PISMO BEACH CITY COUNCIL STAFF REPORT
Agenda Item #9.F
Meeting Date: June 4, 2024
TITLE:
Authorization for Change Order #4 with Jack Handley Construction and Notice of Completion for the Chapman Estate ADA Restroom Remodel and Addition Project RECOMMENDATION:
1. Adopt a Resolution authorizing the City Manager to execute Change Order #4 with Jack Handley Construction Services in the amount of $252,033.26 and appropriating related budget adjustments;
2. Accept the Chapman Estate ADA Restroom Remodel and Addition Project as complete;
3. Authorize the City Manager to sign, and the City Clerk to record, a Notice of Completion for the project.
DISCUSSION:
On January 17, 2023, the City Council awarded a contract to Jack Handley Construction Services (Jack Handley) for the construction of an ADA Restroom at the Chapman Estate.
Over the course of construction, several issues arose increasing the scope of work. On May 15, 2023 Change Order #1 was executed under the City Manager’s Authority with Jack Handley adding 40 working days to the contract time due to an extended lead time on obtaining doors and floor tiles. On August 1, 2023, Council authorized Change Order #2 to address three existing gas lines that were leaking and needed to be repaired or abandoned, the replacement of the sewer line, and dry rot repairs. This work was to be completed on a time-and-material basis. On April 19, 2024, Change Order #3 was executed under the City Manager’s authority to address the cost of the gas leak investigation, sewer lines investigation, concrete flatwork, a new furnace, and drywall not covered by Change Order #2.
Additional was work was completed by Jack Handley under a work directive on a time and material basis to install the sewer lateral, electrical service improvements, plumbing, new awning, wall painting, window floor tiles, roof penetrations and wall insulation.
Construction of the project is now complete, and the contractor has provided their documentation of the actual cost of the added work. The total cost of the proposed Change Order #4 is $252,033.26. This will bring the total construction contract amount to $745,394.41.
Conclusion and Recommendation
Staff recommends the Council adopt a Resolution (Attachment 1) authorizing the City Manager to execute Change Order #4 (Attachment 1.A) to the existing Jack Handley construction contract. Jack Handley has completed the contracted services, and the Chapman Estate ADA Restroom Remodel and Addition Project has been completed in Council Agenda 6-4-2024 9.F-1
accordance with the plans, specifications, and contract documents. Staff also recommends that the City Council accept the project as complete and authorize the Notice of Completion (Attachment 2) to be recorded at the County Clerk’s office.
FISCAL IMPACT:
The fiscal impact of adopting the attached Resolution and approving Change Order #4 is an additional $252,033.26 from the Chapman Estate Fund. The current Fiscal Year 2024 budget is $856,670.48 in the Chapman Estate Fund of which $637,683.65 has been spent or encumbered for the ADA Restroom Remodel and the Addition project. The budget also included funds for the window replacement at the Chapman Estate. Because the windows are no longer being donated, that part of the project is not moving forward and those funds are available to support the ADA Restroom Remodel and Addition project.
Based on the remaining available budget of $226,961.82, an additional $252,033.26 for Change Order #4 will exceed the budget by $25,071.44. In order to close the shortfall, due to projected operating cost savings in the Chapman Estate Fund, staff recommends decreasing the General Fund transfer to the Chapman Estate Fund for operations by $25,072 and increasing the General Fund transfer to the Chapman Estate ADA Restroom Remodel and Addition project by $25,072, for a net fiscal impact across all funds of $0.
The following table illustrates the FY 2024 available budget for Chapman Estate Improvements, the proposed Jack Handley Change Order #4, the budget shortfall, proposed General Fund transfer, and the remaining budget surplus.
Project Funding
FY 2024 Available Budget for Chapman Improvements $226,961.82 Proposed FY 2024 Costs
Proposed Jack Handley Change Order #4 $252,033.26
Budget Surplus/ (Shortfall) $(25,071.44)
General Fund transfer $25,072.00
Remaining Budget Surplus (Shortfall) $0.56
ATTACHMENTS:
1. Resolution
1.A Exhibit A to Resolution: Proposed Jack Handley Change Order #4
2. Notice of Completion
Prepared by:
Erin Olsen, Senior Management Analyst
Submitted by: Benjamin A. Fine, P.E., Director of Public Works/City Engineer City Manager Approval:
Council Agenda 6-4-2024 9.F-2
RESOLUTION NO. R-2024-XXX
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH,
CALIFORNIA AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER #4 WITH JACK HANDLEY CONSTRUCTION SERVICES IN THE AMOUNT OF $252,033.26 AND APPROPRIATING RELATED BUDGET ADJUSTMENTS WHEREAS, on January 17, 2023 the City Council awarded a contract to Jack Handley Construction Services (Jack Handley) for the construction of an ADA Restroom at the Chapman Estate; and
WHEREAS, over the course of construction, several issues arose increasing the scope of work resulting in Change Order #1 (issued May 15, 2023 under the City Manager’s Authority); Change Order #2 (issued August 1, 2023 by the City Council); and Change Order #3 (issued on April 19, 2023 under the City Manager’s authority); and WHEREAS, additional was work was completed by Jack Handley under a work directive on a time and material basis to install the sewer lateral, electrical service improvements, plumbing, new awning, wall painting, window floor tiles, roof penetrations and wall insulation; and
WHEREAS, construction of the project is now complete, and the contractor has provided their documentation of the actual cost of the added work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby authorizes the City Manager to execute Change Order #4 (Exhibit A) with Jack Handley Construction Services in the amount of $252,033.26.
BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby appropriates an additional $25,072 in the Chapman Estate Fund Chapman House Improvements project capital outlay-building account, appropriate an additional $25,072 transfer from the General Fund to the Chapman Estate Fund, and de-appropriate $25,072 of the General Fund operating transfer to the Chapman Estate Fund, all in Fiscal Year 2024.
UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 4th day of June 2024, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
RECUSED:
Council Agenda 6-4-2024 9.F-3
Attachment 1
Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of Pismo Beach, California, on _______________________. ________________________
Erica Inderlied, City Clerk
Council Agenda 6-4-2024 9.F-4
Attachment 1
No 4
Project:
Date of Issuance
Contractor:
floor tile, roof penetrations, wall insulation, and general requirements Change in Contract Price
Original Contract Price:
$80 days
No.1 to No.1 to
No.3 No.3
$40 Days
Contract Time Prior to this Change Order:
$120 days
Net change of this Change Order:
$64 days
$184 days
Recommended:
by
Recommended:
by
Daniel Contreras
Capital Projects Manager
Approved:Approved:Approved:
Benjamin A. Fine, P.E.Jorge E. Garcia Contractor
Director of Public Works/City Manager
City Engineer
CHANGE ORDER
(Instructions Follow)
Jack Handley Construction
Chapman Estate ADA Bathroom Project
You are directed to make the following changes in the Contract Documents.
Description:Additional Extra Work at the Direction of Engineer Purpose of Change Order:Increase budget for extra work at direction of City Engineer for additional sewer lateral installation, electrical service improvements, plumbing, new awning, wall painting, window Attachments: (List documents supporting change)
Change in Contract Time:
327,950.00 Original Contract Time:
Previous Change Orders:Previous Change Orders:
Contract Time with all approved Change Orders:
745,394.41
The amount and time provided in this contract change order are a full and final accord and satisfaction of all costs and time directly and indirectly related and all other claims related hereto are herby waived. The Contractor has reviewed the plans and specifications related to this change order and all changes thereto are accounted for in the attachment labeled "Attachment A". 165,411.15
Contract Price Prior to this Change Order
493,361.15
Net increase (decrease) of this Change Order
252,033.26
Contract Price with all approved Change Orders
Council Agenda 6-4-2024 9.F-5
Attachment 1.A
No 5.2
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install Sewer Lateral to Sewer Main
Verify that sewer system is intact and serviceable
Attachments: (List documents supporting change)
$139,840.21 11 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be exceeded
without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded without
further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Excavate and install 4" sewer lateral, pave pipe trench in street, and restore landscaping from 11/13 to 12/27 Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other _______________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-6
Attachment 1.A
No 10 rev 2
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Extend general requirements contract bid item No. 1
This WD will provide for additional cost under general requirements which includes support from home office and project management to cover the contract time extension for one month Basis for supporting change: The schedule of values for General Requirements is $37,850 for a four month project duration. The monthly value $9,462.50 n/a days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
is $37,850/4 months = $9462.5/month. With a one month extension, the total is $9,463.50. (Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:The contractor's schedule of values has general requirements at 37,850 for a four month project duration If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other _______________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-7
Attachment 1.A
No 12
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install Building Wall Insulation
Because of a changed site condition, water intrusion and mold was discovered after the demolition of interior sheet rock. New wall insulation is required to meet title 24 energy requirements.
Attachments: (List documents supporting change)
$7,561.06 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Install R15 batt insulation in exterior wall cavities If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other: Lowest quote
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-8
Attachment 1.A
No 14
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install flashing at roof penetrations.
The project plans did not show the roof penetrations and related details.
Attachments: (List documents supporting change)
$4,622.95 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:At exhaust vents, bathroom sanitary vents, and heater vent, provide metal flashing at roof penetrations If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-9
Attachment 1.A
No 15
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install water heater and additional ceiling support
and access to heater.
The project plans did not provide for a water heater to serve the kitchen and bathrooms.
Attachments: (List documents supporting change)
$9,172.53 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Water heater for kitchen and bathroom is relocated in drop ceiling above kitchen.
If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-10
Attachment 1.A
No 16
Project:
Date of Issuance
Contractor:Jack Hanley Consruction
Install interior floor tile.
was needed.
Match floor tile pattern and look between the house and the new addition.
Attachments: (List documents supporting change)
$3,977.54 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Floor tile layout was not included in the project plans. To match the house tile pattern, additional tile Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-11
Attachment 1.A
No 17
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Upgrade electrical service to remodel area
and new service for electric water heaters in bathrooms and kitchen
electrical service panel.
Changed design from gas to electrical for heating water.
Attachments: (List documents supporting change)
$31,407.59 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Provide 50 amp service panel, service run from existing house panel, provide additional wire runs to new Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-12
Attachment 1.A
No 18
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new gas lateral run for new FAU heater
and ADA compliant bathroom and kitchen sinks.
Provide ADA compliant dishwasher.
ADA compliant dish washer and kitchen sink. Changed condition for plumbing drain/waste lines routes.
Gas lateral needed for FAU operation and use. Plumbing fixtures and appliances needed for Building Code compliance. Plumbing line routes needed for proper operation.
Attachments: (List documents supporting change)
$13,765.85 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Install gas service line from basement area to remodel area and mount new bathroom sinks and If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-13
Attachment 1.A
No 19
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new awning at exterior S.W. bldg corner
The existing awning conflicts with the new door operation. The new awning will be raised to clear the conflict.
Attachments: (List documents supporting change)
$12,933.96 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Remove existing awning and construct new awning.
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-14
Attachment 1.A
No 20
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide additional interior painting
Additional sheet rock demolition was necessary for the roof leak damage and mold remediation.
Attachments: (List documents supporting change)
$7,713.85 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based Theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Paint interior wall in remodel area and adjacent dining room Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-15
Attachment 1.A
No 21
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new window over kitchen sink
New window will match the other windows and doors in the remodeled area Attachments: (List documents supporting change)
$11,575.22 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title:Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based Theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Remove and replace window and patch and paint stucco.
If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Other:____________________________
DocuSign Envelope ID: A05E810E-A0F2-4B34-A154-4FA235D08514 Council Agenda 6-4-2024 9.F-16
Attachment 1.A
RECORDING REQUESTED BY:
WHEN RECORDED, RETURN TO:
CITY CLERK
CITY OF PISMO BEACH
760 MATTIE ROAD
PISMO BEACH, CA 93449
NO TRANSFERORS
This document is recorded for the benefit of the City of Pismo Beach, a Municipal Corporation, and is exempt from fee per Government Code Section 27383.
NOTICE OF COMPLETION AND ACCEPTANCE
FOR CHAPMAN ESTATE ADA RESTROOM REMODEL AND ADDITION PROJECT NOTICE IS HEREBY GIVEN by the City of Pismo Beach in the County of San Luis Obispo, State of California, as follows:
1.That on the 4th of June 2024, the project hereunder described was considered completed and accepted by the City Council of the City of Pismo Beach.
2.That the description of said project is the construction of Chapman Estate ADA Restroom Remodel and Addition Project, for the City of Pismo Beach.
3.That the name of the political subdivision controlling said project, and the owner of the land upon which the project was constructed, is the City of Pismo Beach, in the County of San Luis Obispo, State of California, whose address is 760 Mattie Road, Pismo Beach, CA 93449.
4.That the name of the owner/contractor on said project is Jack Handley Construction Services, Inc., 2741 McMillian Road, Building A, Unit 1, San Luis Obispo, CA 93401.
5.The name of the Surety on the project is The Ohio Casualty Insurance Company, 790 The City Drive South, Suite 200, Orange, CA 92868.
I certify (or declare) under penalty of perjury that the foregoing is true and correct.
Date:
Jorge E. Garcia, City Manager
Attest:
Erica Inderlied, City Clerk