Contract Change Order No.7
Project Title: Old City Hall Office Renovation, City Project No. 5106 Owner: City of Placentia Contractor: A2Z Construct Inc
You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:
Balancing Change Order to include additional work and time justified at end of project; Includes Liquidated Damages Credit and Deductions for Work Agreed not to be completed by Contractor
1 This Change Order provides:
a) Extra work and credits identified in Exhibit A
$
2 This Change Order came about from:
a)
The Contractor filed a claim for additional work and time beyond initial scope of project. This also includes credits owed to the City for work removed and liquidated damages for exceeding the contract end date. 3 Action to be taken:
a) The Contractor provided a claim for additional work and time and City provided list of credits. 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
Total
5 Contract Time Extension
a) 5 Working Days
$ 16,000.00
$ 16,000.00
$
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits. This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Adminstration.
CHANGE TO CONTRACT COST:
Contract Amount: $ 465,000.00
Previous CCOs:
Adjustment of Line Items
Exceeding 25%
Total Extra Work
Total Field Adjustments
Total Credits
Changes in Line Items:
Current Contract price:
Prepared by:
Recommended:
Recommended:
Approved by:
$ 99,902.30
16,000.00
16,000.00
564,902.30
Raquel Garcia, Project Manager, City of Placentia
Masoud Sepahi, City Engineer, City of Placentia
Luis Estevez, Deputy City Administrator, City of Placentia Damien R. Arrula, City Administrrator, City of Placentia CHANGE TO CONTRACT TIME:
Original Working Days:
Original Date of Completion:
Previous CCOs Working Days:
Additional Working Days:
Adjusted Total of Working Days:
Adjusted Date of Completion:
90 8/18/2022
41 5
136
10/24/2022
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be shown above
Accepted:
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.
ATTACHMENT 1
No.
1 (PLUS 3 Working Days)
CCO No. 7 Exhibit 'A'
Project Title: Old City Hall Office Renovation Project, City Project 5106 Owner: City of Placentia Contractor: A2Z Construct Inc
Description
AC Solid Air Duct Issue - Additional material & labor
Remove and replace concrete footing and wood post to accommodate 2 change in dimension for ADA Restroom - Additional material & labor (PLUS 2 Working Days)
Bid Actual $$ Comments CREDIT EXTRA
LS $5,800.00 $5,800.00
$5,200.00
LS $5,200.00
Replacement of damaged AC parts - Additional material and labor $1,800.00 3 LS $1,800.00
New junction box with flex conduit and new low voltage wire (claimed vague note on plans) - Additional material & labor
4 LS $3,200.00 $3,200.00
CREDIT - Per RFI 13, did not install Crown Molding in Rooms 106, 108, 109, 114 and 115
6 (Approximately 300 LF) 1,500.00 $0.00
CREDIT - Liquidated Damages
7 (29 DAYS at $500 per day) 10/25/22 - 12/8/22 14,500.00 $0.00 Sum of Line Item Adjustments $ 16,000.00 $16,000.00
Change in Contract Cost $0.00