Contract Change Order No. 1
Project Title: Placentia Art Sculpture Pedestal
Owner: City of Placentia Contractor: M.S. Construction Management Group You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:

Additional Nork is needed graffiti coating material raising lights installing drainage pipe and constructing foundation 1 This Change Order provides'
a) Extra work and credits identified in Exhibit A, B, C $ 4,773.67 (A), $ 4,267.76 (8), and $ 5,275.31
2 This Change Order came about from:
a)
There is a need to add additional graffiti coating material. raise lights. install drainage pipes. and construct rock foundation.
3 Action to be taken:
a) The Contractor was directed to provide a lump sum price for this change. 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
$14,316.74
Total $ 14,316.74
5 Contract Time Extension
a) 0
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits.

This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Adminstration.

CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME:

Contract Amount: $ 398,400.00
Previous CCOs: $
Adjustment of Line
Items Exceeding 25%
Total Extra Work $ 14,316,74
Total Field Adjustments $
Total Credits $
Changes in Line Items: $ 14,316.74
Current Contract price: $ 412,716.74
Recommended:

Chris Tanio, City' Engin = = , City of Placentia
Recommended:

Luis
Approved by:
z, Depujy C
r. City of Placentia
Damien R. Arrula, City Administrrator, City of Placentia We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above. and perform all services necessary for the work above specified, and will accept as full payment therefore the Accepted.
1/30/2024
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.

M.S. Construction Mgmnt. Group
General Engineering Contractors
Commercial . Residential
"PROPOSAL "
Request for change order
PROPOSAL NUMBER: PLA -P003
January 24, 2024
TO:

Mr. Luis Estevez
Deputy City Administrator
City of Placentia
License # 721738
PROJECT: Sculpture Installation Concrete Pedestal Construction and Site Improvements Project Placentia, Ca.
************************************************************************************** Per your request, the following is the cost proposal related to apply graffiti coating on the Sculpture foundation wall at the above captioned project:

Please refer to the enclosed cost breakdown $4,726.41
Sub -Total $4.726.41
Bond fee (1%) $ 47.26
Grand Total $4,773.67
1 Grand Total ... ,., $4,773.67
NOTE: Please add 2 working days to the project completion date for this work **********************************************************************a--k***:k* .** Acceptance: You are hereby authorized to perform the above-mentioned extra work for the price indicated. A change order to the original contract would be created at a later date. '
11 Signed: ��ur j,�* Date: //0
1 �

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAKDOWNREPORT C.C.O. NO. REPORT NO. 1
PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $0.00
W.O. # PROPOSAL# PLA -P003 DATE PERFORMED TODAY $4,726.41 DATE OF REPORT 1/24/2024 TO DATE $4,726.41
DESCRIPTION OF WORK Per your request, the following is the cost proposal related to apply graffiti coating on the Sculpture foundation wall at the above captioned project:

EXT ENDED
NO. 1 NAME L1 ABOR POSITION / CLASSIFICATION HOURLYRATEI HOURS AMOUNTS 2 Laborers$96.70 20 $1,934.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.a0
$D.00
$0.o0
$0.00
$0.00
$0.00
LABOR SUB -TOTAL $1,934.00
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
NO, ICALTRANS EQ.

RENTAL CODE
Paint Spreyer
NO.

NO.

EQUIPMENT
NO. MATERIALS
1 Sure Klean Graffiti coating material- 15 gallons X $85.50/gal. 41,282.50 2 Painters protection paper wrap
3 1
2 3
3 The above record is complete and correct
Contractor's Representative
TOTAL COST OF LABOR 1 A 1 $1,934.00

IHOURLY HOURS EXTENDED
RATE I 1 AMOUNTS
$35.00 16.00 $560.00

0.00 0.00 $0.00
$0.00

0.00 $0.00
$0.00

UNIT EXTENDED

COST I I AMOUNTS
a
$1,282.50 $115.43 $1,397.93
$200.00 $18.00 $218.00
$0.00 $0.00
$0.00 $0.00
1 1 $0.00 $0.00
$a.aa $0.00
$0.00 $0.00
TOTAL COST OF EQUIPMENT AND MATERIALS B $2,175.93
15 % on Labor Cost 1 C $290.10
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost 1 ID $326.39 SUBTOTAL - 1: A + B + C + D $4,726.41
0% on Subtotal - 1 I E $0.00
SUBTOTAL - 2: Subtotal - 1+ E $4,726.41
TAX
Paid on Est. No.

Checked by
TOTAL THIS REPORT $4,726.41

PROSOCO

PROTECTIVE TREATMENTS
Blok-Guard® & Graffiti Control 9
Sure Klean® Weather Seal Blok-Guard® & Graffiti
Control 9 is a clear, solvent -based silicone elastomer formulated to weatherproof concrete block and
other porous masonry materials, like brick,
unglazed terra cotta, porous tile, concrete and some
natural stones. Blok-Guard® & Graffiti Control 9
protects masonry surfaces from repeated graffiti
attacks without altering the natural appearance.

Blok-Guard® & Graffiti Control 9 penetrates and
fills pores to prevent water penetration through
exterior walls exposed to normal weathering.

Graffiti removal is fast and easy using PROSOCO's
Graffiti Remover. Blok-Guard® & Graffiti Control 9
is easy to apply with low-pressure spray.

TYPICAL TECHNICAL DATA
FORM

SPECIFIC GRAVITY
pH
WT/GAL

ACTIVE CONTENT

TOTAL SOLIDS

VOC CONTENT

FLASH POINT

FREEZE POINT

SHELF LIFE
Clear, colorless liquid
Petroleum odor

0.802
not applicable

6.67 lbs
9%
9% ASTM D 2369
>600 g/L
100° F (38° C) ASTM D 3278
www.prosoco.com/voccompliance to confirm
compliance with individual district or state
regulations.

SA}ETr INH)kHAT1ON
Always read full label and SDS for precautionary
instructions before use. Use appropriate safety
equipment and job site controls during application
and handling.
24 -Hour Emergency Information:

INFOTRAC at 800-535-5053
Product Data Sheet • Page 1 of 4 • Item #40093 - 120122 • ©2022 PROSOCO, Inc. • prosoco.com

Product Data Sheet
Weather Seal Blok-Guard® & Graffiti Control 9
nivit,4 D4TIflIU
Protect people, vehicles, property, plants, windows,
painted surfaces, anodized aluminum, metal,
glass and all non masonry surfaces from product,
residue, splash, fumes and wind drift. Sure Klean®
Strippable Masking is not appropriate for use with
this product.

Ensure fresh air entry and cross ventilation
during application and drying. Extinguish all
flames, pilot lights and other potential sources of
ignition during use and until all vapors are gone.

When applying to exteriors of occupied buildings,
make sure all windows, exterior intakes and air
conditioning vents are covered and air handling
equipment is shut down during application
and until all vapors have dissipated. Apply at
recommended coverage rates as excess material
may contribute to vapor problems.

Recommended for these substrates. Always test.

Coverage is in sq.ft./m. per gallon.

Substrate Type ; Use? Coverage
Architectural
Concrete
Block
Concrete*
Fired Clay*
Marble,
Travertine,
Limestone
Granite
Burnished
Smooth
Split -faced
Ribbed
Brick
Tile
Precast Panels
Pavers
Cast -in-place
1 Brick
Tile
Terra Cotta (unglazed)
Pavers
Sandstone*
Slate
Polished
Unpolished
Polished
yes
yes
yes
yes
yes
yes
yes
no
yes
yes
yes
yes
no
no
yes
30-100 sq.ft
3-9 sq.m.
75-175 sq.ft.
7-16 sq.m.
50-125 sq.ft.
5-12 sq.m.
no
N/A
100-250 sq.ft.
9-23 sq.m.

N/A
Unpolished
Unpolished
Unpolished
no
yes
N/A
100-150 sq.ft.
9-14 sq.m.
no N/A
'Blok-Guard' & Graffiti Control 9 is suitable for most
substrates. May darken or enhance the natural color of
exposed aggregate, pigmented block or mortar.

Always test to ensure desired results.
' Coverage estimates depend on surface texture and porosity.

Surface should be clean, dry and absorbent.

If cleaning is necessary, use the appropriate
PROSOCO cleaner. Do not use raw acids. Let cleaned
surfaces dry completely.

Newly constructed surfaces and repointed surfaces
should cure for 28 days before application. Sealant
and caulking compounds should be in place and
cured before application. Fill cracks and voids to
prevent penetration of fumes into building.

The top of walls should be capped and made
watertight prior to application.

NOTE: Some floor and wall systems incorporate
asphaltic or other crack -suppression membranes.

This deeply penetrative protective treatment may
penetrate through exposed stone, tile, grout or
paver surfaces and react with the membrane to
mobilize objectionable staining. Always pretest to
ensure desired results.

Surface and air temperatures should be 40-90°F
(4-32°C) during application. Higher temperatures
evaporate the solvent carrier and reduce
penetration. If freezing conditions exist before
application, let the masonry thaw.

Recommended application is by high volume,
low-pressure (<50 psi) spray. Fit spray equipment
with stainless steel or brass fittings and gaskets
suitable for solvent solutions. Fan spray tips are
recommended to avoid atomization of the material.

For small scale application, or when spray
application is not appropriate, product may be
applied using brush or roller. Contact Customer
Care or your local PROSOCO representative for
more information. Brushes and rollers should
be nylon or other synthetic material resistant to
solvent solutions.

Ctn1'ann and NanelI+Rf
Store in a cool, dry place away from potential
ignition sources. Keep tightly closed when not
dispensing. Published shelf life assumes upright
storage of factory -sealed containers in a dry place.

Maintain temperature of 45-100°F (7-38°C). Do not
double stack pallets. Dispose of unused product and
container in accordance with local, state and federal
regulations.

Product Data Sheet • Page 2 of 4 • Item #40093 - 120122 • ©2022 PROSOCO, Inc. • prosoco.com

Product Data Sheet
Weather Seal Blok-Guard® & Graffiti Control 9
R Ptlt frP renRI
Read "Preparation" and the Safety Data Sheet
before use.

ALWAYS TEST a small area of each surface to
confirm suitability, coverage rates and desired
results before starting overall application. Include
in the test area any previous repairs and patches,
including aesthetic cementitious finishes.

Different surface compositions may result in
absorption and/or appearance differences. Test
with the same equipment, recommended surface
preparation and application procedures planned
for general application.

Apply as packaged. Do not dilute or alter. Stir
thoroughly before use. Keep container tightly
sealed until ready to use.

Once opened, Blok-Guard® & Graffiti Control 9 must
be used immediately.

Lightweight block and extremely porous masonry
will need 2 coats. See "Second Coat Application."
Sprayer Application

1. Saturate, "wet -on -wet" spraying from the
bottom up. Avoid excessive overlapping. For
heavily textured and porous surfaces, apply
enough material to create 6-8" rundown below
the contact point. NOTE: When spray applying
to fluted architectural block, spray in an
"overlapping X pattern" for complete coverage of
recessed surfaces.

2. Let first application penetrate masonry surface for
2 to 3 minutes. For heavily textured and porous
surfaces, reapply in same saturating manner to
ensure complete coverage of recessed surfaces.

3. Immediately brush out runs and drips to prevent
build up.

Brush or Roller Application
Recommended for small scale application or when
spray application is not appropriate. Contact
PROSOCO for more information. Thoroughly
saturate the surface. Avoid excessive overlapping.

Brush -out runs and drips to prevent buildup.

Dense, Smooth Surface Application
Apply in a single coat using enough to completely
wet the surface without creating drips, puddles
or rundown. Brush out or back roll all runs and
drips for uniform appearance. DO NOT OVER
APPLY. Over application may cause unacceptable
color change. One application is normally enough.

Always test for application rate.

Second Coat Application
Some surfaces may need 2 coats for maximum
graffiti protection. Apply the second coat as soon
as the first coat is dry to touch, or within 2 hours
of the first coat. Immediately back roll or brush out
runs and drips for a uniform appearance and to
prevent build up.

Allowing more than 2 hours between coats reduces
the effectiveness of the second coat.

Wood Application
Saturate to the point of rejection. Let first
application penetrate 2-3 minutes. Reapply in
the same saturating manner. (Not appropriate for
horizontal wood.)
In normal weather (60-80°F; [16-27°C] 50%
humidity), Blok-Guard® & Graffiti Control 9 dries to
the touch in about 25 minutes. Drying takes longer
at lower temperatures.

Blok-Guard® & Graffiti Control 9 gains its
water -repellency properties in 24 hours. Graffiti
resistance properties fully develop in 3 to 5 days,
depending upon climate conditions. Protect treated
surfaces from rain for at least 4-6 hours after
application.

Clean tools and equipment immediately with
mineral spirits or an equivalent cleaning solvent.

Remove over spray and spills as soon as possible.
i;taffiti RAmnv11
Remove most types of graffiti with PROSOCO's
Graffiti Remover or SafStrip®. See product literature
or call Customer Care at 800-255-4255.

Product Data Sheet • Page 3 of 4 • Item #40093 - 120122 • ©2022 PROSOCO, Inc. • prosoco.com

Product Data Sheet
Weather Seal Blok-Guard® & Graffiti Control 9

WA NA A CITY
The information and recommendations made are
based on our own research and the research of
others, and are believed to be accurate. However,
no guarantee of their accuracy is made because
we cannot cover every possible application of
our products, nor anticipate every variation
encountered in masonry surfaces, job conditions
and methods used. The purchasers shall make
their own tests to determine the suitability of such
products for a particular purpose.

PROSOCO, Inc. warrants this product to be free
from defects. Where permitted by law, PROSOCO
makes no other warranties with respect to
this product, express or implied, including
without limitation the implied warranties of
merchantability or fitness for particular purpose.

The purchaser shall be responsible to make his own
tests to determine the suitability of this product for
his particular purpose. PROSOCO's liability shall be
limited in all events to supplying sufficient product
to re -treat the specific areas to which defective
product has been applied. Acceptance and use of
this product absolves PROSOCO from any other
liability, from whatever source, including liability
for incidental, consequential or resultant damages
whether due to breach of warranty, negligence or
strict liability. This warranty may not be modified
or extended by representatives of PROSOCO, its
distributors or dealers.

CUSTOMER CARt
Factory personnel are available for product,
environment and job -safety assistance with no
obligation. Call 800-255-4255 and ask for Customer
Care - technical support.

Factory -trained representatives are established in
principal cities throughout the continental United
States. Call Customer Care at 800-255-4255, or visit
our website at prosoco.com, for the name of the
PROSOCO representative in your area.

Product Data Sheet • Page 4 of 4 • Item #40093 — 120122 • C2022 PROSOCO, Inc. • proeoco.com

M.S. Construction Mgmnt. Group
General Engineering Contractors
Commercial . Residential
"PROPOSAL "
Request for change order
PROPOSAL NUMBER: PLA -P002
January 24, 2024
TO : Mr. Luis Estevez
Deputy City Administrator
City of Placentia
License # 721738
PROJECT: Sculpture Installation Concrete Pedestal Construction and Site Improvements Project Placentia, Ca.
************************************************************************************** Per your request, the following is the cost proposal related to raise the Tight fixture foundations by 6 inches above the adjacent finish elevation at the above captioned project:

Please refer to the enclosed cost breakdown .... $4,255.21 Sub -Total $4.255.21
Bond fee (1%) $ 42.55
Grand Total $4,267.76
Grand Total . $4,267.76
NOTE: Please add 2 working days to the project completion date for this work ******************************************************:ti***y:*********************** Acceptance: You are hereby authorized to perform the above-mentioned extra work for the price indicated. A change order to the original contract would be created at a later date. 1 Signed: Date: ii 9 74(

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAK DOWN R E P O R T C.C.O, NO. REPORT NO. 1 PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $0.00
W.O. # PROPOSAL# PLA -P002 DATE PERFORMED TODAY $3,365.57 DATE OF REPORT 1/24/2024 TO DATE $3,365.57
DESCRIPTION OF WORK Per your request, the following is the cost proposal related to raise the light fixture foundations by 6 inches above the adjacent finish elevation at the above captioned project:: Form work 8, additional concrete cost OURL
N0. I NAME LABOR EXTENDED H

POSITION / CLASSIFICATION RATE I HOURS AMOUNTS
1 Laborer $96.70 8 $773.60
1 Carpenter$98.81 8 $790.48
$0.00
$0.00
$0,00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
LABOR SUB -TOTAL $1,564.08
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
CALTRANS EQ.

NO. RENTAL CODE
NO.
1 2x6x12- 30 each X $15.00/each= $450.00
1 NO.

NO.

EQUIPMENT

MATERIALS
TOTAL COST OF LABOR I A 1 $1,564.08

HOURLY HOURS EXTENDED

RATE AMOUNTS
1 0.00 50.00
1 0.00 $0.00

0.00 $0.00

0.00 $0.00
$0.00
UNIT

COST EXTENDED

TAX I AMOUNTS
$450.00 $40.50 $490.50
$800.00 $72.00 $872.00
2 Concrete -4 Cu yd.X $200.00/l on= $BUU.UU
3 $0.00 $0.00
$0.00 $0.00
2 1 $0.00 $0.00
3 $0.00 $0.00
3 $0.00 $0.00
TOTAL COST OF EQUIPMENT AND MATE PALS B 51,362.50
15 % on Labor Cost C $234.61
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost D $204.38 SUBTOTAL - 1: A + B + C + D $3,365.57
0% on Subtotal - 1 E $0.00
SUBTOTAL - 2: Subtotal - 1+ E 53,365.57
The above record is complete and correct
Contractor's Representative
Paid on Est. No.

Checked by
F
TOTAL THIS REPORT 1 $3,365.571

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAKDOWNREPORT C.C.O. NO. REPORT NO. 2
PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $3,365.57
W.O. # PROPOSAL# PLA -P002 DATE PERFORMED TODAY $889.64 DATE OF REPORT 1/24/2024 TO DATE 54,255.21
DESCRIPTION OF WORK Per your request, the following is the cost proposal related to raise the light fixture foundations by 6 inches above the adjacent finish elevation at the above captioned project: Remove Form work & clean-up LABOR
NO. I NAME 1 POSITION / CLASSIFICATION
1 Laborer
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
NO.

NO.

HOURLY I
RATE
$96.70
HOURS
8 LABOR SUB -TOTAL

EXTENDED

AMOUNTS
$773.60
$0.00
$0.00
$0.00

50.00 50.00
$0.00

50.00 $0.00
$0.00
$0.00

50.00 $773.60
TOTAL COST OF LABOR ! A I $773.60
CALTNS EQ. EX FENDED
NO. I RENTALCODE 1 EQUIPMENT 1 HOURLY

HOURS AMOUNTS
1 0,00 $0.00

0.00 $0.00

0.00 $0.00

0.00 $0.00
$0.00

COST I I AMOUNT I MATERIALS TAX
UNIT
2 3
1 2
3 3
The above record is complete and correct
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00

50.00 50.00
I $0.00 $0.00
$0.00 $0.00
$0.00 $0.00
TOTAL COST OF EQUIPMENT AND MATERIALS B $0.00
15 % on Labor Cost j C 5116.04
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost I D $0.00 SUBTOTAL - 1: A + B + C + D $889.64
Paid on Est. No.
0% on Subtotal - 1 I E $0.00
Contractor's Representative Checked by
SUBTOTAL - 2: Subtotal - 1+ E $889.64
F
TOTAL THIS REPORT 1 $889.64

M.S. Construction Mgmnt. Group
General Engineering Contractors
Commercial . Residential
"PROPOSAL "
Request for change order
PROPOSAL NUMBER: PLA -P001
January 24, 2024
TO:

Mr. Luis Estevez
Deputy City Administrator
City of Placentia
C
License # 721738
PROJECT: Sculpture Installation Concrete Pedestal Construction and Site Improvements Project Placentia, Ca.
************************************************************************************** Per your request, the following is the cost proposal related to the following scope of work at the above captioned project:

1. Core drill 5 each 2-1/2" diameter hole and install 2" diameter PVC drainage pipes on the sculpture foundation wall.

2. Construct approximately 300 square feet of Filter fabric and 5 tons of crushed rock in the center portion of the sculpture foundation area.

Please refer to the enclosed cost breakdown .... $5,223.08 Sub -Total $5,223.08
Bond fee (1%) $ 52.23
Grand Total $5,275.31
Grand Total ... $5,275.31
NOTE: Please add 3 working days to the project completion date for this work Acceptance: You are hereby authorized to perform the above-mentioned extra work for the price indicated. A change order to theoriginal 'contract would be created at a later date. 1 1
Signed:

Date:
/g

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAKDOWNREPORT C.C.O. NO. REPORT NO. 1
PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $0.00
W.O. # PROPOSAL# PLA -P001 DATE PERFORMED TODAY $1,814.62 DATE OF REPORT 1/24/2024 TO DATE $1,814.82
DESCRIPTION OF WORK Per your request, the following is the cost proposal related to the following scope of work at the above captioned project:

1. Core drill 5 each 2-112" diameter hole and install 2" diameter PVC drainage pipes on the sculpture foundation wall.

NO. I NAME LABOR POSITION /CLASSIFICATION EXTENDED

I HOURS I AMOUNTS
2 Laborers $96.70 6 $773.60
$0.a0
$0.00
$0.00
$$00..0000
$0.00
$0.00
$0.00
$0.00
$0.00
$o.0D
LABOR SUB -TOTAL $773.60
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
NO.

NO.
@ $
@ $
TOTAL COST OF LABOR 1 A I $773.60
NO. ICALTRANS EO. HOURLY EXTENDED
RENTAL CODE 1 EQUIPMENT I RATE HOURS AMOUNTS
Core drilling , $750.00 $750.00
_ 1 0.00 $0.00

0.00 $0.00

0.00 $0.00
$0.00
NO. 1 MATERIALS I UNIT TAX EXTENDED'

COST AMOUNTS
1 12" PVC -pipe- 20 lin. Ft X 2.50/lin. Ft = $50.00 $50.00 $4.50 $54.50 2 1$0.00 $0.00
3 $0.00 $0.00
1 $0.00 50.00
2 I 1 $0.00 $0.00
3 I $0.00 $0.00
3 $0.00 $0.00
TOTAL COST OF EQUIPMENT AND MATERIALS B 5804.50
15 % on Labor Cost 1 C 5116.04
The above record is complete and correct FOR OFFICE USE ONLY 15% on Equipment & Materials Cost I D 5120.68 Contractor's Representative
Paid on Est. No.

Checked by
SUBTOTAL -1:A+B+C+D 51,814.82
0% on Subtotal - 1 1 E $0.00
SUBTOTAL - 2: Subtotal -1+ E $1,814.82
F
TOTAL THIS REPORT $1,814.82

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAK DOWN R E P O R T C.C.O. NO. REPORT NO. 2 PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $1,814.82
W.O. # PROPOSAL# PLA -P001 DATE PERFORMED TODAY $3,408.26 DATE OF REPORT 1/24/2024 TO DATE $5,223.08
DESCRIPTION OF WORK Per your request, the following is the cost proposal related to the following scope of work at the above captioned project:

2.Construct approximately 300 square feet of Filter fabric and 5 tons of crushed rock in the center portion of the sculpture foundatio

EXTENDED
NO. I NAME L1 ABOR POSITION / CLASSIFICATION HOURLY

I HOURS I AMOUNTS
2 Laborers$96.70 16 I $1,547.20
$0.00
$0,00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
LABOR SUB -TOTAL 81,547.20
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
NO. ICALTRANS EQ.

RENTAL CODE
Mini Ex
NO.

NO.

EQUIPMENT
NO. MATERIALS
1 2
3 1
2 3
3 Filter Fabric- 300 Sq. ft. X $1.00/Sq. ft = $300.00
3T4'rum rock-5"lons�C$15O.657on= $7b0.00
The above record is complete and correct
Contractor's Representative
TOTAL COST OF LABOR 1

HOURLY I
RATE !
$68.00
UNIT
COST
$300.00
$750.00
A $1,547.20
L.1(URS IEXTENDED

AMOUNTS

4.00 $272.00

0.00 $0.00

0.00 $800.0000

0.00 $0.00
$0.00

TAX EXTENDED

AMOUNTS
$27.00 8327.00
$67.50 $817.50
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
B $1,416,50
IC $232.08
$212.48
$3,408.26
E $0.00
$3,408.26

TOTAL COST OF EQUIPMENT AND MATERIALS
15 % on Labor Cost
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost
SUBTOTAL -1:A+8+C+D
0% on Subtotal - 1
Paid on Est. No.

Checked by SUBTOTAL - 2: Subtotal - 1+ E
TOTAL THIS REPORT $3,408,261

Project T11le: Placentia Art Sculpture Pedestal Project Owner:

Contract Change Order No. 2
Cite or Pia< en iia Contractor: M.S. Conslrucllon Mananement Group You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract.

Additional work is needed. adding 3R Nema Enclosure, Power Syncs, lighting contractors, photocell, conduit and support posts. 1 This Change Order provides:
a) Extra work and credits identified in Exhibit A
$9,017.37
2 This Change Order came about from:
a)
There is a need to add 3R Nema Enclosure, Power Sync, Lighting Contractor. 3 Action to be taken:
a) The Contractor was directed to provide a lump sum price for this change. 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
Total
5 Contract Time Extension
a) 0
59,017.36
$ 9,017.36
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits This work is an Contractor initialed change and includes all labor, equipment, materials, and supervision and Adminstration
CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME:

Contract Amount: $ 396,400.00
Previous CCOs: 5 14,316.74
Adjustment of Line Items Exceeding 25%
Total Extra Work s 9,017.36
Total Field Adjustments 5
Total Credits 5 _
Changes in Line Items: $ 9,017.36
Current Contract price: $ 421,734.10
Okris fiauAao
Recommended:

Recommended'
Approved by.

Chris Tanio, City Engineer, City of Placentia
Leas fsfw.t5
Luis Eslevez, Deputy City Administrator, City of Placentia 01x3ttIUA, Q
Damien R. Arrula, City Administrrator, City of Placentia We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above Accepted:

If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.

M.S. Construction Mgmnt. Group
General Engineering Contractors
Commercial . Residential
"PROPOSAL "
Request for change order
PROPOSAL NUMBER: PLA -P004
February 19, 2024
TO:

Mr. Luis Estevez
Deputy City Administrator
City of Placentia
License # 721738
PROJECT: Sculpture Installation Concrete Pedestal Construction and Site Improvements Project Placentia, Ca.
************************************************************************************** Per your request, the following is the cost proposal related to supply and install the following additional electrical components for the electrical light fixtures operation as shown on the enclosed marked up drawings and the cut sheet for an 18x16x10 Type 3R enclosure at the above captioned project:

1. Lockable Nima 3 enclosure (18"x16"x10") to house the light fixture power syncs.,

2. Galvanized posts supported with concrete foundation, and unitrusts to support the enclosure indicated in #1 above.

3. Lighting contactor.

4. Photocell, to automatically turn ON/Off the light fixtures from dusk to dawn.

Please refer to the enclosed cost breakdown $8,928.09
Sub -Total $8,928.09
Bond fee (1%) $ 89.28
Grand Total $9,017.37
Grand Total ... $9,017.37
NOTE: Please add 3 working days to the project completion date for this work ********************************************************************************** Acceptance: You are hereby authorized to perform the above-mentioned extra work for the price indicated. A change order to a origi a contract would be created at a later date.

Signed:

Date:
-z49/v/(

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAK DOWN R E P O R T C.C.O. NO. REPORT NO. 1 PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $0.00
W.O. # PROPOSAL# PLA -P004 DATE PERFORMED TODAY $3,499.99 DATE OF REPORT 2/19/2024 TO DATE $3,499.99
DESCRIPTION OF WORK the following is the cost proposal related to supply and install the following additional electrical components for the electrical light fixtures at the above captioned project: Trenching, install additional conduits,backfill & compact. Place concrete foundation & support posts

LABOR HOURLY
NO. I NAME 1 POSITION / CLASSIFICATION RATE
NO.
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
CALTRANS EQ.

RENTAL CODE
(Mini Excavator
1Ccompactor wacker
NO.

NO.

HOURS
1 Laborer $96.70 8
1 Electrician $110.00 8

EQUIPMENT

LABOR SUB -TOTAL
TOTAL COST OF LABOR 1 A
HOURLY

RATE HOURS
$68.00
$45.00
NO. MATERIALS UNIT I
COST
1 1-1/12 x 10' -PVC conduits- 6 each X $25.00/each= $150.00 $150.00 2 1-1/2" x 10' galvenized ngid conduits- 2 each X $105.00/each= $210.UU $210.00 3 2" X 10' galvenized posts & caps to support the enclosure box- 2 each X $120.00/each= $240.00 $240.00 1 12 gage struts channel- 1 each X $45.00/each= $45.00 $43.00 2 Concrete- 1 Cu yd.X $300.00/Ton= $300.00 $300.00 $27.00 3 $0.00
3 $0.00
TOTAL COST OF EQUIPMENT AND MATERIALS 1 B
15 % on Labor Cost 1 C
The above record is complete and correct FOR OFFICE USE ONLY 15% on Equipment & Materials Cost D SUBTOTAL -1:A+B+C+D
0% on Subtotal - 1 E

EXTENDED

AMOUNTS
$773.60
$880.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$o.00
$0.00
$0.00
$0.00
$1,653.60
$1,653.60

EXTENDED

AMOUNTS

4.00 $272.00

2.00 $90.00

0.00 $0.00

0.00 $0.00
$0.00

TAX EXTENDED

AMOUNTS
$13.50 $163.50
$18.90 $228.90
$21.60 $261.60
$3.87 $46.87
$327.00
$0.00
$0.00
$1,389.87
$248.04
$208.48
$3,499.99
$0.00
Contractor's Representative
Paid on Est. No.

Checked by SUBTOTAL - 2: Subtotal - 1+ E
F
$3,499.99
TOTAL THIS REPORT 1 $3,499.99

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAK DOWN R E P O R T C.C.O. NO. REPORT NO. 2 PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE $3,499.99
W.O. # PROPOSAL# PLA -P004 DATE PERFORMED TODAY $5,428.10 DATE OF REPORT 2/19/2024 TO DATE $8,928.09
DESCRIPTION OF WORK the following is the cost proposal related to supply and install the following additional electrical components for the electrical light fixtures Provide & Installthe Type 3R Nema enclosure, Pwer syncs, lighting contactor, Photocell, and wirings for full operation.

I NO.
% LABOR SURCHARGE REGULAR
LABOR ! HOURLY HOURS 1.7,21% -.)NO. NAME N / CLASSIFICATION I RATE I 2 Electricians $110.00 32 $3,520.00
$0.00
$0.00
$0.00
$o.00
$0.00
$0.o0
$o.00
$0.00
$0.00
$0.00
$0.00
LABOR SUB -TOTAL $3,520.00
SUBSISTENCE NO. @ $
TRAVEL EXPENSE NO. @ $
OTHER
TOTAL COST OF LABOR 1 A 1 $3,520.00
CALTNS EQ.

RENTAL CODE EQUIPMENT HOURLY 1 HOURS AMOUNTS
$o.00
$0.00

0.00 $0.00
Ij 0.00 $0.00
$0.00
NO. MATERIALS I COSTUNIT

TAX I AMOUNTS
$675.00 $60.751 $735.75
$196.00 $17.64 $213.64
$35.00$3.15 $38.15
$195.00 $17.55 $212.55
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
TOTAL COST OF EQUIPMENT AND MATERIALS � B 1 $1,200.09
15 % on Labor Cost 1 C $528.00
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost D $180.01 SUBTOTAL - 1: A + B + C + D $5,428.10
Paid on Est. No.
0% on Subtotal - 1 1 E $0.00
1 18"x16"x10" locable Type 3R Nema enclosure- 1 each X $675.00/each= $675.00 2 Lighting contactor power Relay- 1 each X $196.UU/each= $196.00 3 hotocell- 1 each X $35.00/each= $35.00
1 #10 Electrical wires -300 lin. ft X $0.65/1in. ft= $195.00 2 3
3 The above record is complete and correct
Contractor's Representative
Checked by SUBTOTAL - 2: Subtotal - 1+ E
F

TOTAL THIS REPORT
$5,428.10
$5,428.101

/ y
1e
1 8"x1 6"x1 0"
.Ax.,144/6
SUBJECT: Electrical Single -line daigram for light fixture operation PROJECT: Sculpture Installation concrete pedestal construction ans site improvement project LOCATION: Placentia, Ca.

A TRANSTECTOR
an INFINITO brand
18x16x10 Polycarbonate Weatherproof Outdoor IP24 NEMA 3R Enclosure, Modified Base Drilled Mount Vented Lid Black TEBPC181610-00V
Features
• High -Impact, UV Resistant Polycarbonate (Black)
• Stainless steel latches with padlock eye
• NEMA Type 3R / IP24 rated
Applications
• Remote Wireless LAN WiFi 0...T i.; t installations
• Indoor and outdoor installations
• Rapid Deployment Installations
• Fully gasketed vented lid & user installed wall mount- ing brackets
• Includes drilled aluminum mounting plate with AC
socket cutouts
• Corrosive ern .1 1., & hotspot applications
• Protection of equipment from theft or damage
Description
The box is a rugged weatherproof enclosure that is ideal for both indoor and outdoor applications. Constructed from High -Impact, UV Resistant Polycarbonate material that provides superior durability to impacts and ease of modification while maintaining minimum weight.

It is well suited for high temperature or corrosive environments. The lid includes two vents with installed rain guards and filters. The included wall mount brackets come uninstalled and bagged with their hardware inside of the enclosure. Once the brackets are installed the enclosure can be mounted directly to any flat wall surface provided proper screws are used into secure studs. The brackets, once installed, also allow you to use our TEF -PMT pole mount kits. The lid features a non-metallic hinge system that allows for quick removal & can be reattached just as quickly without the need for any tools. The enclosure comes with a pair of stainless-steel latches with padlock eyes allowing you to secure the enclosure from tampering. The enclosure comes in black.

Mounting Plate
The modified aluminum mounting plate included with the TEBPC181610-00V comes with pre -drilled and cut holes to use as needed to mount WLAN equipment or whatever equipment you may require. The enclosure also features holes for two N -Bulkhead lightning protec- tors or IuQ, o i,. ,. a grounding lug and cable conduit connector.

The TEF -PMT series of pole mounting kits allow the populated enclosure to be securely mounted to a variety of different size poles.

Compatible versions include TEF-PMT13, TEF-PMT16, TEF-PMT28, TEF-PMT29, TEF-PMT30 & TEF-PMT33 Size
Outer Height
Outer Width
Outer Depth
Inner Height
Inner Width
Inner Depth
Weight
Enclosure Material

18.9 in [480.06 mm]

16.8 in [426.72 mm]

11.3 in [287.02 mm]

18.2 in [462.28 mm]

16.2 in [411.48 mm]

9.7 in [246.38 mm]

17.3 lbs [7.85 kg]
Polycarbonate
Click the following link (or enter part number in "SEARCH" on website) to obtain additional part information including price, inventory and certifications:
18x16x10 Polycarbonate Weatherproof Outdoor IP24 NEMA 3R Enclosure, Modified Base Drilled Mount Vented Lid Black TEBPC181610-00V 1 TEBPC181610-00V REV 1.0 I © 2020 Infinite Electronics, Inc. Transtector Systems is a registered trademark of Infinite Electronics, Inc. +1 208 635 6400 1 Transtector.com

TRANSTECTOR
an INFINIT https://www.transtector.com/18x16x10-polycarbonate-weatnerproot-outdoor-ip24-nema-3r-tebpc181610-00v-p.aspx The information contained in this document is accurate to the best of our knowledge and representative of the part described herein. It may be necessary to make modifications to the part and/or the documentation of the part, in order to implement improvements. Transtector reserves the right to make such changes as required. Unless otherwise stated, all specifications are nominal. Transtector does not make any representation or warranty regarding the suitability of the part described herein for any particular purpose, and Transtector does not assume any liability arising out of the use of any part or documentation. 2 TEBPC181610-0OV REV 1.0 IQ 2020 Infinite Electronics, Inc. Transtector Systems is a registered trademark of Infinite Electronics, Inc. +1 208 635 6400 1 Transtector.com

+1 208 635 6400 1 Transtector.com
03 m
m
m
z
0 0
m
9 n
0 N
0 3
0 0.
3 8-
00 0
m
'D
r 2 VENT COVER
I �

VIEW D -D

0.63 [15.9] •-
.58[14.7] - ±
} DETAIL A
2X
PLATE
FILTER

16.91[429_5]
1 4.88 [377.8] -1
•
2X 12.00[304.8] MTG SLOTS -
2X 10.00[254.0] MTG HOLEI I =

12.48 [317.0]

11.30 [287.0]

10.12 257.0
1/2" CONDUIT

CONNECTOR
2X 5.74 [145.7]

4.38 111.1

3.38 [85.7

GROUND LUG
0 •
•
•
1 )
1891 [480.3]

16.88 [428.6]
'-4X0.31 [8.0]

LID NOT SHOWN IN THIS VIEW

FOR CLARITY
A-\ B
-01
Io 7r7I
0 P

THESE COMMODITIES, TECHNOLOGY OR SOFTWARE WERE EXPORTED FROM THE UNITED STATES IN ACCORDANCE WITH THE EXPORT ADMINISTRATION REGULATIONS. DIVERSION CONTRARY TO U.S. LAW PROHIBITED.

D
J
REV.

A

REVISIONS

DESCRIPTION

INITIAL RELEASE

9.78 [248.4]
+ u
40- D

UNLESS OTHERWISE SPECIFIED

LEANING DIMENSIONS ARE INCHES

DIMENSIONS IN HARE ARE MIUJMETERS
TOLERANCES:
.X =±.2 [5.08] I FRACTIONS
.XX=±.02 [.511 *1132
_XXX =±.005[.131 ANGLES ±1"
CABLE LENGTH (L) TOLERANCES:

LS12[S051=+1 (2511-0
12 [305] <L i 60 (15241= +2 (51] 1-0
60[1524(<Ls 120(3048)=+4[10211-0
120 p0481< L S 300 (76201=+6 [15211-0
300[7620(<L=+5%LI-0

ALL DIMENSIONS SHOWN
ARE FOR REFERENCE ONLY.

18.74 [476.0]
- 2X 316 SS LATCH
03/8" PADLOCK EYE
1 SECTION B -B

DATE APPROVED
02/042020 MMARTNEZ

19.7 500]
.55 [13.9]
30 [7.6]

DETAIL C
4X

10.0 254]

9.2[235]

A TRANSTECTOR
an INFINITI3 brand
10701 Airport Road, Hayden, ID 83835
Phone: 1.208.635.6400 I 1.800.882.9110
Fax: 1.208.955.2041
Website: wwW.transtector.com
E -mall: sales©transtector.com

SIZE CAGE CODE DRAWN BY
A 30992 DZINN

THIRD -ANGLE PROJECTION

THE INFORMATION AND

DESIGN IN THS DOCUMENT

IS THE PROPERTY OF
TRAN0TECTOR. INC
ALL RIGHTS RESERVED.

SHEET
SCALE
1 OF 1
N/A
ITEM N0.

TEBPC181610-00V
REV
A
6u!MeJa 0V3 A00-01919L3d831
m-
• w
o
O I)
En X
C
O
o .0
t?c�
a 03
0 IS
0- O
• M
• 0)
t• D
0 N
O 0
c o
7 �
N
C

1. a o
1 tD N
ID Z
r
D
w

uGRnNG RXr.RE QUANTITIES AND NOTES
13 - 3FT LONG UGH1 RXII/RES
ID-2FT LONG LIGHT FIXTURES
• ALL COMPONENTS OF THE UGHRNG SYSTEM ARE TO BE PROVEIED WIRE SELECTED CONTRACTOR FOLLOMNG THE WHIM RXNRE SELECTION PROV1050 BY ARTIST. INSTALLATION OF ALL COMPONENTS IS ALSO TO BE PROVIDED BY THE

CONTRACTOR CONTRACTOR WALL PRONE CONDUIT AS NEEDED AS WELL AS DRAINAGE FOR THE LOCATIONS OF THE LIGHT FIXTURES. RXTURES NE RATED FOR EXTERIOR USAGE BUT ARE NOT SUBMERSIBLE IMNUFACNRERS WARRANTY

VALL NOT COVER WATER DAMAGE SO CONTRACTOR MUST PROVIDE ADEQUATE DRAINAGE FOR UGHT RXTURES HW
r -WW
wW

PROPOSEO LOCATION FOR
THE 19116110- TYPE 3R

ENCLOSURE
ut
el Or

CONCRETE
01 LIGHT FIXTURE ON GRADE MOUNTING CONCRETE WAIL PLAN DIMENSIONS 31-1
HW
+Y
•r:

Cliff Garten Studio
1315 Preston Woy
Venice. Colilomio 90291
310.392.2060 TEL
Ui lfgorlen9ludio,com

PROJECT TULE

PLACENTA GATEWAY

PLACENTA, CA

CHROMATIC ASCENSION
SR -57/ ORANGETHORPE. PLACENTIA
wExr
CIN OF PLACENTIA. CALIFORNIA
901 E CHAPMAN AVE
PLACENTIA CA 92870
(714) 993-8120
ARTIST

CUFF GARTEN STUDIO
1315 PRESTON WAY
VENICE. CA 90292
310.392-2060

SCUISTURE DOWERING

PATRELL ENGINEERING GROUP
751 SUNNY GROVE LANE
GLENDORA, CA 91741
626-3354362

DESCRIVTION DATE

KEYPLAN
Site MIS

LIGHT FIXTURE ON GRADE

MOUNTING WALL PLAN

DIMENSIONS
ART -09
DATE
01/96.2023

GENERAL NOTES

1. METALIEMPLAIE TO BE PROVIDED BY ARTIST AT COST TO CONTRACTOR FOR THE PLACEMEN OF ANCHORS, MD AS A REFERENCE FORME SLOPE OF THE TOP OF WALL, SEE ART -42
2 TEMPLATE YALL BE MADE IN COORDINATION VBTH THE CONTRACTOR ACCORDING TO HIS MEANS AND METHODS 3 METAL TEMPLATEVALL ARRVE IN SEGMENTS AND SOME ASSEMBLY WLL BEREOLARED. THE LENGTH OF THE SEGMENTS WILL BE 0ETFAMNED IN COORDINATION WTTR THE CONTRACTOR
4 ARTIST WILL PRO.IDEWSGHTS FOR EACH OF IDE ARTWORK PMELS MD MOOING MO P1CK PONi5. THIS WILL BE COORDINATED

ON THE PRE-CONSIRUCRON MEETING

5. CONTRACTOR IS RESPONSIBLE FOR THE WSTALLAT1ONAM] ASSEMBLY OF ALL FABRICATED COMPONENTS

6. AL. ARTWORK PANELS WILL BE LABELED ON THE TOP PATEINOICATNG THE PANEL'S NAME ANDORENTATION \\I11WII
It6'[10' TYPE 3H.

LOCABLE CMINET
TYPE 3R CABINET- PLAN VIEW
Ike
0-5
01 CROSS SECTION
AAL+
rota n
TYP

24. MINI
#311ES ®d 0.0
444 9 12.O.C/41ORIZONTAL EACH
FACE
3• CIA
TYP
- LIGHT FIXTURE SECURITY COVER
(PROVIDED BY FABRICATOR AT

COST TO CONTRACTOR FOR

CONTRACTOR INSTALLATION)

LIGI-IT FIXTURE (PROVIDED BY

CONTRACTOR)

CONDUIT (SEE ELECTRICAL

ENGINEERING BY CAL TRANS )

TOP SURFACE OF CONCRETE

MUST BE SLOPED FOR DRAINAGE
12X12 W/ (2) 4.4

HORQONTAL Q BOTTOM
02 DETAL
F DOME HEAD SEcupor

GALVAINZED STEEL BOLT (ORAL
ANO
SCHEDULE 40P&E)4

MIMMUM CONNECDO NS PEA

LETTER (PROVIDED BY FABRICATOR)
)}•TH10,LLLIM

PRIED AND
PAWEDPAED STEELST1 VN11IR.

ST F
(PROVIDED BY ABRIC/410EO
SCHEDULE 40 RPENIIHVNYI.

7.7?
(PRONGED BY FABRGATCR
03 000aL
}OP SCHIA
EDE40 PTE

G BY FABRCARIE
4B
WAGLLVd®STEEL

WASHER TOP AND BOTTOM

11.51. IAL HOLE FCR
IN5TNLASTAUATOP TOLERANCE

NDA ASTM FISH GRADE SS

GALVANIZED STEEL ANCHOR ROOS
W/ ALIT 6 WAGLEA AT BOTTOM
(PROIIOED BY CONTRACTOR)

GALVAPCIED STEEL MIT
B %( PAINT, STEEL EASE ;UTE
0ROVEM EY RAMC -ATOM
1HKA(GROUT (TO BE APPLIED
AFTER PAPTL rNSrAUATIONI
CAST ANCHOR RO05 (PRO'AOED
USING TEM23A1O 9IIIO 87BIB I
CE
ALCM ACO ISEESHE£!
MITAo FOR

LOGRONS

OA DENAIL

0. 0E137
MPI
-1—--}^Yo• —t-
1 t DLA SCHEDULE 40 PRE
/ TACT DEO BY ABRGITITR
E£ DIA ASTM F1554 GENIE 55 G4LVA1T15
STEELAVCHOR ROOS X B IAN. FMB IT OC.

MAY W/ MIT WASHER AT BOTTOM -STAGGER
BOLTS } DEW 1008 TPP TROPIC/ED BY
ozNTRAcrORI
1 } DIA SCHEDULE 40 RPE ABOVE
TARO.IDED BY FAN4CATOR)
B MIX X ? CK STANDARD STEEL
BASE PLATEPRAEO 0115
FM04Wm FAB111.10B
GAT ANCNOR RODS TR04DEO
FABRCATOR1 IN PLACE'MID TFANATES
ROMEO BY ARDS, SEE 51@ MT -10
FOR LOUTIO 0110LTING TEMPLATE FOR

CASTH RMO

RACE ANCHORS PRONGED BY

STAT COST TO CONRYCTDRR
MA•47WiXEXATQCK

TCHNG PLATE BEIWEDI

ART SCEEFN SECTIONS

TROMPED BY FABRICATOR)
4t NI. AM SCREEN

PANTED STEEL TOP PLATE
(PRONGED IN FABRICATOR)
e :

Cliff Garton Studio
1315 Preston Way
Venice, California 90291
310.392.2060 TEL
T9i I Igorlensludio. Com
PRaEcrI TLE

PIACENTIA GATEWAY

PLACENTIA , CA

CHROMATIC ASCENSION
SR -57/ ORANGETHORPE, PIACENTIA
GENT

CRY OF PLACENTIA CALIFORNIA
401 E CHAPM N AVE
PLACENTIA CA 92670
(714) 993-5120
MOST

CUFF GAATEN STUDIO
1315 PRESTON WAY
VENICE, CA 90292
310.392-2060
scu5PTLIREENGINEERING

PATRELL ENGINEERING GROUP
751 SUNNY GROVE LANE
GLENDORA, CA 91741
626.3354362
nF_•CAPrpR GATE

MET RAR
Till -t1 WILL

DETAILS
2104
DRAWN BY:

Ora
SCALE
01002023
ART -11

r�i//lll�l0���llll1 //w
01 FATTTSCUlPRIE ELELVATGN
�tl rrrl l rrrrl rrrl l rrrl rrrrl rrrl l rrrll rrrl l r��l �rrl etietn
riettA
rent
j6uPP0AT POST
€OuDAYTON
Vj � Y.F11 SCULPTURE Fi n NATION
02 SDUTH SCULPTURE ELELVAI10N
0 NORTH SCULPTURE 8.ELVATION
Cliff Gorten Studio
1315 Preston Way
Venice. California 90291
310.392.2060 TEL
clillgarleaaludio.com

PROJECT TITLE

PLACENTIA GATEWAY

PLACENTIA, CA

CHROMATIC ASCENSION
5R-57/ ORANGETHORPE, PLACENTIA
wENr
CRY OF PLACENTIA. CALIFORNIA
401 E CHAPMAN AVE.

PLACENTIA CA 92670
(714) 993-8120
ARTIST

CUFF GARTEN STUDIO
1315 PRESTON WAY
VENICE, CA 90292
310-392-2060

SCULPTURE ENPNEENINGG

PATRELL ENGINEERING GROUP
751 SUNNY GROVE LANE
GLEN00RA CA 91741
828-5'+v'382
NO. DESCRIPTION DATE

KEY KAN

ELEVATIONS
arai
DRAWN 0,
01962023
ART -03

Project Title: Placentia Art Sculpture Pedestal Project Owner:

Contract Change Order No. 3
CIN of nrnnYs Contractor: M.s. Constructlon r.1anaaement Grotto You are hereby directed to make the herein described changes from the plans and specifications or to do the following described work not included in the plans and specifications on this contract:

Additional work is needed gnnd existing exterior surface of the sculpture pedestal concrete wall 8 apply new epoxy coating 1 2 This Change Order came about from:

This Change Order provides:
a) Extra work and credits identified in Exhibit A
58,982.57
a)
During the course of the pxgecl. It wee noted Ihet additional work is needed for labor cost to grind the existing exterior surface of the sculp(uro podelal concrete wall. apply now epoxy coating and gala coating 3 Action to be taken:
a) The Contractor was directed to provide a lump sum pace for this change. 4 Compensation
a) Adjustment of Line Items exceeding 25%
b) Extra work
d) Credits
Total
5 Contract Time Extension
a) 0
58,982 57
$ 8,982.57
In addition to work specified in the bid specifications, this change order includes all extra work, field adjustments and credits. This work is an Contractor initiated change and includes all labor, equipment, materials, and supervision and Adminstration.

CHANGE TO CONTRACT COST: CHANGE TO CONTRACT TIME:

Contract Amount: $
Previous CCOs: $
Adjustment of Line Items Exceeding 25%
Total Extra Work
Total Field Adjustments
Total Credits
Changes in Line Items:

Current Contract price:

Recommended:

Approved by:

Luis Estevez, Deputy City Administrator, City of Placentia Damien ' Arrula, City Adminis rator, City of Pfx ntia
5 $
5 $
5 398,400.00
23,334.11
8,982.57
8,982.57
430,716.68
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal, is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above Accepted:

Milt
Mike Saghati, MS Construction
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified.

M.S. Construction Mgmnt. Group
General Engineering Contractors
Commercial . Residential
"PROPOSAL "
Request for change order
PROPOSAL NUMBER: PLA -P005
March 20, 2024
TO :

Mr. Luis Estevez
Deputy City Administrator
City of Placentia
License # 721738
PROJECT: Sculpture Installation Concrete Pedestal Construction and Site Improvements Project Placentia, Ca.
************************************************************************************** Per your request, the following is the cost proposal related to the labor cost to grind the existing exterior surface of the Sculpture pedestal concrete wall, apply new epoxy coating and graffiti coating at the above captioned project:

Please refer to the enclosed cost breakdown $8.893.64
Sub -Total $8.893.64
Bond fee (1%) $ 88.93
Grand Total $8,982.57
Grand Total ,..,,W $8,982.57
NOTE: Please add 3 working days to the project completion date for this work ********************************************************************************** Acceptance: You are hereby authorized to perform the above-mentioned extra work for the price indicated. A change order toithe o 'gina( cntract would be created at a later date.

Signed: � Date: /0"1"/

M.S. CONSTRUCTION MGMNT. GROUP

PUBLIC WORKS -- CONSTRUCTION DIVISION
EXTRA WORK BREAKDOWNREPORT C.C.O. NO. REPORT NO. 1
PROJECT NAME Sculpture Installation Concrete Pedestal Construction and Site Improvements Projec AMOUNT AUTHORIZED Placentia, Ca. PREVIOUS EXPENDITURE

80.00 W,O. # PROPOSAL# PLA•P003 DATE PERFORMED TODAY $8,893.64 DATE OF REPORT 3/20/2024 TO DATE $8,893.64
DESCRIPTION OF wORK Per your request, the following is the cost proposal related to the labor cost to grind the existing exterior surface of the Sculpture pedestal concrete wall, =Iv new enoxv coating and graffiti coating at the above cautioned project:

NO, I
NAME
% LABOR SURCHARGE REGULAR

SUBSISTENCE

TRAVEL EXPENSE
OTHER
NO. ICALTRANS EQ.

RENTAL CODE

LABOR POSITION / CLASSIFICATION HOURLYRATEHOURS I AMOUNTS 2 Cement Masons
889966..76440 $3,865.60
2 Laborers $96.70 40 $3,868.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
LABOR SUB -TOTAL 87,733.60
NO.

NO.

EQUIPMENT
NO. I MATERIALS
1 11 3
1 12
13 I 3
TOTAL COST OF LABOR 1 A
$7,733.60

HOURLY HOURS EXTENDED

RATE AMOUNTS
$0.00

0.00 $0.00

0.00 80.00

0.00 $0.00

80.00 UNIT EXTENDED

COST I TAX I AMOUNTS
Moo 50.00

50.00 50.00

50.00 50.00

50.00 80.00
The above record is complete and correct
Contractor's Representative
TOTAL COST OF EQUIPMENT AND MATE[ALS
15 % on Labor Cost
FOR OFFICE USE ONLY 15% on Equipment & Materials Cost
SUBTOTAL -1:A.+B+C+D
Paid on Est. No.
0% on Subtotal - 1
Checked by SUBTOTAL - 2: Subtotal - 1+ E
$0.00 $0.00
$0.00 $0.00
$0.00 $0.00
1 B $0.00
C 51,160.04
D 50.00
58,893.64
E 50.00
$8,893.64
F
TOTAL THIS REPORT 1 $8,893.64

CITY OF PLACENTIA

CALIFORNIA
(714) 993-8134
VENDOR: MS CONSTRUCTION MANAGEMENT GROUP
32565B GOLDEN LANTERN #475
DANA POINT, CA 92629
Req. #
PR004479
Confirming
❑y yes no

QUANTITY UNIT
1 EA
1 1 EA
Vendor #
V012613
Confirmed to

CONTRACT

CONSTRUCTION SVS

CONSTRUCTION SVS
CHANGE ORDER # 1

CONSTRUCTION SVS
CHANGE ORDER # 2

ACCOUNT DISTRIBUTION
101206 6730 101206 6730
Ship Via
Bestway

DESCRIPTION
AMOUNT
421,734.11
PURCHASE ORDER NO.

P13003

TO RECEIVE PROPER PAYMENT THE ABOVE PO NUMBER MUST APPEAR ON ALL INVOICES. BILLS OF L&DINO PACKAGES. CORRESPONDENCE. ETC.

SHIP TO: CITY OF PLACENTIA
401 E CHAPMAN AVE
PLACENTIA, CA 92870
BILL TO: CITY OF PLACENTIA
401 E CHAPMAN AVE
PLACENTIA, CA 92870
Department

PUBLIC WORKS
Terms
BY:

Date Required
07/27/23

UNIT PRICE
398,400.00
14,316.74

EXTENDED PRICE
398,400.00
14,316.74
9,017.37 9,017.37
Tax 0.00
TOTAL 421,734.11
Director of Finance

CONDITIONS -READ CAREFULLY

1. Shipping charges prepaid by vendor.

2. Payment will be made on complete shipments only,
unless otherwise requested.

3. DELIVERY TICKET MUST ACCOMPANY GOODS.

4. No back orders. We will reorder if available.

5. Please make delivery between 9 A.M. and 4 P.M.

6. All goods received with subsequent privilege to inspect and return at vendors expense if defective or not in corn pliance with our specifications.

7. Indoor delivery if possible.

8. Payment net 30 or according to contract.