City Manager
100 Gregory Lane, Pleasant Hill, CA 94523-3323 – (925) 671-5270 www.pleasanthillca.org
____________, 2022
Janice Jensen, President & CEO
Melanie Mintenko, Project Manager

HABITAT FOR HUMANITY EAST BAY/SILICON VALLEY
2619 Broadway
Oakland, CA 94612
85 Woodsworth Disposition and Development Agreement Schedule of Performance Extension No. 2
Dear Janice and Melanie,
The City of Pleasant Hill (“Seller” or “City”) and Habitat for Humanity East Bay Silicon Valley (“Purchaser”) entered into a Disposition and Development Agreement (“DDA”) for the transfer of 85 Woodsworth Lane, Pleasant Hill, Contra Costa County, California (Assessor’s Parcel Number 150-150-071-2) (“Property”). The Seller agreed to transfer the Property to the Purchaser in order to develop four single-family units of affordable housing, after certain conditions are met.

To date, the Purchaser has:
 engaged architectural, civil, geotechnical, and environmental consultants  completed site surveys, geotechnical reports, and Phase 1 environmental assessments  engaged the environmental consultant to complete Phase 2 environmental assessments  engaged City staff in preparing an entitlement package submittal to the City  recorded loan documents
 secured a Habitat Board resolution that commits to providing backstop funding Exhibit C to the DDA includes a Schedule of Performance that identifies a Project Entitlements deadline of March 31, 2022 and an Other Funding Commitments Deadline of December 31, 2022.

Section 5.4 of the DDA permits the City Manager to modify a time or date for performance of a particular task by 180 days at their reasonable discretion. The Seller and Purchaser signed a letter dated March 7, 2022 to extend the Project Entitlements and Other Funding Commitments deadlines by 180 days, or to September 27, 2022 and June 29, 2023, respectively. Due to delays in the development entitlement process, the Seller and Purchaser desire to further extend certain deadlines set forth in the Schedule of Performance.

Schedule of Performance Extension No. 2
85 WOODSWORTH DISPOSITION AND DEVELOPMENT AGREEMENT
____________, 2022

Page 2 ends

2 By signed execution of this letter, the Seller and Purchaser agree to further extend the following deadlines in the Schedule of Performance:
 Project Entitlements: September 27, 2023
 Other Funding Commitments: December 31, 2023
 Escrow Closing Date: January 31, 2024
The City Council approved these extensions at a regular meeting on October 3, 2022 by adoption of Resolution No. ___.

Please return a signed copy acknowledge receipt of this letter to Troy Fujimoto, City Planner, at [email protected] by _______, 2022.

Executed By:
_______________________________

CITY OF PLEASANT HILL
June Catalano, City Manager
Date: _______________________________
_______________________________

HABITAT FOR HUMANITY EAST BAY/SILICON VALLEY
Janice Jensen, President & CEO
Date: _______________________________