Contract Change Order No.1
Project Title: ADA Access Ramp Installation, City Project No. 1305 Owner: city of worn Ml. Canlreclar. Martin az Ccncreta, Inc.
You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:
Balancing Quantities for Project Closeout
1 This Change Order provides:
a) Extra work and credits identified in Exhibit A
$ (40,940.00)
2 This Change Order came about from:
a)
Balancing change order for all bid items based on actual final quantities. 3 Action to be taken:
a) The City calculated extra quantities or credits based on actual final quantities for this change. 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
$ (40,940.00)
Total $ (40.940.001
5 Contract Time Extension
a) 0
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits. This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Adminstration.
CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME: `fes
Contract Amount: $ 175,050.00
Previous CCOs: $
Adjustment of Line Items
Exceeding 25%
Total Extra Work $ -
Total Field Adjustments $
Total Credits $ 40,940.00
Changes in Line Items: $ (40,940.00)
Current Contract price: $ 134,110.00
Prepared by:
Recommended:
Recommended:
Approved by:
Raquel Garcia, Project Manager, City of Placentia
Masoud Sepahi, City Engineer, City of Placentia
Luis Estevez, Deputy City Administrator, City of Placentia Damien R. Arrula, City Administrrator, City of Placentia We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be shown above
Accepted:
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.
Attachment 1
CCO No. 1 Exhibit 'A'
Project Title: ADA Access Ramp Installation, City Project 1305 Owner: City of Placentia Contractor: Martinez Concrete, Inc.
No. Actual
Description Bid $$ Comments CREDIT EXTRA
4 Adjusted Sidewalk Quantity $ (540.00) $0.00
1000 955
5 Adjusted Curb & Gutter Quantity 400 45 $ (24,850.00) $0.00 6 Adjusted Cross -Gutter Quantity 250 0 $ (6,250.00) $0.00 7 Adiusted AC Pavement Quantity 500 250 $ (2,500.00) $0.00 8 Adjusted Sign & Post Relocating Quantity 2 0 $ (800.00) $0.00 10 Adjusted Survey Markers & Monument Preservation Quantity 1 0 $ (6,000.00) $0 00 $0.00
$000
$0 00
$0.00
$0.00
$0.00
Sum of Line Item Adiustments $
Cost of Line Item adiustments $
Change in Contract Cosi
(40.940.00) $
(40.940.00)
-$40.940.00