EXHIBIT B
locations Priority PIPE SIZE Total Cost to Cost to Total Cost Size and Project Replaced Replaced Replace Replace to Replace Type (LF) (LF) (per ft) (per ft)
Roberta to Patterson
1 10 1,600 $317 $476 $760,800
Byron to Patterson
2 8 2,211 $292 $450 $994,950
SYSTEM UPGRADES And Capital Plan
$1,755,750
$158.50
$146.00

COST UPGRADES

DIABLO VISTA WATER SYSTEM
CIP Project Upgrades next 10 years
additional costs
incidentals (
(per ft)