RESOLUTION NO. ___-22

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PLEASANT HILL

AUTHORIZING A FIRST AMENDMENT TO THE AGREEMENT FOR PROFESSIONAL

CONSTRUCTION MANAGEMENT SERVICES WITH RUGGERI-JENSEN-AZAR (RJA)

WHEREAS, the City has adopted the FY 2022-2027 Capital Improvement Plan which includes the Diablo Vista Water System 12” Main Replacement Phase II (“Project”) as a desired and funded project; and
WHEREAS, the Project provided for the installation of a new 12" water main from the Diablo Vista Pump Station located on the Contra Costa Canal to Stevenson Drive, and from Oakvue Road to Roberta Drive including all valves, laterals and necessary appurtenances; and WHEREAS, the City and RJA (“Consultant”) entered into an Agreement for Professional Services (“Agreement”) for professional design services on February 7, 2017; and WHEREAS, Consultant has submitted a cost proposal to provide additional professional design services for the Project that are needed to complete the Project as requested by the City beyond the original Agreement scope; and
WHEREAS, City and Consultant wish to amend the Agreement to compensate and complete the additional construction management services for the Project.

NOW, THEREFORE, by the City Council of the City of Pleasant Hill that the City Manager is authorized to execute the First Amendment to Agreement for Professional Services with RJA in the form attached hereto.

ADOPTED by the City Council of the City of Pleasant Hill at a regular meeting of the Council held on the 1
st day of August, 2022, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:

MICHAEL G. HARRIS, OD, Mayor
ATTEST:

DANIELLE K. HABR, City Clerk