Contract Change Order No.8
Project Title: Crowther Sewer Line Project
Owner: City of Plancentia Contractor: Kana Pipeline, Inc.
You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:
Description of work done, estimate of quantities and prices to be paid. 1 This Change Order provides:
a) Change to contract amount per exhibit A.
2 This Change Order came about from:
a) Differences between plans and utility locations found by the contractor, efforts to locate utilities in order to proceed with work as planned.
3 Action to be taken:
a) CORs 62, 106, 108, 109,111, 112, 114, 116, 120 are approved per attached Exhibit 'A' 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
Total
5 Contract Time Extension
a) 21
$111,725.80
$111,725.80
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits.
This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Adminstration.
CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME:
Contract Amount: $ 4,696,973.63
Previous CCOs: $199,300.97
Adjustment of Line
Items Exceeding 25%
Total Extra Work
Total Field Adjustments $
Total Credits $
Changes in Line Items:
Current Contract price:
$111,725.80
$ 111,725.80
$ 5,008,000.40
382 Working Days
403 Working Days
Prepared by:
Recommended:
Recommended:
Approved by.
Kevin Koura, Public Works Inspector, City of Placentia
Masoud Sepahi, Construction Manager, Infrastructure Engineers Luis Estevez, Deputy City Administrator, City Of Placentia Damien R. Arrula, City Administrrator, City Of Placentia We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be prices shown above
Accepted:
9.edtaa- Lec.
JOSHUA LOCKE, VICE PRESIDENT OF OPERATIONS
Aug 15, 2023
ZS
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.
No.
1 2
CCO No. 8 Exhibit 'A'
Project Title: Crowther Sewer Line Project
Owner: City of Placentia Contractor: Kana Pipeline, Inc.
Description
COR 62: Day 1: Pour curb and gutter and part of sidewalk at restaurant entrance at State College (before
Orangethorpe) due to cave-in
Day 2: Form and pour curb/gutter and portion of sidewalk at drive approach of
restaurant (18.0"x6' - side walk and gutter) (8'x2.2' - curb gutter). Removed and replaced due to unstable and over
sturated soil colapsed and not suited for backfill
COR 106: Remove and replace Curb & Gutter, & Stamped
Concrete Asta 30+00 on Placentia Ave
Bid Actual Time Extension
(working days)
2 3
Cost
Comments
CREDIT EXTRA
$ 7,020.18 $7,020.18
$ 13,465.00 $13,465.00
COR 108: Breakout manhole connection 24" gas line on
3 the way for core drill. Hand dig point of connection on $3,120.54 $3,120.54 existing
4 COR 109: Reconnect 8" VCP Sewer Lateral @ STA
46+50
1 2
$29,674.00 $29,674.00
COR 111: Remove portion of existing 6" gas line not
5 shown on plans at STA 23+23 and 24+38 $1,083.83
6 showing on plans at STA 37+21, 38+05, and 38+60
7 COR 114: Remove abandoned 18" RCP in conflict with
gas main
COR 112: Remove portion of existing 6" steel gas line not 8 COR 116: T&M Industrial Connection
1 $1,083.83
1 $1,611.50
1 $11,192.00
5 $54,337.05
$1,611.50
$11,192.00
$54,337.05
CCO No. 8 Exhibit 'A'
Project Title: Crowther Sewer Line Project
Owner: City of Placentia Contractor: Kana Pipeline, Inc. 9 COR 119: Standby of Equipment waiting for Gas Company 5 $1,988.88
$1,988.88
10 COR 120: Credit for stamped concrete at STA 30+00 on -$4,747.00 Placentia Ave 0 -$4,747.00
Sum of Line Item Adjustments $ - $111,725.80
Cost of Line Item adjustments $ 111,725.80
Change in Contract Cost $111,725.80