RESOLUTION NO. R-2024-035
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH,
CALIFORNIA AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER #4 WITH JACK HANDLEY CONSTRUCTION SERVICES IN THE AMOUNT OF $252,033.26 AND APPROPRIATING RELATED BUDGET ADJUSTMENTS WHEREAS, on January 17, 2023 the City Council awarded a contract to Jack Handley Construction Services (Jack Handley) for the construction of an ADA Restroom at the Chapman Estate; and
WHEREAS, over the course of construction, several issues arose increasing the scope of work resulting in Change Order #1 (issued May 15, 2023 under the City Manager’s Authority); Change Order #2 (issued August 1, 2023 by the City Council); and Change Order #3 (issued on April 19, 2023 under the City Manager’s authority); and WHEREAS, additional was work was completed by Jack Handley under a work directive on a time and material basis to install the sewer lateral, electrical service improvements, plumbing, new awning, wall painting, window floor tiles, roof penetrations and wall insulation; and
WHEREAS, construction of the project is now complete, and the contractor has provided their documentation of the actual cost of the added work.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby authorizes the City Manager to execute Change Order #4 (Exhibit A) with Jack Handley Construction Services in the amount of $252,033.26.
BE IT FURTHER RESOLVED that the City Council of the City of Pismo Beach hereby appropriates an additional $25,072 in the Chapman Estate Fund Chapman House Improvements project capital outlay-building account, appropriate an additional $25,072 transfer from the General Fund to the Chapman Estate Fund, and de-appropriate $25,072 of the General Fund operating transfer to the Chapman Estate Fund, all in Fiscal Year 2024.
UPON MOTION OF Council Member Newton, seconded by Mayor Pro Tem Reiss, the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 4th day of June 2024, by the following vote:
AYES: 5 Newton, Reiss, Inman, Guthrie, Waage
NOES: 0
ABSENT: 0
ABSTAIN: 0
RECUSED: 0
PAGE 1 OF 8
R-2024-035
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
Approved: Attest:
________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of Pismo Beach, California, on _______________________. ________________________
Erica Inderlied, City Clerk
PAGE 2 OF 8
R-2024-035
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A 6/6/2024
No 4
Project:
Date of Issuance
Contractor:
floor tile, roof penetrations, wall insulation, and general requirements Change in Contract Price
Original Contract Price:
$80 days
No.1 to No. 1 to
No.3 No. 3
$40 Days
Contract Time Prior to this Change Order:
$120 days
Net change of this Change Order:
$64 days
$184 days
Recommended:
by
Recommended:
by
Daniel Contreras
Capital Projects Manager
Approved: Approved: Approved:
Benjamin A. Fine, P.E. Jorge E. Garcia Contractor
Director of Public Works/ City Manager
City Engineer
CHANGE ORDER
(Instructions Follow)
Jack Handley Construction
Chapman Estate ADA Bathroom Project
You are directed to make the following changes in the Contract Documents.
Description:Additional Extra Work at the Direction of Engineer Purpose of Change Order:Increase budget for extra work at direction of City Engineer for additional sewer lateral installation, electrical service improvements, plumbing, new awning, wall painting, window Attachments: (List documents supporting change)
Change in Contract Time:
327,950.00 Original Contract Time:
Previous Change Orders:Previous Change Orders:
Contract Time with all approved Change Orders:
745,394.41
The amount and time provided in this contract change order are a full and final accord and satisfaction of all costs and time directly and indirectly related and all other claims related hereto are herby waived. The Contractor has reviewed the plans and specifications related to this change order and all changes thereto are accounted for in the attachment labeled "Attachment A". 165,411.15
Contract Price Prior to this Change Order
493,361.15
Net increase (decrease) of this Change Order
252,033.26
Contract Price with all approved Change Orders
No 5.2
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install Sewer Lateral to Sewer Main
Verify that sewer system is intact and serviceable
Attachments: (List documents supporting change)
$139,840.21 11 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be exceeded
without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded without
further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Excavate and install 4" sewer lateral, pave pipe trench in street, and restore landscaping from 11/13 to 12/27 Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other _______________________________
PAGE 3 OF 8
R-2024-035
Exhibit A
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
No 10 rev 2
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Extend general requirements contract bid item No. 1
This WD will provide for additional cost under general requirements which includes support from home office and project management to cover the contract time extension for one month Basis for supporting change: The schedule of values for General Requirements is $37,850 for a four month project duration. The monthly v $9,462.50 n/a days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
is $37,850/4 months = $9462.5/month. With a one month extension, the total is $9,463.50. (Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:The contractor's schedule of values has general requirements at 37,850 for a four month project duration If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other _______________________________
No 12
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install Building Wall Insulation
Because of a changed site condition, water intrusion and mold was discovered after the demolition of interior sheet rock. New wall insulation is required to meet title 24 energy requirements.
Attachments: (List documents supporting change)
$7,561.06 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Install R15 batt insulation in exterior wall cavities If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other: Lowest quote
PAGE 4 OF 8
R-2024-035
Exhibit A
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
No 14
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install flashing at roof penetrations.
The project plans did not show the roof penetrations and related details.
Attachments: (List documents supporting change)
$4,622.95 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:At exhaust vents, bathroom sanitary vents, and heater vent, provide metal flashing at roof penetrations If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
No 15
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Install water heater and additional ceiling support
and access to heater.
The project plans did not provide for a water heater to serve the kitchen and bathrooms.
Attachments: (List documents supporting change)
$9,172.53 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Water heater for kitchen and bathroom is relocated in drop ceiling above kitchen.
If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
PAGE 5 OF 8
R-2024-035
Exhibit A
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
No 16
Project:
Date of Issuance
Contractor:Jack Hanley Consruction
Install interior floor tile.
was needed.
Match floor tile pattern and look between the house and the new addition.
Attachments: (List documents supporting change)
$3,977.54 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Floor tile layout was not included in the project plans. To match the house tile pattern, additional tile Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
No 17
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Upgrade electrical service to remodel area
and new service for electric water heaters in bathrooms and kitchen
electrical service panel.
Changed design from gas to electrical for heating water.
Attachments: (List documents supporting change)
$31,407.59 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Provide 50 amp service panel, service run from existing house panel, provide additional wire runs to new Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
PAGE 6 OF 8
R-2024-035
Exhibit A
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
No 18
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new gas lateral run for new FAU heater
and ADA compliant bathroom and kitchen sinks.
Provide ADA compliant dishwasher.
ADA compliant dish washer and kitchen sink. Changed condition for plumbing drain/waste lines routes.
Gas lateral needed for FAU operation and use. Plumbing fixtures and appliances needed for Building Code compliance. Plumbing line routes needed for proper operation.
Attachments: (List documents supporting change)
$13,765.85 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Install gas service line from basement area to remodel area and mount new bathroom sinks and If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
No 19
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new awning at exterior S.W. bldg corner
The existing awning conflicts with the new door operation. The new awning will be raised to clear the conflict.
Attachments: (List documents supporting change)
$12,933.96 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Remove existing awning and construct new awning.
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
PAGE 7 OF 8
R-2024-035
Exhibit A
DocuSign Envelope ID: 76857713-E629-4D2B-A169-C66E228A086A
No 20
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide additional interior painting
Additional sheet rock demolition was necessary for the roof leak damage and mold remediation.
Attachments: (List documents supporting change)
$7,713.85 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based Theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Paint interior wall in remodel area and adjacent dining room Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
No 21
Project:
Date of Issuance
Contractor:Jack Hanley Construction
Provide new window over kitchen sink
New window will match the other windows and doors in the remodeled area Attachments: (List documents supporting change)
$11,575.22 4 days
Recommended:Authorized:
by by
Daniel Contreras Benjamin A. Fine, P.E.
Title: Capital Projects Manager City Engineer/Director of Public Works You are directed to make the following change(s):
If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based Theron will involve one of the following methods of determining the effect of the change(s).
Purpose of Work Directive Change:
WORK DIRECTIVE CHANGE
Contractor's T& M work sheet
(Instructions Follow)
Chapman Estates ADA Restroom Remodel & Addition
May 13, 2024
Description:Remove and replace window and patch and paint stucco.
If the change involves an increase, the
estimated amount is not to be
exceeded without further authorization.
If the change involves an increase, the
estimated time is not to be exceeded
without further authorization.
Method of determining
change in Contract Price:
Method of determining
change in Contract Time
Estimated increase
(decrease) in Contract Price
Estimated increase
(decrease) in Contract Time
Time and Materials
Unit Prices
Cost plus fixed fee
Other:_____________________________
Engineer's Records
Contractor's Records
Cost p us ed ee
Other:____________________________
PAGE 8 OF 8
R-2024-035
Exhibit A