Cities Index.
1.G AWARD CONTRACT TO CJ CONCRETE CONSTRUCTION, INC. FOR FY 2024-25 CONCRETE REPAIR PROJECT, CITY PROJECT NO. 1502

Placentia City Council
January 14, 2025

Document
1.G AWARD CONTRACT TO CJ CONCRETE CONSTRUCTION, INC. FOR FY 2024-25 CONCRETE REPAIR PROJECT, CITY PROJECT NO. 1502
Meeting
January 14, 2025
Body
Placentia City Council
Pages
2
Original file
103 KB
Text extracted from the city's file for reading and search. Open the original on portal.laserfiche.com. That file is the official record.

Agenda Item No: 1.g

PLACENTIA CITY COUNCIL AGENDA REPORT
Meeting Date: January 14, 2025
Submitted by: Samantha Byfield
From: Public Works
Subject:

Award of Contract to CJ Concrete Construction, Inc. for FY 2024-25 Concrete Repair Project, City Project No. 1502
Financial Impact:

Fiscal Impact:

Expense: $ 110,246.40 Total Construction Contract Amount $ 91,872.00 Construction Contract Amount
$ 18,374.40 Construction Contingency Amount
Available Budget: $ 140,780.00 Fiscal Year 2024-25 CIP Budget (791502-6740)
Summary:

The Fiscal Year (FY) 2024-25 Capital Improvement Program (CIP) Budget includes the Concrete Repair Project. The scope of this project includes the removal and replacement of damaged sidewalk, curb and gutter at various locations. The Public Works Department has identified a number of locations where these repairs are needed and plans to utilize this contract to address that work as part of an ongoing annual concrete repair program. The City solicited competitive bids for this project and a total of nine bids were received on November 14, 2024. The lowest bid from CJ Concrete Construction, Inc., was found to be the lowest responsive and responsible bid. Staff recommends that City Council award a construction contract to CJ Concrete Construction, Inc., in the amount of $91,872. In addition to the construction cost, there is a 20% construction contingency amount of $18,374.40 included to cover unforeseen conditions and to address possible additional locations within the existing project budget. The total construction contract cost including the contingency amount is $110,246.40.

Recommendation:

Recommended Action: It is recommended the City Council:

1. Award a Public Works Agreement to CJ Concrete Construction, Inc., for the FY 2024-25 Concrete Repair Project, City Project No. 1502, in the amount of $91,872; and

2. Reject all other bids received and authorize the return of the bid bonds; and

3. Authorize the Interim City Administrator to approve contract change orders up to 20% or $18,374.40 for a total construction contract not-to-exceed amount of $110,246.40; and

4. Authorize the Interim City Administrator and/or his designee to execute all necessary documents, in a form approved by the City Attorney.
1 Strategic Plan Statement:

There is no specific strategic planning goal or objective associated with this agenda item.

Discussion:

The scope of this project includes the removal and replacement of sidewalk, curb and gutter at various locations around the city. The locations have been identified by staff and/or resident reports and have been prioritized to address those locations with the most immediate need for repair within the project budget. A portion of the project budget will be utilized to remove trees which have damaged infrastructure at these locations. That work will be completed by the City's tree services contractor, West Coast Arborists, in conjunction with the concrete work awarded under this agreement.

On November 14, 2024, the City received nine (9) bids from contractors for this work. The results are displayed in the table below:

Contractor Bid Amount
CJ Concrete
Construction, Inc.$91,872.00
All Cities
Engineering, Inc.$106,972.50
TVR Constructions
Engineering, LLC $117,782.50
Gentry General
Engineering, Inc.$121,277.00
We R Builders, Inc.$123,565.50
Pavement Rehab
Company $128,000.00
Red Castle
Construction $187,678.97
Metrocell
Construction, Inc.$190,331.00
HZS Engineering,
Inc.$287,613.00

After reviewing the bids, it was determined that CJ Concrete Construction, Inc., submitted the lowest bid. Staff reviewed and analyzed the bid and found it to be responsive and valid. Staff recommends that Council award a construction contract to CJ Concrete Construction, Inc. for the FY 2024-25 Concrete Repair Project.

Fiscal Impact Summary:

The total construction cost for this project amounts to $110,246.40. This cost consists of the bid amount submitted by CJ Concrete Construction, Inc. in the amount of $91,872 and a construction contingency in the amount of $18,374.40. A total of $155,000 was budgeted in the FY 2024-25 CIP budget for this project. A total of $14,220.00 from the project budget has already been set aside for the tree removals needed under this project. There is an available project balance of $140,780 for the construction of the project. As such, sufficient funds exist for the recommended actions.

Attachments
2 Public Works Agreement with CJ Concrete Construction Inc.pdf 3 Project No. 1502
1 CITY OF PLACENTIA

PUBLIC WORKS AGREEMENT FOR
FY 2024-2025 CONCRETE REPAIR, CITY PROJECT NO. 1502
THIS AGREEMENT (herein “Agreement”) is made and entered into this 14th day of January, 2025 by and between the CITY OF PLACENTIA, a municipal corporation and charter city, (herein “City”) and CJ Concrete Construction, Inc. (herein “Contractor”). The parties hereto agree as follows:

W I T N E S S E T H :

A. WHEREAS, City requires the construction of concrete repairs as set forth more fully in this Agreement.

B. WHEREAS, Contractor represents to City that Contractor is qualified to perform said work and has submitted a proposal to City for the same.

C.WHEREAS, City desires to have Contractor perform said services on the terms and conditions set forth herein.

D.WHEREAS, no official or employee of City has a financial interest, within the provisions of Sections 1090-1092 of the California Government Code, in the subject matter of this Agreement.

NOW, THEREFORE, for and in consideration of the mutual covenants and conditions contained herein and for good and valuable consideration, the receipt and sufficiency of which is acknowledged by both parties, City and Contractor hereby agree as follows:

1.0 DEFINITIONS

1.1 Definitions. As used in this Agreement, the following definitions shall be applicable:
(a) Contractor. Contractor shall mean CJ Concrete Construction, Inc. a (California corporation, partnership, individual) located at 10142 Shoemaker Ave., Santa Fe Springs, CA 90670.
(b)City. City shall mean the City of Placentia, a Municipal Corporation and Charter City, located at 401 E. Chapman Ave., Placentia, California 92870. (c)City Council. City Council shall mean the City Council of the City of Placentia.
(d)Contract Officer. Contract Officer shall mean the person designated by the City Administrator or City Engineer of City and shall have the duties set forth in Section 5.2.
(e)Services. Services shall mean the services to be performed by the Contractor pursuant to this Agreement.
4 Project No. 1502

2 (f) Satisfactory. Satisfactory shall mean satisfactory to the City Administrator or his/her designee.

2.0 SERVICES OF CONTRACTOR

2.1 Scope of Services. In compliance with all terms and conditions of this Agreement, the Contractor shall provide those services specified in the “Scope of Services” attached hereto as Exhibit “A” and incorporated herein by this reference, which services may be referred to herein as the “services” or “work” hereunder. As a material inducement to the City entering into this Agreement, Contractor represents and warrants that Contractor is a provider of first class work and services and Contractor is experienced in performing the work and services contemplated herein and, in light of such status and experience, Contractor covenants that it shall follow the highest professional standards in performing the work and services required hereunder and that all materials will be of good quality, fit for the purpose intended.

2.2 Documents Included in Contract. This contract consists of this Agreement and any Exhibits, which are incorporated herein by this reference. In the event of an inconsistency, the terms of this Agreement shall govern.

2.3 Compliance with Law. All services rendered hereunder shall be provided in accordance with all ordinances, resolutions, statutes, rules, and regulations of the City and any Federal, State, or local governmental agency having jurisdiction in effect at the time service is rendered, including but not limited to, the claims procedure set forth in Public Contract Code Section 9204, a summary of which is attached to this agreement as Exhibit “E”.

2.4 Licenses, Permits, Fees, and Assessments. Contractor shall obtain at its sole cost and expense such licenses, permits, and approvals as may be required by law for the performance of the services required by this Agreement, including registration with the Department of Industrial Relations of the State of California as required by Labor Code Section 1725.5 before commencing performance under this Agreement. Contractor shall have the sole obligation to pay for any fees, assessments, and taxes, plus applicable penalties and interest, which may be imposed by law and arise from or are necessary for the Contractor's performance of the services required by this Agreement, and shall indemnify, defend, and hold harmless City against any such fees, assessments, taxes penalties, or interest levied, assessed, or imposed against City hereunder.

Contractor shall be responsible for all subcontractors' compliance with this Section 2.4.

2.5 Familiarity with Work. By executing this Contract, Contractor warrants that Contractor (a) has thoroughly investigated and considered the scope of services to be performed, (b) has carefully considered how the services should be performed, and (c) fully understands the facilities, difficulties, and restrictions attending performance of the services under this Agreement. If the services involve work upon any site, Contractor warrants that Contractor has or will investigate the site and is or will be fully acquainted with the conditions there existing, prior to commencement of services hereunder. Should Contractor discover any latent or unknown conditions, which will materially affect the performance of the services hereunder, Contractor shall immediately inform the City of such fact and shall not proceed except at Contractor's risk until written instructions are received from the Contract Officer.

2.6 Standard of Performance. Contractor, its subcontractors, and their employees, in the performance of Contractor’s work under this Agreement, shall be responsible for exercising the 5 Project No. 1502

3 degree of skill and care required by customarily accepted good professional practices and procedures used in the Contractor’s field.

Any costs for failure to meet the foregoing standard or to correct otherwise defective work that requires re-performance of the work, shall be borne in total by the Contractor and not by the City. The failure of a project to achieve the performance goals and objectives stated in this Agreement is not a basis for requesting re-performance unless the work conducted by Contractor and/or its subcontractors is deemed by the City to have failed the foregoing standard of performance.

In the event Contractor fails to perform in accordance with the above standard:

1. Contractor will re-perform, at its own expense, any task which was not performed to the reasonable satisfaction of City. Any work re-performed pursuant to this paragraph shall be completed within the time limitations originally set forth for the specific task involved.

Contractor shall work any overtime required to meet the deadline for the task at no additional cost to the City;

2. The City shall provide a new schedule for the re-performance of any task pursuant to this paragraph in the event that re-performance of a task within the original time limitations is not feasible; and

3. The City shall have the option to direct Contractor not to re-perform any task which was not performed to the reasonable satisfaction of the City Project Manager pursuant to application of (1) and (2) above. In the event the City directs Contractor not to re-perform a task, the City shall negotiate a reasonable settlement for satisfactory work performed.

No previous payment shall be considered a waiver of the City’s right to reimbursement.

Nothing contained in this section is intended to limit any of the rights or remedies which the City may have under law.

2.7 Care of Work. The Contractor shall adopt reasonable methods during the life of the Agreement to furnish continuous protection to the work, and the equipment, materials, papers, documents, plans, studies, and/or other components thereof to prevent losses or damages, and shall be responsible for all such damages, to persons or property, until acceptance of the work by City, except such losses or damages as may be caused by City's own negligence.

2.8 Further Responsibilities of Parties. Both parties agree to use reasonable care and diligence to perform their respective obligations under this Agreement. Both parties agree to act in good faith to execute all instruments, prepare all documents and take all actions as may be reasonably necessary to carry out the purposes of this Agreement. Unless hereafter specified, neither party shall be responsible for the service of the other. Contractor shall require all subcontractors to comply with the provisions of this agreement.

2.9 Additional Services. City shall have the right at any time during the performance of the services, without invalidating this Agreement, to order extra work beyond that specified in the Scope of Services or make changes by altering, adding to, or deducting from said work. No such extra work may be undertaken unless a written change order is first given by the Contract Officer to the Contractor, incorporating therein any adjustment in (i) the Contract Sum as set forth in Section

3.1, and/or (ii) the time to perform this Agreement, which said adjustments are subject to the written approval of the Contractor. Any increase in compensation of ten percent (10%) or less of the Contract Sum, or in the time to perform of one hundred eighty (180) days or less, may be approved 6 Project No. 1502

4 by the Contract Officer. It is expressly understood by Contractor that the provisions of this Section shall not apply to services specifically set forth in the Scope of Services or reasonably contemplated therein. Contractor hereby acknowledges that it accepts the risk that the services to be provided pursuant to the Scope of Services may be more costly or time consuming than Contractor anticipates and that Contractor shall not be entitled to additional compensation therefore.

2.10 Prevailing Wage Laws. Contractor represents and warrants that it is registered with the Department of Industrial Relations as required by SB 854 and Labor Code 1725.5 and understands that this project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contractor shall ensure that its subcontractors comply with said requirements. Contractor shall comply with Labor Code Section 1771.4 and shall post all legally required job site notices. In accordance with Labor Code Section 1770 et seq., the Director of the Department of Industrial Relations of the State of California has ascertained a general prevailing rate of wages, which is the minimum amount, which shall be paid to all workers employed to perform the work pursuant to this Agreement. A copy of the general prevailing wage rate determination is on file in the Office of the City Clerk and is hereby incorporated by reference into this Agreement. In accordance with the provisions of Labor Code Section 1810 et seq., eight (8) hours is the legal working day. Contractor must forfeit to the City Twenty Five Dollars ($25.00) a day for each worker who works in excess of the minimum working hours when Contractor does not pay overtime.

Contractor is required to post a copy of such wage rates at all times at the contract site. The statutory penalties for failure to pay prevailing wage or to comply with State wage and hour laws will be enforced. Contractor also shall comply with State law requirements to maintain payroll records and shall provide for certified records and inspection of records as required by California Labor Code Section 1770 et. seq., including Section 1776. Contractor shall comply with all statutory requirements relating to the employment of apprentices.

3.0 COMPENSATION

3.1 Contract Sum. For the services rendered pursuant to this Agreement, the Contractor shall be compensated as specified herein, but not exceeding the maximum contract amount of One Hundred Ten Thousand and Two Hundred Forty Six Dollars and 40/100 ($ 110,246.40 (herein “Contract Sum”), except as provided in Section 2.9. The Contract Sum shall include the attendance of Contractor at all project meetings reasonably deemed necessary by the City; Contractor shall not be entitled to any additional compensation for attending said meetings.

3.2 Progress Payments. Prior to the first day of the month, during the progress of the work, commencing on the day and month specified in the Agreement, Contractor shall submit to the Contract Officer a complete itemized statement of all labor and materials incorporated into the work during the preceding month and the portion of the contract sum applicable thereto. Upon approval in writing by the Contract Officer, payment shall be made in thirty (30) days. City shall pay Contractor a sum based upon ninety-five percent (95%) of the contract price apportionment of the labor and materials incorporated into the work under the contract during the month covered by said statement. The remaining five percent (5%) thereof shall be retained as performance security. Refer to Section 8.4 of this Agreement for retention of funds.

4.0 PERFORMANCE SCHEDULE

4.1 Time of Essence. Time is of the essence in the performance of this Agreement.

7 Project No. 1502

5 4.2 Schedule of Performance. Contractor shall commence the services pursuant to this Agreement upon receipt of a written notice to proceed and shall perform all services within the time period(s) established in the “Schedule of Performance” attached hereto as Exhibit “B”, and incorporated herein by this reference. When requested by the Contractor, extensions to the time period(s) specified in the Scope of Services may be approved in writing by the Contract Officer.

4.3 Force Majeure. The time period(s) specified in the Scope of Services for performance of the services rendered pursuant to this Agreement shall be extended because of any delays due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God or of the public enemy, unusually severe weather, fires, earthquakes, floods, epidemics, quarantine restrictions, riots, strikes, freight embargoes, wars, litigation, and/or acts of any governmental agency, including the City, if the Contractor shall within ten (10) days of the commencement of such delay notify the Contract Officer in writing of the causes for the delay. The Contract Officer shall ascertain the facts and the extent of delay, and extend the time for performing the services for the period of the enforced delay when and if in the judgment of the Contract Officer such delay is justified. The Contract Officer's determination shall be final and conclusive upon the parties to this Agreement.

4.4 Term. Unless earlier terminated in accordance with Section 8.9 of this Agreement, this Agreement shall continue in full force and effect until final approval and acceptance of the project by the Contract Officer. Notwithstanding the foregoing, this Agreement shall terminate no later than January 14, 2026, unless the parties mutually agree in writing to extend the term.

5.0 COORDINATION OF WORK

5.1 Representative of Contractor. The following principals of Contractor are hereby designated as being the principals and representatives of Contractor authorized to act in its behalf with respect to the work specified herein and make all decisions in connection therewith:

CJ Concrete Construction, Inc.

Attn: John C. Sarno
10142 Shoemaker Ave.

Santa Fe Springs, CA 90670

It is expressly understood that the experience, knowledge, capability and reputation of the foregoing principals were a substantial inducement for City to enter into this Agreement. Therefore, the foregoing principals shall be responsible during the term of this Agreement for directing all activities of Contractor and devoting sufficient time to personally supervise the services hereunder.

For purposes of this Agreement, the foregoing principals may not be replaced nor may their responsibilities be substantially reduced by Contractor without the express written approval of City.

5.2 Contract Officer. The Contract Officer shall be such person as may be designated by the City Administrator or City Engineer of City. It shall be the Contractor's responsibility to assure that the Contract Officer is kept informed of the progress of the performance of the services and the Contractor shall refer any decisions that must be made by City to the Contract Officer. Unless otherwise specified herein, any approval of City required hereunder shall mean the approval of the Contract Officer. The Contract Officer shall have authority to sign all documents on behalf of the City required hereunder to carry out the terms of this Agreement.

8 Project No. 1502

6 5.3 Prohibition Against Assignment. The experience, knowledge, capability, and reputation of Contractor, its principals and employees were a substantial inducement for the City to enter into this Agreement. Neither this Agreement nor any interest herein may be transferred, assigned, conveyed, hypothecated, or encumbered voluntarily or by operation of law, whether for the benefit of creditors or otherwise, without the prior written approval of City. Transfers restricted hereunder shall include the transfer to any person or group of persons acting in concert of more than twenty five percent (25%) of the present ownership and/or control of Contractor, taking all transfers into account on a cumulative basis. In the event of any such unapproved transfer, including any bankruptcy proceeding, this Agreement shall be void. No approved transfer shall release the Contractor or any surety of Contractor of any liability hereunder without the express consent of City.

5.4 Independent Contractor. Neither the City nor any of its employees shall have any control over the manner, mode, or means by which Contractor, its subcontractors, agents, or employees, performs the services required herein, except as otherwise set forth herein. City shall have no voice in the selection, discharge, supervision, or control of Contractor's employees, subcontractors, servants, representatives, or agents, or in fixing their number, compensation, or hours of service. Contractor shall perform all services required herein as an independent contractor of City and shall remain at all times as to City a wholly independent contractor with only such obligations as are consistent with that role. Contractor shall not at any time or in any manner represent that it or any of its subcontractors, agents, or employees are agents or employees of City.

City shall not in any way or for any purpose become or be deemed to be a partner of Contractor in its business or otherwise or a joint venture or a member of any joint enterprise with Contractor.

5.5 Identity of Persons Performing Work. Contractor represents that it employs or will employ at its own expense all personnel required for the satisfactory performance of any and all tasks and services set forth herein. Contractor represents that the tasks and services required herein will be performed by Contractor or under its direct supervision, and that all personnel engaged in such work shall be fully qualified and shall be authorized and permitted under applicable State and local law to perform such tasks and services.

5.6 Utility Relocation. City is responsible for removal, relocation, or protection of existing main or trunkline utilities to the extent such utilities were not identified in the invitation for bids or specifications. City shall reimburse contractor for any costs incurred in locating, repairing damage not caused by contractor, and removing or relocating such unidentified utility facilities, including equipment idled during such work. Contractor shall not be assessed liquidated damages for delay arising from the removal or relocation of such unidentified utility facilities.

5.7 Trenches or Excavations. Pursuant to California Public Contract Code Section 7104, in the event the work included in this Agreement requires excavations more than four (4) feet in depth, the following shall apply.

(a) Contractor shall promptly, and before the following conditions are disturbed, notify City, in writing, of any: (1) material that Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law; (2) Subsurface or latent physical conditions at the site different from those indicated; or (3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and 9 Project No. 1502

7 generally recognized as inherent in work of the character provided for in the contract.

(b) City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the work shall issue a change order per Section 2.9 of this Agreement.

(c) That, in the event that a dispute arises between City and Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in Contractor’s cost of, or time required for, performance of any part of the work, Contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. Contractor shall retain any and all rights provided either by contract or by law, which pertain to the resolution of disputes and protests between the contracting parties.

6.0 INSURANCE, INDEMNIFICATION, AND BONDS

6.1 Insurance. The Contractor and all subcontractors, if any, shall procure and maintain, at its sole cost and expense, in a form and content satisfactory to City, during the entire term of this Agreement, including any extension thereof, insurance as set forth in Exhibit “C” attached hereto and incorporated herein by this reference.

Conditions:

In accordance with Public Contract Code Section 20170, the insurance of surety companies who provide or issue the policy shall have been admitted to do business in the State of California with a credit rating of A- or better.

The City of Placentia, its officers, officials, employees, agents, and volunteers shall be named as additional insureds.

Prior to commencement of any work under this contract, Contractor shall deliver to the City insurance endorsements confirming the existence of the insurance required by this contract, and including the applicable clauses as set forth in Exhibit “C” attached hereto and incorporated herein by this reference.

Such endorsements shall be signed by an authorized representative of the insurance company and shall include the signatory's company affiliation and title. Should it be deemed necessary by the City, it shall be Contractor's responsibility to see that the City receives documentation, acceptable to the City, which sustains that the individual signing said endorsements is indeed authorized to do so by the insurance company.

If the Contractor fails to maintain the aforementioned insurance, or secure and maintain the aforementioned endorsement, the City may obtain such insurance, and deduct and retain the amount of the premiums for such insurance from any sums due under the agreement. However, procuring of said insurance by the City is an alternative to other remedies the City may have, and is not the exclusive remedy for failure of Contractor to maintain said insurance or secure said endorsement. In addition to any other remedies 10 Project No. 1502

8 the City may have upon Contractor's failure to provide and maintain any insurance or policy endorsements to the extent and within the time herein required, the City shall have the right to order Contractor to stop work hereunder, and/or withhold any payment(s) which became due to Contractor hereunder until Contractor demonstrates compliance with the requirements hereof.

Nothing herein contained shall be construed as limiting in any way the extent to which Contractor may be held responsible for payments of damages to persons or property resulting from Contractor's or its subcontractor's performance of the work covered under this agreement.

Each contract between the Contractor and any subcontractor shall require the subcontractor to maintain the same policies of insurance that the Contractor is required to maintain pursuant to this Section 6.1.

6.2 Certificates of Insurance. Contractor shall provide to City certificates of insurance showing the insurance coverages, as well as providing the City with the required endorsements, in a form and content approved by City, prior to performing any services under this Agreement.

The certificates of insurance and endorsements shall be attached to this Agreement as Exhibit “D” and are incorporated herein by this reference.

6.3 Indemnification. Contractor shall protect, defend, indemnify, and hold free and harmless the City of Placentia, its officers, officials, employees, agents, and volunteers, at Contractor’s sole expense, from and against any and all actions, suits, claims, damages to persons or property, losses, costs, penalties, obligations, errors, omissions, or liabilities (herein “claims or liabilities”) that may be asserted or claimed by any person, firm, or entity arising or alleged to arise out of or in any way connected with the performance of the work, operations, or activities of Contractor, its agents, employees, subcontractors, or invitees, provided for herein, or arising or alleged to arise from the acts or omissions of Contractor hereunder, or arising or alleged to arise from Contractor's performance of or failure to perform any term, provision, covenant or condition of this Agreement including all acts or omissions, willful misconduct or negligent conduct, whether active or passive, on the part of the Contractor, its employees, and/or subcontractors.

(a) Contractor will defend any action or actions filed in connection with any of said claims or liabilities and will pay all costs and expenses, including legal costs and attorneys’ fees incurred in connection therewith.

(b) Contractor will promptly pay any judgment rendered against the City, its officers, officials, employees, agents, or volunteers for any such claims or liabilities arising or alleged to arise out of or in connection with Contractor’s (or its agents’, employees’, subcontractors’, or invitees’) negligent performance of or failure to perform such work, operations, or activities hereunder; and Contractor agrees to save and hold the City, its officers, officials, employees, agents, and volunteers harmless therefrom.

(c) In the event the City, its officers, officials, employees, agents, or volunteers are made a party to any action or proceeding filed or prosecuted against Contractor for such damages or other claims arising or alleged to arise out of or in connection with the performance of or failure to perform the work, operation or activities of Contractor hereunder, Contractor shall pay to the 11 Project No. 1502

9 City, its officers, officials, employees, agents, or volunteers any and all costs and expenses incurred by the City, its officers, officials, employees, agents, or volunteers in such action or proceeding, including but not limited to, legal costs and attorneys’ fees for counsel selected by City.

(d) Contractor's duty to defend and indemnify as set out in this Section 6.3 shall include any claims, liabilities, obligations, losses, demands, actions, penalties, suits, costs, expenses or damages or injury to persons or property arising or alleged to arise from, in connection with, as a consequence of or pursuant to any State or Federal law or regulation regarding hazardous substances, including but not limited to the Federal Insecticide, Fungicide and Rodenticide Act (“FIFRA”), Comprehensive Environmental Response, Compensation and Liability Act of 1980 (“CERCLA”), Resource Conservation and Recovery Act of 1976 (“RCRA”), the Hazardous and Solid Waste Amendments of 1984, the Hazardous Material Transportation Act, the Toxic Substances control Act, the Clean Air Act, the Clean Water Act, the California Hazardous Substance Account Act, the California Hazardous Waste Control Law or the Porter-Cologne Water Quality Control Act, as any of those statutes may be amended from time to time.

Notwithstanding the foregoing, Contractor shall not be liable for the defense or indemnification of the City for claims, actions, complaints, or suits arising out of the sole active negligence or willful misconduct of the City.

The Contractor's indemnification obligations pursuant to this Section 6.3 shall survive the termination of this Agreement. Contractor shall require the same indemnification from all subcontractors.

6.4 Labor and Materials and Performance Bonds. Concurrently with execution of this Agreement, Contractor shall deliver to City a labor and materials bond and a performance bond each in the sum of the amount of this Agreement, in the forms provided by the City Clerk, which secures the faithful performance of this Agreement. The bonds shall contain the original notarized signature of an authorized officer of the surety and affixed thereto shall be a certified and current copy of his power of attorney. The bonds shall be unconditional and remain in force during the entire term of the Agreement and shall be null and void only if the Contractor promptly and faithfully performs all terms and conditions of this Agreement.

6.5 Sufficiency of Insurer or Surety. Insurance required by this Agreement shall be satisfactory only if issued by companies qualified to do business in California, rated “A-” or better in the most recent edition of Best’s Key Rating Guide or in the Federal Register, and only if they are of a Financial Size Category Class VII or larger, unless such requirements are waived by the Risk Manager of the City due to unique circumstances. In the event the Project Manager and Risk Manager determine that the work or services to be performed under this Agreement creates an increased risk of loss to the City, the Contractor agrees that the minimum limits of the insurance policies required by this Section 6 may be changed accordingly upon receipt of written notice from the Project Manager provided that the Contractor shall have the right to appeal a determination of increased coverage by the Project Manager to the City Council of City within ten (10) days of receipt of notice from the Project Manager.

12 Project No. 1502

10 6.6 Substitution of Securities. Pursuant to California Public Contract Code Section 22300, substitution of eligible equivalent securities for any monies withheld to ensure performance under the contract for the work to be performed will be permitted at the request and expense of the successful bidder.

7.0 RECORDS AND REPORTS

7.1 Reports. Contractor shall periodically prepare and submit to the Contract Officer such reports concerning the performance of the services required by this Agreement as the Contract Officer shall require. Contractor hereby acknowledges that the City is greatly concerned about the cost of work and services to be performed pursuant to this Agreement. For this reason, Contractor agrees that if Contractor becomes aware of any facts, circumstances, techniques, or events that may or will materially increase or decrease the cost of the work or services contemplated herein or, if Contractor is providing design services, the cost of the project being designed, Contractor shall promptly notify the Contract Officer of said fact, circumstance, technique or event and the estimated increased or decreased cost related thereto and, if Contractor is providing design services, the estimated increased or decreased cost estimate for the project being designed.

7.2 Records. Contractor shall keep, and require subcontractors to keep, such books and records (including but not limited to payroll records as required herein) as shall be necessary to perform the services required by this Agreement and enable the Contract Officer to evaluate the performance of such services. The Contract Officer shall have full and free access to such books and records at all times during normal business hours of City, including the right to inspect, copy, audit and make records and transcripts from such records. Such records shall be maintained for a period of three (3) years following completion of the services hereunder, and the City shall have access to such records in the event any audit is required.

7.3 Ownership of Documents. All drawings, specifications, reports, records, documents, and other materials prepared by Contractor, its employees, subcontractors, and agents in the performance of this Agreement shall be the property of City and shall be delivered to City upon request of the Contract Officer or upon the termination of this Agreement, and Contractor shall have no claim for further employment or additional compensation as a result of the exercise by City of its full rights of ownership of the documents and materials hereunder. Contractor may retain copies of such documents for its own use. Contractor shall have an unrestricted right to use the concepts embodied therein. All subcontractors shall provide for assignment to City of any documents or materials prepared by them, and in the event Contractor fails to secure such assignment, Contractor shall indemnify City for all damages resulting therefrom.

7.4 Public Records Act Disclosure. Contractor has been advised and is aware that this Agreement and all reports, documents, information, and data, including, but not limited to, computer tapes, discs or files furnished or prepared by Contractor, or any of its subcontractors, pursuant to this Agreement and provided to City may be subject to public disclosure as required by the California Public Records Act (California Government Code Section 7920.000 et seq.). Exceptions to public disclosure may be those documents or information that qualify as trade secrets, as that term is defined in the California Government Code Section 7924.510, and of which Contractor informs City of such trade secret. The City will endeavor to maintain as confidential all information obtained by it that is designated as a trade secret. The City shall not, in any way, be liable or responsible for the disclosure of any trade secret including, without 13 Project No. 1502

11 limitation, those records so marked if disclosure is deemed to be required by law or by order of the Court.

8.0 GENERAL PROVISIONS

8.1 Governing Law. This Agreement shall be construed and interpreted both as to validity and to performance of the parties in accordance with the laws of the State of California. Legal actions concerning any dispute, claim, or matter arising out of or in relation to this Agreement shall be instituted in the Superior Court of the County of Orange, State of California, or any other appropriate court in such county, and Contractor covenants and agrees to submit to the personal jurisdiction of such court in the event of such action.

8.2 Representatives. The City Administrator or his or her designee shall be the representative of City for purposes of this Agreement and may issue all consents, approvals, directives, and agreements on behalf of the City, called for by this Agreement, except as otherwise expressly provided in this Agreement.

The Principal set forth in Section 5.1 above shall be the representative for Contractor for purposes of this Agreement, and shall be authorized to issue all consents, approvals, directives, and agreements on behalf of Contractor called for by this Agreement, except as otherwise expressly provided in this Agreement.

8.3 Disputes. In the event either party fails to perform its obligations hereunder, the nondefaulting party shall provide the defaulting party written notice of such default. The defaulting party shall have ten (10) days to cure the default; provided that, if the default is not reasonably susceptible to being cured within said ten (10) day period, the defaulting party shall have a reasonable time to cure the default, not to exceed a maximum of thirty (30) days, so long as the defaulting party commences to cure such default within ten (10) days of service of such notice and diligently prosecutes the cure to completion; provided further that if the default is an immediate danger to the health, safety and general welfare, the defaulting party shall take such immediate action as may be necessary. Notwithstanding the foregoing, the nondefaulting party may, in its sole and absolute discretion, grant a longer cure period. Should the defaulting party fail to cure the default within the time period provided in this Section, the nondefaulting party shall have the right, in addition to any other rights the nondefaulting party may have at law or in equity, to terminate this Agreement.

Compliance with the provisions of this Section 8.3 shall be a condition precedent to bringing any legal action, and such compliance shall not be a waiver of any party's right to take legal action in the event that the dispute is not cured.

8.4 Retention of Funds. Progress payments shall be made in accordance with the provisions of Section 3.2 of this Agreement. In accordance with said section, City shall pay Contractor a sum based upon ninety-five percent (95%) of the contract price apportionment of the labor and materials incorporated into the work under the contract during the month covered by said statement. The remaining five percent (5%) thereof shall be retained as performance security to be paid to the Contractor within sixty (60) days after final acceptance of the work by the City Council, after Contractor shall have furnished City with a release of all undisputed contract amounts if required by City. In the event there are any claims specifically excluded by Contractor from the operation of the release, the City may retain proceeds (per Public Contract Code 7107) of up to 150% of the amount in dispute. City’s failure to deduct or withhold shall not affect Contractor’s obligations hereunder.

14 Project No. 1502

12 8.5 Waiver. No delay or omission in the exercise of any right or remedy by a nondefaulting party on any default shall impair such right or remedy or be construed as a waiver. A party's consent to or approval of any act by the other party requiring the party's consent or approval shall not be deemed to waive or render unnecessary the other party's consent to or approval of any subsequent act. Any waiver by either party of any default must be in writing and shall not be a waiver of any other default concerning the same or any other provision of this Agreement.

8.6 Rights and Remedies. Rights and Remedies are cumulative except with respect to rights and remedies expressly declared to be exclusive in this Agreement, the rights and remedies of the parties are cumulative and the exercise by either party of one or more of such rights or remedies shall not preclude the exercise by it, at the same or different times, of any other rights or remedies for the same default or any other default by the other party.

8.7 Legal Action. In addition to any other rights or remedies, either party may take legal action, in law or in equity, to cure, correct or remedy any default, to recover damages for any default, to compel specific performance of this Agreement, to obtain declaratory or injunctive relief, or to obtain any other remedy consistent with the purposes of this Agreement.

8.8 Liquidated Damages. Since the determination of actual damages for any delay in performance of this Agreement would be extremely difficult or impractical to determine in the event of a breach of this Agreement, the Contractor and its sureties shall be liable for and shall pay to the City Five Hundred Dollars ($500.00) as liquidated damages for each working day of delay in the performance of any service required hereunder, as specified in the Scope of Services (Exhibit “A”) or Schedule of Performance (Exhibit “B”). The City may withhold from any monies payable on account of services performed by the Contractor any accrued liquidated damages.

8.9 Termination for Default of Contractor. If termination is due to the failure of the Contractor to fulfill its obligations under this Agreement, Contractor shall vacate any City owned property which Contractor is permitted to occupy hereunder and City may, after compliance with the provisions of Section 8.3, take over the work and prosecute the same to completion by contract or otherwise, and the Contractor shall be liable to the extent that the total cost for completion of the services required hereunder exceeds the compensation herein stipulated (provided that the City shall use reasonable efforts to mitigate such damages), and City may withhold any payments to the Contractor for the purpose of setoff or partial payment of the amounts owed the City as previously stated.

8.10 Notice. Any notice, demand, request, document, consent, approval, or communication either party desires or is required to give to the other party or any other person shall be in writing and shall be deemed to be given when served personally or deposited in the U.S. Mail, prepaid, first-class mail, return receipt requested, addressed as follows:

To City: City of Placentia
401 E. Chapman Ave.

Placentia, California 92870
Attn.: Chris Tanio

To Contractor: CJ Concrete Construction, Inc.
10142 Shoemaker Ave.

Santa Fe Springs, CA 90670
Attn: John C. Sarno
15 Project No. 1502

13 8.11 Non-liability of City Officers and Employees. No officer or employee of the City shall be personally liable to the Contractor, or any successor in interest, in the event of any default or breach by the City or for any amount which may become due to the Contractor or to its successor, or for breach of any obligation of the terms of this Agreement.

8.12 Conflict of Interest. The Contractor warrants that it has not paid or given and will not pay or give any third party any money or other consideration for obtaining this Agreement.

Contractor and its officers, employees, associates, and subcontractors, if any, will comply with all conflict of interest statutes of the State of California applicable to Contractor's services under this agreement, including, but not limited to, the Political Reform Act (Government Code Sections 81000, et seq.) and Government Code Section 1090. During the term of this Agreement, Contractor and its officers, employees, associates, and subcontractor shall not, without the prior written approval of the City Representative, perform work for another person or entity for whom Contractor is not currently performing work that would require Contractor or one of its officers, employees, associates, or subcontractors to abstain from a decision under this Agreement pursuant to a conflict of interest statute. Contractor’s duties and services under this Agreement shall not include preparing or assisting the City with any portion of the City’s preparation of a request for proposals, request for qualifications, or any other solicitation regarding a subsequent or additional contract with the City. The City shall at all times retain responsibility for public contracting, including with respect to any subsequent phase of this project. Contractor’s participation in the planning, discussions, or drawing of project plans or specifications shall be limited to conceptual, preliminary, or initial plans or specifications. Contractor shall cooperate with the public entity to ensure that all bidders for a subsequent contract on any subsequent phase of this project, if any, have access to the same information, including all conceptual, preliminary, or initial plans or specifications prepared by Contractor pursuant to this Agreement.

8.13 Covenant Against Discrimination. Contractor covenants that, by and for itself, its heirs, executors, assigns, and all persons claiming under or through them, that there shall be no discrimination against or segregation of, any person or group of persons on account of race, color, creed, religion, sex, marital status, national origin, or ancestry in the performance of this Agreement.

To the extent required by law, contractor shall take affirmative action to insure that applicants are employed and that employees are treated during employment without regard to their race, color, creed, religion, sex, marital status, national origin, or ancestry.

8.14 Interpretation. The terms of this Agreement shall be construed in accordance with the meaning of the language used and shall not be construed for or against either party by reason of the authorship of this Agreement or any other rule of construction which might otherwise apply.

8.15 Severability. In the event that any one or more of the phrases, sentences, clauses, paragraphs, or sections contained in this Agreement shall be declared invalid or unenforceable by a valid judgment or decree of a court of competent jurisdiction, such invalidity or unenforceability shall not affect any of the remaining phrases, sentences, clauses, paragraphs, or sections of this Agreement which are hereby declared as severable and shall be interpreted to carry out the intent of the parties hereunder unless the invalid provision is so material that its invalidity deprives either party of the basic benefit of their bargain or renders this Agreement meaningless.

8.16 Hiring of Illegal Aliens Prohibited. Contractor shall not hire or employ any person to perform work within the City of Placentia or allow any person to perform work required under this 16 Project No. 1502

14 Agreement unless such person is properly documented and legally entitled to be employed within the United States. Further, Contractor shall comply with the following:

(a) Unauthorized Aliens. Contractor hereby represents and warrants that it will comply with all of the provisions of the Federal Immigration and Nationality Act, 8 U.S.C.A. §§ 1101, et seq., as amended, and in connection therewith, shall not employ unauthorized aliens as defined therein. Should Contractor so employ such unauthorized aliens for the performance of any work and/or services under this Agreement, and should any liability or sanctions be imposed against City for such use of unauthorized aliens, Contractor hereby agrees to reimburse City for any and all liabilities, actions, suits, claims, demands, losses, costs, judgments, arbitration awards, settlements, damages, demands, orders, or penalties which arise out of or are related to such employment, together with any and all costs, including attorneys’ fees, incurred by City.

(b) E-Verify. If Contractor is not already enrolled in the U.S. Department of Homeland Security’s E-Verify program, Contractor shall enroll in the E-Verify program within fifteen (15) days of the effective date of this Agreement to verify the employment authorization of employees assigned to perform work hereunder. Contractor shall verify employment authorization within three (3) days of hiring a new employee to perform work under this Agreement. Information pertaining to the E-Verify program can be found at http://www.uscis.gov , or access the registration page at https://e- verify.uscis.gov/enroll. Contractor shall certify its registration with E-Verify and provide City its registration number within sixteen days of the effective date of this Agreement. Failure to provide certification will result in withholding payment until full compliance is demonstrated.

8.17 Unfair Business Practices Claims. In entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C.

Sec. 15) or under the Cartwright Act (Chapter 2, (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment shall be made and become effective at the time the awarding body renders final payment to the contractor without further acknowledgment by the parties. (Sec. 7103.5, California Public Contract Code).

8.18 Corporate Authority. The persons executing this Agreement on behalf of the parties hereto warrant that (i) such party is duly organized and existing, (ii) they are duly authorized to execute and deliver this Agreement on behalf of said party, (iii) by so executing this Agreement, such party is formally bound to the provisions of this Agreement, and (iv) the entering into this Agreement does not violate any provision of any other Agreement to which said party is bound.

8.19 PERS Eligibility Indemnification. In the event that Contractor or any employee, agent, or subcontractor of Contractor providing services under this Agreement claims or is determined by a court of competent jurisdiction or the California Public Employees Retirement System (PERS) to be eligible for enrollment in PERS as an employee of the City, Contractor shall indemnify, defend, and hold harmless City for the payment of any employee and/or employer 17 Project No. 1502

15 contributions for PERS benefits on behalf of Contractor or its employees, agents, or subcontractors, as well as for the payment of any penalties and interest on such contributions, which would otherwise be the responsibility of City.

Notwithstanding any other agency, State, or Federal policy, rule, regulation, law, or ordinance to the contrary, Contractor and any of its employees, agents, and subcontractors providing service under this Agreement shall not qualify for or become entitled to, and hereby agree to waive any claims to, any compensation, benefit, or any incident of employment by City, including but not limited to eligibility to enroll in PERS as an employee of City and entitlement to any contribution to be paid by City for employer contribution and/or employee contributions for PERS benefits.

8.20 Cooperation. In the event any claim or action is brought against City relating to Contractor’s performance or services rendered under this Agreement, Contractor shall render any reasonable assistance and cooperation which City might require.

8.21 Legal Responsibilities. The Contractor shall keep itself informed of City, State, and Federal laws, ordinances, and regulations, which may in any manner affect the performance of its services pursuant to this Agreement. The Contractor shall at all times observe and comply with all such laws, ordinances, and regulations. Neither the City, nor its officers, agents, or employees shall be liable at law or in equity as a result of the Contractor’s failure to comply with this section.

8.22 Termination for Convenience. The City may terminate this Agreement without cause for convenience of the City upon giving contractor 30 days prior written notice of termination of the Agreement. Upon receipt of the notice of termination the Contractor shall cease all further work pursuant to the Agreement. Upon such termination by the City the Contractor shall not be entitled to any other remedies, claims, actions, profits, or damages except as provided in this paragraph. Upon the receipt of such notice of termination Contractor shall be entitled to the following compensation:

1. The contract value of the work completed to and including the date of receipt of the notice of termination, less the amount of progress payments received by contractor.

2. Actual move-off costs including labor, rental fees, equipment transportation costs, the costs of maintaining on-site construction office for supervising the mover-off.

3. The cost of materials custom made for this Agreement which cannot be used by the Contractor in the normal course of his business, and which have not been paid for by City in progress payments.

4. All costs shall not include any markups as might otherwise be allowed by any plans or specifications which were a part of the Agreement.

The provisions of this paragraph shall supersede any other provision of the Agreement or any provision of any plans, specification, addendums, or other documents which are or may become a part of this Agreement. City and Contractor agree that the provisions of this paragraph are a substantive part of the consideration for this Agreement.

8.23 Responsibility for Errors. Contractor shall be responsible for its work and results under this Agreement. Contractor, when requested, shall furnish clarification and/or explanation 18 Project No. 1502

16 as may be required by the City’s representative, regarding any services rendered under this Agreement at no additional cost to City. In the event that an error or omission attributable to Contractor occurs, then Contractor shall, at no cost to City, provide all necessary design drawings, estimates, and other Contractor professional services necessary to rectify and correct the matter to the sole satisfaction of City and to participate in any meeting required with regard to the correction.

8.24 Order of Precedence. In the event of an inconsistency in this Agreement and any of the attached Exhibits, the terms set forth in this Agreement shall prevail. If, and to the extent this Agreement incorporates by reference any provision of any document, such provision shall be deemed a part of this Agreement. Nevertheless, if there is any conflict among the terms and conditions of this Agreement and those of any such provision or provisions so incorporated by reference, this Agreement shall govern over the document referenced.

8.25 Costs. Each party shall bear its own costs and fees incurred in the preparation and negotiation of this Agreement and in the performance of its obligations hereunder except as expressly provided herein.

8.26 No Third Party Beneficiary Rights. This Agreement is entered into for the sole benefit of City and Contractor and no other parties are intended to be direct or incidental beneficiaries of this Agreement and no third party shall have any right in, under or to this Agreement.

8.27 Headings. Paragraphs and subparagraph headings contained in this Agreement are included solely for convenience and are not intended to modify, explain or to be a full or accurate description of the content thereof and shall not in any way affect the meaning or interpretation of this Agreement.

8.28 Construction. The parties have participated jointly in the negotiation and drafting of this Agreement. In the event an ambiguity or question of intent or interpretation arises with respect to this Agreement, this Agreement shall be construed as if drafted jointly by the parties and in accordance with its fair meaning. There shall be no presumption or burden of proof favoring or disfavoring any party by virtue of the authorship of any of the provisions of this Agreement.

8.29 Counterparts. This Agreement may be executed in one or more counterparts, each of which shall be deemed an original. All counterparts shall be construed together and shall constitute one agreement.

8.30 Funding Source Conditions – Contractor’s Obligation. Contractor acknowledges that the City may be paying for the Project by using funds it receives or will receive from various funding sources in the form of grants and/or subsidies, and the like under certain terms and conditions. Contractor warrants that it is not suspended or debarred from doing business with the United States government and can legally be paid from federal funds. Contractor acknowledges and agrees that any failure of the Contractor and/or its subcontractors to perform its obligations under the Contract, including, but not limited to, timely submitting accurate reports and records, that in any way results in the City not meeting the terms and conditions placed on the funds by the funding source, or forfeiting its entitlement to or, otherwise, not receiving, the funds, then the Contractor shall be liable to pay the City for the funds not granted to the City on the Project.

19 Project No. 1502

17 8.31 Entire Agreement. This Agreement constitutes the entire agreement between the parties with respect to any matter referenced herein and supersedes any and all other prior writings and oral negotiations. This Agreement may be modified only in writing, and signed by the parties in interest at the time of such modification. The terms of this Agreement shall prevail over any inconsistent provision in any other contract document appurtenant hereto, including exhibits to this Agreement.

IN WITNESS WHEREOF, the parties have executed and entered into this Agreement as of the date first written above.

ATTEST:

CITY OF PLACENTIA,
A municipal corporation and Charter City

__________________________________ Date: __________________________ Rosanna Ramirez, Acting City Administrator

ATTEST:

________________________________
Robert S. McKinnell, City Clerk

APPROVED AS TO FORM:

CONTRACTOR:

__________________________________ Date: __________________________ Signature

__________________________________
John C. Sarno, President

__________________________________
Taxpayer ID Number

__________________________________ Date: ________________________ Christian L. Bettenhausen, City Attorney

954578126
John C. Serno
12/12/2024
20 Project No. 1502

18 APPROVED AS TO INSURANCE:

____________________________________ Date: ________________________ Krystle Murillo, Risk Manager

APPROVED AS TO CONTENT:

____________________________________ Date: ________________________ Samantha Byfield, Project Manager

DEPARTMENTAL APPROVAL:

___________________________ Date: _________________________ Chris Tanio, Director of Public Works

12/12/2024
12/12/2024
21 EXHIBIT A

SCOPE OF SERVICES

The project includes providing all labor, materials, equipment, tools and incidentals as required to install new concrete sidewalk, curb and gutter improvements at locations listed in the Specifications and Contract Documents. The scope of work includes removal of existing sidewalk, curb and gutter and any other existing conditions to allow construction of new sidewalks, curb and gutter, full depth AC slot pavement, restoration of landscaping and irrigation system, and all items not mentioned but included in the plans and specifications. All work must be performed in accordance with the approved plans and specifications for this project and as directed by the City. 22 EXHIBIT B

SCHEDULE OF PERFORMANCE

All work must be complete within Thirty (30) working days starting from the date mentioned in the Notice to Proceed.

23 E X H I B I T C

INSURANCE REQUIREMENTS
A. Minimum Scope and Limits of Insurance
City reserves the right to review any and all of the required insurance policies and/or endorsements, but has no obligation to do so. Failure to demand evidence of full compliance with the insurance requirements set forth in this Agreement or failure to identify any insurance deficiency shall not relieve Contractor from, nor be construed or deemed a waiver of, its obligation to maintain the required insurance at all times during the performance, including any extension thereof, of this Agreement.

Consultant shall obtain, maintain, and keep in full force and effect during the life of this Agreement, including any extension thereof, all of the following minimum scope of insurance coverages:

1. Commercial General Liability Insurance

Commercial general liability insurance no less broad than Insurance Services Office (ISO) form CG 00 01.

Minimum Limits: $2,000,000.00 per occurrence; $4,000,000.00 general aggregate; $4,000,000.00 products/completed operations aggregate. The aggregate limit, encompassing the above coverage, shall apply separately to this project/location. The required limits may be provided by a combination of general liability insurance and commercial excess or umbrella liability insurance. If Contractor maintains higher limits than the specified minimum limits, City requires and shall be entitled to coverage for the higher limits maintained by the Contractor.

Any deductible or self-insured retention shall be shown on the certificate of insurance. If the deductible or self-insured retention exceeds $25,000.00, it must be approved in advance by City. Contractor is responsible for any deductible or self-insured retention and shall fund it upon City’s written request, regardless of whether Contractor has a claim against the insurance or is named as a party in any action involving City.

Coverage shall be continued for three (3) years after completion of the work.

City shall be endorsed as an additional insured for liability arising out of ongoing and completed operations by or on behalf of the Contractor. City shall continue to be an additional insured for completed operations for three (3) years after completion of the work. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance at least as broad as one of the following ISO ongoing operations forms: CG 20 10 or CG 20 26 or CG 20 33 (not allowed from subcontractors), or CG 20 38; and one of the following ISO completed operations forms: CG 20 37, 2039 (not allowed from subcontractors), or CG 20 40.

The policy definition of “insured contract” shall include assumptions of liability arising out of both ongoing operations and the products/completed operations 24 hazard (“f” definition of insured contract in ISO form CG 00 01, or equivalent).

The insurance provided to the additional insureds shall be primary to, and non- contributory with, any insurance or self-insurance program maintained by them.

The policy shall cover inter-insured suits and include a “separation of insureds” or “severability” clause which treats each insured separately.

The policy shall be endorsed to include a written waiver of the insurer’s right to subrogate against all persons or entities that are, or are required to be, additional insureds.

The policy shall not contain a contractors’ warranty or other similar language which eliminates or restricts insurance because of a subcontractor's failure to carry specific insurance or to supply evidence of such insurance.

Required evidence of coverage:

1. Copy of the endorsements naming the City of Placentia, its officers, officials, employees, agents, and volunteers as additional insureds;

2. Copy of the endorsement or policy language indicating that coverage applicable to the additional insureds is primary and non-contributory;

3. Properly completed certificate of insurance; and

4. Completed and signed Agent/Broker Questionnaire with supporting documentation as required.

2. Business Automobile Liability Insurance

Minimum Limit: $2,000,000.00 combined single limit per accident.

Coverage shall apply to all owned, hired, leased, and non-owned vehicles.

City shall be endorsed as additional insured.

Required evidence of coverage:

1. Copy of the endorsement naming the City of Placentia, its officers, officials, employees, agents, and volunteers as additional insureds; and

2. Properly completed certificate of insurance.

3. Workers’ Compensation & Employer’s Liability Insurance

Workers’ compensation insurance with statutory limits as required by the Labor Code of the State of California.

Employer’s liability with limits of $1,000,000.00 per accident; $1,000,000.00 disease per employee; $1,000,000.00 disease per policy.

The policy shall include a written waiver of the insurer’s right to subrogate against City.

Required evidence of coverage:

1. Subrogation waiver endorsement; and

2. Properly completed certificate of insurance.
25 4. Contractor’s Pollution Liability Insurance
Minimum Limits: $2,000,000.00 per pollution incident; $2,000,000.00 policy aggregate.

Coverage shall apply to pollution incidents at or from any location at which Contractor is performing work under this Agreement.

Any deductible or self-insured retention shall be shown on the certificate of insurance. If the deductible or self-insured retention exceeds $25,000.00, it shall be approved in advance by City. Contractor is responsible for any deductible or self-insured retention and shall fund it upon City written request, regardless of whether Contractor has a claim against the insurance or is named as a party in any action involving City.

City shall be endorsed as an additional insured for liability arising out of ongoing and completed operations by or on behalf of the Contractor. Additional insured status shall continue for three (3) years after completion of the work.

The insurance provided to the additional insureds shall apply on a primary and non-contributory basis with respect to any insurance or self-insurance program maintained by them.

The insurance shall be continued for three (3) years after completion of the work.

Required evidence of coverage:

1. Copy of the endorsement naming the City of Placentia, its officers, officials, employees, agents, and volunteers as additional insureds;

2. Copy of the endorsement or policy language indicating that coverage for the additional insureds is primary and non-contributory; and

3. Properly completed certificate of insurance.

5. Surety Bonds

Bid bond.

Performance and payment bonds for the entire contract price.

The surety must be authorized to issue these bonds in the State of California.

6. Standards for Insurance Companies

All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commission to transact business of insurance or is on the List of Approved Surplus Line Insurers in the State of California, with an assigned policyholders’ rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best’s Key Rating Guide.

B. Documentation and Other Provisions

1. The certificate of insurance shall include the following reference: FY 2024-25 Concrete Repair Project – City Project No. 1502.
26 2. The name and address for additional insured endorsements and certificates of insurance is: City of Placentia, 401 E. Chapman Ave., Placentia, CA 92870.

3. Defense fees and costs shall not deplete the limits of any insurance provided under this Agreement.

4.Contractor shall require and verify that all subcontractors maintain insurance meeting all the requirements stated herein, and Contractor shall ensure the City is an additional insured on insurance required from subcontractors.

5. Contractor agrees to waive and to obtain endorsements from insurers waiving subrogation rights against the City of Placentia, its officers, officials, employees, agents, and volunteers for losses arising from work performed by Contractor for the City and to require each of its subcontractors, if any, to do likewise under their insurance policies.

6. The Contractor’s insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the City of Placentia, its officers, officials, agents, employees, and volunteers. Any other insurance maintained by the City of Placentia shall be excess and not contributing with the insurance provided by this policy.

7. Coverage shall be on a standard occurrence form. Claims-made forms are not acceptable. Modified, limited, or restricted occurrence forms are not acceptable.

8. Said policies shall not terminate, nor shall they be cancelled or coverage reduced, without at least thirty (30) days’ written notice to the City. In the event of any cancellation or reduction in coverage or limits of any insurance, Contractor shall forthwith obtain and submit proof of substitute insurance. Should Contractor fail to immediately procure other insurance, as specified, to substitute for any cancelled policy or reduction in the required insurance limits, the City may procure such insurance at Contractor’s sole cost and expense.

9. Current evidence of coverage shall be provided for the entire required period of insurance.

10. Upon written request, certified copies of required insurance policies shall be provided within thirty (30) days.

27 E X H I B I T D

C E R T I F I C A T E S O F I N S U R A N C E A N D E N D O R S E M E N T S

................................................................................ 28 29

30 COMMERCIAL AUTO
CA 04 49 11 16
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

PRIMARY AND NONCONTRIBUTORY -

OTHER INSURANCE CONDITION
This endorsement modifies insurance provided under the following:

AUTO DEALERS COVERAGE FORM

BUSINESS AUTO COVERAGE FORM

MOTOR CARRIER COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement.

A.The following is added to the Other Insurance
Condition in the Business Auto Coverage Form
and the Other Insurance - Primary And Excess
Insurance Provisions in the Motor Carrier
Coverage Form and supersedes any provision to
the contrary:

This Coverage Form's Covered Autos Liability
Coverage is primary to and will not seek
contribution from any other insurance available to
an "insured" under your policy provided that:

1.Such "insured" is a Named Insured under
such other insurance; and

2.You have agreed in writing in a contract or
agreement that this insurance would be
primary and would not seek contribution from
any other insurance available to such
"insured".

B.The following is added to the Other Insurance
Condition in the Auto Dealers Coverage Form and
supersedes any provision to the contrary:

This Coverage Form's Covered Autos Liability
Coverage and General Liability Coverages are
primary to and will not seek contribution from any
other insurance available to an "insured" under
your policy provided that:

1.Such "insured" is a Named Insured under
such other insurance; and

2.You have agreed in writing in a contract or
agreement that this insurance would be
primary and would not seek contribution from
any other insurance available to such
"insured".
© Insurance Services Office, Inc., 2016 Page 1 of 1
CA 04 49 11 16 Policy Number: 1845023 Transaction Effective Date: 11/12/2024

31 EXHIBIT E

CLAIMS PROCEDURE
SUMMARY OF PUBLIC CONTRACT CODE § 9204

The following procedure will apply to any claims by the Contractor on the City:

A “claim” is a separate demand on the City by a contractor on a public works project and sent by registered mail or certified mail with return receipt requested, for one or more of the following:

A time extension, including relief from penalties for delay Payment by the City of money damages under the terms of the contract Payment of an amount that is disputed by the City
Initial Review
The claim must be supported by appropriate documentation. The City has 45 days within which to review the claim and provide the contractor with a written statement identifying the disputed and undisputed portions of the claim. If the City does not issue a written statement, the claim is deemed rejected in its entirety. The City will pay any undisputed portion of the claim within 60 days of issuing the statement.

Meet & Confer
If the contractor disputes the City’s written response, or if the City does not issue one, the contractor may request in writing an informal conference to meet and confer for possible settlement of the claim. The City will schedule the meet and confer conference within 30 days of this request and provide a written statement identifying the remaining disputed and undisputed portions of the claim within 10 business days of the meet and confer. The City will pay the undisputed portion within 60 days of issuing this statement.

Mediation
With respect to any disputed portion remaining after the meet and confer, the City and contractor will submit the matter to nonbinding mediation, agree to a mediator within 10 business days after issuing the written statement, and share mediation costs equally. If mediation is unsuccessful, then the terms of the public works agreement and applicable law will govern resolution of the dispute.

Miscellaneous Provisions
Amounts not paid by the City in a timely manner bear interest at 7% per annum.

Subcontractors may submit claims via this procedure through the general contractor. The City and contractor may waive the requirement to mediate but cannot otherwise waive these claim procedures.

32 ABCDEFGHI J
Dear Policyholder,
Thank you for choosing Federated Insurance to handle your insurance and risk management needs. The attached certificate document(s) have been issued or updated.

Please feel free to contact us with any additional changes, additions or deletions that may be needed by contacting the Federated Client Contact Center at:

E-mail:[email protected]
Phone:1-888-333-4949
Fax:507-446-4664
Thank you for your business!
Client Contact Center
Enclosed:

Certificate Document(s)
MISC-0829 (03-22)

33 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED BY CONTRACT ENDORSEMENT
This endorsement modifies insurance provided under the following:

BUSINESS AUTO COVERAGE PART
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement.

A.WHO IS AN INSURED for "bodily injury" and "property damage" liability is amended to include:

Any person or organization other than a joint venture, for which you have agreed by written contract to procure bodily injury or property damage "auto" liability insurance arising out of operation of a covered "auto" with your permission. However, this additional insurance does not apply to:
(1)The owner or anyone else from whom you hire or borrow a covered "auto". This exception does not apply if the covered "auto" is a "trailer" connected to a covered "auto" you own. (2)Your "employee" if the covered "auto" is owned by that "employee" or a member of his or her household.
(3)Someone using a covered "auto" while he or she is working in a business of selling, servicing, repairing, parking or storing "autos" unless that business is yours. (4)Anyone other than your "employees", partners (if you are a partnership), members (if you are a limited liability company), or a lessee or borrower or any of their "employees", while moving property to or from a covered "auto".
(5)A partner (if you are a partnership), or a member (if you are a limited liability company) for a covered "auto" owned by him or her or a member of his or her household.

B.The coverage extended to any additional insured by this endorsement is limited to, and subject to all terms, conditions, and exclusions of the Coverage Part to which this endorsement is attached.

In addition, coverage shall not exceed the terms and conditions that are required by the terms of the written agreement to add any insured, or to procure insurance.

C.The limits of insurance applicable to such insurance shall be the lesser of the limits required by the agreement between the parties, or the limits provided by this policy.

D.Additional exclusions. The insurance afforded to any person or organization as an insured under this endorsement does not apply:

1.To "loss" which occurs prior to the date of your contract with such person or organization;

2.To "loss" arising out of the sole negligence of any person or organization that would not be an insured except for this endorsement.

3.To "loss" for any leased or rented "auto" when the lessor or his or her agent takes possession of the leased or rented "auto" or the policy period ends, whichever occurs first.

Includes copyrighted material of Insurance Services Office, Inc. with its permission.

CA-F-127 (03-03) Policy Number: 1845023 Transaction Effective Date:11/12/2024

34 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

BLANKET WAIVER OF TRANSFER OF RIGHTS OF RECOVERY
This endorsement modifies insurance provided under the following:

BUSINESS AUTO COVERAGE PART
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by the endorsement.

In the event of any payment for a loss under this Business Auto Coverage Part arising out of your ongoing operations, we agree to waive our rights under the TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US condition against any person or organization, its subsidiaries, directors, agents or employees, for which you have agreed by written contract, prior to the occurrence of any loss, to waive such rights, except when the payment results from the sole negligence of that person or organization, its subsidiaries, directors, agents or employees.

Includes copyrighted material of Insurance Services Office, Inc. with its permission.

CA-F-128 (03-03) Policy Number: 1845023 Transaction Effective Date:11/12/2024

35 COMMERCIAL GENERAL LIABILITY
CG 20 01 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

PRIMARY AND NONCONTRIBUTORY -

OTHER INSURANCE CONDITION
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

LIQUOR LIABILITY COVERAGE PART

PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART
The following is added to the Other Insurance
Condition and supersedes any provision to the
contrary:

Primary And Noncontributory Insurance
This insurance is primary to and will not seek
contribution from any other insurance available to
an additional insured under your policy provided
that:
(1)The additional insured is a Named Insured
under such other insurance; and
(2)You have agreed in writing in a contract
or agreement that this insurance would be
primary and would not seek contribution
from any other insurance available to the
additional insured.
© Insurance Services Office, Inc., 2018 Page 1 of 1
CG 20 01 12 19 Policy Number: 1845023 Transaction Effective Date: 11/12/2024

36 POLICY NUMBER: 1845023 COMMERCIAL GENERAL LIABILITY CG 20 10 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED - OWNERS, LESSEES OR

CONTRACTORS - SCHEDULED PERSON OR

ORGANIZATION
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s):Location(s) Of Covered Operations
City of Placentia
401 E Chapman Ave
Placentia, CA 92670
Any coverage provided by this endorsement
applies only to Project #1502, FY 24-25
Concrete Repair Project, Placentia, CA.

Subject to the terms and conditions of the
policy, Additional Insureds also includes
City of Placentia, its officers, officials,
employees, agents, and volunteers.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

A.Section II - Who Is An Insured is amended to
include as an additional insured the person(s) or
organization(s) shown in the Schedule, but only
with respect to liability for "bodily injury",
"property damage" or "personal and advertising
injury" caused, in whole or in part, by:

1.Your acts or omissions; or

2.The acts or omissions of those acting on your
behalf;
in the performance of your ongoing operations for
the additional insured(s) at the location(s)
designated above.

However:

1.The insurance afforded to such additional
insured only applies to the extent permitted by
law; and

2.If coverage provided to the additional insured
is required by a contract or agreement, the
insurance afforded to such additional insured
will not be broader than that which you are
required by the contract or agreement to
provide for such additional insured.

B.With respect to the insurance afforded to these
additional insureds, the following additional
exclusions apply:

This insurance does not apply to "bodily injury" or
"property damage" occurring after:

1.All work, including materials, parts or
equipment furnished in connection with such
work, on the project (other than service,
maintenance or repairs) to be performed by or
on behalf of the additional insured(s) at the
location of the covered operations has been
completed; or

2.That portion of "your work" out of which the
injury or damage arises has been put to its
intended use by any person or organization
other than another contractor or subcontractor
engaged in performing operations for a
principal as a part of the same project.
© Insurance Services Office, Inc., 2018 Page 1 of 2
CG 20 10 12 19 Policy Number: 1845023 Transaction Effective Date: 12/07/2024

37 C.With respect to the insurance afforded to these
additional insureds, the following is added to
Section III - Limits Of Insurance:

If coverage provided to the additional insured is
required by a contract or agreement, the most we
will pay on behalf of the additional insured is the
amount of insurance:

1.Required by the contract or agreement; or
Insured:

C J Concrete Construction, Inc.
10142 Shoemaker Ave
Santa Fe Springs, CA 90670-3404

2.Available under the applicable limits of
insurance;
whichever is less.

This endorsement shall not increase the
applicable limits of insurance.

Page 2 of 2 ends

CG 20 10 12 19 Policy Number: 1845023 Transaction Effective Date: 12/07/2024

38 POLICY NUMBER: 1845023 COMMERCIAL GENERAL LIABILITY CG 20 37 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

ADDITIONAL INSURED - OWNERS, LESSEES OR

CONTRACTORS - COMPLETED OPERATIONS
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART

SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s)Location And Description Of Completed Operations City of Placentia
401 E Chapman Ave
Placentia, CA 92670
Any coverage provided by this
endorsement applies only to Project
#1502, FY 24-25 Concrete Repair Project,
Placentia, CA. Subject to the terms and
conditions of the policy, Additional
Insureds also includes City of
Placentia, its officers, officials,
employees, agents, and volunteers.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

A.Section II - Who Is An Insured is amended to
include as an additional insured the person(s) or
organization(s) shown in the Schedule, but only
with respect to liability for "bodily injury" or
"property damage" caused, in whole or in part, by
"your work" at the location designated and
described in the Schedule of this endorsement
performed for that additional insured and included
in the "products-completed operations hazard".

However:

1.The insurance afforded to such additional
insured only applies to the extent permitted by
law; and

2.If coverage provided to the additional insured is
required by a contract or agreement, the
insurance afforded to such additional insured
will not be broader than that which you are
required by the contract or agreement to
provide for such additional insured.

B.With respect to the insurance afforded to these
additional insureds, the following is added to
Section III - Limits Of Insurance:

If coverage provided to the additional insured is
required by a contract or agreement, the most we
will pay on behalf of the additional insured is the
amount of insurance:

1.Required by the contract or agreement; or

2.Available under the applicable limits of
insurance;
whichever is less.

This endorsement shall not increase the applicable
limits of insurance.

Insured:

C J Concrete Construction, Inc.
10142 Shoemaker Ave
Santa Fe Springs, CA 90670-3404
© Insurance Services Office, Inc., 2018 Page 1 of 1
CG 20 37 12 19 Policy Number: 1845023 Transaction Effective Date: 12/07/2024

39 COMMERCIAL GENERAL LIABILITY
CG 24 53 12 19
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

WAIVER OF TRANSFER OF RIGHTS OF RECOVERY

AGAINST OTHERS TO US (WAIVER OF SUBROGATION) -

AUTOMATIC
This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

ELECTRONIC DATA LIABILITY COVERAGE PART

LIQUOR LIABILITY COVERAGE PART

POLLUTION LIABILITY COVERAGE PART DESIGNATED SITES

POLLUTION LIABILITY LIMITED COVERAGE PART DESIGNATED SITES

PRODUCTS/COMPLETED OPERATIONS LIABILITY COVERAGE PART

RAILROAD PROTECTIVE LIABILITY COVERAGE PART

UNDERGROUND STORAGE TANK POLICY DESIGNATED TANKS
The following is added to Paragraph 8. Transfer Of
Rights Of Recovery Against Others To Us of Section
IV - Conditions:

We waive any right of recovery against any person or
organization, because of any payment we make under
this Coverage Part, to whom the insured has waived
its right of recovery in a written contract or
agreement. Such waiver by us applies only to the
extent that the insured has waived its right of recovery against such person or organization prior to loss.
© Insurance Services Office, Inc., 2018 Page 1 of 1
CG 24 53 12 19 Policy Number: 1845023 Transaction Effective Date: 11/12/2024

40 POLICY NUMBER: 1845023 COMMERCIAL GENERAL LIABILITY CG 25 03 05 09
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.

D E SI GN AT ED C ON ST RU CT IO N PR O J E CT (S )G E NE RA L AG G R EG AT E LI M I T This endorsement modifies insurance provided under the following:

COMMERCIAL GENERAL LIABILITY COVERAGE PART

SCHEDULE
Designated Construction Project(s):

Each construction project as required by written contract or written agreement.

Information required to complete this Schedule, if not shown above, will be shown in the Declarations.

A.For all sums which the insured becomes legally
obligated to pay as damages caused by
"occurrences" under Section I - Coverage A, and
for all medical expenses caused by accidents
under Section I - Coverage C, which can be
attributed only to ongoing operations at a single
designated construction project shown in the
Schedule above:

1.A separate Designated Construction Project
General Aggregate Limit applies to each
designated construction project, and that limit
is equal to the amount of the General
Aggregate Limit shown in the Declarations.

2.The Designated Construction Project General
Aggregate Limit is th e most w e will pay f or the
sum of all damages under Coverage A, except
damages because of "bodily injury" or
"property damage" included in the "products-
completed operations hazard", and for medical
expenses under Coverage C regardless of the
number of:
a.Insureds;
b.Claims made or "suits" brought; or
c.Persons or organizations making claims
or bringing "suits".

3.Any payments made under Coverage A for
damages or under Coverage C for medical
expenses shall reduce the Designated
Construction Project General Aggregate Limit
for that designated construction project. Such
payments shall not reduce the General
Aggregate Limit shown in the Declarations nor
shall they reduce any other Designated
Construction Project General Aggregate Limit
for any other designated construction project
shown in the Schedule above.

4.The limits shown in the Declarations for Each
Occurrence, Damage To Premises Rented To
You and Medical Expense continue to apply.

However, instead of being subject to the
General Aggregate Limit shown in the
Declarations, such limits will be subject to the
applicable Designated Construction Project
General Aggregate Limit.

CG 25 03 05 09 © Insurance Services Office, Inc., 2008 Page 1 of 2

41 B.For all sums which the insured becomes legally
obligated to pay as damages caused by
"occurrences" under Section I - Coverage A, and
for all medical expenses caused by accidents
under Section I - Coverage C, which cannot be
attributed only to ongoing operations at a single
designated construction project shown in the
Schedule above:

1.Any payments made under Coverage A for
damages or under Coverage C for medical
expenses shall reduce the amount available
under the General Aggregate Limit or the
Products-completed Operations Aggregate
Limit, whichever is applicable; and

2.Such payments shall not reduce any
Designated Construction Project General
Aggregate Limit.

C.When coverage for liability arising out of the
"products-completed operations hazard" is
provided, any payments for damages because of
"bodily injury" or "property damage" included in
the "products-completed operations hazard" will
reduce the Products-completed Operations
Aggregate Limit, and not reduce the General
Aggregate Limit nor the Designated Construction
Project General Aggregate Limit.

D.If the applicable designated construction project
has been abandoned, delayed, or abandoned and
then restarted, or if the authorized contracting
parties deviate from plans, blueprints, designs,
specifications or timetables, the project will still
be deemed to be the same construction project.

E.The provisions of Section III - Limits Of Insurance
not otherwise modified by this endorsement shall
continue to apply as stipulated.

Page 2 of 2 ends

42 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE

THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS.

INSURER(S) AFFORDING COVERAGE
INSURER F :

INSURER E :

INSURER D :

INSURER C :

INSURER B :

INSURER A :

NAIC #
NAME:

CONTACT
(A/C, No):

FAX
E-MAIL
ADDRESS:

PRODUCER
(A/C, No, Ext):

PHONE

INSURED
REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed.

If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).

THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS

CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.

OTHER:
(Per accident)
(Ea accident)
$
$
N / A
SUBR
WVD
ADDL
INSD

THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS

CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. $
$
$
$PROPERTY DAMAGE
BODILY INJURY (Per accident)
BODILY INJURY (Per person)

COMBINED SINGLE LIMIT

AUTOS ONLY

AUTOSAUTOS ONLY

NON-OWNED

SCHEDULEDOWNED

ANY AUTO

AUTOMOBILE LIABILITY
Y / N

WORKERS COMPENSATION

AND EMPLOYERS' LIABILITY
OFFICER/MEMBER EXCLUDED?
(Mandatory in NH)
DESCRIPTION OF OPERATIONS below
If yes, describe under

ANY PROPRIETOR/PARTNER/EXECUTIVE
$
$
$
E.L. DISEASE - POLICY LIMIT
E.L. DISEASE - EA EMPLOYEE
E.L. EACH ACCIDENT
ER
OTH-

STATUTE
PER

LIMITS(MM/DD/YYYY)

POLICY EXP
(MM/DD/YYYY)

POLICY EFF

POLICY NUMBERTYPE OF INSURANCELTR
INSR
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)

EXCESS LIAB
UMBRELLA LIAB $EACH OCCURRENCE
$AGGREGATE
$
OCCUR

CLAIMS-MADE
DED RETENTION $
$PRODUCTS - COMP/OP AGG
$GENERAL AGGREGATE
$PERSONAL & ADV INJURY
$MED EXP (Any one person)
$EACH OCCURRENCE

DAMAGE TO RENTED
$PREMISES (Ea occurrence)

COMMERCIAL GENERAL LIABILITY

CLAIMS-MADE OCCUR
GEN'L AGGREGATE LIMIT APPLIES PER:

POLICY PRO-

JECT LOC

CERTIFICATE OF LIABILITY INSURANCE

DATE (MM/DD/YYYY)

CANCELLATION

AUTHORIZED REPRESENTATIVE
ACORD 25 (2016/03)
© 1988-2015 ACORD CORPORATION. All rights reserved.

CERTIFICATE HOLDER
The ACORD name and logo are registered marks of ACORD
HIRED

AUTOS ONLY
12/6/2024
Behr Insurance Services Inc.
1420 E Los Angeles Ave #203
Simi Valley CA 93065
888-988-2347
[email protected]
CJ Concrete Construction Inc
10142 SHOEMAKER AVE
SANTA FE SPRINGS CA 90670-3404
COREPOINTE INS CO 10499
A Y Y CTP1002477 05/08/2024 05/08/2025
8 1,000,000
1,000,000
1,000,000
FY 24-25 CONCRETE REPAIR PROJECT
CITY PROJECT NO. 1502
Waiver of subrogation applies to workers compensation per attached WC 04 03 06 endorsement City of Placentia
401 E. Chapman Ave
Placentia, CA 92870
43 WORKERS COMPENSATION AND EMPLOYERS LIABILITY INSURANCE POLICY WC 04 03 06

(Ed. 04-84)

WAIVER OF OUR RIGHT TO RECOVER FROM OTHERS ENDORSEMENTCALIFORNIA

We have the right to recover our payments from anyone liable for an injury covered by this policy. We will not enforce our right against the person or organization named in the Schedule. (This agreement applies only to the extent that you perform work under a written contract that requires you to obtain this agreement from us.)

You must maintain payroll records accurately segregating the remuneration of your employees while engaged in the work described in the Schedule.

The additional premium for this endorsement shall be 2.00% of the California workers’ compensation premium otherwise due on such remuneration.

Schedule

Person or Organization Job Description

Any person or organization as required by written contract

Notes:

1. This endorsement may be used to waive the company’s right of subrogation against named third parties who may be responsible for an injury.

2. The sentence in ( ) is optional with the company. It limits the endorsement to apply only to specific jobs of the insured, and only to the extent that the insured is required to obtain this waiver.

This endorsement changes the policy to which it is attached and is effective on the date issued unless otherwise stated. (The information below is required only when this endorsement is issued subsequent to preparation of the policy.)

Endorsement Effective Policy No. Endorsement No.

Insured Insurance Company

Countersigned By

44

← All documents from this meeting