PISMO BEACH CITY COUNCIL STAF REPOR
Agenda Item #9.G
Meetin Date: Ma 5, 2026

TITLE:

Award of Contract to Water Systems Consulting, Inc. for the 2025 Urban Water Management Plan and Water Master Plan Update

RECOMMENDATION:

Adopt a Resolution authorizing the City Manager to enter into a Professional Services Agreement with Water Systems Consulting, Inc. in an amount not to exceed $221,703 for the 2025 Urban Water Management Plan and Water Master Plan Update.

DISCUSSION:

The City of Pismo Beach has a current population of approximately 7,860 people.

However, as a vacation destination, the number of people served by the water system surges dramatically in the summer and holiday seasons. The City currently serves 1.5 million gallons on an average day.

The City’s water distribution system consists of more than 50 miles of pipeline ranging from 4-inch to 16-inch diameter, eight pressure zones, six booster stations, four turnouts from the Lopez Project, and two groundwater wells. Water storage is provided by eight tanks with capacities ranging from 220,000 gallons to 1 million gallons.

As the distribution system ages and overall growth slows, the City anticipates a shift in capital expenditures from system expansion to asset renewal and replacement. However, changes in growth patterns, increasing density of development and growth of tourism are increasing potential demand on the system. To date, these potential increases in demand have not been fully realized, as the City has actively implemented and will continue to pursue water conservation measures to offset demand associated with growth.

The Urban Water Management Plan (UWMP) and Water Master Plan (WMP) will evaluate the effects of growth, densification, and conservation on the City’s water supply and distribution systems. The UWMP, which is required to be updated every five years, was most recently adopted in 2021 and provides a long-term framework for sustainable water supply and asset management. The WMP, last adopted in 2020, will be updated to ensure that system maintenance and capital improvements are prioritized and implemented efficiently, supporting effective long-range planning and budgeting.

A formal Request for Proposals was issued for professional engineering and planning services for the 2025 UWMP and WMP Update. Two proposals were received on April 16, 2026 and evaluated by a review panel. Water Systems Consulting, Inc. (WSC) was determined to be the most qualified and has been selected to perform the work.

Council Agenda 5-5-2026 9.G-1

Conclusion and Recommendation
Staff recommends the Council adopt a resolution (Attachment 1) authorizing the City Manager to enter into a Professional Services Agreement (Attachment 2) with WSC in an amount not to exceed $221,703 for the 2025 Urban Water Management Plan and Water Master Plan Update.

FISCAL IMPACT:

The fiscal impact of adopting the attached resolution is an additional cost of $221,703.

The Fiscal Year (FY) 2026 Water Enterprise Funds’ WMP professional services account budget includes $250,000 to support the project. The estimated project costs are shown in Table 1 below.

Table 1. FY 2026 Budget and Estimated Project Cost
Item Fiscal Impact
Available Pro ect Bud et $250,000
WSC Contract Cost $221,703
Bud et Surplus / Shortfall $28,297
ATTACHMENTS:

1. Resolution

2. WSC Professional Services Agreement
Prepared by:

Erin Olsen, Senior Management Analyst
Submitted by: Rosemarie Gaglione, PE, Director of Public Works City Manager Approval:

Council Agenda 5-5-2026 9.G-2

RESOLUTION NO. R-2026-XXX

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PISMO BEACH,

CALIFORNIA AUTHORIZING THE CITY MANAGER TO ENTER INTO A

PROFESSIONAL SERVICES AGREEMENT WITH WATER SYSTEMS CONSULTING, INC. IN AN AMOUNT NOT TO EXCEED $221,703 FOR THE 2025 URBAN WATER

MANAGEMENT PLAN AND WATER MASTER PLAN UPDATE
WHEREAS, the City is required to update its Urban Water Management Plan (UWMP) every five years; and
WHEREAS, the UWMP will prepare the City for a long-term strategy to renew existing assets and form an integrated component of the City’s long-term water planning documents; and
WHEREAS, the Water Master Plan (WMP) Update evaluates the water system to identify improvement projects necessary to meet current and future water system requirements; and
WHEREAS, a formal Request for Proposals was issued for professional engineering and planning services for the 2025 UWMP and WMP Update; and WHEREAS, two proposals were received and evaluated by a review panel; and WHEREAS, Water Systems Consulting, Inc. was determined to be the most qualified and has been selected to perform the work.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pismo Beach hereby authorizes the City Manager to enter into a Professional Services Agreement, in substantially the form attached to staff’s report dated May 5, 2026, with Water Systems Consulting, Inc. in an amount not to exceed $221,703 for the 2025 Urban Water Management Plan and Water Master Plan Update
UPON MOTION OF Council Member , seconded by Council Member , the foregoing resolution was adopted by the City Council of the City of Pismo Beach this 5th day of May 2026, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

RECUSED:

Approved: Attest:

Council Agenda 5-5-2026 9.G-3
Attachment 1

________________________ ________________________
Ed Waage, Mayor Erica Inderlied, City Clerk
IN WITNESS WHEREOF, I have hereunto set my hand and official seal of the City of Pismo Beach on _______________________.
________________________
Erica Inderlied, City Clerk
Council Agenda 5-5-2026 9.G-4
Attachment 1

1 of 12
Vendor Agreement (Rev. 3/2024)

CITY OF PISMO BEACH

VENDOR AGREEMENT FOR PROFESSIONAL SERVICES
This Vendor Agreement for Professional Services (“AGREEMENT”) is made and entered into as of the date the AGREEMENT is fully executed by all parties (the “Effective Date”), by and between the City of Pismo Beach, a municipal corporation (“CITY”), and Water Systems Consulting, Inc. (“VENDOR”). In consideration of the mutual covenants and conditions set forth herein, the parties agree as follows:

RECITALS:

CITY wishes to retain the services of an experienced and qualified VENDOR to provide the following services:
2025 Urban Water Management Plan and Water Master Plan Update VENDOR represents and warrants that it is qualified to perform those services.

AGREEMENT:

I. SERVICES TO BE PERFORMED BY VENDOR
VENDOR will provide the services listed in the Scope of Services attached hereto as Exhibit A.

VENDOR warrants that all work and services set forth in the Scope of Services will be performed in a competent, professional and satisfactory manner. Extra work beyond that described in the Scope of Services is not authorized without the express written approval of CITY. VENDOR shall request and receive written approval prior to performing any extra work. Any work beyond that reflected in the approved Scope of Services shall not be compensated by CITY unless prior written approval was provided under this paragraph. To the extent that Exhibit A is a proposal from VENDOR, such proposal is incorporated only for the description of the Scope of Services and no other terms and conditions from any such proposal shall apply to this AGREEMENT unless specifically agreed to by CITY in writing.

II.TERM
Unless earlier terminated in accordance with Section IV below, or unless the Scope of Services are substantially completed, the AGREEMENT will continue in full force and effect from the Effective Date through June 30, 2027. Upon mutual written agreement, the term of this AGREEMENT can be extended annually under the same terms for an additional one (1) year period, or longer as the parties agree in writing.

III.COMPENSATION
A.VENDOR’s Fee
For services rendered pursuant to this AGREEMENT, VENDOR will be paid in accordance with the Compensation Schedule attached hereto as Exhibit B. However, in no event will the total amount of money paid VENDOR, for services initially contemplated by this AGREEMENT and associated expenses, exceed the sum of two hundred twenty-one thousand seven hundred and three dollars ($221,703), unless otherwise first approved in writing by CITY.

Should this AGREEMENT be extended pursuant to Section II, VENDOR’s fee may be IV. TERMINATION OF AGREEMENT
A. CITY may at any time, for any reason, with or without cause, suspend or terminate this AGREEMENT, or any portion hereof, by serving upon VENDOR at least ten (10) days' prior written notice. Upon receipt of said notice, VENDOR shall immediately cease all work under this AGREEMENT, unless the notice provides otherwise. If CITY suspends or terminates a portion of this AGREEMENT, such suspension or termination shall not make void or invalidate the remainder of this AGREEMENT.

B. In the event this AGREEMENT is terminated pursuant to this Section, CITY shall pay to VENDOR the actual value of the work performed up to the time of termination, provided that the work performed is of value to CITY. Upon termination of the AGREEMENT pursuant to this Section, VENDOR will submit an invoice to CITY pursuant to Section III.

V.FORCE MAJEURE
If any party fails to perform its obligations because of strikes, lockouts, labor disputes, embargoes, "acts of God," inability to obtain labor or materials or reasonable substitutes for labor or materials, governmental restrictions, governmental regulations, governmental control, judicial orders, enemy or hostile governmental action, civil commotion, fire or other casualty, or other causes beyond the reasonable control of the party obligated to perform, then that party’s performance shall be excused for a period equal to the period of such cause for failure to perform.

VI. RETENTION OF FUNDS
VENDOR authorizes CITY to deduct from any amount payable to VENDOR (whether or not arising out of this AGREEMENT) any amounts the payment of which may be in dispute or that are necessary to compensate CITY for any losses, costs, liabilities, or damages suffered by CITY, and all amounts for which CITY may be liable to third parties, by reason of VENDOR’s acts or omissions in performing or failing to perform VENDOR’s obligations under this AGREEMENT. In the event that any claim is made by a third party, the amount or validity of which is disputed by VENDOR, or any indebtedness exists that appears to be the basis for a claim of lien, CITY may withhold from any payment due, without liability for interest because of the withholding, an amount sufficient to cover the claim. The failure of CITY to exercise the right to deduct or to withhold will not, however, affect the obligations of VENDOR to insure, indemnify, and protect CITY as elsewhere provided in this AGREEMENT.

Council Agenda 5-5-2026 9.G-5
Attachment 2

3 of 12
Vendor Agreement (Rev. 3/2024)
VII.CITY REPRESENTATIVE
The Engineer is designated as the “City Representative,” authorized to act in its behalf with respect to the work and services specified in this AGREEMENT and to make all decisions in connection with this AGREEMENT. Whenever approval, directions, or other actions are required by CITY under this AGREEMENT, those actions will be taken by CITY Representative, unless otherwise stated. CITY’s City Manager has the right to designate another CITY Representative at any time, by providing notice to VENDOR.

VIII. VENDOR REPRESENTATIVE(S)
The person(s) employed by VENDOR whose name(s) are set forth immediately following the signatures of the parties executing this AGREEMENT are designated as being the representative(s) of VENDOR authorized to act on its behalf with respect to the work specified in this AGREEMENT and make all decisions in connection with this AGREEMENT.

IX. INDEPENDENT CONTRACTOR
VENDOR is, and at all times will remain as to CITY, a wholly independent contractor. Neither CITY nor any of its elected officials, officers, employees or agents will have control over the conduct of VENDOR or any of VENDOR’s employees, except as otherwise set forth in this AGREEMENT and then only as to the results to be accomplished and not the method by which VENDOR provides the Scope of Services. VENDOR may not, at any time or in any manner, represent that it or any of its agents or employees are in any manner agents or employees of CITY.

X.BUSINESS LICENSE
VENDOR must obtain a CITY business license prior to the start of work under this AGREEMENT, unless VENDOR is qualified for an exemption.

XI. OTHER LICENSES AND PERMITS
VENDOR warrants that it has all professional, contracting and other permits and licenses required to undertake the work contemplated by this AGREEMENT.

XII. VENDOR’S ACCOUNTING RECORDS; OTHER PROJECT RECORDS A. VENDOR shall maintain complete and accurate records with respect to sales, costs, expenses, receipts, and other such information required by CITY that relate to the performance of services under this AGREEMENT. VENDOR shall maintain adequate records of services provided in sufficient detail to permit an evaluation of services.

B. All such records shall be maintained in accordance with generally accepted accounting principles and shall be clearly identified and readily accessible. VENDOR shall provide free access to the representatives of CITY or its designees at reasonable times to such books and records; shall give CITY the right to examine and audit said books and records; shall permit CITY to make transcripts or copies therefrom as necessary; and shall allow inspection of all work, data, documents, proceedings, and activities related to this AGREEMENT. Such records, together with supporting documents, shall be maintained for a period of three (3) years after receipt of final payment. Upon completion of, or in the event of termination or suspension of this AGREEMENT, all original documents, designs, drawings, maps, models, computer files, surveys, notes, and other documents prepared in the course of providing the XIII.INDEMNIFICATION
A. Non-design, non-construction Professional Services:

Council Agenda 5-5-2026 9.G-6
Attachment 2

5 of 12
Vendor Agreement (Rev. 3/2024)
C. Design Professional Services:

In the event VENDOR is a "design professional," and the Scope of Services require VENDOR to provide “design professional services” as those phrases are used in Civil Code Section 2782.8, this paragraph shall apply in place of paragraphs A or B. To the fullest extent permitted by law (including, but not limited to California Civil Code Sections 2782 and 2782.8) VENDOR shall indemnify, defend and hold harmless CITY and its elected officials, officers, employees, volunteers and agents (“City Indemnitees”), from and against all claims, damages, injuries, losses, and expenses including costs, attorney fees, expert consultant and expert witness fees arising out of, pertaining to or relating to, the negligence, recklessness or willful misconduct of VENDOR, except to the extent caused by the sole negligence, active negligence or willful misconduct of CITY. Negligence, recklessness or willful misconduct of any subcontractor employed by VENDOR shall be conclusively deemed to be the negligence, recklessness or willful misconduct of VENDOR unless adequately corrected by VENDOR. In the event CITY Indemnitees are made a party to any action, lawsuit, or other adversarial proceeding arising from VENDOR’s performance of this AGREEMENT, VENDOR shall provide a defense to CITY Indemnitees or at CITY’s option, reimburse CITY Indemnitees their costs of defense, including reasonable legal fees, incurred in defense of such claims. In no event shall the cost to defend charged to VENDOR under this paragraph exceed VENDOR’s proportionate percentage of fault. However, notwithstanding the previous sentence, in the event one or more defendants is unable to pay its share of defense costs due to bankruptcy or dissolution of the business, VENDOR shall meet and confer with other parties regarding unpaid defense costs.

D. Payment by CITY is not a condition precedent to enforcement of the indemnities in paragraph A, B, or C. In the event of any dispute between VENDOR and CITY, as to whether liability arises from the active negligence, sole negligence or willful misconduct of CITY or its officers, employees, or agents, VENDOR will be obligated to pay for CITY’s defense until such time as a final judgment has been entered adjudicating CITY as having been actively negligent, solely negligent or as having engaged in willful misconduct. Except as otherwise required by Civil Code Section 2782.8, VENDOR will not be entitled in the absence of such a determination to any reimbursement of defense costs including but not limited to attorney’s fees, expert fees and costs of litigation. The provisions of this Section 13 shall survive completion of VENDOR’s services or the termination of this AGREEMENT.

XIV. NON-LIABILITY OF CITY OFFICERS AND EMPLOYEES

No elected official, officer, employee, or agent of CITY will be personally liable to VENDOR, in the event of any default or breach by CITY or for any amount that may become due to VENDOR.

XV. INSURANCE

A. Without limiting VENDOR’s indemnification of CITY, and prior to commencement of the Scope of Services, VENDOR shall obtain, provide and maintain at its own expense during the term of this AGREEMENT, policies of insurance of the type and amounts described below and in a form that is satisfactory to CITY.

1. General liability insurance. VENDOR shall maintain commercial general liability insurance with coverage at least as broad as Insurance Services Office (ISO) form CG 00 01, in an amount not less than $1,000,000 per occurrence, $2,000,000 general aggregate, for bodily injury, personal injury, and property damage. The policy must include contractual liability that has not been amended. Any endorsement restricting standard ISO “insured contract” language will not be accepted.

Council Agenda 5-5-2026 9.G-7
Attachment 2

7 of 12
Vendor Agreement (Rev. 3/2024)
CITY will withhold amounts sufficient to pay premium from VENDOR payments. In the alternative, CITY may terminate this AGREEMENT as provided in paragraph IV.

5. Acceptable insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance or is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ Rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best’s Key Rating Guide, unless otherwise approved by CITY’s Risk Manager.

6. Waiver of subrogation. All insurance coverage maintained or procured pursuant to this AGREEMENT shall be endorsed to waive subrogation against CITY, its elected or appointed officials, agents, officers, employees, and volunteers or shall specifically allow VENDOR or others providing insurance evidence in compliance with these specifications to waive their right of recovery prior to a loss. VENDOR hereby waives its own right of recovery against CITY, and shall require similar written express waivers and insurance clauses from each of its subconsultants.

7. Enforcement of contract provisions (non-estoppel). VENDOR acknowledges and agrees that any actual or alleged failure on the part of CITY to inform VENDOR of non- compliance with any requirement imposes no additional obligations on CITY nor does it waive any rights hereunder.

8. Requirements not limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance.

Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type. If VENDOR maintains higher limits than the minimums shown above, CITY requires and shall be entitled to coverage for the higher limits maintained by VENDOR. Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to CITY.

9. Notice of cancellation. VENDOR agrees to oblige its insurance agent or broker and insurers to provide to CITY with a thirty (30) day notice of cancellation (except for nonpayment for which a ten (10) day notice is required) or nonrenewal of coverage for each required coverage. In the event VENDOR’s policy of insurance cannot be endorsed to provide this notice of cancellation, VENDOR shall provide CITY notice of such cancellation, in writing, not later than 24 hours following the effective time of such cancellation.

10. Additional insured status. General liability policies shall provide or be endorsed to provide that CITY and its officers, officials, employees, and agents shall be additional insureds under such policies. This provision shall also apply to any excess/umbrella liability policies. Each such insurance policy shall contain language substantially similar to the following clause:
"The City of Pismo Beach, its elected and appointed officials, officers, employees, and agents are named as additional insureds as respects operations of the named insured performed under contract with the City of Pismo Beach." CITY need not be named as an additional insured on professional liability insurance policies.

11. Prohibition of undisclosed coverage limitations. None of the coverages required herein will be in compliance with these requirements if they include any limiting endorsement XVI. SUBCONTRACTORS

Before VENDOR retains or hires a subcontractor to provide any work, labor, or services relative to this AGREEMENT, VENDOR must:

A. Present the name and identifying information of the subcontractor that will provide any work, labor, or services to CITY;

B. Present to CITY the form of subcontract that will be used with the subcontractor for CITY’s approval, which approval will not be unreasonably withheld. Such subcontract agreement must include an indemnity agreement that is generally in accord with the indemnity obligations contained in paragraph XII of this AGREEMENT and must specifically name CITY as an indemnified party; and

C. Secure from the subcontractor evidence of insurance coverage that meets with this AGREEMENT including naming CITY as an additional insured as required by this Council Agenda 5-5-2026 9.G-8
Attachment 2

9 of 12
Vendor Agreement (Rev. 3/2024)
AGREEMENT, unless such requirement is waived in writing by CITY's Risk Manager as provided in paragraph XXV below.

XVII. CONFLICT OF INTEREST

No officer or employee of CITY may have any financial interest, direct or indirect, in this AGREEMENT, nor may any officer or employee participate in any decision relating to the AGREEMENT that affects the officer or employee’s financial interest or the financial interest of any corporation, partnership, or association in which the officer or employee is directly or indirectly interested, in violation of any law, rule or regulation.

No person may offer, give, or agree to give any officer or employee or former officer or employee, nor may any officer or employee solicit, demand, accept, or agree to accept from another person, a gratuity or an offer of employment in connection with any decision, approval, disapproval, recommendation, preparation or any part of a program requirement or a purchase request, influencing the content of any specification or procurement standard, rendering of advice, investigation, auditing, or in any other advisory capacity in any way pertaining to any program requirement, contract or subcontract, or to any solicitation or proposal.

XVIII. NOTICE

All notices, requests, demands, or other communications under this AGREEMENT will be in writing.

Notice will be sufficiently given for all purposes as follows:

A. Personal delivery. When personally delivered to the recipient; notice is effective on delivery.

B. First Class mail. When mailed first class to the last address of the recipient known to the party giving notice; notice is effective three mail delivery days after deposit in a United States Postal Service office or mailbox.

C. Certified mail. When mailed certified mail, return receipt requested; notice is effective on receipt, if delivery is confirmed by a return receipt.

D. Overnight delivery. When delivered by an overnight delivery service, charges prepaid or charged to the sender’s account; notice is effective on delivery, if delivery is confirmed by the delivery service.

E. Facsimile transmission. When sent by fax to the last fax number of the recipient known to the party giving notice; notice is effective on receipt. Any notice given by fax will be deemed received on the next business day if it is received after 5:00 p.m. (recipient’s time) or on a non- business day.

Addresses for purpose of giving notice are as set forth immediately following the signatures of the parties executing this AGREEMENT.

F. Any correctly addressed notice that is refused, unclaimed, or undeliverable because of an act or omission of the party to be notified, will be deemed effective as of the first date the notice was refused, unclaimed or deemed undeliverable by the postal authorities, messenger or overnight delivery service.

XIX. PROHIBITION AGAINST ASSIGNMENT AND SUBCONTRACTING

This AGREEMENT and all exhibits are binding on the heirs, successors, and assigns of the parties.

The AGREEMENT may not be assigned or subcontracted by either CITY or VENDOR without the prior written consent of the other.

XX. INTERPRETATION

The terms of this AGREEMENT shall be construed in accordance with the meaning of the language used and shall not be construed for or against either party by reason of the authorship of this AGREEMENT or any other rule of construction that might otherwise apply.

XXI. SEVERABILITY

If any part of this AGREEMENT is found to be in conflict with applicable laws, that part will be inoperative, null and void insofar as it is in conflict with any applicable laws, but the remainder of the AGREEMENT will remain in full force and effect.

XXII. TIME OF ESSENCE

Time is of the essence in the performance of this AGREEMENT.

XXIII. GOVERNING LAW; JURISDICTION

This AGREEMENT will be administered and interpreted under the laws of the State of California.

Jurisdiction of and venue for any litigation arising from the AGREEMENT will be in the Superior Court of the San Luis Obispo County, or in the United States District Court for the Central District of California.

XXIV. COMPLIANCE WITH STATUTES AND REGULATIONS

VENDOR will be knowledgeable of and will comply with all applicable federal, state, county and city statutes, rules, regulations, ordinances and orders. VENDOR and its subcontractor(s) shall not discriminate against any person in the performance of this AGREEMENT on the basis of race, religion, national origin, color, age, sex, sexual orientation, AIDS, HIV status, disability, or any other basis protected by state or federal law, and shall comply with applicable federal and state equal employment opportunity laws, ordinances, rules and regulations.

XXV. WAIVER OF BREACH

No delay or omission in the exercise of any right or remedy by a nondefaulting party on any default will impair the right or remedy or be construed as a waiver. A party’s consent or approval of any act by the other party requiring the party’s consent or approval will not be deemed to waive or render unnecessary the other party’s consent to or approval of any subsequent act. Any waiver by either party of any default must be in writing and will not be a waiver of any other default concerning the same or any other provision of this AGREEMENT.

Council Agenda 5-5-2026 9.G-9
Attachment 2

11 of 12
Vendor Agreement (Rev. 3/2024)
XXVI. ATTORNEY’S FEES

Except as provided for in paragraph XV, in any dispute, litigation, arbitration, or other proceeding by which one party either seeks to enforce its rights under this AGREEMENT (whether in contract, tort or both) or seeks a declaration of any rights or obligations under this AGREEMENT, the prevailing party will be awarded reasonable attorney’s fees, together with any costs and expenses, to resolve the dispute and to enforce any judgment, including post judgment attorney’s fees costs and expenses and any attorneys’ fees or costs incurred on appeal of any judgment.

XXVII. EXHIBITS

All exhibits identified in this AGREEMENT are incorporated into the AGREEMENT by this reference.

In the event of any conflict between the terms of this AGREEMENT and the terms of an exhibit, the terms of this AGREEMENT shall control. Notwithstanding the foregoing sentence, the provisions of Section XIII of this AGREEMENT shall not be altered, amended, limited or otherwise affected in any manner by any language included in an exhibit to this AGREEMENT, even if such exhibit purports to affect the provisions of Section XIII.

XXVIII. VENDOR’S AUTHORITY TO EXECUTE

The persons executing this AGREEMENT on behalf of the VENDOR warrant that:

A. the VENDOR is duly organized and existing under the appropriate State laws; B. they are duly authorized to execute this AGREEMENT on behalf of the VENDOR; C. by so executing this AGREEMENT, the VENDOR is formally bound to the provisions of this AGREEMENT; and
D. entering into this AGREEMENT does not violate any provision of any other AGREEMENT to which the VENDOR is bound.

XXIX. INTEGRATION; AMENDMENT

This AGREEMENT represents the entire understanding of CITY and VENDOR as to those matters contained in it. No prior oral or written understanding will be of any force or effect with respect to the terms of this AGREEMENT. The AGREEMENT may not be modified or altered except in writing signed by both parties.

IN WITNESS WHEREOF, the parties hereto have caused this AGREEMENT to be executed the day and year last written below.

Signatures begin on next page.

CITY:

ATTEST:

Signed:

Name: Erica Inderlied
Title: City Clerk

APPROVED AS TO FORM:

Signed:

Name: Dean J. Pucci
VENDOR:

Exhibit A: Scope of Service
Exhibit B: Compensation Schedule
Council Agenda 5-5-2026 9.G-10
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 17
Project Scope of Work
Task 1 Project Managementand Coordination
Project and schedule management will be a critical component of this effort to keep the UWMP on track and advance it to completion as efficiently as possible and complete the WMP in a timely manner. As shown in the project schedule, we anticipate completing UWMP tasks concurrently with other project activities to fast-track itsdelivery.

In addition, all project deliverables will be subjected to internal quality control by our QA/QC lead prior to submittal to the City. Our QA/QC lead is responsible for identifying technical issues as well as scope elements that have not been fully addressed.

1.1 Project Administration
x Prepare monthly progress reportssummarizing project status, budget, and schedule updatesto be submitted with each invoice. It is assumed that the project duration is 14 months.
x Provide project administration and management, including invoicing and preparation of monthly progress reports in a format that is acceptable to the City. x Update the project schedule as needed. Maintain a log of the action items and key project decisions made throughout the duration of the project.

1.2 Coordination Meetings
x Project Kickoff: Plan, organize and conduct one kickoff meeting. The purpose of the kickoff meeting will be to:
Establish roles and responsibilities
Review scope, schedule, and deliverables
Review available data and establish data needs
Review UWMP and WMP update requirements and methodology Review public outreach plan
x Monthly Progress Meetings: Plan, organize, and conduct up to 8, one-hour monthly progress meetings with the City. These meetings are assumed to be virtual. x Key Milestone Meetings: Plan, organize, and conduct workshops with the City at key project milestones, anticipated to include:
Draft Water Demand Projections Review Meeting
Draft UWMP Review Meeting
Hydraulic Model Update and Calibration Review Meeting
Draft Capital Improvement Project Review and Phasing Meeting Draft WMP Review Meeting
x Ongoing and as-needed coordination with the City related to the UWMP and WMP Deliverables:
([KLELW$
Understanding and Scope of Work
2025 Water M aster Plan and Urban Water Management Plan Update City of Pismo Beach | 18
(1)Monthly progress reports.
(2)Detailed project schedule.
(3)Meeting agendas provided ahead of each meeting. Meeting summary provided following each meeting.

Assumptions:
(1)Project duration is 14 months.
(2)Kickoff meeting is assumed to be up to two-hours long and will be held in person at the City offices. Regular monthly progress meetings and other milestone meetings are up to one-hour long and will be held virtually.

Task 2 Data Collection and Review
Our project team developed the City’s 2020 UWMP and most recent WMP, and is deeply familiar with the City’s water system, supply portfolio, and planned projects. We will leverage this knowledge to hit the ground running on the UWMP and WMP. Attached to this proposal is a UWMP data request to support the timely completion of the UWMP.

2.1 Data Request
x Prepare a comprehensive data request needed to update the UWMP and WMP.

Update data request log as data is provided.
x Review City provided supporting documents and data.

2.2 Staff Interviews
x Conduct interviews with City operations staff to review system operations, constraints, and operational practices that will need to be considered in the UWMP, WMP, and updated hydraulic model.

Deliverables: Comprehensive data request log.

Assumptions:
(1)An initial UWMP data request is included with this proposal to support the City gathering the required data to fast track its completion. A comprehensive data request for the UWMP and WMP will be provided prior to the Kickoff Meeting. (2)WSC assumes up to four hours for in-person staff interviews.

Task 3 Demand Evaluation and Projections
We propose to update the City’s demand projections by incorporating recent water use trends and projected growth. This effort will begin with development of a baseline demand projection for use in the UWMP, hydraulic model, and WMP analyses. Recognizing the inherent uncertainty in long-term demand forecasting, our scope also includes development of alternative Council Agenda 5-5-2026 9.G-11
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 19
demand scenarios that account for factors such as future densification, alignment with land use, changes in water use patterns driven by conservation, State water use efficiency regulations, and other uncertainties. For example, a comparison of historical demands with future urban water use objective (UWUO) targets is presented in the figure below.

3.1 Planning and Design Criteria
x In coordination with City standards and operational practices and California Waterworks Standards, WSC will update the water system evaluation criteria as needed, including:
Land use and duty factors
Peaking factorsand fire flow requirements
Minimum and maximum operating pressure
Pipeline velocity
Storage volume and production capacity criteria

3.2 Baseline Demand
x Review historic water production data, billing meter data, and existing land uses/zoning to establish land use-based demand factors, average day demand, maximum day demand, peak hour demand, and demand peaking factors.

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 20
x Evaluate non-revenue water using available production and billing dataand AWWA water loss audits. Compare real water losses to the City’s water loss standard mandated by the State. Identify planning-level strategies to reduce system losses. x Develop updated population and demand projections through the 2050 planning horizon in five-year increments for the UWMP and buildout conditions. Demand projections will consider recent water use and conservation trends, current and projected land use based on the City’s General Plan, and State water use efficiency regulations.
x Develop spatially allocated baseline water demands for current, near term, and buildout conditions for loading in the hydraulic model using customer meter and APN data.

3.3 Demand Envelope
x Prepare up to three demand scenarios that consider the uncertainty in the demand projections, based on direction provided by the City. The demand scenarios are anticipated to apply adjustments to the baseline demand projection, and may include:
Adjustments to water demand factors considering water conservation measures and policy and/or customer behavior.
Changes to population growth, buildout densification, and/or Regional Housing Needs Allocation.
Future General Plan updates and potential changes in land use. Adjustment considering factors such as climate change or water rates.

3.4 Evaluation Criteria and Water Demand Projection Memo x WSC will provide a draft memo summarizing evaluation criteria, water demand projections and assumptions, spatial allocation loading for the hydraulic model, alternative demand projections and demand envelope, and proposed peaking factors for review.
x Develop final memo incorporating City comments.

Deliverables: Draft and Final Water Demand Projection Development Memo.

Assumptions: The City will have billing data that can be linked to a geographic location, such as parcel and land use data via APN, address, or meter coordinates.

Task 4 System Condition and Operational Assessment
We will compile condition assessment information from site visits, City staff input and institutional knowledge, previous inspection and condition assessment reports, maintenance records, and other available facility documentation. This information will be used to identify and develop near-term rehabilitation and improvement projects for the major water system facilities and annual rehabilitation and renewal budgets for the system pipelines.

Council Agenda 5-5-2026 9.G-12
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 21
In addition, we will use the updated and calibrated hydraulic model to evaluate existing and future system operations and assess opportunities to improve overall system performance under a range of demand and operational conditions.

4.1 Condition Assessment
x Conduct site visits to the City booster pump station sites with City operational staff to evaluate site condition and configuration. Document condition of the site and pump station components and develop near-term rehabilitation projects for the booster pump stations.
x Review existing storage tank inspection reports and any other task condition data.

Develop near-term rehabilitation projects for the storage tanks. x Review well condition information and incorporate City feedback to develop a rehabilitation project for Well 5, if needed.
x Perform a desktop condition assessment of distribution pipelines considering condition information such as: staff knowledge,age, diameter, material, break history, maintenance records, and expected useful lifetimes based on literature and City experience. Identify areas with reliability concerns that should be addressed. Prepare annual budgets for system replacement and renewal.

4.2 Operational Assessment
x Evaluate the existing system pressure zone configuration and the potential to optimize pressure zone boundaries, improve system water age, and move water between pressure zones to improve system performance.
x Evaluate the pressure zone configuration under buildout conditions and future operations with planned projects (e.g. Central Coast Blue with higher groundwater production). Evaluate the potential to optimize the distribution system under future conditions.
x Identify opportunities to improve operational flexibility, reliability, and overall system performance.

Deliverables:
(1) Draft condition assessment project tables for discussion. (2) Draft operational assessment project maps and tables for discussion.

Assumptions:
(1)Booster pump station site visits can be completed in one day with the project’s Condition Assessment Lead and Project Engineer. City operational staff will facilitate site visits.
(2)Task 4.2 would occur following Task 5 and use the updated hydraulic model.

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 22
Task 5 Hydraulic Model Development and Calibration
We propose to update the City’s existing water system model rather than develop a new model.

The City’s current hydraulic model was developed and calibrated in 2016 using the City’s GIS data and incorporates unique GIS-IDs for system elements. These identifiers allow the model to be efficiently updated using more recent GIS datasets. Updating the existing model, rather than building a new one, will reduce overall project costs while maintaining consistency with prior analyses.

While not specifically listed in the RFP, we recommend updating the model’s extended period simulation (EPS) calibration in addition to steady-state calibration using the hydrant flow test data. The EPS analysis evaluates system performance over time and allows simulation of conditions such as water age and system-wide operational impacts, providing a more comprehensive assessment of system behavior under varying demand and operational scenarios.

We also propose preparing a model development and calibration memorandum to document the model updates and calibration results.

5.1 Update Water Model
x Update the City’s existing hydraulic model using current GIS system mapping. Update the model controls and operation based on staff input collected during Task 2.2. x Load spatially allocated current, near-term, and buildout demands in the updated hydraulic model. Update model demand scenarios using updated demand projections and peaking factors.

5.2 Model Calibration
x Prepare a hydrant flow testing plan to collect data for model calibration. Refine hydrant flow locations based on City feedback and considering drought/conservation requirements. The hydrant flow testing plan will include proposed test locations, including flowing and residual hydrant, procedures, and a data collection sheet. x Calibrate the model under steady-state conditions by evaluating modeled pressures to observed pressures collected during the hydrant flow tests performed by the City.

Make adjustments to pipe roughness factors or minor lossesto achieve acceptable agreement between model results and observed test results. x Recalibrate the City’s EPS scenarios using a week of consecutive SCADA data showing tank levels, and pump, well, and turnout status, flowrates, and discharge pressure (as available). Update modeled pump, well, and turnout controls and adjust the diurnal demand pattern applied in the model to simulate tank cycling similar to observed tank cycling in the distribution system.
x Review calibration results with City staff and make refinements based on City direction as needed.

Council Agenda 5-5-2026 9.G-13
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 23

5.3 Model Update and Calibration Memo
x Document the model update and calibration in a draft technical memorandum. x Incorporate City comments in a final technical memorandum.

Deliverables:
(1)Hydrant flow testing plan and maps.
(2)Draft and Final Model Update and Calibration Technical Memorandum. (3)Updated and calibrated hydraulic model and associated files.

Assumptions:
(1)WSC anticipates 6-8 locations for hydrant flow testing. (2)City staff will conduct the hydrant testing plan and provide measures hydrant static and residual pressure, hydrant flow data, and boundary conditions at the time of the flow test including tank levels, well and turnout operation, and booster pump station status.
(3)Acceptable model calibration tolerance is +/-5 psi from observed pressures during hydrant flow testing.
(4)While not specifically listed in the RFP, WSC scope includes EPS calibration and preparing a model development and calibration memorandum.

Task 6 Performance Evaluation and Capacity Analysis
We will update the system performance and capacity analysis using update demand projections. We anticipate capacity projects identified in the 2020 WMP that have not yet been completed may still be required and will reevaluate the need for these projects and the recommended sizing. We will also leverage the datasets developed during the 2020 WMP and the recently completed Water Storage Analysis in this task.

6.1 Model Existing Conditions
x Analyze system performance under existing conditions by simulating average day, maximum day, peak hour, and maximum day plus fire flow demand. Evaluate system pressures, pipeline velocities, and available fire flow against the updated evaluation criteria developed in Task 3.
x Identify areas of the water distribution system that do not meet the City’s criteria and develop operational and/or capital improvement projects to resolve existing deficiencies.

6.2 Model Future Conditions
x Analyze future system performance under buildout conditions by simulating average day, maximum day, peak hour, and maximum day plus fire flow demand. Evaluate pressures, velocities, and available fire flow against the evaluation criteria.

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 24
x Incorporate planned system modifications and planned infrastructure as necessary to serve future development, as directed by the City, for purposes of planning-level evaluation.
x Identify locations with future capacity constraints and performance limitations.

Develop operational and/or capital improvement projects to resolve future deficiencies.

6.3 Pumping and Storage Analysis
x Evaluate the capacity of existing water system production and pumpingfacilities against current and future demands. Identify production and pumping deficiencies and develop recommendations to improve deficiencies.
x Update the water system storage volume for the system under current and projected demands and comparethe required storageto the current storage volume. WSC will develop recommendations to improve storage deficiencies.

Deliverables:
(1)Draft capacity assessment project maps and tables for discussion.

Task 7 Capital Improvement Plan
WSC will compile recommended projects to develop a prioritized 30-year capital improvement plan (CIP) with short, medium, and long term projects identified. The CIP will address system capacity, conditions, and reliability improvements. We will develop project costs using recent local bids for similar project and include an appropriate contingency for planning level estimates.

7.1 Develop Capital Improvement Projects
x Develop a comprehensive map and list of capital projects, including project descriptions, that address capacity, risk and reliability, and condition related deficiencies under existing and projected demands.
x Establish criteria for determining the prioritization of the identified projects. Prioritize projects as short, intermediate, and long-term projects.

7.2 Prepare Cost Estimates
x Develop planning-level (AACE Class 4) unit cost figures and estimate costs for capital projectsand annual rehabilitation and renewal budgets.

Deliverables:
(1)Draft CIP map and tablewith project descriptions.
(2)Final CIP map and table with project descriptions.

Assumptions:
(1)Fee estimate assumes up to 30 CIP projects and annual renewable and rehabilitation strategies for short, intermediate, and long-term periods.

Council Agenda 5-5-2026 9.G-14
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 25
Task 8 Water Master Plan Report
WSC will prepare the Water Master Plan Report to summarize the efforts and results for the tasks described herein.

8.1 Administrative Draft Water Master Plan
x WSC will compile the information developed in the previous tasks to develop the Water Master Plan Report. The Water Master Plan findings will align with the UWMP.

8.2 Final Draft Water Master Plan
x WSC will address District comments from the Administrative Draft Report to develop a Final Draft Report.

8.3 Final Water Master Plan Report
x WSC will address City comments from Final Draft Water Master Plan to develop a Final Report.

Deliverables:
(1)Administrative Draft Report in Word and PDF format
(2)Final Draft Report in Word and PDF format
(3)Final Report in PDF format
Assumptions:
(1)The City will provide one set of consolidated comments and edits on the Administrative and Final Draft Reports.

Task 9 2025 UWMP Update
We understand the importance of preparing and submitting a comprehensive, fully compliant UWMP on an expedited schedule. Having led updates to the City’s two most recent UWMPs, and through our ongoing work with the City and the Northern Cities Management Area Technical Advisory Committee, we bring an in-depth understanding of the City’s water supply portfolio. This familiarity allows us to efficiently update the UWMP while ensuring consistency with prior planning efforts and current regulatory requirements. Also, this project team has prepared over 20 UWMPs during the 2025 cycle and will apply lessons learned to effectively and efficiently prepare the City’s 2025 UWMP.

9.1 UWMP Sections Update
x Update Plan Preparationand System Description
Describe the purpose and background of the UWMP; coordination with other agencies and public outreach efforts; and plan adoption and submittal required by the UWMP Act.

Understanding and Scope of Work
2025 Water M aster Plan and Urban Water Management Plan Update City of Pismo Beach | 26
Describe the City’s water distribution system, service area, population and demographics, climate, government structure, and known development projects. x Update System Demands
Update historical water demands based on customer consumption and total production data from 2021 through 2025.
Document SBx7-7 water use compliance based on DWR’s requirements. Conduct a water loss audit consistent with DWR requirementsfor use in the UWMP.
Use baseline water demand projections developed in Task 3.2for use in the UWMP. Develop estimated lower income household demand per UWMP requirements.
Update and provide a narrative description of the demand management measures (DMM) implemented by the City based on any changes to DMM implementation since the 2020 UWMP and DWR requirements.
x System Supplies and Water Shortage Contingency Planning Describe water supply sources, existing and projected supply volumes, potential future water supply options, and future water supply projects. Describe reliability of the City's water supply and projection of the reliability of the water supply through 2050. The description shall include normal water year, single GU\\HDUDQGGURXJKWODVWLQJ¿YH\HDUV
Update the City’s Water Shortage Contingency Plan (WSCP) integrating components from the 2025 UWMP.

Assumptions:
(1)City will provide all required data necessary to update the UWMP. (2)System supply descriptions from the 2025 Northern Cities Management Area Annual Report will be utilized for the UWMP.
(3)The City will provide direction on supply and reliability assumptions given current Lopez Lake litigation and groundwater yield projections. WSC does not anticipate analysis of potential changes to entitlement based on evolving downstream release and storage scenarios.
(4)The WSCP will only require minor updates.

9.2 UWMP Report Update
x Prepare an Administrative Draft UWMP:
Compile work completed in Task 9.1 into the UWMP report following DWR’s 2025 Guidebook.
Compile all appendices into an electronic file in PDF format. Update DWR’s UWMP checklist with relevant sections of the UWMP Perform quality control reviews of deliverable.
Submit to the City for review.

Council Agenda 5-5-2026 9.G-15
Attachment 2

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 27
Deliverables: One (1) electronic copy of the Administrative Draft UWMP.

Assumptions: City will provide one set of consolidated comments within two weeks of delivery of the Administrative Draft UWMP.
x Prepare a Final Draft UWMP:
Incorporate comments and direction from the City provided on the Administrative Draft. Prepare the Final Draft UWMP and compile all appendices into an electronic file.

Deliverables: One (1) electronic copy of the Final Draft UWMP.

Assumptions: City will provide one set of consolidated comments within two weeks of delivery of the Final Draft UWMP.

NOTE: To accelerate the UWMP schedule,the Final Draft UWMP step could be skipped assuming that the City does not have substantial comments on the Admin Draft UWMP. x Prepare aPublic Draft UWMP:
Incorporate comments and direction from theCity provided on the Final Draft.

Prepare the Public Draft UWMP and compile all appendices into an electronic file in PDF format.

Deliverables: One (1) electronic copy of the Final Public Draft UWMP.

Assumptions: The City will print hardcopies of the Public Draft UWMP and keep a copy in its office for public review.
x Prepare a Final UWMP
Review public comments with the City, incorporate selected comments from the Public Draft Hearing, including the public and the City Council. Insert the City Council’s UWMP and WSCP adoption resolution(s). Prepare the Final UWMP and compile all appendices into an electronic file in PDF format. Report in the standardized water use reporting form established by DWR. Prepare and submit an electronic copy of the UWMP to DWR, including any standardized forms, tables, or displays specified by DWR.

Deliverables:
(1) One (1) electronic copy of the Final UWMP to the City, County, surrounding agencies, wholesale suppliers, DWR, and the California State Library.

Assumptions: The UWMP scope assumes two draft UWMPs for internal City Review, a Public Draft UWMP, and a final UWMP consistent with the scope provided in the RFP.

Depending on the of comments the City provides on the Administrative Draft UWMP, we may be able to skip the Final Draft UWMP and develop the Public Draft UWMP to expedite the schedule.

Understanding and Scope of Work
2025 Water Master Plan and Urban Water Management Plan Update City of Pismo Beach | 28
Task 10 Public and Adoption Support
WSC will provide the City support for the UWMP public hearing and adoption and WMP adoptions, including preparation of presentation materials and presenting at the City Council.

10.1 UWMP Presentation Support
x Prepare PowerPoint presentation and materials to support the UWMP Public Hearing and Adoption.
x Attend the public hearing to present the 2025 UWMP to the City Council and answer questions. Addressing City Council and public comments is included in Task 9.2.

10.2 WMP PresentationSupport
x Prepare PowerPoint presentation and materials to support the WMP Adoption meeting.
x Attend the WMP adoption meeting to present the WMP update and findings to the City Council and answer questions.
x Incorporate any revisions based on City Council direction, as needed, in the Final WMP report.

Assumptions: One WSC staff member will attend up totwo City Council meetings:
(1)For the UWMP Public Hearing and Adoption
(2)For the WMP presentation to the City Council.

Optional Task 1 Project Summary Sheets
Optionally, we are including scope to prepare summary sheets for each of the capital projects in the Water Master Plan. These were included in the previous Water Master Plan report.

O1.1 Capital Project Summary Sheets
y Develop one-page capital project summary sheets that summarizes the existing deficiency and need for the project, detailed description of the project, summarized project cost estimate, and individual project map.

Deliverables:
(1)Draft and Final Project Summary Sheets.

Assumptions:
(1)Fee estimate assumes project summary sheets for up to 30 capital projects.

Council Agenda 5-5-2026 9.G-16
Attachment 2

City of Pismo Beach
2025 Urban Water Management Plan and Water Master Plan 4/1ϲ/2026
Pr
i
n
c
i
p
a
l

i
n

Ch
a
r
g
e
QA
/
Q
C
Co
n
d
i
t
i
o
n

As
s
e
s
s
m
e
n
t
L
e
a
d
Pr
o
j
e
c
t

Ma
n
a
g
e
r
UW
M
P

a
n
d

Su
p
p
l
y

Le
a
d
De
m
a
n
d

Le
a
d
En
g
i
n
e
e
r
i
n
g
S
u
p
p
o
r
t
Pr
o
j
e
c
t

Ad
m
i
n
WSC
Labor
Hours
WSC
Labor Fee Expenses Total Fee
Rob
Morrow
Jeroen
Olthof
Michael
Goymerac
Heather
Freed
Michael
Steele
Spencer
Waterman
Cason
Roberts Kay Merrill
Billing rates, $/hr $415 $370 $291 $278 $278 $278 $188 $186 1 Project Management and Coordination

1.1 Project Administration 4 14 16 34 8,528$ -$ 8,528$

1.2 Coordination Meetings 2 1 15 2 1 15 36 8,945$ -$ 8,945$ SUBTOTAL 6 0 1 29 2 1 15 16 70 17,473$ -$ 17,473$ 2 Data Collection and Review

2.1 Data Request 2 4 2 2 16 26 5,814$ -$ 5,814$

2.2 Staff Interviews 6 8 14 3,172$ -$ 3,172$ SUBTOTAL 0 0 2 10 2 2 24 0 40 8,986$ -$ 8,986$ 3 Demand Evaluation and Projections

3.1 Planning and Design Criteria 1 4 5 1,030$ -$ 1,030$

3.2 Baseline Demand 4 16 16 36 8,568$ -$ 8,568$

3.3 Demand Envelope 2 12 16 30 6,900$ -$ 6,900$

3.4 Evaluation Criteria and Water Demand Projection Memo 1 4 10 20 35 8,022$ -$ 8,022$ SUBTOTAL 0 1 0 11 0 38 56 0 106 24,520$ -$ 24,520$ 4 System Condition and Operational Assessment

4.1 Condition Assessment 16 8 32 56 12,896$ -$ 12,896$

4.2 Operational Assessment 16 32 48 10,464$ -$ 10,464$ SUBTOTAL 0 0 16 24 0 0 64 0 104 23,360$ -$ 23,360$ 5 Hydraulic Model Development and Calibration

5.1 Update Water Model 6 24 30 6,180$ -$ 6,180$

5.2 Model Calibration 12 32 44 9,352$ -$ 9,352$

5.3 Model Update and Calibration Memo 2 4 12 18 4,108$ -$ 4,108$ SUBTOTAL 0 2 0 22 0 0 68 0 92 19,640$ -$ 19,640$ 6 Performance Evaluation and Capacity Analysis

6.1 Model Existing Conditions 8 20 28 5,984$ -$ 5,984$

6.2 Model Future Conditions 8 20 28 5,984$ -$ 5,984$

6.3 Pumping and Storage Analysis 4 16 20 4,120$ -$ 4,120$ SUBTOTAL 0 0 0 20 0 0 56 0 76 16,088$ -$ 16,088$ 7 Capital Improvement Plan

7.1 Develop Capital Improvement Projects 1 8 20 29 6,354$ -$ 6,354$

7.2 Prepare Cost Estimates 2 15 45 62 13,370$ -$ 13,370$ SUBTOTAL 0 3 0 23 0 0 65 0 91 19,724$ -$ 19,724$ Task
No.Task Description
([KLELW%City of Pismo Beach
2025 Urban Water Management Plan and Water Master Plan
4/14/2026
Pr
i
n
c
i
p
a
l

i
n

Ch
a
r
g
e
QA
/
Q
C
Co
n
d
i
t
i
o
n

As
s
e
s
s
m
e
n
t
L
e
a
d
Pr
o
j
e
c
t

Ma
n
a
g
e
r
UW
M
P

a
n
d

Su
p
p
l
y

Le
a
d
De
m
a
n
d

Le
a
d
En
g
i
n
e
e
r
i
n
g
S
u
p
p
o
r
t
Pr
o
j
e
c
t

Ad
m
i
n
WSC
Labor
Hours
WSC
Labor Fee Expenses Total Fee
Rob
Morrow
Jeroen
Olthof
Michael
Goymerac
Heather
Freed
Michael
Steele
Spencer
Waterman
Cason
Roberts Kay Merrill
Billing rates, $/hr $415 $370 $291 $278 $278 $278 $188 $186 Task
No.Task Description
8 Water Master Plan Report

8.1 Administrative Draft Water Master Plan 8 20 6 60 94 21,468$ -$ 21,468$

8.2 Final Draft Water Master Plan 4 10 40 54 11,780$ -$ 11,780$

8.3 Final Water Master Plan 1 6 20 27 5,798$ -$ 5,798$ SUBTOTAL 0 13 0 36 6 0 120 0 175 39,046$ -$ 39,046$ 9 2025 UWMP Update

9.1 UWMP Sections Update 2 8 25 50 85 19,314$ 2,772$ 22,086$

9.2 UWMP Report Update 4 10 30 60 104 23,880$ -$ 23,880$ SUBTOTAL 0 6 0 18 55 0 110 0 189 43,194$ 2,772$ 45,966$ 10 Public Adoption and Support

10.1 UWMP Presentation Support 6 8 14 3,172$ -$ 3,172$

10.2 WMP Presentation Support 4 4 8 16 3,728$ -$ 3,728$ SUBTOTAL 0 0 0 10 4 0 16 0 30 6,900$ -$ 6,900$ COLUMN TOTALS 6 25 19 203 69 41 594 16 973 218,931$ 2,772$ 221,703$ 1 OT 1 Project Summary Sheets
OT 1.1 Capital Project Summary Sheets 30 120 150 30,900$ -$ 30,900$ OPTIONAL TASKS TOTAL 0 0 0 30 0 0 120 0 150 30,900$ -$ 30,900$ Rates are subject to revision as of January 1 each year.

Mileage will be reimbursed at the prevailing federal milage reimbursement rate in effect at the time of travel 10% mark-up on direct expenses; 5% mark-up for sub-contracted services *Optional Task Not Included in Contract Scope
*
Council Agenda 5-5-2026 9.G-17