City of Placentia
Contract Change Order No.3
Placentia Public Safety Canter Phase 1
TTS Engineering, Inc.
JN: 2022-23
You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:
Description of work done, estimate of quantities and prices to be paid. 1 This Change Order provides:
a) Extra work as listed in Exhibit A and the detailed COR #23301-06, #23301-07, #23301-08, #23301-09, #23301-10, #23301 -11,#23301 -12,#23301 -13,#23301 -14,#23301-15,#23301-16,#23301-17,#23301-18,#23301-19,#23301. 20, and COR #23301-21 in the attachments.
2 This Change Order came about from:
a) Due to the need for Contractor to A) add linear feet to the proposed sewer line per revised sheet C-6, B) perform additional exploratory work for the existing fire water line, C) mitigate site damage due to excessive rains, D) add footings to the Butler foundation design, E) install electrical and plumbing stub ups in the Butler slab, F) run SCE line deeper per revised SCE plans, G) install additional linear footage to SCE lines per revised SCE plans, H) install new manholes per RFI #7, I) MWD sewer Investigation and repair damage to an unmarked fire water line, J) install more linear feet to the fire and domestic water lines based on actual locations vs. what is shown on plan, K) adjust sewer lines in Butler pad per conflict with footings, L) remove and dispose of abandoned slurry -filled vault, M) rent the generator past the original 56 days, N) extend General Conditions, 0) adjust concrete fors due to stair relocation, and P) excavate footing pads further due to anchor bolt depth adjustment. 3 Action to be taken:
a) The Contractor was directed to perform the additional work items accordingly. 4 Compensation
a) Adjustment of Line Items exceeding 25% $
b) Extra work $ 328,755.43
d) Credits $
Total $ 328,755.43
5 Contract Time Extension
a) /t is agreed that there has been delay to the project. The time extension has been agreed at 13 working days. The end date is now 6/23/23.
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits. This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Administration.
CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME:
Contract Amount: $1,324,000.00
Previous CCOs:
Adjustment of Line Items
Exceeding 25%
Total Extra Work
Total Field Adjustments
Total Credits
Changes in Line Items:
Current Contract price:
Prepared by:
Recommended:
Recommended:
Approved by:
$ 117,166.18
$ 328,755.43
$
$ 445,921.61
$ 1,769,921.61
13 Working Days
Danny Kilo `Senior Project Manager, Totum Consulting
Project Manager, City of Placentia
Luis Estevez, P.E., Director of Public Works/ City Engineer, City of Placentia Damien Arrula, City Manager, City of Placentia
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be shown above
Accepted:
Kyle Wagner tl .
Kyle Wagner , Project Manager, TTS Engineering, Inc.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.
PCO No., EW,
or CREDIT
Owner: City of Placentia
CCO No.3 Exhibit 'A'
Placentia Public Safety Center Phase 1
Contractor: TTS Engineering, Inc.
Description Bid Actual
23301-06 Added sewer per revised C-6 EXCLUDES MWD
23301-07 Extra exploratory work for fire water per RFI -06 23301-08 Rain water mitigation / removal. Negotiated
23301-09 Added Footings
23301-10 Interior plumbing 8 electric
23301-11 SCE redesign changes. added depth
23301-12 Added conduit SCE
23301-13 Storm drain manholes RFI#17
23301-14 Repair Fireline MWD Building
23301-15 Added fire and water line
23301-16 Move sewer inside building
23301-17 Remove slurry filled abandoned vault
23301-18 Added generator rental
23301-19 General Conditions due to delays #2
23301-20 Adjust forms due to stair relocation
23301-21 Additional pad footing excavation
Project Cost
10% of Project Cost $
$1,324,000.00
132,400.00
4.6% See attached PCO
1.8% See attached PCO
1.0% See attached PCO
2.7% See attached PCO
1.8% See attached PCO
0.6% See attached PCO
1.4% See attached PCO
0.7% See attached PCO
1.3% See attached PCO
1.7% See attached PCO
1.8% See attached PCO
0.9% See attached PCO
3.8% See attached PCO
0.2% See attached PCO
0.3% See attached PCO
0.3% See attached PCO
Comments
Sum of Line Item Adjustments $
Cast of Line Item adjustments $
RBF JN: 2019-20
CREDIT EXTRA
5 60,252.88
$ 23,447.94
5 12,867.31
5 35,868.74
$ 23,385.16
$ 7.776.13
$ 19,019.12
S 9,373.35
S 17,684.76
$ 22,235.17
$ 23,633.53
$ 11,300.81
5 50,000.00
$ 3,290.17
$ 4,087.02
$ 4,531.34
- I $328,755.43
328,755.43
Change in Contract Cost $ 328,755.43
Sub A $
328,755.43
% A 24.83%