3.A. STAFF REPORT - FY 22-23 STREET REHABILITATION PROJECT 1301

Placentia City Council
October 17, 2023

Document
3.A. STAFF REPORT - FY 22-23 STREET REHABILITATION PROJECT 1301
Meeting
October 17, 2023
Body
Placentia City Council
Pages
4
Original file
8 KB
Text extracted from the city's file for reading and search. Open the original on portal.laserfiche.com. That file is the official record.

TO:

VIA:

FROM:

DATE:

Placentia Cit Council

AGENDA REPORT

CITY COUNCIL

CITY ADMINISTRATOR

DEPUTY CITY ADMINISTRATOR / PUBLIC SERVICES AND INFRASTRUCTURE OCTOBER 17, 2023
SUBJECT: APPROVAL OF PLANS AND SPECIFICATIONS AND AWARD OF CONSTRUCTION CONTRACT TO R.J. NOBLE COMPANY FOR THE FISCAL YEAR 2022-23 STREET REHABILITATION PROJECT, CITY PROJECT NO. 1301 FISCAL
IMPACT: EXPENSE: $6,014,496.88 TOTAL CONSTRUCTION COST
$5,383,306.25 CONSTRUCTION CONTRACT AMOUNT
$ 538,330.63 CONSTRUCTION CONTINGENCY AMOUNT
$ 92,860.00 CONSTRUCTION INSPECTION COSTS
AVAILABLE BUDGET: $6,014,539.00 TOTAL PROJECT BUDGET
$ 800,000.00 FISCAL YEAR 2023-24 CIP BUDGET (171301-6740) $ 635,710.00 FISCAL YEAR 2023-24 CIP BUDGET (181301-6740) $1,360,849.00 FISCAL YEAR 2023-24 CIP BUDGET (601301-6740) $3,003,608.00 FISCAL YEAR 2023-24 CIP BUDGET (791301-6740) $ 63,272.00 FISCAL YEAR 2023-24 CIP BUDGET (501301-6740) $ 151,100.00 Proposed Budget Resolution (601301-6740)
SUMMARY:

The Scope of the Fiscal Year ("FY") 2022-23 Street Rehabilitation Project entails the rehabilitation of several arterial, collector and residential streets totaling 1.4 million square feet of roadways. In general, the work consists of pavement reconstruction; replacement of damaged sidewalk, curb, and gutter; installation of new concrete bus pads; and new signing, striping, markings, and pavement legends. The location and limits of the work include Orangethorpe Avenue (East of Placentia Avenue to West of Kraemer Boulevard), Crowther Avenue (East of Placentia Avenue to East of 57 Freeway Overpass), Bradford Avenue (North of Chapman Avenue to South of Yorba Linda Boulevard), Kraemer Boulevard (South of Chapman Avenue to South of Yorba Linda Boulevard) in addition to five residential cul-de-sac streets in the neighborhood east of Kraemer Boulevard (between Bastanchury Road and Yorba Linda Boulevard). (Attachment No. 3) There was an Additive Bid "B" Schedule that included the rehabilitation of Chapman Avenue (East of Placentia Avenue to West of Kraemer Boulevard). Unfortunately, that portion of work would increase the budget by an additional $1.1 million, in order to keep this project within our current budget, it will need to be constructed as part of the next street rehabilitation project.

3.a.

Oct. 17, 2023

City Council Agenda
October 17, 2023

Page 2 of 4 ends

The City solicited competitive bids for the project. A total of six (6) bids were received for this project on October 5, 2023. These bids consisted of two portions: Bid "A" + Additive Bid "B". The total of both bids was used as the basis in determining the low bid for this project. The contract will only be for the amount represented by Bid "A". The low bid received from R. J. Noble Company was found to be the lowest responsive and responsible bid received. Staff recommends that City Council award a construction contract to R. J. Noble Company ("RJ Noble") in the amount of $5,383,306.25.

This bid also includes an active alternate bid item for protecting the fiber network that was recently installed by SiFi Network. The bid amount received for protecting the fiber lines will be billed to SiFi to cover this cost. In addition to the construction cost, a ten percent (10%) construction contingency amount of $538,330.63 is provided to cover any unforeseen conditions found during construction. The total construction contract cost including contingency amounts is $5,921,636.88.

RECOMMENDATION:

It is recommended that the City Council take the following actions:

1. Approve the Engineered Plans and Specifications prepared by Transtech, Inc. for the FY 2022-23 Street Rehabilitation Project No. 1301; and

2. Approve a Public Works Agreement with R. J. Noble Company for the FY 2022-23 Street Rehabilitation Project in the amount of $5,383,306.25; and

3. Reject all other bids received and authorize return of the bid bonds; and

4. Authorize the City Administrator to approve contract change orders up to ten percent (10%) of the contract amount, or $538,330.63, for a total construction contract not -to - exceed amount of $5,921,636.88; and

5. Approve a Cooperative Agreement with the City of Anaheim for the construction cost for Anaheim's share of the project that is estimated to be $200,000, with the final cost to be based on the actual bid received and final construction contract costs; and

6. Adopt Resolution No. R-2023-81, A Resolution of the City Council of the City of Placentia, California authorizing a budget amendment in Fiscal Year 2023-24 in compliance with City Charter of the City of Placentia §§1206 and 1209 pertaining to appropriations for actual expenditures; and

7. Authorize the City Administrator and/or his designee to execute all necessary documents, in a form approved by the City Attorney.

City Council Agenda
October 17, 2023

Page 3 of 4 ends

STRATEGIC PLAN STATEMENT:

This item conforms to Strategic Plan Goal 5 and Objective 5.8, Implement the 2022 Pavement Management Plan Report to prioritize streets and roads.

DISCUSSION:

The Scope of Work for the Fiscal Year 2022-23 Street Rehabilitation Project includes several arterial, collector and residential streets that entails pavement reconstruction; replacement of damaged sidewalks, curb, and gutter; installation of new concrete bus pads; and new signing, striping, markings, and pavement legends. A total of 1.4 million square feet of roadways will be rehabilitated as part of this project.

On October 5, 2023, the City received six (6) bids from contractors to construct the project. The following table provides the total bid amounts received from each contractor:

Contractor Bid "A" Amount
RJ Noble $5,383,306.25
All American Asphalt $5,589,969.40
Hardy & Harper, Inc $5,994,000.00
Sequel Contractors, Inc $6,250,257.50
Onyx Paving Company, Inc $6,334,000.00
Sully -Miller Contracting Company $7,082,011.00
After reviewing the bids, it was determined that RJ Noble submitted the lowest responsible bid.

Staff reviewed and analyzed their bid proposal, and it was found to be responsive and valid. Based upon RJ Noble's reference check, submitted bid and City Staff's experience working with RJ Noble on similar projects in the past, Staff recommends awarding a construction contract to RJ Noble for the FY 2022-23 Street Rehabilitation Project.

FISCAL IMPACT:

The total construction cost for the Fiscal Year 2022-23 Street Rehabilitation Project amounts to $6,014,496.88. This cost consists of the bid amount submitted by RJ Noble in the amount of $5,383,306.25, a construction contingency in the amount of $538,330.63, and a Construction Inspection contract with Fountainhead in the amount of $92,860.

City Council Agenda
October 17, 2023

Page 4 ends

Funding for this project is supported by numerous sources as outlined below:

Funding Source Amount
1 FY23/24 Measure M Funds $635,710
1 FY23/24 Gas Tax $800,000
FY23/24 SB1/RMRA Funds $1,360,849
FY23/24 Measure U Funds $3,003,608
FY23/24 OCTA Grant $63,272
FY23/24 Additional RMRA (Resolution R-2023-81) $151,100 1 Total $6,014,539
Reimbursements Amount
City of Anaheim's Project Share $200,000 1
1 City of Fullerton's Project Share $200,000 1
Construction costs still remain high and at 20% higher than in the prior year. Therefore, Staff is recommending Resolution R-2023-81 to appropriate $151,100 from the existing RMRA fund balance to support the cost of the proposed project.

Prepared by:

Reviewed and approved:

Chris Tanio, P.E. Jennifer Lampman
Deputy Director of Public Works/City Engineer Director of Finance Reviewed and approved:

Luis Estevez
Deputy City Administrator
Reviewed approved:

Damien R. Arrula
City Administrator
Attachments:

1. Agreement with R. J. Noble Company

2. Cooperative Agreement with City of Anaheim

3. Project Area Map

4. Budget Amendment Resolution -R-2023-81