FY 23/24 Street Rehabilitation
Construction Updates
January 14, 2025
City of Placentia
Residential Slurry Seal
•Construction began on January 13th
•Performing localized full depth reconstruction and misc. concrete repairs •Performing full depth reconstruction work on Hudson, Willamette, Roanoke, Little Big Horn, and Susquehanna. •Anticipated completion date is end of February 2025
Arterial Street Rehabilitation
•Construction anticipated to begin on January 21st
•Construction notices are being distributed to the affected areas the week of January 13th
•Anticipated completion date in mid-April 2025