Capital Improvement Program Semi-
Annual Report
Agenda Item 12.A
By: Benjamin A. Fine, P.E.

Director of Public Works/City Engineer
Meeting Date: March 5, 2024

Investing in Pismo Beach
•Capital Projects
•Maintenance of existing facilities/assets
•Investing in future needs

Projects Under Construction

Paving Project
•Contract awarded –April 19, 2022 ($10.5M/$14.5M)
•Construction commenced –May 2022
•Current Work
•Wadsworth
•Vista del Mar
•Boeker
•Upcoming Work
•Paving of City Hall Parking Lot
•Price Street
6 Paving Project
•Completed
7 Paving Project
•Completed
8 Chumash and Palisades Park
•Contract awarded –July 18, 2023
•Construction commenced –September 11, 2023
•Ribbon Cutting –Pending weather
9 Chapman Estate ADA Restroom
Create ADA restroom at Chapman Estate
•Contract awarded –January 2023
•Construction commenced –May 2023
•Significant change orders
•Sewer work
•Building structural Improvements
•Estimated completion date –February 2024
•Pool leak and necessary repair
•Demolition of pool -$380,000 to $450,000
•Save the pool -$850,000
•Staff recommends working with a consultant to develop engineering options to determine scope and cost

James Way Beautification Project
•Contract awarded –September 5, 2023
•Construction began –November 2023
•Anticipated completion –End of Summer 2024
11 Wastewater Treatment Plant Improvements
•Completed Items
•Belt Filter Press Rehab
•Dissolved Air Flotation Tank
•Digester #2 repairs
•Clarifier rehab –Bid Summer 2024
•Cleaning of oxidation ditches –Spring 2024
•Demolition of Digester #1 –Bid Spring 2024
•Construction of new 60’x60’ steel building
•Pending demolition of digester #1
•Repaving of Corp Yard
•Pending completion of Public Safety Facility

Parking and Police Annex Building
•Advertised for bids September 14, 2023
•Award of contract –October 3, 2023
•Completion –Fall 2024

Projects Under Design

Paving Needs
•5 Year Plan to maintain and
improve the City’s Streets (PCI)

How are Projects Selected
•Pavement Management Plan
•Pavement Condition Index (PCI) Score
•Adjacency (reduce mobilization cost)
•Available Budget
•Currently about $2M a year
•Funds sunset April 2027
•About $6M total through 2027
•Coordinate other capital projects (utilities)

Year 1 (Phase 1)
Year 3 Streets Included in Year 1 Year 4 Streets Included in Year 1

Phase 1
Year 5 Streets Included in Year 1

Water Issues
•Esparto to Palisade

What’s Left?
Phase 2
•*Esparto $605,000
•Morro $250,000
•*Placentia $262,000
•Vista del Mar $274,000
•Wawona $354,000
•*Windward $365,000
•TOTAL $2,110,000
* Observed water issues

What’s Left
Phase 3
•Palomar $21,000
•*Leeward $27,000
•*Pier $85,000
•*Palisade $105,000
•*Seaview $105,000
•Cliff $16,000
•*Pearl $76,000
•*Water $20,000
•*Ocean $19,000
•(Windward to Cliff)
•TOTAL $474,000 * Observed water issues

What’s Left
Phase 3
•Bello $432,000
•Ocean View $59,000
•Stimson $42,000
•Dell $117,000
•Total $650,000

What’s Left
Phase 3
•El Portal $42,000
•Indio $78,000
•Encanto $2,000
•Topaz $3,000
•Florin $26,000
•Hermosa $24,000
•Total $175,000

What’s Left
Phase 4 •Searidge $172,000
•Beachcomber $41,000
•Silver Shoals $18,000
•Ebb Tide $81,000
•Boeker $347,000
•Pismo $21,000
•Main $154,000
•Tulare $243,000
•Visalia $257,000
•Stratford $88,000
•Total $1,423,000

What’s Left
•Phase 5

What’s Left
Phase 5 •Cypress $56,000•Porterville $19,000•Taft $67,000•Hanford $152,000•Lemoore $282,000•Selma $30,000•Stimson $127,000•Baker $17,000•Coburn $27,000•Naomi $18,000•Paddock $16,000•Ruby $4,000•Seacliff $39,000•Solano $24,000•Spyglass $26,000•Stimson $5,000 •Total $909,000

Paving Cost Summary (2024 dollars)
Phase II $2,110,000
Phase III $1,299,000
Phase IV $1,423,000
Phase V $909,000
Total $5,741,000
*Shell Beach Drainage Improvements $5,000,000
Total $10,741,000
*Assumes $500,000 per street, actual cost pending drainage study and design (due 3/28/24)

Central Coast Blue
•Final design and permitting efforts are ongoing
•Design of AWPF –90%
•EIR Addendum adopted September 2023
•Applications for UPRR crossing submitted
•Second joint meeting of the three City Councils and JPA •June 5, 2023
•Management Team and TAC continue to meet monthly
29 Public Safety Center
•Anticipated construction –May 2024
30 New Groundwater Production Well
•Contract awarded for design February 7, 2023
•Construction with Central Coast Blue-This will be
advanced

Bello St/Wadsworth Ave Water Line
•Design contract awarded January 16, 2024

•Toucan Terrace Sewer Trestle Rehabilitation (3/19/24 award) •Projects Preparing Bid Documents
•Pier Avenue Stairs Removal
•Hinds/Oceanview Pedestrian Path
•Bello and Price Canyon Road Signal
•Addie Street Restroom Replacement
•PRBC –Public Art Recommendations –Done
•Planning Commission
•State Lands
•Cliff Ave/Ocean Blvd Storm Drain Repair
•60% design plans
•Right of Way Phase –subsurface easement obtained from adjacent private property owner. Working with PG&E for utility pole relocation •FHWA time extension pending
Other Projects

Projects On Hold

Ventana Tennis Courts Project
•Design contract awarded –May 17, 2022
•Authorization to bid –February 21, 2023
•Project on hold –pending funding
35 Charles Street and Bello Street Reservoirs
•Replace Charles Street Reservoir
•Construct a new roof over Bello Street Reservoir
•On hold pending staffing

•Shell Beach Pickle Ball Parking Lot –Conceptual options prepared
•Chapman Estate Window Replacement and other
improvements
•Bello Bridge Trail Continuation
Other Projects

Questions
CIP Update