside the median. Never block any traffic lanes during the day and ONLY block any lanes between 9pm and 5am! The traffic jams are bad already, don't make them worse!
Response to comment 3:

The specific progression of construction activities will be at the discretion of the contractor. The contractor will be best equipped to determine a feasible, safe, and efficient manner in which to complete construction as it progresses.

A traffic management plan will be prepared to minimize impacts to traffic during construction, and will include hours and days of lane closures.

Comment 4:

Of the 3 plans presented to the Pismo Beach City Council on October 20, 2020, please proceed with the most effective plan that can be completed the fastest.

Response to comment 4:

Alternative 2 was selected as the preferred alternative because it provides the longest extent of the part-time travel lane while remaining within the cost range of the other options.

Comment 5:

At the same time, instigate, plan and complete, as fast as is humanly possible, the connection between the existing third lane/climbing lane and the Spyglass/Mattie Road - Exit #193. Nobody is going wait until 2024 for Caltrans/SLOCOG to get their acts together to do something about the severe, sometimes mind-bending daily traffic jams in Pismo Beach.

Response to comment 5:

The preferred alternative (Alternative 2) will eliminate the truck-climbing lane as part of the overall project, creating two full-time travel lanes and the part- time travel lane. The traffic study indicated that extending the truck-climbing lane as an independent feature would not provide congestion relief.

Attachment 3
Council Agenda 12-5-2023 12.A-193
Packet Page 444

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 170
Comment 6:

The Spyglass Connection is the connection between the existing third lane/climbing lane and the Spyglass/Mattie Road - Exit #193. Everyone thought that with the passage of funding in 2018 (SB 1?) that this connection would be completed right away, especially because of the fact that 50% or more of the connection ALREADY EXISTS!! 50% of the paving needed to extend the climbing lane to the Syglass exit already exists on the median, to the left of the fast lane. In fact , that section was recently repaved during the October repaving project. Quite simply, all Caltrans needs to do is finish roughly 500-700 feet of paving, restripe the freeway and add a sign or two (right lane must exit...thru traffic merge left) and you're done! Response to comment 6:

Extending the truck-climbing lane to the Spyglass exit does not remove the need to merge, which is driving the congestion at that location. Furthermore, it does nothing to address the congestion that is developing farther south.

Comment 7:

Making the Spyglass Connection would do a number of good things. First, it would lessen the volume and intensity of the traffic jams by 20 to 30%. As all of the Shell Beach and Palisades residents get used to, and use, the new lane/exit, the number of cars re-merging and slowing traffic would decrease dramatically. Second, lighter or less frequent traffic would relieve the traffic on Shell Beach road through the recently completed Shell Beach Streetscape.

Why spend 10 million dollars to make things better only to have gridlock from cars trying to escape the freeway traffic jams. And finally, quickly finishing the Spyglass Connection by June 1, 2021, would show everyone just how good and how fast Caltrans can be. It would be a major public relations win for both Caltrans and the City of Pismo Beach with all attending media publicity.

Response to comment 7:

Please see response to comment 6.

Geo Pecci, Pismo Beach
Comment 1:

I am definitely in favor of the 7-year pilot operational improvement project that widens 101 to address traffic delays that occur during periods of high traffic volumes on the southbound lanes of US 101 through Shell Beach and Pismo Beach. Anything to help reduce the bad congestion southbound in the afternoons.

Response to comment 1:

Comment noted.

Attachment 3
Council Agenda 12-5-2023 12.A-194
Packet Page 445

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 171
Jonathan Harms, Pismo Beach
Comment 1:

I am writing to voice my concern regarding possible changes being considered to the 101 corridor between Avila Beach and Pismo Beach. As a part time resident of Pismo Beach, I am aware of the bottleneck that occurs most days during the late afternoon/early evening. It can be a bit frustrating at times to experience these delays. With the increase in area population and the many visitors that enjoy their vacations here, I understand the need for addressing our traffic issues. However, I do have concerns regarding the aesthetics that would be compromised with these improvements. My primary concern is the use of “sound walls” placed at various locations adjacent to the 101, as well as the proposed concrete walls which would stand up to eleven feet in height. These barriers would greatly impact the beautiful vistas that our local residents cherish and our many visitors enjoy. I would hope that the powers that be consider these concerns and that the treasure that is Pismo Beach and surrounding areas not be compromised.

Response to comment 1:

Soundwalls that would block views of the Pacific Ocean have been removed from consideration. Refer to section 2.1.2 Visual/ Aesthetics and section

4.1.4 Soundwalls for additional details. The retaining wall that would be constructed between the highway and Price Street is necessary to avoid impacts to Pismo Rock; it will not block views of the hills. Since this wall will be in a commercially developed area of Pismo Beach and will receive aesthetic treatments, it is not expected to stand out as an unusually urbanizing feature.

Ken Meerson, Pismo Beach
Comment 1:

As a Pismo Beach resident, I support converting the truck climbing lane into the rightmost travel lane, eliminating the merge. I believe it would help alleviate the traffic problem on Hwy.101.

Response to comment 1:

Comment noted.

Lindsey Harms
Comment 1:

I am writing to express my objection to the Pismo Beach congestion relief project. This small section of highway provides the only view of the Pacific Ocean on Highway 101 with the exception of Ventura, and it is singular in its panoramic beauty. The proposed concrete barriers and sound walls will permanently deprive residents and visitors of this experience.

Attachment 3
Council Agenda 12-5-2023 12.A-195
Packet Page 446

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 172
Response to comment 1:

Soundwalls that would block views of the Pacific Ocean have been removed from consideration. There could be limited views for some northbound drivers due to the higher median barrier. The opinion expressed regarding the project is noted.

Comment 2:

Further, the proposed project is out of character with the area, and a dispro- portionate measure compared to the relatively low severity and amount of traffic.

I have commuted daily for years between San Luis Obispo and Pismo Beach, and as someone who experiences the peak traffic times firsthand, I consider it a small price to pay for the experience of driving through this lovely area. I do not believe that the commuter/visitor traffic justifies the proposed change.

I respectfully ask you to reconsider. This type of project may be appropriate in highway segments that are already built-up and don't benefit from the juxtaposition of the natural landscape, but I do not believe you can apply the same broad brush to every traffic situation. This project would move us towards a suffocating urbanization and erode the joy afforded to us by California's natural wonders.

Response to comment 2:

The commentor’s objection to the project is noted. Caltrans has acknowledged that the project would be out of character for the area and has determined that this would be an unmitigable significant impact from the project. However, Caltrans and the San Luis Obispo Council of Governments have determined that the benefits to the public outweigh these impacts.

Michelle Harms, Pismo Beach
Comment 1:

I am stating my objection to the Pismo congestion relief project for the following reasons:

The beauty of the current freeway is irreplaceable. There is a joie de vivre experience when driving past Pismo Beach on Highway 101. The dramatic emotional experience comes from the accumulative visual effects of the ocean, the hills, the dunes, and the natural landscaping in its entirety.

I make the trip between Pismo Beach and San Diego several times per year.

Driving north, I pass several counties and drive on several freeways looking at hundreds of miles of sound walls and concrete barriers. Looking at all the concrete is mentally and physically taxing. When I arrive in Pismo Beach, the natural beauty on Hwy 101 relieves this stress. The actual experience of driving on the 5-mile length of Hwy 101 in Pismo Beach is joyful.

Attachment 3
Council Agenda 12-5-2023 12.A-196
Packet Page 447

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 173
I have driven south from Avila Beach during the commuter congestion. It is not like sitting in traffic on other freeways. There are beautiful views to enjoy during the commute. You can even watch the sunset in your rearview mirror while the traffic proceeds. The proposed project is not proportional to mitigate approximately 2 hours of commuter traffic, by eliminating a natural master- piece that cannot be experienced on any freeway in North America.

Please work with public transit authorities to instate express bus routes for commuters living south of Pismo Beach. Do not proceed with this project.

Response to comment 1:

The commentor’s objection to the project is noted. Although every effort will be made to minimize the appearance of the additional hardscape and urbanization caused by the project, these impacts have been determined to be unmitigable and significant. However, the vast majority of respondents have been in favor of the project, so Caltrans and the San Luis Obispo Council of Governments have determined that the benefits to the public outweigh these impacts.

Richard4844, Pismo Beach
Comment 1:

I have a comment about reckless drivers’ use of the existing truck-climbing lane as a high-speed passing lane. I live in Pismo Beach and I frequently travel on US 101 between Pismo Beach and San Luis Obispo. Anyone driving southbound on US 101 has to be careful about reckless drivers who use the truck-climbing lane as a highspeed, right-side passing lane. Reckless drivers do this at all times; not just during times of congestion. Perhaps, if the truck- climbing lane were extended as the slower right lane, there would be less risk of collisions.

Response to comment 1:

The selection of Alternative 2 will convert the truck-climbing lane to the right- most continuous, general-use travel lane and eliminate the inappropriate use.

Tom Worby, Nipomo
Comment 1:

I recommend extending the “truck climbing lane” from Avila Beach Drive all the way to Spyglass to eliminate the merge before Spyglass. I often see vehicles merging from the lane 3 climbing lane to lane 2 then immediately exiting at Spyglass.

Response to comment 1:

The selection of Alternative 2 will convert the truck-climbing lane to the rightmost continuous, general-use travel lane and eliminate the need for vehicles to merge.

Attachment 3
Council Agenda 12-5-2023 12.A-197
Packet Page 448

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 174
Other Public Input
On October 12, 2020 during the public comment period for the draft environmental document, Assemblyman Jordan Cunningham created a post on his Facebook page encouraging the public to sign his petition in favor of the project. The petition received 1,687 signatures from across his jurisdiction in response to the statement, “I support the U.S. 101 San Luis Obispo South County Congestion Relief Project because it will help relieve traffic congestions along the Central Coast and improve roadway safety for drivers.” The results of this petition were sent to Caltrans on November 16, 2020 and therefore have been considered as comments received during the public review period.

The number of signatures received follows the name of each town of residence: Santa Maria 246; San Luis Obispo 240; Arroyo Grande 231; Nipomo 152; Paso Robles 136; Atascadero 130; Pismo Beach 106; Grover Beach 80; Lompoc 67; Morro Bay 61; Los Osos 58; Templeton 36; Oceano 30; Cambria 22; Avila Beach 16; Cayucos 16; Orcutt 11; Shell Beach 10; Creston 9; Guadalupe 7; San Miguel 6; Santa Margarita 6; Bradley 3; Shandon 3; Agoura Hills 1; Rancho Cucamonga 1; Porterville 1; Madera 1; Monterey 1.

Public Hearing Discussion
On October 20, 2020, Caltrans and the Council of Governments held a public hearing via Zoom, with a simulcast on YouTube. Staff from both agencies presented project information through maps, diagrams, and video, as well as live description. The hearing was taped and has been available on the Caltrans and Council of Governments project web pages. The following is a condensed and paraphrased transcript of the discussion with relevant time-stamps.
37:20 Craig Cummings
I live in Shell Beach on Windward Avenue. The truck-climbing lane currently creates a lot of bottleneck so I’m totally in favor of seeing that extended past at least the Spyglass off-ramp. I know people tend to use that as an auxiliary lane and it ends up still becoming a bottleneck. Those of us who live in Shell Beach have to merge into the slow lane and then progress another quarter mile to the off-ramp—a large inconvenience. If the truck-climbing lane is extended at least past the off-ramp, does that change where the temporary- use lane begins, or does that temporary-use lane begin at the same point farther down the hill towards Avila?
I understand the purpose of the retaining wall along Price Street is to shift the lanes to the right towards the beach and get them around the Pismo Rock.

Totally in agreement with that. Obviously, for the residents who live here and also the tourists and everybody else, because Price Street is a major artery in our neighborhood, I think Caltrans would be remiss if they don’t give some Attachment 3
Council Agenda 12-5-2023 12.A-198
Packet Page 449

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 175
aesthetic treatment to that retaining wall, something that would possibly reflect the beach community of Pismo and Shell Beach and make this something attractive for us that use that road constantly. And also our visitors to our area in order to enhance that road rather than put up a solid, concrete, monolithic pour.

The single soundwall on the northbound off-ramp maybe makes good sense for that community. I don’t see that that’s a real visual impact. But for southbound Route 101, I am totally against any concrete barrier soundwalls going up because of the negative visual impact it would have.

Not just on our community, but when you’re traveling south on the 101 from a long ways north, this is the first view of the ocean you get along the California coast. If it turns into a soundwall cut-up cookie-cutter look that you see in the middle of urban areas, I don’t think it enhances or adds to our community and I think it would be objectionable to see that. If the soundwalls have to be employed, hopefully there can be a transparent soundwall. Your graphic representations of the soundwalls pretty much show what they would look like from the highway side. I have to think about what they’re going to look like from our neighbor-hood side. We not only look towards the ocean, we also look toward the beautiful hills. So those concern me quite a bit. My preference would be no soundwalls. We have pretty much the same volume of traffic, however it’s going to be flowing at a faster rate during these hours of use of that temporary lane. I’m questioning if the visual impact of the soundwall is worth it for a specific period of time when the noise is going to be worse than it was the other 16 hours of the day. In my opinion, I don’t think they’re worth it. I notice retaining walls will have to go in to support the vertical load of those soundwalls, again an aesthetic treatment of anything that’s facing our community would be a requirement.
45:08 Response to Cummings
The starting point of the part-time travel lane is the same for both Alternative 1 and the truck-climbing lane variation. The starting point with Alternative 2 starts farther north, just past San Luis Obispo Creek. With this alternative, the part-time travel lane doesn’t start as its own separate lane. Instead, the travel lanes ease over to the right and the truck-climbing lane that is currently there becomes the right-most travel lane. Therefore, with three lanes built, the left one becomes the part-time travel lane. What was the truck-climbing lane continues to the south without any further need to merge.

The retaining wall, which will be visible from Price Street, will be aesthetically treated. This is specified in a measure in section 2.1.2 Visual/ Aesthetics. Furthermore, see section 2.1.2 Visual/ Aesthetics and section

4.1.4 Soundwalls for details regarding consideration of aesthetic impacts of the soundwalls. Preservation of the scenic quality of the corridor and minimization of aesthetic impacts are of importance. Public input will be further considered per the noise abatement process outlined in section 4.1.4 Attachment 3
Council Agenda 12-5-2023 12.A-199
Packet Page 450

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 176
Soundwalls. Based on the studies completed to date and input from the public, Caltrans does not intend to incorporate noise abatement in the form of soundwalls, but the final decision on noise abatement will be made upon completion of the project design.
48:09 George Gibson
Was there an alternative looked at simply removing the truck-climbing lane? The southbound traffic prior to the San Luis Bay interchange is moving at speed with no congestion. There isn’t a large change in the amount of traffic between San Luis Bay bridge and Spyglass, and yet there’s a bottleneck and the congestion starts because of the idiots who sneak over into that truck lane and barrel down the freeway and then merge back in, causing people to slam on their brakes and cause a backup that takes an hour and half to clear. Traffic is moving smoothly southbound north of the San Luis Bay bridge. If you remove that truck lane there is nothing to stop that smooth movement of traffic south into Arroyo Grande.
50:13 Response to Gibson
We did look at that scenario. The existing issue is because, during peak periods, the traffic volume exceeds capacity. If we remove the truck-climbing lane, we’re still going to see stop-and-go traffic. With Alternative 2, we have basically removed the truck-climbing lane, but we still need the part-time lane to have enough capacity to handle the traffic demands.
51:17 George Gibson
My concern is that traffic capacity is being handled north of San Luis Bay intersection, and suddenly you introduce a third lane that people use inappropriately causing hard braking at the merge point before Spyglass, and if it could handle the capacity just 2 miles farther to the north, why can’t it handle the capacity at Spyglass with just two lanes, getting rid of the truck lane? I truly believe that the capacity flowing down the freeway north of San Luis Bay Drive is being affected by driving habits that’s offered by that truck lane. If you keep them in two lanes, they’re going to move smoothly because they’re not going to be jockeying for position.
53:09 Response to Gibson
The bottleneck that’s causing the slowdown that backs up to the Spyglass area and also the Avila Beach interchange is actually farther down south. But we do recognize that the truck-climbing lane exacerbates the problem. With Alternative 1 and the truck-climbing lane variation, we start the part-time travel lane about one-third mile north of the Spyglass exit, slightly north of where the merge location is. We end up with 4-lane capacity in that section, which is able to handle the capacity. With Alternative 2, we removed the truck-climbing lane, which addresses your concern, but we still need the third lane capacity. The part-time travel lane provides three-lane capacity all the way south through the corridor.

Attachment 3
Council Agenda 12-5-2023 12.A-200
Packet Page 451

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 177
55:25 George Gibson
Signing for the truck-climbing lane is non-existent. It’s confusing if you try to go into that lane and suddenly you find yourself on Avila Beach Drive. Where it merges back into two lanes is a poor location. Truckers are not using the climbing lane because of the accelerating cars coming up on the right-hand side and they can’t move over in time. So there are a number of points that make that truck-climbing lane hazardous. For $61 million, there’s a much simpler and less costly fix. Thanks for the opportunity and I look forward to the project.
56:52 Lori
Many areas in California have constructed temporary lanes for congestion relief. Eventually, those temporary lanes become permanent, full-time lanes due to traffic volumes. When are these temporary lanes expected to become full-time lanes?
57:13 Response to Lori
The traffic study looked at traffic growth in 2026 and 2046; we used the projected 2046 volumes in the model. It showed that, with the part-time travel lane, the corridor is still able to handle the traffic demands to 2046 and beyond.
1:00:20 Craig Cummings
I became aware of this hearing via our Facebook SOS page by our neighborhood historian, but I never heard in any other fashion. How is the public notified of these meetings, because it doesn’t seem like we have a very large turnout here? Maybe if there’s another one coming up it could be distributed to the residents and get a little more input. 1:01:04 Response to Cummings
The San Luis Obispo Council of Governments (Council of Governments) worked with their Public Information Officer and the Caltrans counterpart to do press releases and posted them to the Council of Governments’ social media sites, e-mail blasts, and newsletters. The meeting competed with other jurisdictional meetings and game 1 of the World Series. Also, a New Times ad was taken out. There’s better participation streaming in on YouTube right now. We have both a recording and a live stream on YouTube, which will be posted to the Council of Governments and Caltrans web sites for those who are unable to attend. In addition, Caltrans’ Public Information Officer was interviewed by KSBY for a story on October 8, 2020. In the closer statement of that story, aired for an 11:00 p.m. news brief and reiterated on KSBY’s newsfeed, they advertised this meeting as well. This project will also be presented to the public during the coastal development permitting process. In March 2020, a letter was sent to residents adjacent to the highway to give a heads up that the public comment period was coming. Anyone who responded to the Notice of Attachment 3
Council Agenda 12-5-2023 12.A-201
Packet Page 452

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 178
Preparation, sent out in 2017, or to the March letter was sent an email notification as well. It was anticipated that there would be word-of-mouth notification. Lastly, it was brought up as an item on the Pismo City Council meeting (happening concurrently), and on the South County Chamber of Commerce web site. The hearing recording will be posted, as well as the email address for comments, which will be accepted until November 17, 2020. Is there a better way of getting the word out?
1:05:35 Craig Cummings
Not really. Effie McDermott, a local historian in Shell Beach with the SOS (Save Old Shell Beach) page on Facebook, is how I was notified about this.

The other organization we have here is SBIG.
1:07:19 Lori
There is no “word of mouth” during COVID. In Shell Beach, we often get postcards for new meetings for projects in the area. We did not get any postcards for this.
1:07:32 Response to Lori
Postcards can be very expensive. We initially looked at the properties within 200 feet of the project and it resulted in thousands of addresses. But we are continually improving our outreach process so if you have any ideas, we welcome hearing them.

Soundwalls
After the close of the public comment period, Caltrans, the Council of Governments, and the City of Pismo Beach received comments related to soundwalls and noise levels, particularly within Shell Beach. To address some of the misinformation and uncertainty related to the soundwalls, additional information was provided to relevant agencies and individuals, and is contained below.

According to federal regulations and Caltrans policy, noise abatement must be considered under the National Environmental Policy Act when predicted noise levels with a project are 12 decibels or more above existing levels, or when the predicted noise levels are within 1 decibel of the federal noise abatement criteria level for specific land uses. The exterior noise abatement criteria level for residential properties is 67 decibels, which is comparable to a loud conversation or a vacuum cleaner. (A table showing the noise abatement criteria levels can be found in section 2.2.3 Noise.) To begin the noise study, Caltrans team members specializing in noise evaluations took sound measurements at selected locations within the project limits and created a computer model that allowed them to input various factors in order to calculate the anticipated project noise levels within the project limits. (This process is explained in more detail in the Attachment 3
Council Agenda 12-5-2023 12.A-202
Packet Page 453

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 179
Noise Study Report.) The results of this modeling showed that, at most locations, existing noise levels are below the noise abatement criteria of 67 decibels. Data from the Traffic Operations Analysis Report was input into the model, as well as factors related to variables such as terrain and existing structures, and the results indicated that, although no location showed more than a 7.4-decibel increase in noise level, with the project constructed quite a few would exceed the noise abatement criteria of 67 decibels or would be within 1 decibel of the noise abatement criteria. (A table with all the results of existing and predicted noise levels can be found in the Noise Study Report.) This meant the team would have to consider adding noise abatement in the form of soundwalls.

Before soundwalls can be added to a project, they must be determined to be feasible and reasonable. A soundwall is determined to be feasible if it will result in a 5-decibel reduction in the noise level at the receptor.

Soundwalls of between 8 and 16 feet high were evaluated at 13 locations along the highway corridor—6 on the southbound shoulder and 7 on the northbound; all were determined to be acoustically feasible. (The neighborhoods of Beachcomber Drive and Silver Shoals Drive would have benefited from one of these soundwalls. No other location within Shell Beach warranted the consideration of noise abatement.) However, in order to be determined reasonable, a soundwall must benefit a certain number of receptors to justify the cost. A federal limit of $107,000 is allowed for each receptor that would receive at least 5 decibels of noise reduction from a soundwall. The total allowance for each soundwall is calculated by multiplying the number of benefited receptors by the $107,000 allowance.

Only 3 of the 13 soundwalls met this criterion. These soundwalls are described in this document and shown in figure 2-17.

Section 2.1.2 Visual/Aesthetics contains photo simulations of how the soundwalls might appear, as shown in figures 2-7, 2-13, and 2-15. As noted in the discussion, these simulations are intended to be conceptual only and not necessarily realistic representations. They are included to show the degree of view obstruction and urbanization that would result from the construction of soundwalls.

During the public review period of the draft environmental document, Caltrans received few comments in support of the soundwalls. In addition, the City of Pismo Beach and the California Coastal Commission have both indicated they would not approve soundwalls that block ocean views. (Both agencies have permitting authority over the project.) While there has been some speculation over the use of transparent walls, Caltrans has determined the project location is not suitable for this type of installation.

Caltrans’ experience has been that the transparent panels erode over time and eventually become clouded, thereby defeating the purpose of maintaining coastal views. In addition, where transparent panels are used, it is Caltrans practice to place them on a solid wall at least 8 feet high for maintenance reasons (graffiti, damage, etc.) At the southbound locations considered on this project, an 8-foot-high solid wall would still block ocean views, with or without a transparent panel on top.

Attachment 3
Council Agenda 12-5-2023 12.A-203
Packet Page 454

Chapter 4 Ÿ Comments and Coordination
Pismo Congestion Relief Pilot Project Ÿ 180
Caltrans recognizes the impact the increase in noise would have on neighborhoods and has acknowledged it as a significant impact under the California Environmental Quality Act. However, the adverse effect of obstructing ocean views, coupled with the lack of support from the public and our partner agencies during the public comment period, was determined to be greater and affected a larger portion of the population.

Therefore, the southbound soundwalls (soundwalls 2 and 3) were dropped from the project. However, Caltrans takes its responsibility to minimize adverse impacts from construction projects seriously. To that end, the project team has been working with the City of Pismo Beach on other solutions that might reduce highway noise and nuisance. One of those options considered was a short, continuous wall, no taller than 4 feet, along the southbound shoulder within key sections of the project limits that could have provided up to a 3-decibel reduction in highway noise for some residents. After reviewing the data, including photo simulations, the City of Pismo Beach rejected the option due to its impacts to views of the ocean and community, citing that it would be inconsistent with the City’s Local Coastal Plan.

The process is on-going and will continue throughout the design and permitting phase of project development, during which time there will be more opportunity for public input.

Attachment 3
Council Agenda 12-5-2023 12.A-204
Packet Page 455

Pismo Congestion Relief Pilot Project Ÿ 181
Chapter 5 List of Preparers
This document was prepared by the following Caltrans staff:

Carr, Robert, Landscape Associate. B.S., Landscape Architecture; 29 years of experience in visual impact analysis and landscape architecture.

Contribution: Visual Impact Analysis.

Domingos, Andrew, Associate Environmental Planner (Natural Sciences).

B.S., Environmental Science (Resource Management); 13 years of experience in biological studies. Contribution: Natural Environment Study.

Gomez, Raymond, Transportation Engineer. B.S., Environmental Engineering; 1 year of experience in environmental engineering.

Contribution: Noise Study Report.

Haydu, Damon, Associate Environmental Planner (Cultural Resources). M.A., Cultural Resources Management, B.A. Anthropology; 23 years of experience in prehistoric and historic archaeology. Contribution:

Oversight and compilation of Historic Property Survey Report.

Ho, Jackson, P.E., Transportation Engineer. B.S., Civil Engineering; 15 years of experience in civil engineering. Contribution: Noise Abatement Decision Report.

Huddleston, Paula, Associate Environmental Planner. B.A., Anthropology; 29 years of experience in environmental analysis. Contribution:

Environmental studies coordination and research.

Inkrott, Kristin, P.E., Transportation Engineer (Hydraulics). B.S., Environmental Engineering; 25 years of experience in hydraulics and water resources. Contribution: Location Hydraulics Study.

Koradia, Rajvi, P.E., Transportation Engineer (Environmental Engineering).

M.S., Civil and Environmental Engineering; 2 years of experience in environmental engineering. Contribution: Air Quality and Water Quality Reports.

Leckie, Daniel, Associate Environmental Planner (Cultural Resources). M.S., Historic Preservation; B.A., American History and Sociology; 5 years of experience in architectural history and historic preservation.

Contribution: Historic Resources Evaluation Report.

Leyva, Isaac, Engineering Geologist. B.S., Geology; 29 years of experience in petroleum geology, environmental, and geotechnical engineering.

Contribution: Initial Site Assessment and paleontology study.

Attachment 3
Council Agenda 12-5-2023 12.A-205
Packet Page 456

Chapter 5 Ÿ List of Preparers
Pismo Congestion Relief Pilot Project Ÿ 182
Riegelhuth, Pete, Landscape Architect (Stormwater). B.S., Landscape Architecture; 13 years of experience as Stormwater Coordinator.

Contribution: Storm Water Data Report.

Other project team members:

Beard, David, P.E., Senior Transportation Engineer. B.S., Civil Engineering; 29 years of experience in civil engineering.

Bertaina, Lara, Senior Environmental Planner. B.A., Environmental Studies and Planning; 20 years of experience in environmental analysis.

Bonner, Larry, Senior Environmental Planner (Biology). B.S., Natural Resources Management; 22 years of experience in environmental analysis.

Kiaha, Krista, Senior Environmental Planner (Cultural Resources). M.S. and B.A., Anthropology; more than 20 years of experience in cultural resource management.

Mikel, Karl, P.E., Senior Transportation Engineer (Environmental Engineering). M.S., Civil and Environmental Engineering; B.S., Environmental Engineering; 12 years of experience in environmental engineering.

Valadao, Paul, P.E., Project Manager. B.S., Civil Engineering; 21 years of experience in civil engineering.

Attachment 3
Council Agenda 12-5-2023 12.A-206
Packet Page 457

Pismo Congestion Relief Pilot Project Ÿ 183
Chapter 6 Distribution List
In addition to those notified by the State Clearinghouse, the following agencies and individuals received notice of the availability of the Draft Environmental Impact Report/Environmental Assessment:

Jessica Adams
National Marine Fisheries Service
Long Beach, CA
Captain Greg Klingenberg
California Highway Patrol
San Luis Obispo, CA
U.S. Fish and Wildlife Service
Ventura, CA 93003
U.S. Army Corps of Engineers
Ventura, CA
Steve Hulbert
California Department Fish and
Wildlife
Fresno, CA
Central Coast Regional Water
Quality Control Board
San Luis Obispo, CA
Jeff Winklepleck
Planning Department
City of Pismo Beach
Pismo Beach, CA
Kerry Brown
Planning and Building Department
County of San Luis Obispo
San Luis Obispo, CA
Sean Drake
California Coastal Commission
Sacramento, CA
Katie Butler, Brian O’Neill
California Coastal Commission
Santa Cruz, CA
Native American Heritage
Commission
West Sacramento, CA
California Transportation
Commission
Sacramento, CA
Stephen Hanamaikai
SLOCOG
San Luis Obispo, CA
Mona Tucker
Northern Chumash Tribe
Arroyo Grande, CA
Attachment 3
Council Agenda 12-5-2023 12.A-207
Packet Page 458

Pismo Congestion Relief Pilot Project Ÿ 184
Appendix A Resources Evaluated Relative
to the Requirements of
Section 4(f): No-Use
Determination
Section 4(f) of the Department of Transportation Act of 1966, codified in federal law at 49 U.S. Code 303, declares that “it is the policy of the United States Government that special effort should be made to preserve the natural beauty of the countryside and public park and recreation lands, wildlife and waterfowl refuges, and historic sites.” The project does not use or affect any of the types of facilities protected under this law.

This appendix discusses historic properties found within or next to the project area that do not trigger Section 4(f) protection because they are not eligible historic properties under Section 4(f).

Archaeological Resources
For an archaeological site to be eligible for protection under Section 4(f), it must be listed or eligible for listing on the National Register of Historic Places.

Specifically, they must be listed or eligible for listing under criterion A; that is, they must contribute to the major pattern of American history.

Extended Phase 1 and Phase 2 testing, as well as research of previously identified historic resources within the project area, was conducted and subsequently noted 10 archaeological sites in the vicinity of the proposed project. (See section 2.1.3, Cultural Resources for more information on these sites.) One site, CA-SLO-839, had been determined not eligible for the National Register, and 2 sites—CA-SLO-832 and CA-SLO-1003/1420—had been previously determined eligible for the National Register under criterion D (meaning the property has yielded or may be likely to yield information important to history or prehistory). Therefore, the provisions of Section 4(f) do not apply to these properties. Seven of the remaining sites were unevaluated; four of these were determined to be outside of the area of potential effects and therefore were also not considered under Section 4(f).

The remaining three sites—CA-SLO-801, CA-SLO-2885, and CA-SLO- 80/H—are all within the area of potential effects and were unevaluated for National Register eligibility. In accordance with Section 106 of the National Historic Preservation Act, Caltrans requested concurrence from the State Historic Preservation Officer on the eligibility of these sites. (Supporting documentation prepared during environmental review mistakenly identified CA-SLO-80/H as having already been determined eligible.) Findings demonstrate that the portion of CA-SLO-801 within the Caltrans right-of-way has undergone extensive landform modification associated with US 101 Attachment 3
Council Agenda 12-5-2023 12.A-208
Packet Page 459

Appendix A Ÿ Resources Evaluated Relative to the
Requirements of Section 4(f): No-Use Determination
Pismo Congestion Relief Pilot Project Ÿ 185
construction; however, intact cultural deposits remain and confirm the integrity of the deposit. Additionally, evidence suggests that CA-SLO-801 was an important prehistoric habitation and cemetery site for the ancient Chumash and is considered by the modern Native American community to be a location important in California prehistory. Therefore, Caltrans recommended that CA- SLO-801 be found eligible for listing in the National Register under both criteria A and D; CA-SLO-2885 and CA-SLO-80/H were recommended under criterion D only.

If the State Historic Preservation Officer had concurred that CA-SLO-801 were eligible under criterion A, the site would have been determined a Section 4(f) property. However, Caltrans received concurrence on eligibility only under criterion D for all three sites; therefore, they are not Section 4(f) properties and the provisions of Section 4(f) do not apply.

Architectural Resources
Seven historic-period built-environment properties (the former Machado residence at 2920 Shell Beach Road and six properties directly north of the Wadsworth Avenue northbound off-ramp: 470 and 472 Pismo Avenue; 901, 951, and 991 Bello Street; and 475 Hollister Avenue) were identified within the project’s area of potential effects. Caltrans formally evaluated the properties to determine whether they were eligible for listing in the National Register of Historic Places and determined that none met any of the criteria for eligibility. All additional resources, including 13 bridges within the area of potential effects, have been previously determined to be ineligible for the National Register. None of the properties are a Section 4(f) property, there- fore the provisions of Section 4(f) do not apply.

Attachment 3
Council Agenda 12-5-2023 12.A-209
Packet Page 460

Pismo Congestion Relief Pilot Project Ÿ 186
Appendix B Title VI Policy Statement
Attachment 3
Council Agenda 12-5-2023 12.A-210
Packet Page 461

Pismo Congestion Relief Pilot Project Ÿ 187
Appendix C Avoidance, Minimization
and/or Mitigation Summary
The following summarizes the measures that could be included in the project to avoid or minimize impacts to environmental resources as a result of the project. Anticipated impacts to visual quality and cultural resources have been determined to be significant under CEQA, as well as impacts from the increase in noise and emissions as a result of the project. Measures to mitigate significant or potentially significant impacts under CEQA are identified. Impacts to other resources have been determined to be less than significant under CEQA. The potential impacts and specific measures are discussed in more detail in Chapter 2.

Visual/Aesthetics
Soundwalls, retaining walls, bridge rail, concrete slope paving, contrast surface treatment, and concrete weed control will include aesthetic treatment.

Metal components, including but not limited to poles, cabinets, equipment and connectors, and fences, will be painted or otherwise colored. Barriers and guardrail will be placed at the lowest possible elevation. The project will include new landscaping; any constructed soundwalls would be obscured with vegetation as much as possible. The park-and-ride lot will include landscaping that reduces the visibility of parked vehicles as seen from US 101. The project will include the minimum number of signals, lights and signs required to meet the project’s functional and safety requirements.

Visual impacts from the project have been determined to be significant under CEQA. These measures would minimize, but not fully mitigate the impacts to below the level of significance.

Cultural Resources
Construction will be monitored by qualified individuals. Treatment measures would be necessary to address the effects of the project on the deposits eligible for the National Register or the California Register. Treatment measures typically would include data recovery excavations with full analysis and interpretations based on a research design. However, due to the nature of the freeway project, archaeological excavations prior to construction are not feasible due to safety and access issues. Given the breadth of this project, which covers most of the Pismo terrace, additional treatment could include ethnographic studies, compilation of previous archaeological data, and/or oral history interviews from modern descendant communities. Also, measures should include a form of public outreach. Public interpretive materials would include, but not be limited to, an exhibit or sign approved by Caltrans, the County of San Luis Obispo, and the City of Pismo Beach with input and consultation with local Native Americans to be placed in an easily accessible location, on a website, or a static exhibit suitable for display at The Attachment 3
Council Agenda 12-5-2023 12.A-211
Packet Page 462

Appendix C Ÿ Avoidance, Minimization and/or Mitigation Summary Pismo Congestion Relief Pilot Project Ÿ 188
History Center, San Luis Obispo Public Library, and/or other appropriate public location within the City of Pismo Beach.

Impacts from the project have been determined to be significant under CEQA and potentially significant under NEPA. These measures would minimize, but not fully mitigate, the impacts to below the level of significance under CEQA; impacts under NEPA would be considered less than significant with these measures included.

Water Quality and Storm Water Runoff
The project design would incorporate permanent storm water treatment best management practices to treat a minimum of 9 acres of impervious surface.

The project would also repair damaged slope paving that is currently suffering from erosion, and all disturbed areas would be treated with erosion control or be replanted to prevent runoff that could cause siltation. A Storm Water Pollution Prevention Plan would be prepared for the project and would include selected best management practices to be included in the project.

Noise
Soundwalls would mitigate significant noise impacts under CEQA; if not constructed, these areas would experience significant impacts that could not be mitigated. Open-graded pavement would temporarily minimize the impact by reducing noise levels to some degree, but it cannot be considered a federal noise abatement measure.

Impacts from the project have been determined to be significant under CEQA and cannot be fully mitigated.

Biological Resources
Activities in Pismo Creek would be limited to the dry season, and the creek would be returned to natural contours after construction. Tree removal would avoid impacts to nesting birds. Other work windows would be applied to minimize impacts to sensitive species. Pre-construction surveys would be conducted for aquatic species; if individuals were found, they would be relocated. Applicable measures of the California red-legged frog program- matic biological opinion would be adhered to; these measures would also protect other aquatic species. The measures include a training session for construction personnel, biological monitoring, modifications to equipment to prevent harm to protected aquatic species, removal of exotic aquatic species, and revegetation of the project areas with an assemblage of native riparian, wetland, and upland vegetation suitable for the area.

Attachment 3
Council Agenda 12-5-2023 12.A-212
Packet Page 463

Pismo Congestion Relief Pilot Project Ÿ 189
Appendix D Revisions Since Public
Circulation
The following changes have been made to the document since the draft environmental document was circulated to the public; the public circulation and comment period ran from October 2, 2020 to November 17, 2020.

Cover—The document title was changed to Final Environmental Impact Report/Environmental Assessment with Finding of No Significant Impact and the date changed to the document signing month. The inside cover information was updated to include the public circulation period and access information for the document. The Memorandum of Understanding date was updated to the date of the latest Memorandum of Understanding date of May 27, 2022.

Page iii—The document title was changed to Final Environmental Impact Report/Environmental Assessment with Finding of No Significant Impact, and the State Clearinghouse number was added. Contact information was added.

Page iv—The Finding of No Significant Impact (FONSI) was added.

Page v—The header called NEPA Assignment was added. The Memorandum of Understanding date was updated to the date of the latest Memorandum of Understanding date of May 27, 2022. The 10-year term of the new Memorandum of Understanding was added.

Summary—Under Visual/Aesthetics, reference to shorter length with less median barrier for Alternative 2 was removed. Under Air Quality, Alternative 1 and No-Build were changed to note an increase in carbon dioxide emissions rather than a decrease. Under Natural Communities, notation of temporary impacts to arroyo willow habitat that had been left out of the draft document was included. Under Wetlands and Other Waters, temporary impacts to other waters were corrected and increased to 8,300 square feet for Alternative 1.

Under Threatened and Endangered Species, information was changed from protective measures taken to impacts incurred.

1.1 Introduction—A sentence was added stating that Caltrans is the lead agency for CEQA and NEPA and the Council of Governments is a funding partner.

1.3 Project Description—The park-and-ride location was corrected to Mattie Road and Price Street.

1.4.1 Build Alternatives—The height of the lane-use control signals was added. The park-and-ride location was corrected to Mattie Road and Price Street, and a description of the lot plans was added. Figure 1-4 Location of Attachment 3
Council Agenda 12-5-2023 12.A-213
Packet Page 464

Pismo Congestion Relief Pilot Project Ÿ 190
Park-and-Ride Lot was added. Also added was a description of the California Highway Patrol observational areas.

1.6 Identification of a Preferred Alternative—This heading and section content were added.

1.8 Permits and Approvals Needed—The status of consultations with the U.S. Fish and Wildlife Service and the National Marine Fisheries Service was updated to “complete.” Consultation with the State Historic Preservation Officer and the Programmatic Agreement and Historic Properties Treatment Plan were added as “complete.”
Chapter 2, Environmental Justice—Language was updated to provide more information to support the determination.

Chapter 2, Air Quality—Information was corrected to identify the County’s non-attainment status for ozone and small particulate matter; information was added to describe the project’s consistency with state air quality plans; a statement on air quality conformity was added.

2.1.1 Coastal Zone, Affected Environment—Policy D-28 on visual quality was added to the list for City of Pismo Beach Local Coastal Program.

2.1.1 Coastal Zone, Environmental Consequences—Under Visual and Scenic Resources, a statement was added noting the corridor as a scenic highway by the City of Pismo Beach.

2.1.2 Visual/Aesthetics, Affected Environment—Under the Soundwalls header, a sentence was added to state that soundwalls 2 and 3 were dropped from the project. To further clarify this, the words “if constructed” were added before the description of soundwalls 2 and 3, and a statement was added to specify that they would have been located on the southbound side of US 101.

2.1.2 Visual/Aesthetics, Environmental Consequences—Information was added on the height of the signal poles, and the number required for Alternative 2 was increased. Also, under Soundwalls, information was updated to note the current disposition of the proposed soundwalls.

2.1.3 Cultural Resources, Affected Environment—Information on CA-SLO- 80/H was corrected to indicate that the site had not previously been found eligible for the National Register and that Caltrans received concurrence on its eligibility during project consultation with the State Historic Preservation Officer. The name of cultural site CA-SLO-2885 was added now that it is known.

2.1.3 Cultural Resources, Environmental Consequences—Text was updated to state that a soundwall has been removed from the project and therefore no longer poses a risk of impacts. A statement was added stating that due to the Attachment 3
Council Agenda 12-5-2023 12.A-214
Packet Page 465

Pismo Congestion Relief Pilot Project Ÿ 191
confidentiality of the cultural site locations, the specific soundwall location is not disclosed. A finding of effect statement was added. The name of cultural site CA-SLO-2885 was added now that it is known.

2.1.3 Cultural Resources, Avoidance, Minimization, and/or Mitigation Measures—The section was updated to include a more detailed and comprehensive description of the measures to be incorporated into the project. The begin date for the annual cultural update was updated to December 31, 2022, rather than December 31, 2021. This update was needed to reflect the later-than-anticipated finalization of the Programmatic Agreement.

2.2.1 Hydrology and Floodplain, Environmental Consequences—Figure 2- 16 Flood Hazard Map was added, as well as a statement that the project would not result in a significant floodplain encroachment.

2.2.3 Noise, Environmental Consequences—A statement was added under the secondary impacts header to specify that soundwalls 2 and 3 were dropped from the project, but soundwall 6 would be further considered in the project design phase.

2.2.3 Noise, Avoidance, Minimization, and/or Abatement Measures—A statement was added that the project currently will not include noise abatement and that a final decision on noise abatement will be made upon completion of project design.

2.3.2 Wetlands and Other Waters, Environmental Consequences—Figure 2- 19 Impacts to Other Waters was added. The incorrect reference to additional 4,600 square feet of temporary impacts to other waters was removed.

2.3.4 Threatened and Endangered Species, Environmental Consequen- ces—Temporary and permanent impacts to steelhead critical habitat were corrected (reduced). Under California Red-legged Frog, Steelhead, and Tidewater Goby, the Section 7 effects determination information was updated.

Also, a statement was added that a “no effects” finding was made on all other listed species and critical habitat.

2.4 Construction Impacts—Information about occurrence of single lane closures was added. Information about subsurface investigations was also added. This information includes an overview of the subsurface investigation work, environmental consequences information, and avoidance, minimization, and/or mitigation measure information.

3.2.3 Air Quality, question B—The information was corrected to note that the county is within a non-attainment area for ozone and small particulate matter.

The impact determination was changed to “less than significant impact.” Attachment 3
Council Agenda 12-5-2023 12.A-215
Packet Page 466

Pismo Congestion Relief Pilot Project Ÿ 192

3.2.3 Air Quality, question C—Information was added related to equipment exhaust.

3.2.9 Hazards and Hazardous Materials—Information was updated to include results of testing for lead and asbestos.

3.3.3 Climate Change - Project Analysis—The quantities in Table 3-2 were revised based on updates to the Traffic Operations Analysis Report in 2021, and the quantities in the CEQA Conclusion were updated. These updates do not change the conclusion of the greenhouse gas analysis.

4.1.1 Early Coordination—Information within Chapter 4 of the draft environmental document was reorganized under this new heading, and information on the March 2020 public outreach effort was added. Information related to coordination efforts with the Tribe was reorganized under the subheading Tribal Coordination, and updates were added.

4.1.2 Comments on the Draft Document—This section was added; it contains public comments on the draft environmental document and Caltrans’ responses.

4.1.3 Public Hearing Discussion—This section was added; it contains information on the public hearing, including public comments and Caltrans’ responses.

4.1.4 Soundwalls—This section was added; it contains additional information pertaining to soundwall evaluation.

Appendix A—A statement was added that the project does not affect any type of Section 4(f) facility. Under Archaeological Resources, the information was corrected to include CA-SLO-80/H as one of the sites evaluated during project review. The name of cultural site CA-SLO-2885 was added now that it is known.

Appendix D—This appendix was added; it contains a summary of substantive changes that were made to the document since circulation of the draft environmental document to the public.

List of Technical Studies—The Preliminary Extended Phase I and Archaeological Evaluation Report was added to the list of studies not available to the public due to confidential information.

Attachment 3
Council Agenda 12-5-2023 12.A-216
Packet Page 467

Pismo Congestion Relief Pilot Project Ÿ 193
List of Technical Studies
The following technical reports were prepared for the project and contain detailed information that was summarized in this document. These reports are contained in Volume 2.

Air Quality Report
Natural Environment Study
Hazardous Waste Initial Site Assessment
Paleontology Study
Location Hydraulic Study
Noise Abatement Decision Report
Noise Study Report
Visual Impact Assessment
Traffic Operations Analysis Report
Water Quality Report
The following approvals and reports were obtained for the project. These reports are contained in Volume 2.

State Historic Preservation Officer Programmatic Agreement U.S. Fish and Wildlife Service Species List
National Marine Fisheries Species List
The following documents are available separately, upon request:

U.S. Fish and Wildlife Service Biological Opinion
National Marine Fisheries Service Biological Opinion
To obtain a copy of one or more of these reports or a printed copy of the Final Environmental Impact Report/Environmental Assessment with Finding of No Significant Impact, please send your request using the contact information listed on the inside cover of this document. Please indicate the project name and project identifying code (under the project name on the cover of this document) and specify the technical report or document you would like.

Provide your name and email address or U.S. postal service mailing address (street address, city, state, and zip code).

Attachment 3
Council Agenda 12-5-2023 12.A-217
Packet Page 468

Pismo Congestion Relief Pilot Project Ÿ 194
The following reports were also prepared for the project to document cultural resources. These documents are confidential and not available to the public.

Historical Property Survey Report
·Historic Resource Evaluation Report
·Historic Architectural Survey Report
·Archaeological Survey Report
·Preliminary Extended Phase I and Archaeological Evaluation Report Attachment 3
Council Agenda 12-5-2023 12.A-218
Packet Page 469

PISMO BEACH COUNCIL AGENDA REPORT
Agenda Item #12.B
SUBJECT/TITLE:

BUDGET ADJUSTMENTS FOR FISCAL YEARS 2024 AND 2025
RECOMMENDATION:

Adopt a Resolution approving and appropriating budget adjustments for Fiscal Years 2024 and 2025.

EXECUTIVE SUMMARY:

The City of Pismo Beach operates on a two-year budget cycle, which allows for long-term planning, coordination of multi-year capital projects, and efficiency of staff time as budget preparation only occurs every other year. To maintain accuracy of the budget and update the City’s financial plan, it is important to review and revise it periodically (i.e., every six months) to ensure the budget reflects current revenues received and operating costs and trends. The purpose of this agenda item is to provide an opportunity for the City Council to review, approve, and/or make changes to staff’s recommended mid-year budget adjustments for Fiscal Years (FY) 2024 and 2025, via adoption of a Resolution provided as Attachment 1.

The FY 2024 and FY 2025 proposed mid-year budget adjustments reflect: the 2012 Wastewater Enterprise Fund bond redemption, revenue adjustments, technical corrections, operating costs, workforce development, Information Technology (IT) allocations, a funding source change, and project savings. The net fiscal impact of approving all these changes across all funds is a net additional cost of $3,058,737.16 in FY 2024 and net cost savings of $273,279.50 in FY 2025. Table 1 below illustrates the net fiscal impact for each category and fiscal year, where negative amounts reflect additional costs or reduced revenues, and positive amounts reflect reduced costs or additional revenues.

Table 1: Proposed Mid-Cycle Budget Adjustments Fiscal Impact by Category Category
FY 2024 Proposed
Budget Adjustment
Fiscal Impact
FY 2025 Proposed
Budget Adjustment
Fiscal Impact
2012 Wastewater Bond Redemption (2,926,660.01)$ 393,637.50$ Technical correction (1,006,392.00) (6,392.00) Revenue (892,728.00) -
Operating costs (190,721.98) (106,466.00)
Workforce Development (29,000.00) (7,500.00)
Funding Source changes - -
IT Allocation - -
Project Savings 1,986,764.83 -
Total Fiscal Impact (3,058,737.16)$ 273,279.50$ Council Agenda 12-5-2023 12.B-1
Packet Page 470

2012 Wastewater Bond Redemption
The following proposed budget adjustments reflect the budget transactions necessary to reflect the Series 2012 Wastewater refunding revenue bond redemption. On October 17, 2023, the City Council adopted Resolution R-2023-078 to redeem these bonds effective November 1, 2023. This transaction includes paying off $3,320,000 of the outstanding principal balance plus debt service interest costs. The net fiscal impact of the 2021 Wastewater bond redemption proposed budget adjustment is a net additional cost of $2,926,660 in FY 2024 and ongoing savings of $393,638 in FY 2025 compared to budget.

Table 2 below illustrates the net fiscal impact of the proposed budget adjustments by fund.

Table 2: Proposed Budget Adjustments for 2012 Wastewater Bond Redemption Description Fund
One-time/
Ongoing
FY 2024
Proposed
Budget
Adjustment
FY 2025
Proposed
Budget
Adjustment
Revenues
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Interest
Public Financing Authority
Debt Service
one-time (60,732)$ (94,738)$
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Interest
Wastewater Treatment Fund one-time 267 (295,000)
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Principal
Public Financing Authority
Debt Service
one-time 3,040,000 (295,000)
Subtotal Revenues 2,979,535$ (684,738)$
Expenditures
2012 Wastewater Refunding Revenue bonds -
redeemed
Public Financing Authority
Debt Service
one-time 3,320,000$ -$
2012 Wastewater Refunding Revenue bonds -
redeemed, Urban Futures Continuing
Disclosure for 2012 Wastewater Refunding
Bonds
Wastewater Treatment Fund ongoing (1,900) (1,900)
2012 Wastewater Refunding Revenue bonds -
redeemed, US Bank Bond Trustee for 2012
WW Bonds
Wastewater Treatment Fund ongoing (2,000) (2,000)
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Interest
Public Financing Authority
Debt Service
ongoing (109,113) (94,738)
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Interest
Wastewater Treatment Fund ongoing (60,792) (94,738)
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Principal
Public Financing Authority
Debt Service
ongoing (280,000) (295,000)
2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Principal
Wastewater Treatment Fund one-time 3,320,000 (295,000) 2012 Wastewater Refunding Revenue bonds -
redeemed, WWTP Bonds Principal
Wastewater Treatment Fund ongoing (280,000) (295,000) Subtotal Expenditures 5,906,195$ (1,078,375)$
Net Fiscal Impact (Revenues - Expenditures)(2,926,660)$ 393,638$ Council Agenda 12-5-2023 12.B-2
Packet Page 471

Technical Corrections
The following proposed budget adjustments include technical corrections in FY 2024 and FY 2025. The most significant item is a one-time move of the $1,000,000 Housing in Lieu Fee Fund budget for the 2655 Shell Beach Road affordable housing project from FY 2023 to FY 2024. The other adjustments reflect reallocating the internet portion of the phone budget to the internet account and revising the internet budget to account for updated costs. The net fiscal impact across all funds is an additional cost of $1,006,392 in FY 2024 and $6,392 FY 2024. Table 3 below illustrates the net fiscal impact of the proposed changes by fund.

Table 3: Proposed Budget Adjustments for Technical Corrections

Revenue Adjustments
The following proposed one-time budget adjustments reflect updating revenue budgets based on updated projections in FY 2024 transient occupancy tax (TOT), Lodging Business Improvement District (LBID) assessment revenues, Local Transportation Fund revenues, and legal settlement revenues. The net fiscal impact across all funds for these revenue adjustments is a net reduction of revenues compared to budget by $892,728 in FY 2024. Table 4 below illustrates the net fiscal impact of the proposed budget adjustments by fund, followed by a brief description of the major changes.

Fund Description
One-time/
Ongoing
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
Expenditures
General Fund Move phone budget to internet and reflect
increased internet charges
ongoing 3,042$ 3,042$
Housing In Lieu Fee Was moved from FY 2023 as an expense to FY 2024 after CIP carryforwards were done, so
budget was not carried forward.
one-time 1,000,000$ -$
Water Enterprise Fund Move phone budget to internet and reflect increased internet charges
ongoing 530$ 530$
Wastewater Treatment
Fund
Move phone budget to internet and reflect
increased internet charges
ongoing 2,120$ 2,120$
Parking Enterprise Fund Move phone budget to internet and reflect increased internet charges
ongoing 250$ 250$
Technology Service Fund Move phone budget to internet and reflect increased internet charges
ongoing 450$ 450$
Subtotal Expenditures 1,006,392$ 6,392$
Net Fiscal Impact (Revenues - Expenditures)(1,006,392)$ (6,392)$ Council Agenda 12-5-2023 12.B-3
Packet Page 472

Table 4: Proposed Budget Adjustments for Revenue Adjustments Projected TOT revenue adjustment: Anticipating a decrease in Transient Occupancy Tax (TOT) revenues based on the FY 2024 First Quarter Financial Status Report, staff projects a $790,000 shortfall in comparison to the budget. This reduction is attributed to lower room rates, decreased occupancy, and an expected rainy winter. To address this, staff recommends Council de-appropriate $790,000 from the TOT revenue budget in the General Fund.
LBID Assessment revenue adjustment: The Lodging Business Improvement District (LBID) Fund’s assessment revenues, mirroring the trends in TOT revenues, account for 1% of gross room rental revenues. In light of this correlation, staff recommends that the City Council de-appropriate $269,000 of LBID Assessment revenues in FY 2024 in the LBID Fund.
LBID Assessment Revenues for Physical Improvements: LBID Fund assessment revenues for physical improvements represents another 1% assessment on gross room rental revenues to support various visitor-serving improvements, following the same trend as TOT revenues. As such, staff recommends that the Council de- appropriate $269,000 of LBID assessment revenues for physical improvements in FY 2024.
Legal settlement revenues: Legal settlement revenues are non-recurring funds tied to the resolution of legal matters. In FY 2024, two recent settlements have been reached, with $400,000 attributed to the Pismo Beach Self-Storage matter and $175,000 related to the Shell Beach Streetscape project. To accurately account for these settlements, staff recommends appropriating $575,000 in revenues within the General Fund.
Local Transportation Fund revenues: In light of revised projections from the San Luis Obispo Council of Governments (SLOCOG), the City is anticipated to receive an Fund Title Description
FY 2024 Proposed
Budget Adjustment
General Fund Reduce TOT based on updated projections (790,000)$ General Fund Legal settlement revenues 400,000$
Local Transportation Reduce Local Transportation Fund (LTF) budget based on SLOCOG's LTF annual apportionment
(89,728)$
LBID Fund Reduce projected COPS grant revenues based
on prior year revenues
(50,000)$
LBID Fund Reduce LBID Assessment based on updated
projections
(269,000)$
LBID Fund Reduce LBID Assessment for physical
improvements based on updated projections
(269,000)$
Capital Projects Settlement for Shell Beach Streetscape project 175,000$ Subtotal Revenues (892,728)$
Net Fiscal Impact (Revenues - Expenditures)(892,728)$
Council Agenda 12-5-2023 12.B-4
Packet Page 473

annual apportionment for the Local Transportation Fund (LTF) that is $89,728 less than the initially budgeted amount for FY 2024. In response to this one-time reduction, staff recommends that the Council modifies the FY 2024 LTF budget by reducing it by $89,728 to accurately reflect the updated revenue estimate.

Operating Costs
The subsequent proposed budget adjustments reflect various projected additional operating costs in FY 2024 and FY 2025. The net fiscal impact across all funds is a net additional cost of $192,722 in FY 2024 and $109,466 in FY 2025. Table 5 below illustrates the net fiscal impact of the proposed changes by fund, followed by a brief description of the major components of this category.

Table 5: Proposed Budget Adjustments for Operating Costs Fund Department Description
One-time/
Ongoing
FY 2024
Proposed
Budget
Adjustment
FY 2025
Proposed
Budget
Adjustment
Revenues
General Fund Public Works Adopt-a-Bench program revenues one-time 15,000$ -$ Motor Vehicle Fund Public Works Vehicle maintenance costs ongoing 2,000 3,000 Subtotal Revenues 15,000$ -$
Expenditures
General Fund Administrative Services Vehicle maintenance costs ongoing 1,000$ 1,500$ General Fund Fire Batteries for Fire's lower emission equipment ongoing 2,700 2,700 General Fund Management Services IGOE Monthly Administration fee for Flex benefit payments
ongoing 1,920 2,016
General Fund Management Services Staff furniture one-time 6,500 - General Fund Police Watchguard Police Body Camera cloud storage one-time 6,000 - General Fund Police 0 ongoing - 4,000
General Fund Public Works Electrical repairs Addie Parking Lot one-time 5,000 - General Fund Public Works Increase in boot budget and cost of safety equipment
ongoing 3,000 3,000
General Fund Public Works Increase in event restroom rentals one-time - 3,000 General Fund Public Works Paint interior of Bello Vets Hall one-time 10,000 - General Fund Public Works Purchase gas powered equipment: weed eaters, blowers, etc. for Parks
one-time 12,000 -
General Fund Public Works Station 63 Project - landscaping one-time 4,000 - General Fund Public Works Tree trimming emergency services city-wide ongoing 25,000 10,000 General Fund Public Works Adopt-a-Bench program - purchase 5 benches one-time 15,000 - Water Enterprise Fund Public Works Codification change to reflect updated Sewer Use Ordinance
one-time 1,000 -
Water Enterprise Fund Public Works Wastewater Treatment Plant Supplies & Maintenance additional costs
ongoing 15,000 20,000
Water Enterprise Fund Public Works Water and wastewater rate study, consultant and prop 218 mailings
one-time 4,187 -
Wastewater Treatment
Fund
Public Works Replace air vacs and saddles that have had critical failures resulting in sewage spills
one-time 30,000 30,000
Pier Enterprise Fund Public Works Electrical repairs on Pier one-time 5,000 - Pier Enterprise Fund Public Works Replacement bollards at Pier parking lot one-time 9,500 - Parking Enterprise Fund Police Vehicle maintenance costs ongoing 1,000 1,500 Technology Service Fund Administrative Services Add Zoom Web Conference Subscription for Council and Advisory Board meetings
one-time 6,048 6,350
Technology Service Fund Administrative Services Encryption of Police radio channel and reprogramming of all Police radios with the
encrypted channels of other agencies in the County
one-time 28,800 -
Technology Service Fund Administrative Services Static IP address registered to the City for Police Licenes Plate Reader (LPR) system
ongoing 1,400 2,400
Technology Service Fund Administrative Services Watchguard Police Body Camera cloud storage ongoing 11,667 20,000 Motor Vehicle Fund Public Works Add IT vehicle budget, reduce Building vehicle budget
one-time - -
Motor Vehicle Fund Public Works Vehicle maintenance costs ongoing 2,000 3,000 Subtotal Expenditures 207,722$ 109,466$
Net Fiscal Impact (Revenues - Expenditures)(192,722)$ (109,466)$ Council Agenda 12-5-2023 12.B-5
Packet Page 474

Wastewater air vacs and saddles replacement: Allocate $30,000 in both FY 2024 and FY 2025 from the Wastewater Enterprise Fund to address critical failures in air vacs and saddles due to pipe metal degradation. This one-time investment aims to prevent potential sewage spills by fully replacing air vacs and saddles across the entire line that were installed simultaneously.
Police Radio Encryption Upgrade: Invest $28,800 in FY 2024 to encrypt the Police radio channel and reprogram all Police radios as part of a mandatory upgrade project with the County. This initiative includes acquiring Police encryption licenses and keys, reprogramming existing radios, implementing encryption for parking staff's new radios, and providing new radios with encryption for Public Works field staff and the City Clerk, who serves as the City's Emergency Operations Center representative. City-Wide Tree Trimming Services: Add $25,000 in FY 2024 and $10,000 in FY 2025 for tree trimming services City-wide.
Police Watchguard Body Camera Cloud Storage Solution: Invest $17,667 in FY 2024 and $24,000 in FY 2025 for the Police Watchguard Body camera cloud storage solution. This includes a one-time $6,000 cost to implement the cloud storage solution, $10,500 in FY 2024 and $18,000 for a full year in FY 2025 of ongoing internet increased internet bandwidth costs, and $1,167 in FY 2024 and $6,000 in FY 2025 for ongoing license and support fees.
Adopt-a-Bench Program: Add $15,000 for Adopt-a-Bench program expenditures and corresponding revenues to purchase new and replacement benches. Parks Equipment: Add $12,000 in FY 2024 for the purchase of gas-powered equipment weed eaters, blowers, and other equipment for the City’s Parks activity. Veterans Hall Interior Painting: Add $10,000 in FY 2024 to paint the interior of the Pismo Beach Bello Street Veterans Hall to address damage on the interior of the building.
Pier Plaza Parking Lot Bollard Replacement: Add $9,500 in FY 2024 to replace the bollards in the Pier Plaza parking lot, ensuring safety and functionality.

Workforce Development
The following proposed budget adjustments include workforce development costs in FY 2024 and FY 2025, including a net additional cost of $29,000 in FY 2024 and $7,500 in FY 2025. Table 6 below illustrates the net fiscal impact of the proposed changes by fund, followed by a brief description of the proposed adjustments.

Council Agenda 12-5-2023 12.B-6
Packet Page 475

Table 6: Proposed Budget Adjustments for Workforce Development Public Works Facilities Division Workforce Development: Incorporate an additional $4,000 in FY 2024 and $2,500 in FY 2025 into the General Fund budget for mandatory Class B license training, Facilities Manager training, and attendance at a management conference, enhancing the skill set and knowledge base of the Public Works Facilities team.
Public Works safety boot allowance: Allocate an extra $5,000 in both FY 2024 and FY 2025 within the budget to cover the safety boot allowance for Public Works staff. This adjustment accounts for updated costs associated with boots and related materials, ensuring that employees have the necessary safety gear. City-wide Software training: Increase the Technology Services Fund by $20,000 beyond the existing training budget to facilitate professional, citywide software training for all departments. Given technological advancements and staff turnover, it is imperative to periodically train employees on the latest software programs, including Microsoft Office 365, Adobe Acrobat, and Laserfiche, which are integral to the efficient functioning of most City operations.

IT Cost Allocation
The subsequent proposed budget adjustments reflect allocating costs budgeted in the Technology Services Fund to all the other City funds. For any proposed budget adjustments that impact the Technology Services Fund, these costs are allocated to other funds based on the type of expenditure. The fiscal impact across all funds is $0, and the impact to each fund is illustrated in Table 7.

Fund Description
One-time/
Ongoing
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
Expenditures
General Fund Class B License Training one-time 3,500$ -$ General Fund Facilities Manager Travel/Training ongoing 500$ 1,000$ General Fund Increased boot budget safety equipment one-time 5,000$ 5,000$ General Fund Training, MMASC Conference ongoing -$ 1,500$ Technology Service Fund Citywide Software training - Office 365, Adobe Acrobat, Laserfiche.
one-time 20,000$ -$
Subtotal Expenditures 29,000$ 7,500$
Net Fiscal Impact (Revenues - Expenditures)(29,000)$ (7,500)$ Council Agenda 12-5-2023 12.B-7
Packet Page 476

Table 7: Proposed Budget Adjustments for Carryforward Vehicle Budgets Funding Source Change
The following proposed budget adjustments reflect shifting $18,536 of General Fund support of the Paving project to the Gas Tax Fund. This modification aligns with the projection of additional funds available in the Gas Tax Fund, specifically the Senate Bill 1 Road Maintenance and Rehabilitation Account, earmarked for road maintenance and rehabilitation. These adjustments result in a corresponding increase of $18,536 in the Gas Tax Fund expenditure budget and a parallel reduction in the General Fund expenditure budget, inclusive of related transfers between funds, for FY 2024, as detailed in Table 8.

Table 8: Proposed Budget Adjustments for Funding Source Change Fund
One-time/
Ongoing
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
Revenues
Technology Service Fund ongoing 68,365$ 29,200$
Subtotal Revenues 68,365$ 29,200$
Expenditures
General Fund ongoing 53,865$ 28,190$
Lodging Business Improvement ongoing - -
Chapman Estate Fund ongoing - -
Water Enterprise Fund ongoing 5,987 21
Wastewater Treatment Fund ongoing 5,845 21
Parking Enterprise Fund ongoing 2,523 965
Technology Service Fund ongoing - -
Motor Vehicle Fund ongoing 145 3
Subtotal Expenditures 68,365$ 29,200$
Net Fiscal Impact (Revenues - Expenditures)-$ -$
Fund
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
Revenues
Capital Projects -$ -$
Subtotal Revenues -$ -$
Expenditures
General Fund (18,536)$ -$
Gas Tax Fund 18,536 -
Subtotal Expenditures -$ -$
Net Fiscal Impact (Revenues - Expenditures)-$ -$
Council Agenda 12-5-2023 12.B-8
Packet Page 477

Project Savings
The following proposed budget adjustments reflect various one-time project adjustments to existing projects to reflect cost savings from completing and deferring projects. The largest project de-appropriations are in the Parking Enterprise Fund, including $1,198,916.28 from the Parking Garage/Parking Inventory project and $750,000 from the Parking property paving project. Staff recommends de-appropriating these costs as these projects are delayed due to the use of $4.00 million from the Parking Enterprise Fund to support the Public Safety Facility. Table 9 below illustrates the net fiscal impact of the proposed changes by fund.

Table 9: Proposed Budget Adjustments for Project Savings Conclusion and Recommendation
Staff recommends that the City Council adopt a Resolution (Attachment 1) approving and appropriating budget adjustments for FY 2024 and FY 2025.

FISCAL IMPACT:

The net fiscal impact of approving the attached Resolution (Attachments 1) across all funds is net additional costs of $3,058,737.16 in FY 2024 and net cost savings of $273,279.50 in FY 2025. All funds have sufficient fund balances to support the one-time costs and net operating surpluses sufficient to support the ongoing costs. Table 10 below illustrates the proposed revenue and expenditure budget adjustments by fund and fiscal year.

Fund Project Description
FY 2024 Proposed
Budget Adjustment
Revenues
Technology Service Fund Microsoft Office 365 De-appropriate, project completed $ (5,802.73) Subtotal Revenues (5,802.73)$
Expenditures
General Fund Economic Impact Study De-appropriate, project completed $ (26,960.82) General Fund Microsoft Office 365 De-appropriate, project completed (5,802.73) Parking Enterprise Fund Parking Garage De-appropriate remaining parking land purchase budget
(1,198,916.28)
Parking Enterprise Fund Parking Mgmt Study De-appropriate - parking management plan completed
(5,085.00)
Parking Enterprise Fund Parking property paving De-appropriate - parking property paving (750,000.00) Technology Service Fund Microsoft Office 365 De-appropriate, project completed (5,802.73) Subtotal Expenditures (1,992,567.56)$
Net Fiscal Impact (Revenues - Expenditures)1,986,764.83$ Council Agenda 12-5-2023 12.B-9
Packet Page 478

Table 10: Proposed Mid-Cycle Budget Adjustments

ALTERNATIVES:

1. Approve some of the proposed mid-cycle budget adjustments.

2. Do not approve the proposed mid-cycle budget adjustments; provide alternative direction to staff.

Fund Title Type
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
General Fund Rev (200,000.00)
General Fund Exp 106,872.45 64,951.00
Subtotal General Fund Net (306,872.45) (64,951.00) Gas Tax Fund Exp 18,536.00
Subtotal Gas Tax Fund Net (18,536.00) -
Local Transportation Rev (89,728.00)
Subtotal Local Transportation Net (89,728.00)
Grants - Non-Capital Rev (50,000.00)
Subtotal Grants - Non-Capital Net (50,000.00)
Housing In Lieu Fee Exp 1,000,000.00
Subtotal Housing In Lieu Fee Net (1,000,000.00) - LBID Fund Rev (538,000.00)
LBID Fund Exp - -
Subtotal LBID Fund Net (538,000.00) -
Chapman Estate Fund Exp - -
Subtotal Chapman Estate Fund Net - - Capital Projects Rev -
Subtotal Capital Projects Net -
Public Financing Authority Debt Service Rev 2,979,267.72 (389,737.50) Public Financing Authority Debt Service Exp 2,930,887.50 (389,737.50) Subtotal Public Financing Authority Debt Service Net 48,380.22 - Water Enterprise Fund Exp 26,703.98 20,551.00 Water Enterprise Fund Total Net (26,703.98) (20,551.00) Wastewater Treatment Fund Rev 267.49 (295,000.00) Wastewater Treatment Fund Exp 3,013,272.72 (656,496.50) Subtotal Wastewater Treatment Fund Net (3,013,005.23) 361,496.50 Pier Enterprise Fund Exp 14,500.00
Subtotal Pier Enterprise Fund Net (14,500.00) - Parking Enterprise Fund Exp (1,950,228.28) 2,715.00 Subtotal Parking Enterprise Fund Net 1,950,228.28 (2,715.00) Technology Service Fund Rev 62,562.27 29,200.00 Technology Service Fund Exp 62,562.27 29,200.00 Subtotal Technology Service Fund Net 0.00 - Motor Vehicle Fund Rev 2,000.00 3,000.00 Motor Vehicle Fund Exp 2,000.00 3,000.00 Subtotal Motor Vehicle Fund Net - - T otal All Funds (3,058,737.16)$ 273,279.50$
Council Agenda 12-5-2023 12.B-10
Packet Page 479

ATTACHMENTS:

1. Resolution for Mid-Year Budget Adjustments

1.A. Exhibit A to Resolution: Summary of Budget Adjustments by Fund and Fiscal Year for FY 2024 and FY 2025
Submitted by: Meeting Date: December 5, 2023
Nadia Feeser, Administrative Services Director
City Manager Approval:

Council Agenda 12-5-2023 12.B-11
Packet Page 480

RESOLUTION NO. R-2023-XXX

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH,

CALIFORNIA APPROVING AND APPROPRIATING BUDGET ADJUSTMENTS FOR FISCAL YEARS 2024 AND 2025
WHEREAS, the City of Pismo Beach operates on a two-year budget cycle, which allows for long-term planning, coordination of multi-year capital projects, and efficiency of staff time as budget preparation only occurs every other year; and WHEREAS, in order to maintain accuracy of the budget and update the City’s financial plan, it is important to review and revise it periodically to ensure the budget reflects current revenues received and operating costs and trends; and
WHEREAS, City staff proposes mid-year budget adjustments to reflect updated projections and estimates to the FY 2024 and FY 2025 budgets; and WHEREAS, the FY 2024 and FY 2025 proposed budget adjustments reflect the 2012 Wastewater Enterprise Fund bond redemption, revenue adjustments, technical corrections, operating costs, workforce development, and Information Technology (IT) allocations, funding source changes, and project savings; and WHEREAS, the net fiscal impact of the mid-year budget adjustments across all funds is net additional costs of $3,058,737.16 in FY 2024 and a net cost savings of $273,279.50 in FY 2025.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby appropriates changes in revenues and expenditures for FY 2024 and FY 2025 as summarized in the table below, and detailed in attached Exhibit A, which by this reference are made a part hereof. This table and attached exhibit include net additional costs of $3,058,737.16 in FY 2024 and net cost savings of $273,279.50 in FY 2025 across all funds, to reflect the Council-approved budget adjustments.

Fund Title Type
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
General Fund Rev (200,000.00)
General Fund Exp 106,872.45 64,951.00
Subtotal General Fund Net (306,872.45) (64,951.00)
Gas Tax Fund Exp 18,536.00
Subtotal Gas Tax Fund Net (18,536.00) -
Local Transportation Rev (89,728.00)
Subtotal Local Transportation Net (89,728.00)
Grants - Non-Capital Rev (50,000.00)
Subtotal Grants - Non-Capital Net (50,000.00)
Attachment 1
Council Agenda 12-5-2023 12.B-12
Packet Page 481

BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby appropriates any transfers or allocations between funds necessary to implement these Council-approved adjustments for FY 2024 and FY 2025.

UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 5th day of December 2023, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

RECUSED:

Fund Title Type
FY 2024 Proposed
Budget Adjustment
FY 2025 Proposed
Budget Adjustment
Housing In Lieu Fee Exp 1,000,000.00
Subtotal Housing In Lieu Fee Net (1,000,000.00) -
LBID Fund Rev (538,000.00)
LBID Fund Exp - -
Subtotal LBID Fund Net (538,000.00) -
Chapman Estate Fund Exp - -
Subtotal Chapman Estate Fund Net - -
Capital Projects Rev -
Subtotal Capital Projects Net -
Public Financing Authority Debt Service Rev 2,979,267.72 (389,737.50) Public Financing Authority Debt Service Exp 2,930,887.50 (389,737.50) Subtotal Public Financing Authority Debt Service Net 48,380.22 - Water Enterprise Fund Exp 26,703.98 20,551.00
Water Enterprise Fund Total Net (26,703.98) (20,551.00) Wastewater Treatment Fund Rev 267.49 (295,000.00) Wastewater Treatment Fund Exp 3,013,272.72 (656,496.50) Subtotal Wastewater Treatment Fund Net (3,013,005.23) 361,496.50 Pier Enterprise Fund Exp 14,500.00
Subtotal Pier Enterprise Fund Net (14,500.00) -
Parking Enterprise Fund Exp (1,950,228.28) 2,715.00
Subtotal Parking Enterprise Fund Net 1,950,228.28 (2,715.00) Technology Service Fund Rev 62,562.27 29,200.00
Technology Service Fund Exp 62,562.27 29,200.00
Subtotal Technology Service Fund Net 0.00 -
Motor Vehicle Fund Rev 2,000.00 3,000.00
Motor Vehicle Fund Exp 2,000.00 3,000.00
Subtotal Motor Vehicle Fund Net - -
Total All Funds (3,058,737.16)$ 273,279.50$
Attachment 1
Council Agenda 12-5-2023 12.B-13
Packet Page 482

Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk
Attachment 1
Council Agenda 12-5-2023 12.B-14
Packet Page 483

Mid-Year Budget Adjustments December 5, 2023
Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed
4001 Public
Financing
Authority Debt
Service
Debt Service 57009 Oth Fin Use-Early
Redem
No Project one-time 3,320,000.00
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
Urban Futures
Continuing
Disclosure for
2012
Wastewater
Refunding
Bonds
6201 Wastewater
Treatment
Fund
Debt Service 52101 Professional
Services
No Project ongoing
(1,900.00) (1,900.00)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed, US
Bank Bond
Trustee for
2012 WW
Bonds
6201 Wastewater
Treatment
Fund
Debt Service 52103 Bond Trustee No Project ongoing
(2,000.00) (2,000.00)
Attachment 1.A
Council Agenda 12-5-2023 12.B-15
Packet Page 484

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Interest
4001 Public
Financing
Authority Debt
Service
Debt Service 44003 Loan Interest No Project one-time
(60,732.28) (94,737.50)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Interest
4001 Public
Financing
Authority Debt
Service
Debt Service 57002 Interest No Project ongoing
(109,112.50) (94,737.50)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Interest
6201 Wastewater
Treatment
Fund
General
Government
44001 Interest No Project one-time
267.49 (295,000.00)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Interest
6201 Wastewater
Treatment
Fund
Debt Service 57002 Interest No Project ongoing
(60,792.28) (94,737.50)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Principal
4001 Public
Financing
Authority Debt
Service
Debt Service 44119 Loan Proceeds No Project one-time
3,040,000.00 (295,000.00)
Attachment 1.A
Council Agenda 12-5-2023 12.B-16
Packet Page 485

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Principal
4001 Public
Financing
Authority Debt
Service
Debt Service 57001 Principal No Project ongoing
(280,000.00)

(295,000.00)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Principal
6201 Wastewater
Treatment
Fund
Debt Service 57001 Principal No Project ongoing
(280,000.00)

(295,000.00)
2012
Wastewater
Bond
Redemption
2012
Wastewater
Refunding
Revenue
bonds -
redeemed,
WWTP Bonds
Principal
6201 Wastewater
Treatment
Fund
Debt Service 57009 Oth Fin Use-Early
Redem
No Project one-time
3,320,000.00

(295,000.00)
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund City Manager 52206 Phone No Project ongoing (468.00)

(468.00)
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund City Manager 52206 Phone No Project ongoing (1,800.00)

(1,800.00)
Attachment 1.A
Council Agenda 12-5-2023 12.B-17
Packet Page 486

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund City Manager 52219 Internet No Project ongoing 530.00 530.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund City Manager 52219 Internet No Project ongoing 2,650.00 2,650.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund Fire 52206 Phone No Project ongoing
(480.00) (480.00)
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund Fire 52219 Internet No Project ongoing 1,550.00 1,550.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund Public Works 52219 Internet No Project ongoing 530.00 530.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-18
Packet Page 487

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
1001 General Fund Community
Development
52219 Internet No Project ongoing
530.00 530.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
6101 Water
Enterprise
Fund
Public Works 52219 Internet No Project ongoing
530.00 530.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
6201 Wastewater
Treatment
Fund
Public Works 52219 Internet No Project ongoing
2,120.00 2,120.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
6501 Parking
Enterprise
Fund
Police 52206 Phone No Project ongoing
(2,450.00) (2,450.00)
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
6501 Parking
Enterprise
Fund
Police 52219 Internet No Project ongoing
2,700.00 2,700.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-19
Packet Page 488

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
7101 Technology
Service Fund
Administrative
Services
52219 Internet No Project ongoing
350.00

350.00
Technical
correction
Move phone
budget to
internet and
reflect
increased
internet
charges
7101 Technology
Service Fund
Administrative
Services
52308 Radio Maintenance No Project ongoing
100.00

100.00
Technical
correction
Was moved
from FY 2023
as an expense
to FY 2024
after CIP
carryforwards
were done, so
budget was not
carried
forward.
2005 Housing In
Lieu Fee
Community
Development
58008 Other Financing
Uses
Affordable
Housing
2655 Shell
one-time
1,000,000.00

Revenue Legal
settlement
revenues
1001 General Fund General
Government
48001 Misc Revenue No Project one-time
400,000.00

Revenue Reduce LBID
Assessment
based on
updated
projections
2006 Lodging
Business
Improvement
General
Government
41601 LBID Assessment
Revenue
No Project one-time
(269,000.00)

Revenue Reduce LBID
Assessment
for physical
improvements
based on
updated
projections
2006 Lodging
Business
Improvement
General
Government
41604 LBID Assessment-
Improvements
No Project one-time
(269,000.00)

Attachment 1.A
Council Agenda 12-5-2023 12.B-20
Packet Page 489

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Revenue Reduce Local
Transportation
Fund (LTF)
budget based
on SLOCOG's
LTF annual
apportionment
2002 Local
Transportation
General
Government
45301 Local Transp Tax No Project one-time
(88,181.00)

Revenue Reduce Local
Transportation
Fund (LTF)
budget based
on SLOCOG's
LTF annual
apportionment
2002 Local
Transportation
General
Government
45302 LTF-Bikepaths No Project one-time
(1,547.00)

Revenue Reduce
projected
COPS grant
revenues
based on prior
year revenues
2004 Grants - Non-
Capital
Police 45201 State Gov't Grants SLESF-
COPS Grant
one-time
(50,000.00)

Revenue Reduce TOT
based on
updated
projections
1001 General Fund General
Government
41301 Trans Occupancy
Tax
No Project one-time
(790,000.00)

Revenue Settlement for
Shell Beach
Streetscape
project
1001 General Fund Public Works 48001 Misc Revenue Shell Beach Streetscape
one-time
175,000.00

Operating
costs
Add IT vehicle
budget, reduce
Building
vehicle budget
7201 Motor Vehicle
Fund
Public Works 56003 Cap Outlay-
Automotive
No Project one-time
36,783.43

Operating
costs
Add IT vehicle
budget, reduce
Building
vehicle budget
7201 Motor Vehicle
Fund
Public Works 56003 Cap Outlay-
Automotive
No Project one-time
(36,783.43)

Attachment 1.A
Council Agenda 12-5-2023 12.B-21
Packet Page 490

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Operating
costs
Add Zoom
Web
Conference
Subscription
for Council and
Advisory Board
meetings
7101 Technology
Service Fund
Administrative
Services
52201 Contract Services No Project one-time
6,048.00 6,350.00
Operating
costs
Adopt-a-Bench
program -
purchase 5
benches
1001 General Fund Public Works 52306 Operating Supp &
Maint
Adopt-A-
Bench
one-time
15,000.00
Operating
costs
Adopt-a-Bench
program
revenues
1001 General Fund Public Works 48005 Adopt A Bench No Project one-time 15,000.00
Operating
costs
Batteries for
Fire's lower
emission
equipment
1001 General Fund Fire 52306 Operating
Supply&Maintenance
No Project ongoing
2,700.00 2,700.00
Operating
costs
Codification
change to
reflect updated
Sewer Use
Ordinance
6101 Water
Enterprise
Fund
Public Works 52202 Codification No Project one-time
1,000.00
Operating
costs
Electrical
repairs Addie
Parking Lot
1001 General Fund Public Works 52313 Major Repair & Maint No Project one-time $5,000.00 Operating
costs
Electrical
repairs on Pier
6401 Pier
Enterprise
Fund
Public Works 52313 Major Repair & Maint No Project one-time $5,000.00 Operating
costs
Encryption of
Police radio
channel and
reprogramming
of all Police
radios with the
encrypted
channels of
other agencies
in the County
7101 Technology
Service Fund
Administrative
Services
52308 Radio Maintenance No Project one-time
28,800.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-22
Packet Page 491

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Operating
costs
IGOE Monthly
Administration
fee for Flex
benefit
payments
1001 General Fund Management
Services
52201 Contract Services No Project ongoing
1,920.00 2,016.00
Operating
costs
Increase in
boot budget
and cost of
safety
equipment
1001 General Fund Public Works 52304 Safety Equipment No Project ongoing $3,000.00 $3,000.00 Operating
costs
Increase in
event restroom
rentals
1001 General Fund Public Works 52201 Contract Services No Project one-time $3,000.00 Operating
costs
Paint interior of
Bello Vets Hall
1001 General Fund Public Works 52336 Vets Hall Op
Supplies & Maint
No Project one-time $10,000.00
Operating
costs
Purchase gas
powered
equipment:
weed eaters,
blowers, etc.
for Parks
1001 General Fund Public Works 52314 Minor Equipment No Project one-time $12,000.00 Operating
costs
Replace air
vacs and
saddles that
have had
critical failures
resulting in
sewage spills
6201 Wastewater
Treatment
Fund
Public Works 52335 Collection System
Maintenance
No Project one-time
30,000.00 30,000.00
Operating
costs
Replacement
bollards at Pier
parking lot
6401 Pier
Enterprise
Fund
Public Works 52313 Major Repair & Maint No Project one-time $9,500.00 Operating
costs
Staff furniture 1001 General Fund Management
Services
52301 Office Supplies No Project one-time
6,500.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-23
Packet Page 492

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Operating
costs
Static IP
address
registered to
the City for
Police License
Plate Reader
(LPR) system
7101 Technology
Service Fund
Administrative
Services
52219 Internet No Project ongoing
1,400.00 2,400.00
Operating
costs
Station 63
Project -
landscaping
1001 General Fund Public Works 52311 Bldg. & Grounds
Oper S&M
No Project one-time $4,000.00
Operating
costs
Tree trimming
emergency
services city-
wide
1001 General Fund Public Works 52201 Contract Services No Project ongoing $25,000.00 $10,000.00 Operating
costs
Vehicle
maintenance
costs
1001 General Fund Administrative
Services
52380 MV Operations No Project ongoing
1,000.00 1,500.00
Operating
costs
Vehicle
maintenance
costs
6501 Parking
Enterprise
Fund
Police 52380 MV Operations No Project ongoing
1,000.00 1,500.00
Operating
costs
Vehicle
maintenance
costs
7201 Motor Vehicle
Fund
Public Works 46712 MV Rental Charge No Project ongoing
2,000.00 3,000.00
Operating
costs
Vehicle
maintenance
costs
7201 Motor Vehicle
Fund
Public Works 52390 MV Repairs -
Parking
No Project ongoing
1,000.00 1,500.00
Operating
costs
Vehicle
maintenance
costs
7201 Motor Vehicle
Fund
Public Works 52393 MV Repairs -
Administration
No Project ongoing
1,000.00 1,500.00
Operating
costs
Wastewater
Treatment
Plant Supplies
& Maintenance
additional
costs
6101 Water
Enterprise
Fund
Public Works 52324 Water sys Supp &
Maintenance
No Project ongoing
15,000.00 20,000.00
Operating
costs
Watchguard
Police Body
Camera cloud
storage
1001 General Fund Police 52201 Contract Services No Project ongoing 4,000.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-24
Packet Page 493

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Operating
costs
Watchguard
Police Body
Camera cloud
storage
1001 General Fund Police 56001 Cap Outlay-Mach &
Equip
Body
Camera
Replacement
one-time
6,000.00
Operating
costs
Watchguard
Police Body
Camera cloud
storage
7101 Technology
Service Fund
Administrative
Services
52201 Contract Services No Project ongoing
1,167.00 2,000.00
Operating
costs
Watchguard
Police Body
Camera cloud
storage
7101 Technology
Service Fund
Administrative
Services
52219 Internet No Project ongoing
10,500.00 18,000.00
Operating
costs
Water and
wastewater
rate study,
consultant, and
prop 218
mailings
6101 Water
Enterprise
Fund
Public Works 52101 Professional
Services
Water WW
Rate Study
one-time
2,093.48
Operating
costs
Water and
wastewater
rate study,
consultant and
prop 218
mailings
6101 Water
Enterprise
Fund
Public Works 52101 Professional
Services
Water WW
Rate Study
one-time
2,093.50
Workforce
Development
Citywide
Software
training - Office
365, Adobe
Acrobat,
Laserfiche.
7101 Technology
Service Fund
Administrative
Services
52225 Misc Schools &
Training
No Project one-time
20,000.00
Workforce
Development
Class B
License
Training
1001 General Fund Public Works 52225 Misc Schools &
Training
No Project one-time $3,500.00
Workforce
Development
Facilities
Manager
Travel/Training
1001 General Fund Public Works 52225 Misc Schools &
Training
No Project ongoing $500.00 $1,000.00
Workforce
Development
Increased boot
budget safety
equipment
1001 General Fund Public Works 52304 Safety Equipment No Project one-time $5,000.00 $5,000.00 Attachment 1.A
Council Agenda 12-5-2023 12.B-25
Packet Page 494

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Workforce
Development
Training,
MMASC
Conference
1001 General Fund Public Works 52225 Misc Schools &
Training
No Project ongoing $1,500.00
IT Allocation IT Allocation 1001 General Fund City Council 52412 Technology Costs No Project ongoing 434.00 7.00
IT Allocation IT Allocation 1001 General Fund City Manager 52412 Technology Costs No Project ongoing 289.00 5.00
IT Allocation IT Allocation 1001 General Fund City Manager 52412 Technology Costs No Project ongoing 2,232.00 1,289.00
IT Allocation IT Allocation 1001 General Fund Management Services
52412 Technology Costs No Project ongoing
7,992.00 1,925.00
IT Allocation IT Allocation 1001 General Fund Management Services
52412 Technology Costs No Project ongoing
470.00 8.00
IT Allocation IT Allocation 1001 General Fund Administrative Services
52412 Technology Costs No Project ongoing
1,228.00 21.00
IT Allocation IT Allocation 1001 General Fund Police 52412 Technology Costs No Project ongoing 26,709.00 22,553.00
IT Allocation IT Allocation 1001 General Fund Fire 52412 Technology Costs No Project ongoing 723.00 12.00
IT Allocation IT Allocation 1001 General Fund Fire 52412 Technology Costs No Project ongoing 162.00 20.00
IT Allocation IT Allocation 1001 General Fund Public Works 52412 Technology Costs No Project ongoing 1,879.00 32.00
IT Allocation IT Allocation 1001 General Fund Public Works 52412 Technology Costs No Project ongoing 5,768.00 13.00
IT Allocation IT Allocation 1001 General Fund Public Works 52412 Technology Costs No Project ongoing 1,070.00 969.00
IT Allocation IT Allocation 1001 General Fund Public Works 52412 Technology Costs No Project ongoing 148.00 6.00
IT Allocation IT Allocation 1001 General Fund Community Development
52412 Technology Costs No Project ongoing
2,593.00 1,294.00
IT Allocation IT Allocation 1001 General Fund Community Development
52412 Technology Costs No Project ongoing
1,012.00 17.00
IT Allocation IT Allocation 1001 General Fund Community Development
52412 Technology Costs No Project ongoing
1,301.00 22.00
IT Allocation IT Allocation 6101 Water
Enterprise
Fund
Administrative
Services
52412 Technology Costs No Project ongoing

72.00 1.00
Attachment 1.A
Council Agenda 12-5-2023 12.B-26
Packet Page 495

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
IT Allocation IT Allocation 6101 Water
Enterprise
Fund
Public Works 52412 Technology Costs No Project ongoing
5,915.00

20.00 IT Allocation IT Allocation 6201 Wastewater
Treatment
Fund
Administrative
Services
52412 Technology Costs No Project ongoing

72.00 1.00
IT Allocation IT Allocation 6201 Wastewater
Treatment
Fund
Public Works 52412 Technology Costs No Project ongoing
5,773.00

20.00 IT Allocation IT Allocation 6501 Parking
Enterprise
Fund
Police 52412 Technology Costs No Project ongoing
2,523.00

965.00
IT Allocation IT Allocation 7101 Technology
Service Fund
General
Government
46401 IT Service Charges No Project ongoing
68,365.00

29,200.00
Funding
Source
changes
Increase
transfer from
Gas Tax Fund
for Paving
project, reduce
General Fund
support
1001 General Fund Public Works 59301 Transfer Out Cap
Project
FY 2022
Paving
Project
one-time
(18,536.00)

Funding
Source
changes
Increase
transfer from
Gas Tax Fund
for Paving
project, reduce
General Fund
support
2001 Gas Tax Fund Public Works 59301 Transfer Out Cap
Project
FY 2022
Paving
Project
one-time
18,536.00

Funding
Source
changes
Increase
transfer from
Gas Tax Fund
for Paving
project, reduce
General Fund
support
3001 Capital
Projects
Public Works 49101 Transfer In General
Fund
FY 2022
Paving
Project
one-time
(18,536.00)

Attachment 1.A
Council Agenda 12-5-2023 12.B-27
Packet Page 496

Category Report
Description
Fund Fund Title Dept Title Account Account Description Project Title One-time/ Ongoing
FY 2024
Budget
Adjustment
FY 2025
Budget
Adjustment
Funding
Source
changes
Increase
transfer from
Gas Tax Fund
for Paving
project, reduce
General Fund
support
3001 Capital
Projects
Public Works 49201 Transfer In Gas Tax FY 2022
Paving
Project
one-time
18,536.00
Project
Savings
De-appropriate
-parking
management
plan completed
6501 Parking
Enterprise
Fund
Police 52101 Professional
Services
Parking
Mgmt. Study
one-time
(5,085.00)
Project
Savings
De-appropriate
-parking
property
paving
6501 Parking
Enterprise
Fund
Public Works 56006 Land Improvements Parking
property
paving
one-time
(750,000.00)
Project
Savings
De-appropriate
remaining
parking land
purchase
budget
6501 Parking
Enterprise
Fund
Public Works 56005 Capital Outlay-Land Parking
Garage
one-time
(1,198,916.28)
Project
Savings
De-
appropriate,
project
completed
1001 General Fund City Manager 52101 Professional
Services
Economic
Impact Study
one-time
(26,960.82)
Project
Savings
De-
appropriate,
project
completed
1001 General Fund Administrative
Services
59711 Transfer Out IT Fund Microsoft
Office 365
one-time
(5,802.73)
Project
Savings
De-
appropriate,
project
completed
7101 Technology
Service Fund
Administrative
Services
49101 Transfer In General
Fund
Microsoft
Office 365
one-time
(5,802.73)
Project
Savings
De-
appropriate,
project
completed
7101 Technology
Service Fund
Administrative
Services
52201 Contract Services Microsoft
Office 365
one-time
(2,814.36)
Project
Savings
De-
appropriate,
project
completed
7101 Technology
Service Fund
Administrative
Services
52225 Misc Schools &
Training
Microsoft
Office 365
one-time
(2,988.37)
Attachment 1.A
Council Agenda 12-5-2023 12.B-28
Packet Page 497

PISMO BEACH CITY COUNCIL STAFF REPORT
Agenda Item #12.C

SUBJECT/TITLE:
2024 STATE LEGISLATIVE AGENDA AND AMENDMENT #1 TO THE AGREEMENT

WITH TOWNSEND PUBLIC AFFAIRS
RECOMMENDATION:

Adopt a Resolution approving Amendment #1 to the agreement with Townsend Public Affairs for state legislative advocacy services from January 2024 through June 2026, in an amount not to exceed $138,000; and approving the 2024 State Legislative Agenda.

BACKGROUND:

Townsend Public Affairs (Townsend) has provided the City with grant writing and legislative advocacy services at the state level since June 2016. During that time, Townsend has formulated the City's State Legislative Agendas and provided focused and effective grant writing and legislative advocacy services in accordance therewith.

Townsend has been very successful in helping to obtain funds for various City priorities including Central Coast Blue, and in acting as a liaison to state legislators with respect to complex issues including transportation and housing.
2024 Legislative Agenda
Townsend has proposed a State Legislative Agenda for 2024, provided as Attachment

1.B. The legislative agenda serves as the City's official policy document for interacting with state officials and for taking positions on legislation. At this meeting, Eric O’Donnell of Townsend will review the proposed 2024 Legislative Agenda and provide an overview of current activity at the state level.

Agreement for Legislative Advocacy Services
The current contract with Towsend Public Affairs expires on December 31, 2023, but allows for extensions of the agreement. Staff recommends extending the term of the agreement for another two and a half-year period. In order to maximize the value to the City, staff recommends a modification to the scope of work to expand grant writing services from a support role, to a full-service grant writing, strategy, and coordination level of service that will provide a significant return on investment and reduce the burden on limited staff resources. The proposed Amendment #1 (Attachment 1.A) includes increases in years two and three of the agreement. To align the contract with the fiscal year for budgeting purposes, staff is also recommending a modified contract period to be consistent with other similar services.

Conclusion and Recommendation
Staff recommends that the Council adopt a Resolution (Attachment 1) approving Amendment #1 to the contract with Townsend Public Affairs for state legislative advocacy services through June 2026 in an amount not to exceed $138,000, and approving the 2024 Legislative Agenda.

12.C-1Council Agenda 12-5-2023
Packet Page 498

FISCAL IMPACT:

The fiscal impact of approving the subject Resolution is $138,000 over a two and a half- year contract term, or $4,000 per month for the first 6 months between January 1, 2024 through June 30, 2024, $4,500 per month for Fiscal Year (FY) 2025, and $5,000 per month for FY 2026. If approved, the amendment will total $24,000 in FY 2024, $54,000 in FY 2025, and $60,000 in FY 2026. This cost will be shared 50% in the General Fund and 50% in the Water and Wastewater Enterprise Funds. Of the 50% share in the Water and Wastewater Enterprise Funds, 33% of this will be allocated to the Water Enterprise Fund for the Central Coast Blue project and 67% of this will be allocated to the Wastewater Enterprise Fund for the Central Coast Blue project. There are sufficient budgeted amounts in both FY 2024 and FY 2025 to support this cost.

ALTERNATIVES:

1. Modify the Amendment with Towsend Public Affairs and Modify the State Agenda;

2. Deny the Amendment and Federal Agenda; provide direction.

ATTACHMENTS:

1. Resolution

1.A. Exhibit A to Resolution: Amendment #1 to Agreement

1.B. Exhibit B to Resolution: 2024 State Legislative Agenda Submitted by: Meeting Date: December 5, 2023
Jorge Garcia, City Manager
City Manager Approval:

12.C-2Council Agenda 12-5-2023
Packet Page 499

RESOLUTION NO. R-2023-XXX

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH, CALIFORNIA APPROVING AMENDMENT #1 TO THE AGREEMENT WITH

TOWNSEND PUBLIC AFFAIRS FOR LEGISLATIVE ADVOCACY SERVICES FROM JANUARY 2024 THROUGH JUNE 2026, IN AN AMOUNT NOT TO EXCEED $138,000; AND APPROVING THE 2024 STATE LEGISLATIVE AGENDA WHEREAS, Townsend Public Affairs has provided the City with grant writing and legislative advocacy services at the state level since June 2016; Townsend has formulated the City's State Legislative Agendas during that time, and has been very successful in helping to obtain funds for various City priorities, and in acting as a liaison to state legislators with respect to complex issues including transportation and housing; and
WHEREAS, Townsend has proposed a State Legislative Agenda for 2024, which will serve as the City's official policy document for interacting with state officials and for taking positions on legislation; and
WHEREAS, the City’s current contract with Townsend expires on December 31, 2023, but allows for extensions of the agreement; staff recommends extending the term of the agreement for a two and a half-year period to allow the City to continue engaging the services of Townsend throughout the construction of Central Coast Blue and other important initiatives.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby approves Amendment #1 (Exhibit A) to the agreement with Townsend Public Affairs, Inc. for state grant writing and legislative advocacy services for the period of January 1, 2024 through June 30, 2026 in an amount not to exceed $138,000, including $24,000 in Fiscal Year (FY) 2024, $54,000 in FY 2025, and $60,000 in FY 2026.

BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby approves the 2024 State Legislative Agenda (Exhibit B).

UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 5th day of December 2023, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

RECUSED:

Attachment 1

12.C-3Council Agenda 12-5-2023
Packet Page 500

Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk
Attachment 1

12.C-4Council Agenda 12-5-2023
Packet Page 501

AMENDMENT # 1
to the
December 10, 2020 AGREEMENT BETWEEN THE CITY OF PISMO BEACH AND Townsend Public Affairs, Inc.

Pursuant to the December 10, 2020 Agreement for Professional Services between the City of Pismo Beach, hereinafter referred to as “City,” and Townsend Public Affairs, Inc., hereinafter referred to as “Vendor,” City and Vendor hereby agree as follows:

1. Continued services shall be performed as set forth in Exhibit A dated December 5, 2023, attached hereto and incorporated herein by reference.

2. Compensation for and timing of the additional services shall be as set forth Exhibit B, attached hereto and incorporated herein by reference. Compensation for the additional services shall not exceed the amount of one hundred thirty-eight thousand dollars ($138,000), including $24,000 in Fiscal Year (FY) 2024, $54,000 in FY 2025, and $60,000 in FY 2026, without prior written approval of the City.

FEE SCHEDULE:
Year one, partial (January 1, 2024—June 30, 2024):
o Four thousand dollars ($4,000) per month.
Year two (July 1, 2024—June 30, 2025):
o Four thousand five hundred dollars ($4,500) per month. Year three (July 1, 2025—June 30, 2026):
o Five thousand dollars ($5,000) per month.
inclusive of normal business expenses, not to exceed $138,000 for the two and a half- year period ending June 30, 2026.

3. The revised fee under the December 10, 2020 contract, plus this addendum, is two hundred seventy thousand dollars ($270,000).

4. The agreement term end date is hereby revised to June 30, 2026.

5. All other provisions of the above agreement between City and Vendor shall remain in full force and effect.

Signatures begin on the following page.

Attachment 1.A

12.C-5Council Agenda 12-5-2023
Packet Page 502

CITY:

City of Pismo Beach, a Municipal Corporation
Signed:

Name: Jorge E. Garcia
Title: City Manager
Dated: ________________________________
ATTEST:

Signed:

Name: Erica Inderlied
Title: City Clerk
APPROVED AS TO FORM:

Signed:

Name: David M. Fleishman
Title: City Attorney
VENDOR:

Townsend Public Affairs, Inc.

Signed:

Name: ________________________________
Title: _________________________________
Dated: ________________________________
Address for giving notice:
(if changed from prior agreement)
______________________________________
______________________________________
Email address for official communications:
(if changed from prior agreement)
______________________________________
Vendor Representative:
(if changed from prior agreement)
Name/Title: ____________________________
Attachment 1.A

12.C-6Council Agenda 12-5-2023
Packet Page 503

EXHIBIT “A”
TO

AGREEMENT FOR CONSULTANT SERVICES
December 5, 2023
SERVICES: GRANT WRITING AND FUNDING ADVOCACY
A. Conduct Detailed Orientation: TPA utilizes a comprehensive onboarding process that includes extensive meetings with various relevant members of leadership and key departments to help develop a strategic plan that is carefully tailored to satisfy the needs of the client and is designed for maximum success in the current political climate and funding environment.

B. Craft Strategic Funding Plan: Utilizing the information gathered during the onboarding process, TPA will coordinate with the client to develop a proactive and comprehensive strategic funding plan that serves the needs of the client’s priorities. The plan will do more than simply identify client projects; it will outline and prioritize multiple funding options for each project and develop a specific plan of work tailored for each project. It will also identify key “strings attached” to help assess the cost/benefit ratio for each grant opportunity.

C. Identify, Research, and Monitor Grant Funding Opportunities: TPA will utilize list-serve subscription programs, funding workshops, agency canvassing, and other networking tactics to ensure every potential opportunity is identified and reviewed for relevance with the client’s projects. TPA will then share these opportunities with the client for further assessment and determination if a grant application is warranted. The client will also receive a grant matrix of funding programs that is updated regularly as new opportunities arise.

D. Community Outreach: TPA will assist the client with community outreach required for grant applications by ensuring the client is aware of specific requirements, helping develop materials that capture all elements required by the grant, and compiling the outreach data for inclusion in the application.

E. Grant Application Development and Submittal: TPA will develop, draft, submit, and follow up on each client grant application through the following process:
a. Establishment of Clear Accountabilities: TPA will coordinate with the client to ensure the assignment of responsibilities and tasks are made clear so that confusion and inefficiency are avoided, and the client is burdened as little as possible while TPA pursues a grant opportunity. b. Provide Overview of Full Application Requirements: For each grant application, TPA will provide the client with a detailed overview of the requirements for the grant program and corresponding application to ensure that the program is a strong fit for the client’s project. This will include:
i. Application timeline
ii. Eligible project types
iii. Funding availability and award maximums and minimums Attachment 1.A

12.C-7Council Agenda 12-5-2023
Packet Page 504

iv. List of application components, including proposal questions and any required attachments
c. Assemble Project Background and Details: TPA will conduct a detailed informational interview with client staff most involved with each project in order to gain a full understanding of the project background and scope details necessary for developing the grant proposal and addressing all application questions.
d. Coordinate Technical Project Details: For technical application components such as site plans, detailed cost estimates, project timelines, engineering plans, and cost-benefit analyses, TPA will coordinate with client staff to compile all necessary attachments and ensure consistency across all elements of the application. e. Draft Written Proposal: TPA will fully draft all narrative components of the application and, when applicable, will indicate where additional input or project detail from the client could be provided during the proposal review process.
f. Incorporate Feedback to Finalize Proposal: Well ahead of the application deadline, TPA will provide the client with a full draft for review and feedback. TPA will incorporate any additional details or revisions provided during this process to finalize the grant application and will obtain client approval for the final version of the application prior to submission.
g. Submit Completed Application: TPA will ensure that applications are submitted prior to the deadline, whether the submission is electronic or through hard copies, in accordance with submission instructions for each individual program. For hard copy submissions, TPA will print and package applications according to submission instructions and will ship applications through a reliable carrier service such as FedEx in order to provide the client with tracking and delivery confirmation for the application. TPA will also obtain a receipt for proof of submission and provide the client with a final copy of all submitted application documents.
h. Funding Advocacy: Throughout the grant application process TPA will leverage relationships with relevant officials and program officers in various state and federal funding agencies to ensure that client grant applications are aligned with the goals of the specific grant program and that the applications are well-crafted and well-positioned for funding.

F. Post-Grant Submittal Advocacy: TPA will frequently contact legislators and agency officials to follow up on the status of a grant application and promote its need and urgency. This will include drafting letters of support after grant submissions and distributing them to legislators for their consideration. In addition, TPA will work with legislators to reach out to individual granting agencies to provide background on client’s projects and convey their support for those projects.

Attachment 1.A

12.C-8Council Agenda 12-5-2023
Packet Page 505

G. Post-Award Grant Administration and Compliance: TPA will also assist, as needed, with post-award administration and compliance for all grant applications submitted by TPA on behalf of the client. This assistance will include interacting with granting agencies on behalf of the client, providing support for the drafting and submission of required reports and evaluations, and other tasks related to the successful monitoring of and compliance with the program requirements.

H. Post-Award Services—Above and Beyond Advocacy: TPA has a track record of success with post-award grant administration and retention. TPA has worked on behalf of clients who, due to unforeseen circumstances, have needed to request an extension of the grant performance period to accomplish project deliverables. TPA is prepared to engage in the legislative process and work with legislators to get bills passed that would allow for the client to retain its grant funding after the performance period would have otherwise ended. Additionally, TPA is prepared to work directly with the client and agencies to secure scope of work changes to already awarded projects to ensure the client will not have to return any hard-won grant funding.

I. Comprehensive Follow-Up on Unsuccessful Applications: Despite all best efforts, some grant applications are not selected for funding. In those instances where grant applications are unsuccessful, TPA will work with the relevant state and federal funding agencies to set up in-person or telephone debriefing sessions to discuss the grant applications and how to best revise the grant applications for the next funding round to ensure success.

J. Provide Monthly Progress Reports: TPA will confer regularly with the client on our activities. TPA will provide timely electronic monthly reports on the status of all funding activity, such as current funding opportunities, current applications, submitted applications, and post-grant submittal advocacy. In addition to written reports, TPA will be available to the client for conference calls, in-person briefings, and meetings.

Attachment 1.A

12.C-9Council Agenda 12-5-2023
Packet Page 506

LEGISLATIVE ADVOCACY
A. Conduct Detailed Orientation: TPA utilizes a comprehensive onboarding process that includes extensive meetings with various relevant members of leadership and key departments to help develop a strategic plan that is carefully tailored to satisfy the needs of the client and is designed for maximum success in the current political climate and funding environment.

B. Develop Legislative Strategy: Utilizing the information gathered during the onboarding process, TPA will coordinate with the client to develop an official legislative platform and strategy that represents the client’s priorities in Sacramento and Washington, DC. This blueprint will be shared with key stakeholders in the State Legislature and Governor’s Administration as well as Congress and the Biden Administration.

C. Implement the Legislative Strategy: TPA will advocate for the client’s legislative agenda utilizing the following methods:
a. Build and Strengthen Relevant Relationships: TPA has cultivated a network of valuable relationships that will be leveraged to promote the client’s legislative agenda.
b. Leverage Relationships for Strategic Advocacy Plan: TPA will engage various techniques to leverage our network of key relationships on behalf of the client:
i. Schedule meetings for the client to discuss relevant legislation ii. Prepare all briefing materials and talking points for the client iii. Brief legislative offices and stakeholders on the client’s legislative agenda
iv. Follow-up on meetings to ensure commitments and deliverables are being met
c. Coordinate Advocacy Trips: TPA will work with the client to coordinate advocacy trips to Sacramento and Washington, DC to meet with the client’s legislative delegation, as well as legislators that serve on committees relevant to the client’s agenda. Furthermore, whenever possible, TPA will also schedule site visits by legislators to the client. d. Track Legislation: TPA will identify, analyze, and monitor all bill introductions and amendments relevant to the client’s legislative platform and assess their potential impact on the client.
e. Craft Testimony and Position Letters: TPA will prepare and submit written and verbal testimony regarding legislation relevant to the client. TPA will also draft and deliver position letters to legislators and key officials on specific bill language.
f. Draft Bill Language: TPA will draft language and amendments for relevant legislation, as required to protect and promote the client’s agenda. g. State Budget Funding Opportunities: In an effort to maximize state funding, TPA will work with the client to identify projects and other funding priorities that may be suitable for funding through the State Budget. TPA Attachment 1.A

12.C-10Council Agenda 12-5-2023
Packet Page 507

will coordinate with the client to develop supporting materials for the budget request. TPA will also work with members of the client’s state legislative delegation, along with the Assembly and Senate Budget Committees, to gain support for the inclusion of the client’s project in the final State Budget approved by the Legislature.
h. Federal Earmark Opportunities: In an effort to maximize federal funding, TPA will work with the client to identify projects and other funding priorities that may be suitable for funding through the Federal Earmark process.

TPA will coordinate with the client to develop supporting materials for the earmark request. TPA will also work with members of the client’s federal legislative delegation to gain support for the inclusion of the client’s project.

D. Provide Progress Reports: TPA will confer regularly with the client on our activities. TPA will provide timely electronic reports on the status of all legislative activity, such as bill language, amendments, and committee analyses. In addition to written reports, TPA will be available to the client for conference calls, in-person briefings, and meetings.

E. Prepare and File Lobbying Disclosure Reports: TPA will prepare and file, on behalf of the client, all applicable state and federal lobbying disclosure reports.

CITY Initials _________
VENDOR Initials ________
Attachment 1.A

12.C-11Council Agenda 12-5-2023
Packet Page 508

EXHIBIT “B”
TO

AGREEMENT FOR CONSULTANT SERVICES
FEE SCHEDULE: Year 1, partial (January 1, 2024—June 30, 2025): $4,000 per month Year 2 (July 1, 2024—June 30, 2025): $4,500 per month
Year 3 (July 1, 2025—June 30, 2026): $5,000 per month
Optional:

Year 4 (July 1, 2026—June 30, 2027): $5,000 per month
Year 5 (July 1, 2027—June 30, 2028): $5,000 per month
CITY Initials _________
VENDOR Initials ________
Attachment 1.A

12.C-12Council Agenda 12-5-2023
Packet Page 509

2024 STATE

LEGISLATIVE
AGENDA
City of Pismo Beach, California
December 2023
Attachment 1.B

12.C-13Council Agenda 12-5-2023
Packet Page 510

2024 State Legislative Agenda Page 1

Townsend  Public Affairs, Inc., is proud and honored to represent the City of Pismo Beach.  This legislaƟve agenda is prepared in alignment with City Council goals and objecƟves, and to provide background informaƟon and recommendaƟons for the City as part of its criƟcal work on behalf of its residents and visitors.

Pismo Beach City Council
Mayor Ed Waage
Mayor Pro Tempore  Mary Ann Reiss
Council Member Marcia Guthrie
Council Member Stacy Inman
Council Member ScoƩ Newton

Jorge Garcia, City Manager

December 2023

Attachment 1.B

12.C-14Council Agenda 12-5-2023
Packet Page 511

2024 State Legislative Agenda Page 2
2024 State LegislaƟve Agenda
CITY OF PISMO BEACH, CALIFORNIA
Governance, AdministraƟve and Finance
Central to many of the City’s funcƟons is its ability to effecƟvely govern, administer and financially sustain its municipal operaƟons and assets on behalf and for the benefit of its residents.  Among the prioriƟes for the City are following:
Preserve local control by the City for its various permiƫng, land use, contracƟng and other discreƟonary acƟons;
Ensure transparency in government and the ability of residents to parƟcipate, comment and access informaƟon on local decision‐making and budgetary acƟons; Maintain the ability to provide sustainable reƟrement and medical programs for City employees and their families; and
Protect the City and its residents from State legislaƟve or administraƟve direcƟves without full cost‐recovery or miƟgaƟon.

The City should oppose legislaƟve efforts to eliminate or restrict local control of permiƫng and cost‐recovery efforts.  The City should support measures increasing local autonomy, protecƟng privacy, and maintaining local authority over public records.  The City should oppose mandates from the State that don’t include funding or other miƟgaƟon.  The City should oppose any effort to restrict its ability to contract for goods or services in a way that increases costs to the City or results in the reducƟon of services.  The City should support efforts to provide addiƟonal flexibility to the City in the provision and administraƟon of reƟrement and medical benefit programs, while ensuring those programs are sustainable for past, current, and future employees.

Attachment 1.B

12.C-15Council Agenda 12-5-2023
Packet Page 512

2024 State Legislative Agenda Page 3
General Infrastructure
City faciliƟes are heavily uƟlized by residents and are oŌen lower in priority compared to transportaƟon, water, and other faciliƟes impacted by usage, accidents, and weather.  The following needs are generally high on the list of necessary improvements:
Replacing or rehabilitaƟng outdated public building faciliƟes, including a city hall and administraƟve funcƟons, public safety faciliƟes for law enforcement and fire departments, as well as specialized departments;
Shore and coastal protecƟon and erosion measures; and
Energy and water efficiency improvements to faciliƟes that provide cost savings to the City, as well as benefits for the environment and health.

RecommendaƟons include supporƟng State legislaƟon and administraƟve acƟons to direct funding into grant programs for energy and water efficiency improvements.  The City should support the capitalizaƟon of revolving loan fund programs to assist local agencies with financing of capital costs.

Currently, funding for capital costs of building replacement and rehabilitaƟon are severely constrained, but there are opportuniƟes in a couple of areas:
The Governor’s Office of Business and Economic Development (GO‐Biz) and the California Infrastructure and Economic Development Bank (IBank) offer the State Infrastructure Revolving Fund Program with low‐interest‐rate loans, that could benefit efforts with the City’s old city hall, public safety facility improvements, and capital projects. Through the proceeds from cap and trade, the State provides periodic Water‐Energy Grant Program funding for facility improvements to effect savings of those resources.

Attachment 1.B

12.C-16Council Agenda 12-5-2023
Packet Page 513

2024 State Legislative Agenda Page 4
Transporta Ɵon Infrastructure
Transporta Ɵon faciliƟes that provide safe and efficient movement of people and goods are criƟcal to the City.  Priority will be placed on efforts to secure funding for the following areas of need:
Safety for pedestrians and bicyclists, including students, who share the transportaƟon corridors and faciliƟes;
Efficient circulaƟon in the City, parƟcularly in the downtown core, including parking availability;
Bridge and related infrastructure funding to ensure usage of exisƟng faciliƟes; CoordinaƟon with State highways and infrastructure;
Improvements to transportaƟon corridors for aestheƟcs and environmental and water benefits; and
Maintenance and preservaƟon of exisƟng faciliƟes to ensure life cycle usage and reduced costs of rehabilitaƟon and replacement.

RecommendaƟons include supporƟng State legislaƟon to increase the amount of funding available through the Highway Users Tax  Account and Road Maintenance and RehabilitaƟon Account, as well as specific grant programs.  Similarly, support for efforts to expedite project delivery processes to enable projects to move forward.  The City should support legislaƟon and administraƟve acƟons to make grant funding more compeƟƟve for City projects, through revisions of screening and scoring criteria that create an equitable distribuƟon of funding for all communiƟes. The City should oppose any aƩempts by the Legislature or AdministraƟon to withhold transportaƟon funding from jurisdicƟons related to their progress toward or status of their Regional Housing Needs Assessment (RHNA) or Housing Element compliance.

Funding and collaboraƟve work with State agencies will help the City advance priority projects and efforts, including:

Attachment 1.B

12.C-17Council Agenda 12-5-2023
Packet Page 514

2024 State Legislative Agenda Page 5
 CirculaƟon and parking improvements with potenƟal funding from programs such as the Caltrans Sustainable Transporta Ɵon Planning Grants and congesƟon management funds.  AestheƟc and other improvements to corridors such as Shell Beach, that provide a visual and quality‐of‐life incenƟve to increased pedestrian and bicyclist use.  The AcƟve Tra nsporta Ɵon Program provides funding to encourage this type of usage.  Similarly, cap and trade aucƟon proceeds fund programs for greening improvements to public faciliƟes (Urban and Community Forestry Program and Urban Greening Grant Program).  Regional congesƟon management proposals that benefit the City, including improvements to U.S. Highway 101, county and city roadways, and other modes of transportaƟon (SoluƟons for Congested Corridors Program).

Water  Infrastructure and Resources
The State’s ongoing drought cycles have highlighted the need for conƟnued conservaƟon pracƟces, as well as a focus on ways to maximize the use of water resources, including recharging the area’s groundwater for future use and examining the potenƟal of innovaƟve reuse.  These short‐term and long‐term strategies are high prioriƟes for the Governor and AdministraƟon.

Policies related to these prioriƟes include:
 ConƟnuaƟon of the City’s history of water conservaƟon at public faciliƟes and by residents;
 Improvements to storm water and drainage infrastructure;  Treatment and recycling of wastewater for recharging groundwater resources;  Reuse of treated wastewater for potable and other innovaƟve purposes; and  Pursuit of regional partnerships to effecƟvely and efficiently leverage the infrastructure and collaboraƟon benefits of recycled water.

RecommendaƟons include supporƟng policies at the State Water  Resources Control Board (Water Board) that allow local agencies to set and achieve realisƟc and meaningful water Attachment 1.B

12.C-18Council Agenda 12-5-2023
Packet Page 515

2024 State Legislative Agenda Page 6
conservaƟon targets and encourage the Water  Board to consider the impacts to staff resources of the many reporƟng requirements.  The City should support further efforts by the Governor and Legislature to appropriate addiƟonal funding to key  water grant and loan programs.  Similarly, the City should support and encourage State funding for planning, outreach, design, construcƟon, and ongoing operaƟon efforts to local and regional projects for water recycling and basin recharge.

The City already has a strong history of working collaboraƟvely with the Water  Board on water projects.  Listed below are funding opportuniƟes available and being pursued for specific projects:

 The Water Board administers the Clean Water State Revolving Fund (SRF) which provides low‐interest‐rate loans and grants for water projects, parƟcularly those involving recycled water.   SupporƟng addiƟonal funds for the SRF program may help the City’s various water and wastewater projects advance faster toward funding.
 As part of Central Coast Blue (regional recycled water project) , the City has also pursued funding from the Water Board’s Groundwater Grant Program, funded from ProposiƟon 1.  Also as part of Central Coast Blue, the City is pursuing a grant from the SRF’s Recycled Water  Funding program.

Park, RecreaƟon and Open Space
Providing residents with a high quality of life, and visitors with an incredible experience to encourage addiƟonal visits, conƟnues to be a significant priority for the City.  Tourism  is one of the economic drivers for  the City that provides the opportunity for increased services and infrastructure improvements that keep residents saƟsfied.

As part of this quality of life and visitor experience, recreaƟonal and open space opportuniƟes are key.  Important needs and policies include:

Attachment 1.B

12.C-19Council Agenda 12-5-2023
Packet Page 516

2024 State Legislative Agenda Page 7
IdenƟfying and taking acƟon to acquire and retain open space areas; Maintaining park space in the City to ensure opportuniƟes for acƟvity, cleanliness, and visual benefit;
Developing improvements to park and open space faciliƟes to ensure access; and Leveraging partnerships to ensure all park, open space, and recreaƟonal faciliƟes are acquired, developed, and uƟlized.

RecommendaƟons include supporƟng State legislaƟve efforts to increase funding for programs that support these spaces, including legislaƟve bond measures for consideraƟon by voters.  The City should support the repurposing of previous grant funds that have not been uƟlized so addiƟonal cycles can be solicited.  LegislaƟve efforts to revise exisƟng grant programs to allow for addiƟonal uses that more closely align with City needs should be supported.

The City’s priority on parks and open space is evident in its work to idenƟfy opportuniƟes and collaborate with regional partners.  Several of the specific projects and funding opportuniƟes for the City include:
The City has a long history of working collaboraƟvely with the Land Conservancy of San Luis Obispo County (LCSLO) at the Pismo Preserve and remains commiƩed to the ongoing operaƟon and potenƟal future addiƟonal development of the project. The faciliƟes and open space in Price Canyon provide an opportunity to access addiƟonal funds toward the purpose of tourism and resident quality of life. The City will also seek to apply for funding from the programs funded by ProposiƟon 68 or other statewide bonds to provide recreaƟonal and open space opportuniƟes for residents and visitors as appropriate.  These opportuniƟes will contribute significantly to the City’s quality of life and economic vitality.

Attachment 1.B

12.C-20Council Agenda 12-5-2023
Packet Page 517

2024 State Legislative Agenda Page 8
Public Safety and Health
As noted above in General Infrastructure, faciliƟes for the City’s public safety services remains a very high priority, and needs and opportuniƟes are outlined in that secƟon.  Similarly, ensuring the City has the financial resources to provide services remains key.  Several areas of policy should also be considered, including:
Ensure appropriate funding levels for idenƟfied needs of law enforcement and fire departments;
Support policies related to data management that provide ciƟes maximum flexibility in meeƟng State standards with regards to collecƟon, accessibility, and preservaƟon; Ensure the ability of local law enforcement to comply and address changes to issues such criminal sentencing policies;
Ensure the City and its officials are prepared and able to respond appropriately to disasters and emergencies, including fire prevenƟon and suppression; and Ensure the City is prepared to prevent, respond, and recover from public health emergencies, including but not limited to the coronavirus (COVID‐19).

RecommendaƟons include supporƟng State legislaƟve efforts or Governor’s acƟons to provide addiƟonal budgetary and grant funding for programs that address a need idenƟfied by the City’s police and fire departments.  Similarly, the City should support efforts to prevent disasters, as well as to plan for appropriate emergency response, including training for officials and funding for equipment and other response and recovery efforts.

In parƟcular, the City should conƟnue to support State efforts providing funding and other coordinaƟon resources for  the prevenƟon and suppression of wildfires.  These efforts should include funding and support for updated mapping resources to serve in mutual aid and other Attachment 1.B

12.C-21Council Agenda 12-5-2023
Packet Page 518

2024 State Legislative Agenda Page 9
suppression acƟviƟes.  The City should oppose any State efforts to complicate via permiƫng or increasing the cost of rouƟne fuel modificaƟon work for wildfire prevenƟon. In addiƟon, the City should support funding for technology resources for mobile emergency operaƟon center needs and evacuaƟon preparedness efforts, including cellular and internet connecƟvity infrastructure.

The City should also support legislaƟve efforts to improve fire safety, emergency noƟficaƟon, and more effecƟve policing without compromising officer or resident safety. Finally, the City should support legislaƟve, administraƟve, and ballot efforts to maintain appropriate sentencing and parole standards and ensure the safety of our residents and community.

RecommendaƟons also include preparing the City and its residents for future health emergencies similar to the COVID‐19 pandemic.  The City should conƟnue to support efforts by the Governor and State Legislature to provide funding to local jurisdicƟons with flexibility for the use of that funding to support a variety of needs unique to each jurisdicƟon, including the conƟnuaƟon of public services and personnel, backfill for lost tax revenue, and to support State and county public health outreach and efforts.  The City should also support efforts to assist communiƟes such as Pismo Beach with a significant reliance on tourism to ensure public services are not severely impacted by the loss of transient occupancy and sales tax revenues.  The City should support direct funding and resource allocaƟons to municipal governments, instead of at county or statewide levels, allowing for the rapid deployment of such items as personal protecƟve equipment and other criƟcal materials and funding.

Attachment 1.B

12.C-22Council Agenda 12-5-2023
Packet Page 519

2024 State Legislative Agenda Page 10
Housing and Homelessness
The State Legislature and Governor conƟnue to work on soluƟons to the State’s crisis regarding the availability and affordability of housing.  In many areas of the State, local communiƟes are either struggling with a lack of available housing, or with prices so high as to make homeownership prohibiƟve, or both.  Reports by the California Department of Housing and Community Development (HCD) and other housing stakeholders have noted concerns with “local barriers” to effecƟvely addressing this housing situaƟon and concerns about methodologies for the establishment of impact fees among other local policy authoriƟes.

Every community is different, and for  the City, there are several policies to consider:
 Ensure local permiƫng and regulatory processes do not serve as barriers to an appropriate amount of available housing; Examine housing affordability so families and individuals can own or rent as they choose;
 Ensure there is available workforce housing to ensure a quality of life is available for all residents and individuals contribuƟng to the City’s economy.

RecommendaƟons include supporƟng State legislaƟve efforts to streamline the development of housing, while protecƟng the City’s permiƫng, impact, fee and regulatory processes.  The City should support efforts to provide funding mechanisms for developing housing and other related infrastructure, as well as funding for effecƟve housing development and ownership programs.

The City should support efforts to provide funding for grant programs that connect housing with employment, recreaƟon, schools, and public services.

The future of housing funding remains very much uncertain.  While the Legislature and Governor have approved a significant amount of housing‐related legislaƟon over the last few years, the voter‐approved housing bond and other mechanisms in these efforts are untested and their Attachment 1.B

12.C-23Council Agenda 12-5-2023
Packet Page 520

2024 State Legislative Agenda Page 11
effecƟveness to address the housing crisis remains to be seen.  For the City, opƟons to consider may include:
CreaƟon of funding mechanisms such as financing districts and tax increment proposals that have the benefits and potenƟal for guaranteed revenue streams; Cap and trade funding through the Affordable Housing and Sustainable CommuniƟes Program, which emphasizes higher density housing developments with a high degree of connecƟvity to jobs and transit; and
PotenƟal funding from the State through budgetary agreements between the Governor and Legislature.

The City should support efforts to harmonize and seek legislaƟon mandaƟng changes in land use to promote housing with the Coastal Act. The Coastal Act must be followed, but oŌen conflicts with State law without much clarity on navigaƟng between the two sets of regulaƟons. Efforts should be made to ensure that moving forward, this conflict is addressed by future legislaƟon.

Economic Vitality and Quality of Life
Many of the subject areas described in this plaƞorm, if not all, play key  roles in the economic vitality of the City: parks and open space provide recreaƟonal opportuniƟes, well‐maintained infrastructure provides clean water and easily‐navigated streets, and public safety provides peace of mind.  Residents don’t want to live somewhere that doesn’t meet these standards, nor do visitors want to frequent the place.  PrioriƟes areas to consider include:
Ensuring the business climate is posiƟve and able to aƩract and retain businesses that provide quality employment opportuniƟes and good products and services; Ensuring public infrastructure is adequate for business development needs; SupporƟng tourism and visitors while maintaining the quality of life for residents; and All opportuniƟes for economic investment and sustainability acƟviƟes are pursued.

Attachment 1.B

12.C-24Council Agenda 12-5-2023
Packet Page 521

2024 State Legislative Agenda Page 12
RecommendaƟons include supporƟng State legislaƟve efforts to create and foster community incenƟves for financing of public improvements.  The City should support legislaƟve and administraƟve efforts to improve the acƟviƟes at GO‐Biz which could benefit the City.  Similarly, the City should support funding programs to support local transportaƟon planning efforts to help circulaƟon, parking, and other specific plan elements.  The City should support legislaƟve efforts to provide a framework for short‐term vacaƟon rentals that protects local control and accessibility to data, while ensuring the City captures all transient occupancy taxes.

Given the City’s status as a desƟnaƟon for  visitors and tourism, enhancing the visitor experience is key  to helping drive the City’s economic vitality.  Several efforts and opportuniƟes are below:
The City conƟnues to maximize the potenƟal for  places such as Pismo Preserve and Price Canyon by pursuing funding opportuniƟes in collaboraƟon with regional partners.  These efforts will result in increased accessibility to recreaƟonal and educaƟonal opportuniƟes. The City conƟnues to pursue and support the reintroducƟon of the Pismo Clam and potenƟal funding from sources such as the Natural Resources Agency and Ocean ProtecƟon Council that may help with those efforts. ReintroducƟon of the clam will provide yet another opportunity for the City to showcase one of its best resources to visitors.

Attachment 1.B

12.C-25Council Agenda 12-5-2023
Packet Page 522

PISMO BEACH CITY COUNCIL STAFF REPORT
Agenda Item #12.D

SUBJECT/TITLE:
2024 FEDERAL LEGISLATIVE AGENDA AND AMENDMENT #1 TO AGREEMENT

WITH THORN RUN PARTNERS
RECOMMENDATION:

Adopt a Resolution approving Amendment #1 to the agreement with Thorn Run Partners for federal legislative advocacy services from January 2024 through June 2026, in an amount not to exceed $153,000; and approving the 2024 Federal Legislative Agenda.

BACKGROUND:

Thorn Run Partners currently provides the City with grant writing and legislative advocacy services at the federal level. As part of its services, Thorn Run has formulated the City's Federal Legislative Agendas for several years and provided focused and effective grant writing and legislative advocacy services in accordance therewith. Thorn Run has been very successful in helping to obtain funds for various City priorities and acting as a liaison to federal legislators with respect to complex issues.
2024 Legislative Agenda
Thorn Run has proposed a Federal Legislative Agenda for 2024, provided as Attachment

1.B. The legislative agenda serves as the City's official policy document for interacting with federal officials and for taking positions on legislation. At this meeting, Greg Burns of Thorn Run will review the proposed 2024 Legislative Agenda and provide an overview of current activity at the federal level.

Agreement for Legislative Advocacy Services
The current contract with Thorn Run Partners expires on December 31, 2023, but allows for extensions of the agreement. Staff recommends extending the term of the agreement for another two and a half-year period. This will allow the City to continue engaging the services of Thorn Run Partners and Mr. Burns throughout the construction of Central Coast Blue which involves applying for grants and financing with various federal agencies.

The proposed Amendment #1 (Attachment 1.A) includes modest increases in years two and three of the agreement. To align the contract with the fiscal year for budgeting purposes, staff is also recommending a modified contract period to be consistent with other similar services.

Conclusion and Recommendation
Staff recommends that the Council adopt a Resolution (Attachment 1) approving Amendment #1 to the contract with Thorn Run Partners for federal legislative advocacy services through June 2026 in an amount not to exceed $153,000, and approving the 2024 Legislative Agenda.

12.D-1Council Agenda 12-5-2023
Packet Page 523

FISCAL IMPACT:

The fiscal impact of approving the subject Resolution is $153,000 over a two and a half- year contract term, or $4,500 per month for the first 6 months between January 1, 2024 through June 30, 2024, $5,000 per month for Fiscal Year (FY) 2025, and $5,500 per month for FY 2026. If approved, the amendment will total $27,000 in FY 2024, $60,000 in FY 2025, and $66,000 in FY 2026. This cost will be shared 50% in the General Fund and 50% in the Water and Wastewater Enterprise Funds. Of the 50% share in the Water and Wastewater Enterprise Funds, 33% of this will be allocated to the Water Enterprise Fund for the Central Coast Blue project and 67% of this will be allocated to the Wastewater Enterprise Fund for the Central Coast Blue project. There are sufficient budgeted amounts in both FY 2024 and FY 2025 to support this cost.

ALTERNATIVES:

1. Approve the Amendment with Thorn Run Partners and Modify the Federal Agenda;

2. Deny the Amendment and Federal Agenda; provide direction.

ATTACHMENTS:

1. Resolution

1.A. Exhibit A to Resolution: Amendment #1 to Agreement

1.B. Exhibit B to Resolution: 2024 Federal Legislative Agenda Submitted by: Meeting Date: December 5, 2023
Jorge Garcia, City Manager
City Manager Approval:

12.D-2Council Agenda 12-5-2023
Packet Page 524

RESOLUTION NO. R-2023-XXX

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH, CALIFORNIA APPROVING AMENDMENT #1 TO THE AGREEMENT WITH THORN

RUN PARTNERS FOR FEDERAL LEGISLATIVE ADVOCACY SERVICES FROM JANUARY 2024 THROUGH JUNE 2026, IN AN AMOUNT NOT TO EXCEED $153,000; AND APPROVING THE 2024 FEDERAL LEGISLATIVE AGENDA WHEREAS, Thorn Run Partners currently provides the City with grant writing and legislative advocacy services at the federal level; Thorn Run has formulated the City's Federal Legislative Agendas for several years and has been very successful in helping to obtain funds for various City priorities and acting as a liaison to federal legislators with respect to complex issues; and
WHEREAS, Thorn Run has proposed a Federal Legislative Agenda for 2024, which will serve as the City's official policy document for interacting with federal officials and for taking positions on legislation; and
WHEREAS, the City’s current contract with Thorn Run Partners expires on December 31, 2023, but allows for extensions of the agreement; staff recommends extending the term of the agreement for another two and a half-year period to allow the City to continue engaging the services of Thorn Run Partners throughout the construction of Central Coast Blue and other important initiatives.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby approves Amendment #1 (Exhibit A) to the agreement with Thorn Run Partners, LLC, for federal grant writing and legislative advocacy services for the period of January 1, 2024 through June 30, 2026 in an amount not to exceed $153,000, including $27,000 in Fiscal Year (FY) 2024, $60,000 in FY 2025, and $66,000 in FY 2026.

BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby approves the 2024 Federal Legislative Agenda (Exhibit B).

UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 5th day of December 2023, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

RECUSED:

Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk

12.D-3Council Agenda 12-5-2023
Attachment 1
Packet Page 525

AMENDMENT # 1
to the
December 23, 2020 AGREEMENT BETWEEN THE CITY OF PISMO BEACH AND Thorn Run Partners, LLC
Pursuant to the December 23, 2020 Agreement for Professional Services between the City of Pismo Beach, hereinafter referred to as “City,” and Thorn Run Partners, LLC, hereinafter referred to as “Vendor,” City and Vendor hereby agree as follows:

1. Continued services shall be performed as set forth in Exhibit A to the December 23, 2020 agreement.

2. Exhibit B to the December 23, 2020 agreement shall be revised to reflect the payment amounts and schedule set forth below. Compensation for the continued services shall not exceed the amount of one hundred fifty-three thousand dollars ($153,000), including $27,000 in Fiscal Year (FY) 2024, $60,000 in FY 2025, and $66,000 in FY 2026, without prior written approval of the City.
(b) Schedule for Payments:

VENDOR shall bill CITY for services rendered under this Agreement. Billing shall be made monthly, as follows:
Year one, partial (January 1, 2024—June 30, 2024):
o Four thousand five hundred dollars ($4,500) per month. Year two (July 1, 2024—June 30, 2025):
o Five thousand dollars ($5,000) per month.
Year three (July 1, 2025—June 30, 2026):
o Five thousand five hundred dollars ($5,500) per month.

3. The revised fee under the December 23, 2020 contract, plus this addendum, is three hundred and three thousand dollars ($303,000).

4. The agreement term end date is hereby revised to June 30, 2026.

5. All other provisions of the above agreement between City and Vendor shall remain in full force and effect.

Signatures begin on the following page.

12.D-4Council Agenda 12-5-2023
Attachment 1.A
Packet Page 526

CITY:

City of Pismo Beach, a Municipal Corporation
Signed:

Name: Jorge E. Garcia
Title: City Manager
Dated: ________________________________
ATTEST:

Signed:

Name: Erica Inderlied
Title: City Clerk
APPROVED AS TO FORM:

Signed:

Name: David M. Fleishman
Title: City Attorney
VENDOR:

Thorn Run Partners, LLC
Signed:

Name: ________________________________
Title: _________________________________
Dated: ________________________________
Address for giving notice:
(if changed from prior agreement)
______________________________________
______________________________________
Email address for official communications:
(if changed from prior agreement)
______________________________________
Vendor Representative:
(if changed from prior agreement)
Name/Title: ____________________________

12.D-5Council Agenda 12-5-2023
Attachment 1.A
Packet Page 527

City of Pismo Beach, California
2024 Federal Legislative Agenda

12.D-6Council Agenda 12-5-2023
Attachment 1.B
Packet Page 528

Prepared by Thorn Run Partners for the

Pismo Beach City Council

Mayor Ed Waage
Mayor Pro Tempore Mary Ann Reiss
Council Member Marcia Guthrie
Council Member Stacy Inman
Council Member Scott Newton

Jorge Garcia, City Manager

Questions regarding the information in this book may be directed to:

Greg Burns Jorge Garcia
(202) 849-8523 (805) 773-7007

December 2023

12.D-7Council Agenda 12-5-2023
Attachment 1.B
Packet Page 529

City of Pismo Beach
2024 Federal Legislative Agenda
Water Resources and Infrastructure
Central Coast Blue & Infrastructure
Support continued full funding the Bureau of Reclamation’s Title XVI Program. Support City efforts to secure federal funding for the Central Coast Blue project as well as other infrastructure projects while federal agencies implement the Bipartisan Infrastructure Law.

Energy & Environment
Energy Issues
Oppose the expansion of offshore oil and gas exploration in California’s federal waters. Support the development of offshore wind energy off the coast of California. Support the continued operation of the Diablo Canyon Nuclear Power Plant.

Proposed Designation of the Chumash Heritage National Marine Sanctuary Oppose the proposed designation of the Chumash Heritage National Marine Sanctuary.

Land and Water Conservation Fund; Open Space Opportunities & Park Amenities Support the state conservation grant program of the Land and Water Conservation Fund, which would provide opportunities for the City of Pismo Beach for acquisition or land preservation improvement opportunities.

Endangered Species Act Issues; Designation of Critical Habitat for the Monarch Butterfly Monitor the classification of the monarch butterfly as an endangered species and the subsequent designation of critical habitat for the species.

Public Safety
Grant Funding for Fire and Emergency Services
Support continued funding for FEMA’s Assistance to Firefighters Grants and Staffing for Adequate Fire and Emergency Response Grants. Support any City of Pismo Beach applications for these funds.

Social Services and Health Care
Community Development Block Grant Program
Support adequate funding for the Community Development Block Grant program for future fiscal years.

12.D-8Council Agenda 12-5-2023
Attachment 1.B
Packet Page 530

FEDERAL ISSUE: Central Coast Blue & Infrastructure
BACKGROUND: To respond to increasingly frequent drought concerns, the City of Pismo Beach and its local partners, including the cities of Arroyo Grande and Grover Beach, created Central Coast Blue, a recycled water project to boost the region’s water supply and relieve concerns related to groundwater overdraft. The project will allow the region to take an effluent stream that is otherwise pumped into the ocean and put it through an advanced filtration process and then inject it into the groundwater basin, thereby helping to provide a sustainable source of water for the region. Not only will the recycled augment the natural ground water supplies, it will also create a saltwater intrusion barrier to help prevent saltwater intrusion into the basin. Once complete, the project could recycle up to 900 acre-feet of water per year in Phase One and up to an additional 3,530 acre-feet per year in Phase Two. It is expected to cost $93 million.

To capture federal funding for the project, the City of Pismo Beach submitted a feasibility study to the Bureau of Reclamation’s Title XVI WIIN Act Program that was approved in 2018. Since then, the City was awarded $796,094 in FY 2018, $1.7 million in FY 2021, and $14,124,000 in FY 2022 from the Bureau’s Title XVI program for Central Coast Blue. The City and the Central Coast Blue Regional Recycled Water Authority intend to submit for a final round of funding from the program in December 2023 and would like to reach the maximum 25 percent federal contribution, or $23 million in federal funding. The project has also received $24 million in funding from the state of California and may utilize an EPA WIFIA loan for the remaining non-federal portion of the project.

The latest Notice of Funding Opportunity (NOFO) for the Title XVI program will be used to allocate up to $179 million in available funding from the Bipartisan Infrastructure Law plus a portion of $60 million provided by Congress in the Fiscal Year 2023 Interior Appropriations bill, for a total of up to $239 million. Up to 30 awards are anticipated to be provided because of this NOFO.

POSITION: Support continued full funding of the Bureau of Reclamation’s Title XVI Program. Support City efforts to secure federal funding for the Central Coast Blue project as well as other infrastructure projects while federal agencies implement the Bipartisan Infrastructure Law.

12.D-9Council Agenda 12-5-2023
Attachment 1.B
Packet Page 531

FEDERAL ISSUE: Energy Issues
BACKGROUND:

Oil & Gas Exploration
For many years, the federal government has developed five-year Outer Continental Shelf (OCS) Oil and Gas Leasing programs to guide energy exploration activities in federal waters. The last two OCS Oil and Gas Leasing programs for 2012-2022 do not include new oil or gas leasing sales off the coasts of California, Oregon, and Washington. This was due in part to consistent efforts by the governors of the states to express opposition to oil and gas development off the coast of their states.

However, in 2018, the Bureau of Ocean Energy Management (BOEM) released a draft proposed program (DPP) for the National Outer Continental Shelf Oil and Gas Leasing Program for 2019-2024. The DPP included 47 potential lease sales in 25 of the 26 planning areas, including the Pacific Coast, regardless of previous efforts to keep certain areas free from drilling. The City commented in opposition to the DPP, particularly in opposition to the two leases in the Southern California region, which includes the water off the shores of Pismo Beach.

Offshore Wind Development
In late 2021, BOEM announced the designation of the Morro Bay Wind Energy Area (WEA). The Morro Bay WEA is located approximately 20 miles offshore the central California coastline and comprises approximately 240,898 acres (376 square miles).

Then, in late 2022, BOEM announced results from their wind energy auction for five leases offshore California, drawing competitive high bids from 5 companies covering 373,268 total acres off central and northern California. BOEM claims the leased areas have the potential to produce over 4.6 gigawatts of offshore wind energy, enough to power over 1.5 million homes.

Diablo Canyon Nuclear Power Plant
The Diablo Canyon Nuclear Power Plant was planned to close in 2025 under a 2016 agreement1 between Pacific Gas and Electric (PG&E), then-Governor Jerry Brown, labor unions representing plant workers, and environmentalists who objected to the plant's location near an earthquake fault line, the potential for dangerous accidents and the problem of what to do with radioactive waste. More recently, Governor Newsom and the California legislature extended the plant's life span to 20302 to stave off blackouts while the state pursues its goal of a carbon-free grid by 2045. In November 2023, PG&E officially requested federal permission from the Nuclear Regulatory Commission (NRC) to keep the Diablo Canyon plant open for 20 more years. The NRC’s evaluation of the request will likely take years to complete and will include opportunities for public comment.

POSITION: Oppose the expansion of offshore oil and gas exploration in California’s federal waters.

Support the development of offshore wind energy off the coast of California. Support the continued operation of the Diablo Canyon Nuclear Power Plant.
1 https://subscriber.politicopro.com/article/eenews/2016/12/09/anti-nuclear-movement-set-its-sight-on-calif- closures-066637
2 https://subscriber.politicopro.com/article/2022/09/newsom-signs-california-nuclear-power-plant-extension-into- law-00054758

12.D-10Council Agenda 12-5-2023
Attachment 1.B
Packet Page 532

← All documents from this meeting