MEMORANDUM
To: Matt Todd, TRANSPAC
Chris Weeks, SWAT
Robert Sarmiento, TRANSPLAN
Sai Midididdi, TVTC
John Nemeth, WCCTAC
Sivakumar Natarajan, LPMC
From: Timothy Haile, Executive Director
Date: January 11, 2024
Re: Items of interest for circulation to the Regional Transportation Planning Committees (RTPCs)
At its December 20, 2023 meeting, the Authority discussed the following items, which may be of interests to the Regional Transportation Planning Committees:
A. Bay Area Rapid Transit (BART) – Central County BART Next Generation Fare Gates (NGFG) (Project 10001-09) – Approval to Appropriate Measure J Funds to BART for Design and Construction Phases
Recommendation: Staff sought approval of Resolution 23-48-p, which will appropriate $3.5 million in Measure J funds to BART for design and construction phases of the Central County BART NGFG project.
Action: The Authority Board approved Resolution 23-48-p, which will appropriate $3.5 million in Measure J funds to BART for the design and construction phases of the Central County BART NGFG project.
B. Interstate 680/State Route 4 Interchange Improvements, Phases 1, 2A, and 4 (Project 6001) (Project) – Approval of Resolution 23-21-P to Adopt Amendment No. 2 to the 2022 Measure J Strategic Plan
RTPC Memorandum
January 11, 2024
https://cctauthority.sharepoint.com/sites/Common/09Correspondences/RTPC Memos/2023/December 20 2023 RTPC Memo_Final_.doc Recommendation: Staff sought approval of Resolution 23-21-P, which will adopt Amendment No. 2 to the 2022 Measure J Strategic Plan, to reprogram $150,000 from the Central County – Construction Reserve to the Project.
Action: The Authority Board approved Resolution 23-21-P, which will adopt Amendment No. 2 to the 2022 Measure J Strategic Plan, to reprogram $150,000 from the Central County – Construction Reserve to the Project.
C. Authorization to Execute Funding Memorandum of Understanding (MOU) Agreement No. 679 with Contra Costa County for $1,470,00 of Measure X Funds to Support Implementation of the Accessible Transportation Strategic Plan
Recommendation: Staff sought authorization for the Chair to execute Funding MOU Agreement No. 679 with Contra Costa County for the Authority to receive $1,470,000 in Measure X funding, authorize the funds to be used for the tasks identified in the Service Plan in Agreement No. 679, and to allow the Executive Director or designee to make any nonsubstantive changes to the language.
Action: The Authority Board approved authorization for the Chair to execute Funding MOU Agreement No. 679 with Contra Costa County for the Authority to receive $1,470,000 in Measure X funding, authorize the funds to be used for the tasks identified in the Service Plan in Agreement No. 679, and to allow the Executive Director or designee to make any nonsubstantive changes to the language.
D. 2025 Countywide Transportation Plan (CTP) Environmental Impact Report (EIR) – Authorization to Execute Agreement No. 680 with Circlepoint for Environmental Analysis Services
Recommendation: Staff sought authorization for the Chair to execute Agreement No. 680 with Circlepoint in the amount of $424,687.66, for development of the 2025 CTP EIR, and to allow the Executive Director or designee to make any non-substantive changes to the language. The term will be through December 20, 2026.
RTPC Memorandum
January 11, 2024
https://cctauthority.sharepoint.com/sites/Common/09Correspondences/RTPC Memos/2023/December 20 2023 RTPC Memo_Final_.doc Action: The Authority Board approved authorization for the Chair to execute Agreement No. 680 with Circlepoint in the amount of $424,687.66, for development of the 2025 CTP EIR, and to allow the Executive Director or designee to make any non-substantive changes to the language with a term extended through December 20, 2026.
E. Consider the Conduct for Meetings of the Legislative Bodies of the Authority for December 2023
Recommendation: Staff requested that the Authority Board consider the options for meeting conduct after December 2023 and provide direction to staff on the conduct of meetings for the Authority’s legislative body.
Action: The Authority Board authorized staff to conduct all of the Authority’s legislative body meeting in‐person with a hybrid component for public participation and comment effective January 2, 2023.
F. Approval of the 2023 Congestion Management Program (CMP) Update for Contra Costa County
Recommendation: Staff sought approval of Resolution 23-43-G, which will adopt the 2023 CMP update for Contra Costa County, authorize staff to make any non-substantive changes to finalize the document, and authorize staff to forward the CMP to the Metropolitan Transportation Commission.
Action: The Authority Board approved Resolution 23-43-G, which will adopt the 2023 CMP update for Contra Costa County, authorize staff to make any non-substantive changes to finalize the document, and authorize staff to forward the CMP to the Metropolitan Transportation Commission.
G. Approval to Form a Sub-Committee of the Authority Board to Develop the Countywide Transportation Plan 2050 (CTP2050)
Recommendation: Staff sought approval to form a sub-committee of up to three members of the Authority Board to assist with the development of the CTP2050, and appointment of members to serve on the sub-committee.
Action: The Authority Board approved the formation of a CTP2050 SubCommittee of up to three members of the Authority Board to assist with the RTPC Memorandum
January 11, 2024
https://cctauthority.sharepoint.com/sites/Common/09Correspondences/RTPC Memos/2023/December 20 2023 RTPC Memo_Final_.doc development of the CTP2050, and appointed Commissioners Carlson, Kelley, and Sos to serve on the CTP Sub-Committee.
Authority Board Meeting MINUTES
MEETINGDATE: Wednesday, December 20, 2023
MINUTESPREPAREDBY: Tarienne Grover
MEMBERSPRESENT: STAFFPRESENT: MEMBERS ABSENT:
Federal Glover, Chair/MTCRep.
Newell Arnerich, Vice Chair
Paul Fadelli, Commissioner
Loella Haskew, Commissioner
Chris Kelley, Commissioner
Aaron Meadows, Commissioner
Colin Clarke
Tarienne Grover
Timothy Haile
Jack Hall
John Hoang
Stephanie Hu
Ken Carlson, Commissioner
H.E. Christian Peeples, Ex-Officio Rep.
Sue Noack, Commissioner/MTC Rep. Lindy Johnson
Renata Sos, Commissioner
Lamar Thorpe, Commissioner
Scott Perkins, Commissioner
Mark Foley, Ex-Officio Rep.
Rashida Kamara
Brian Kelleher
Matt Kelly
Daniel Mermelstein
Hisham Noeimi
Emily Owen
Ivan Ramirez
Jackie Reyes
Ying Smith
Sherri Sylva
Yuliana Tjeng
Neal Parish, Legal Counsel
1. CONVENE MEETING: Federal Glover, Chair
DISCUSSION: Chair Glover convened the meeting at 6:00 PM. Commissioner Carlson and Rep. Peeples were absent.
2. PLEDGE OF ALLEGIANCE
3. PUBLIC COMMENT: Members of the public are invited to address the Authority regarding any item that is not listed on the agenda. Please refer to the Teleconferencing Special Notice for Public Comment guidelines.
DISCUSSION: There were no public comments on items not on the agenda.
4. PRESENTATIONS
A. Richmond-San Rafael Bridge Updates: Representatives from Bay Area Toll Authority/Metropolitan Transportation Commission will provide an update on Authority Board Meeting MINUTES
December 20, 2023
current pilot projects and planned improvements as part of the Richmond-San Rafael Bridge Forward project.
DISCUSSION: Hisham Noeimi, Director, Programming, provided a brief background and introduced Lisa Klein with the Metropolitan Transportation Commission to present the item.
Ms. Klein provided an overview of the Richmond-San Rafael (RSR) Bridge Access Improvement pilot program, an update from the Bay Area Toll Authority (BATA) Oversight Committee, discussed pilot design for the purpose of reducing congestion and improving the bicycle/pedestrian access, bicycle and pedestrian path usage, success of reducing congestion on Eastbound Interstate 580 through use of a part-time transit lane on the lower deck, incident and safety response, next steps and timeline for the pilot program.
Ms. Klein further discussed considerations for westbound traffic and the potential impacts on congestion and air quality in addition to the cost of converting the third lane to a part-time high-occupancy vehicle (HOV)/bus lane, and summarized that there is a significant cost for improvements, it would need to meet California Environmental Quality Act of 1970 requirements, and that no funding has been identified in BATA’s Capital Improvement Plan for these improvements.
She further discussed the projects that are fully funded with Regional Measure 3 as part of the RSR Forward Project which will include open road tolling, an HOV lane extension, Richmond Parkway improvements, and would help reduce congestion, freeway operations, and air quality in the City of Richmond. However, this doesn’t include structural strengthening as part of the proposed budget for improvements.
Commissioners provided comments. Ms. Klein and David Ambuehl with the California Department of Transportation responded to comments from commissioners.
Public Comment:
Bruce Ohlson, Bike East Bay
CONSENT CALENDAR
ACTION: Commissioner Thorpe moved to approve the consent calendar, seconded by Commissioner Noack. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Authority Board Meeting MINUTES
December 20, 2023
Noes-None
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: Commissioner Kelley provided comments on Consent Calendar Item 6G. Rep.
Foley responded to the comments.
5. APPROVAL OF MINUTES
A. Authority Board Minutes of November 15, 2023
6. Administration & Projects Committee - Consent:
A. Accept Monthly Accounts Payable Invoice Report for October 2023 Recommendation: Staff seeks acceptance of the monthly accounts payable invoice report for October 2023.
B. Authorization to Execute Amendment No. 3 to Agreement No. 489 with Tai Ginsberg & Associates, LLC (TGA) for Federal Advocacy Services Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 3 to Agreement No. 489 with TGA in the amount of $7,000 per month ($84,000/year), with an additional $3,500 per year for pre-approved travel expenses, for a new total agreement value of $546,500 for federal advocacy services, extend the agreement termination date to January 1, 2026, and to allow the Executive Director or designee to make any non-substantive changes to the language.
C. Authorization to Execute Amendment No. 6 to Agreement No. 451 with Mark Watts Advocacy, LLC (MWA) for State Advocacy Services
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 6 to Agreement No. 451 with MWA in the amount of $5,000 per month ($60,000/year), for a new total agreement value of $468,000, to provide state advocacy services, extend the agreement termination date to December 31, 2026, and to allow the Executive Director or designee to make any non-substantive changes to the language.
D. Project and Program Management (PPM) Services – Authorization to Issue Request for Proposals (RFP) No. 23-7 for PPM Services
Recommendation: Staff seeks authorization to issue RFP No. 23-7 to obtain proposals from firms interested in providing the Authority with PPM services.
E. Authorization to Execute Amendment No. 1 to Agreement No. 596 with Elevate Public Affairs (EPA) for Media Relations Services
Authority Board Meeting MINUTES
December 20, 2023
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 1 to Agreement No. 596 with EPA to provide media relations services and increase EPA’s billing fees to its 2023 rates.
F. Bollinger Canyon Road – Iron Horse Trail (IHT) Bicycle and Pedestrian Overcrossing (POC) (Project 120025):
1. Authorization to Execute Amendment No. 4 to Agreement No. 545 with COWI North America, Inc. (COWI) for Additional Design and Engineering Services Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 4 to Agreement No. 545 with COWI in the amount of $160,000, for a new total agreement value of $2,926,082, to provide additional design and engineering services, and to allow the Executive Director or designee to make any non-substantive changes to the language.
2. Approval of Resolution 23-47-P for Construction Services Recommendation: Staff seeks approval of Resolution 23-47-P, which will establish a total construction allotment of $21,817,973.07 for construction services of which $200,000 will be in contingency, and authorize the Executive Director or designee to shift funds between construction allotment categories as long as the total expenditures do not exceed the total construction allotment.
G. Bay Area Rapid Transit (BART) – Central County BART Next Generation Fare Gates (NGFG) (Project 10001-09) – Approval to Appropriate Measure J Funds to BART for Design and Construction Phases
Recommendation: Staff seeks approval of Resolution 23-48-P, which will appropriate $3.5 million in Measure J funds to BART for the design and construction phases of the Central County BART NGFG project.
H. Project and Program Management (PPM) Services for the Construction Program – Authorization to Issue Request for Proposals (RFP) No. 23-6 for the Construction Program
Recommendation: Staff seeks authorization to issue RFP No. 23-6 to obtain proposals from firms interested in providing the Authority with PPM services for the construction program.
I. Project and Program Management (PPM) Services for the Construction Program – Authorization to Execute Amendment No. 6 to Agreement No. 521 with Cole Management & Engineering, Inc. (CME) for Additional PPM Services Authority Board Meeting MINUTES
December 20, 2023
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 6 to Agreement No. 521 with CME in the amount of $483,683.33, for a new total agreement value of $5,955,596.23, to provide additional PPM services, and to allow the Executive Director or designee to make any non-substantive changes to the language.
J. Interstate 680/State Route 4 Interchange Improvements, Phases 1, 2A, and 4 (Project 6001) (Project) – Approval of Resolution 23-21-P to Adopt Amendment No. 2 to the 2022 Measure J Strategic Plan
Recommendation: Staff seeks approval of Resolution 23-21-P, which will adopt Amendment No. 2 to the 2022 Measure J Strategic Plan, to reprogram $150,000 from the Central County – Construction Reserve to the Project.
K. Legislative Update
Recommendation: Staff will provide an update on legislation, along with addressing any questions that may arise. The Authority may take action on any item presented in the attachment or any State or Federal legislation pertaining to the Authority’s legislative program.
L. Interstate 80 (I-80)/San Pablo Dam Road Interchange, Phase 2 (Project 7002) (Project):
1. Authorization to Execute Amendment No. 10 to Agreement No. 316 with AECOM Technical Services Inc. (AECOM) for Engineering Support Services Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 10 to Agreement No. 316 with AECOM, in the amount of $4,797,013, for a new total agreement value of $11,543,013, to provide additional design and right-of-way services for the Project, and to allow the Executive Director or designee to make any non-substantive changes to the language. This amendment will extend the agreement termination date from December 31, 2023 to December 31, 2026.
2. Authorization to Execute Cooperative Agreement No. 07W.08 with the City of San Pablo (City)
Recommendation: Staff seeks authorization for the Chair to execute Cooperative Agreement No. 07W.08 with the City to outline the roles and responsibilities for Phase 2 of the Project, and to allow the Executive Director or designee to make any non-substantive changes to the language.
M. State Route 4 Mokelumne Bike Trail/Pedestrian Overcrossing (Project 5002b):
1. Approval to Increase the Construction Allotment for Agreement No. 561 with Joseph J. Albanese for Construction Services
Authority Board Meeting MINUTES
December 20, 2023
Recommendation: Staff seeks approval of Resolution 21-41-P (Rev 2), which will increase the construction allotment amount by $131,987, for a new total construction allotment value of $10,334,257, to provide additional construction services.
2. Authorization to Approve Contract Change Order No. 24 (CCO No. 24) to Construction Contract No. 561 with Joseph J. Albanese, Inc. (JJA) for Construction Services
Recommendation: Staff seeks approval of CCO No. 24 to Construction Contract No. 561 with JJA in the amount of $462,477.40, for the direct costs associated with measures to make the deck grades at Frame 3 compliant with the Americans with Disabilities Act of 1990, contingent upon approval of Resolution 21-41-P (Rev 2).
3. Approval of Resolution 23-49-P to Submit a Regional Measure 3 Allocation Request
Recommendation: Staff seeks approval of Resolution 23-49-P, which will authorize submittal of an allocation request to the Metropolitan Transportation Commission for an additional amount of $1 million for construction services.
N. NEW ITEM: Authorization to Execute Task Order No. 5 (TO5) to Letter Agreement No. 601 with Fennemore LLP dba Fennemore Wendel (Fennemore) for Legal Services to Trademark the Authority’s Assets
Recommendation: Staff seeks authorization for the Chair to execute TO5 to Letter Agreement No. 601 with Fennemore, in an amount not-to-exceed $4,645, to provide legal services to trademark the Authority’s PRESTO mobility brand, with a term through March 15, 2024.
O. NEW ITEM: Authorization to Execute Amendment No. 3 to Agreement No. 578 with Baker Tilly US, LLP (Baker Tilly) for Executive Recruitment Services Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 3 to Agreement No. 578 with Baker Tilly in the amount of $30,000, for a new total agreement value of $135,000, to provide additional executive recruitment services, and to allow the Executive Director or designee to make any nonsubstantive changes to the language. The agreement termination date will be extended through December 31, 2024.
7. Planning Committee - Consent:
Authority Board Meeting MINUTES
December 20, 2023
A. Authorization to Execute Amendment No. 01 to Agreement No. ARV-20-008 with the California Energy Commission (CEC) to Revise the Terms, Scope, and Budget Allocation and to Rename Previous Amendment No. 1 to Amendment A - Streamlining Terms and Conditions
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 01 to Agreement No. ARV-20-008 with the CEC to modify the scope, budget allocation between categories, and extend the term from March 17, 2024 to March 17, 2026, to rename previous Amendment No. 1 to Amendment A - Streamlining Terms and Conditions, and to allow the Executive Director to enter into necessary amendments with the cities of Richmond and Pittsburg, the Community Choice Aggregator previously named Marin Clean Energy, and Advanced Mobility Group that are consistent with Amendment No. 01.
B. City of Pleasant Hill (City) – Contra Costa Boulevard Improvements, Viking Drive to Harriet Drive (Project 120054/130026) (Project) – Approval to Revise Project Scope for Previous Measure J Funding Appropriation Resolution 23-09-G for Construction Phase
Recommendation: Staff seeks approval of the proposed revised scope (still consistent with Attachment A to Resolution 23-09-G as adopted on May 17, 2023) to be constructed with the previously appropriated Measure J Transportation for Livable Communities (Program 12) funds in the amount of $3,792,000 and Pedestrian, Bicycle, and Trail Facilities (Program 13) funds in the amount of $1,000,000, for a total of $4,792,000 in Measure J funds to the City, for the construction phase of the Project.
C. Town of Danville (Town) – Approval of Resolution 16-02-G (Rev 4) to Withdraw the Sycamore Valley Park and Ride Expansion (Project 120052) to Reprogram and Appropriate its $1,500,000 Savings to the Diablo Road Circulation Improvements (Project 120030/24035) – Construction Phase
Recommendation: Staff seeks approval of Resolution 16-02-G (Rev 4), on behalf of the Town, to withdraw the Sycamore Valley Park and Ride Expansion (Project 120052) from the Measure J Transportation for Livable Communities (TLC) and Pedestrian, Bicycle, and Trail Facilities Programming Plan, and authorization to reprogram and appropriate (a funding resolution action to extend 16-02-G past its current expiration of December 31, 2023) Measure J TLC project savings in the amount of $1,500,000 from the Sycamore Valley Park and Ride Expansion (Project 120052) to the Diablo Road Circulation Improvements (Project 120030/24035), also known as the Diablo Road Trail project.
D. Development of the Bi-County Travel Model (Project) – Authorization to Execute Amendment No. 1 to Cooperative Agreement No. 18W.04 with Alameda County Transportation Commission (Alameda CTC) for a Time Extension Authority Board Meeting MINUTES
December 20, 2023
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 1 to Cooperative Agreement No. 18W.04 with Alameda CTC, to allow additional time to complete the Project, and to allow the Executive Director or designee to make any non-substantive changes to the language. This amendment will extend the agreement termination date from December 31, 2023 to December 31, 2024.
E. Approval of Proposed Action to Funding Resolution
Recommendation: Staff seeks approval of Resolution 12-43-G (Rev 8), which will extend the term of the resolution to December 31, 2025 with the Town of Moraga for the Livable Moraga Road (Project 120022).
F. Authorization to Execute Funding Memorandum of Understanding (MOU) Agreement No. 679 with Contra Costa County for $1,470,000 of Measure X Funds to Support Implementation of the Accessible Transportation Strategic Plan Recommendation: Staff seeks authorization for the Chair to execute Funding MOU Agreement No. 679 with Contra Costa County for the Authority to receive $1,470,000 in Measure X funding, authorize the funds to be used for the tasks identified in the Service Plan in Agreement No. 679, and to allow the Executive Director or designee to make any non-substantive changes to the language.
G. NEW ITEM: 2025 Countywide Transportation Plan (CTP) Environmental Impact Report (EIR) – Authorization to Execute Agreement No. 680 with Circlepoint for Environmental Analysis Services
Recommendation: Staff seeks authorization for the Chair to execute Agreement No. 680 with Circlepoint in the amount of $424,687.66, for development of the 2025 CTP EIR, and to allow the Executive Director or designee to make any nonsubstantive changes to the language. The term will be through December 20, 2026.
H. NEW ITEM: Approval of the City of Antioch Calendar Years CY 2020 and 2021 Measure J Growth Management Program (GMP) Compliance Checklist Recommendation: Staff seeks approval of the City of Antioch GMP Compliance Checklist and payment of $1,781,217 in Fiscal Year (FY) 2020-21 Local Street Maintenance and Improvement funds to the City of Antioch, with a second (offyear) payment of FY 2022-23 funds on the one-year anniversary of the first payment.
I. NEW ITEM: Approval of the City of Martinez Calendar Years 2020 and 2021 Measure J Growth Management Program (GMP) Compliance Checklist Recommendation: Staff seeks approval of the City of Martinez GMP Compliance Checklist and payment of $750,637 in Fiscal Year (FY) 2021-22 Local Street Maintenance and Improvement funds to the City of Martinez, with a second (offyear) payment of FY 2022-23 funds on the one-year anniversary of the first payment.
Authority Board Meeting MINUTES
December 20, 2023
REGULAR AGENDA ITEMS
8. Administration & Projects Committee - Regular:
A. Interstate 680/State Route 4 Interchange Improvements, Phases 1, 2A, and 4 (Project 6001) – Authorization to Execute Amendment No. 4 to Agreement No. 503 and Task Order 1A (TO1A) with WMH Corporation (WMH) for Environmental and Final Design Services
Recommendation: Staff seeks authorization for the Chair to execute Amendment No. 4 to Agreement No. 503 and TO1A with WMH in the amount of $3 million, for a new total agreement value of $26,155,044, to provide additional environmental revalidation, final design, and bid support services, and to allow the Executive Director or designee to make any non-substantive changes to the language.
ACTION: Vice Chair Arnerich moved to authorize the Chair to execute Amendment No. 4 to Agreement No. 503 and Task Order 1A with WMH Corporation in the amount of $3 million, for a new total agreement value of $26,155,044, to provide additional environmental revalidation, final design, and bid support services, and to allow the Executive Director or designee to make any non-substantive changes to the language, seconded by Commissioner Kelley. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Noes-None
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: Ivan Ramirez, Director, Construction, provided an overview and background of the project including environmental revalidation, issues encountered, and potential solutions to reduce design errors during construction such as 3D building models.
Commissioners provided comments. Staff responded to comments from commissioners.
Public Comment:
Bruce Ohlson, Bike East Bay
B. NEW ITEM: Approval of Fourth Amendment to Employment Agreement with Timothy Haile, Executive Director
Recommendation: The Chair seeks Authority Board approval of the fourth amendment to the Authority’s employment agreement with Timothy Haile, Executive Director, which will adjust his compensation to $365,967 per year effective December 27, 2023. The term of the amendment will be extended for three additional years through December 27, 2026.
Authority Board Meeting MINUTES
December 20, 2023
ACTION: Vice Chair Arnerich moved to approve the fourth amendment to the Authority’s employment agreement with Timothy Haile, Executive Director, which will adjust his compensation to $365,967 per year effective December 27, 2023 and extend the term of the amendment for three additional years through December 27, 2026, seconded by Commissioner Haskew. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Noes-None
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: Tarienne Grover, Director, Administrative Services, provided a brief overview and stated the recommendation in accordance with the Brown Act to memorialize the Authority Board’s amendment to the agreement with Timothy Haile, Executive Director.
Chair Glover requested that the Authority Board Chair be given a more significant role in the evaluation process for future amendments.
C. NEW ITEM: Consider the Conduct for Meetings of the Legislative Bodies of the Authority
Recommendation: Staff requests that the Authority Board consider the options for meeting conduct after December 2023, and provide direction to staff on the conduct of meetings for the Authority’s legislative body meetings.
ACTION: Commissioner Noack moved to authorize staff to return to in-person meetings with a remote component for public participation and comment effective January 2, 2024 for all legislative body meetings of the Authority, seconded by Commissioner Perkins. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Noes-None
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: Tarienne Grover, Director, Administrative Services, provided a background and overview of the options for legislative body meetings after December 2023, and sought direction from the Authority Board on meeting conduct for all legislative body meetings.
Commissioners provided comments. Commissioner Sos requested that we monitor a potential legislative bill related to Citizens Advisory Committees and their ability to continue meeting remotely. Staff responded to comments from commissioners.
Authority Board Meeting MINUTES
December 20, 2023
9. Planning Committee - Regular:
A. PUBLIC HEARING: Approval of the 2023 Congestion Management Program (CMP) Update for Contra Costa County
Recommendation: Staff seeks approval of Resolution 23-43-G, which will adopt the 2023 CMP update for Contra Costa County, authorize staff to make any nonsubstantive changes to finalize the document, and authorize staff to forward the CMP to the Metropolitan Transportation Commission.
ACTION: Commissioner Kelley moved to approve Resolution 23-43-G, which will adopt the 2023 Congestion Management Program (CMP) update for Contra Costa County, authorize staff to make any non-substantive changes to finalize the document, and authorize staff to forward the CMP to the Metropolitan Transportation Commission, seconded by Commissioner Sos. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Noes-None
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: Matt Kelly, Senior Transportation Planner, provided an overview and background of the 2023 CMP update for Contra Costa County, discussed the five components such as monitoring the level-of-service standards on roadways and major arterials, establishing performance measures for roadways and the multimodal system, developing a Capital Improvement Program, analyzing the impacts of land use on the transportation system, and establishing a Travel Demand Element, and discussed the current efforts to demonstrate consistency with Plan Bay Area 2050, monitor level-of-service at intersections around the county, and adopt the Metropolitan Transportation Commission’s model.
Chair Glover opened the Public Hearing at 7:28 PM. There were no public comments received. Chair Glover closed the Public Hearing at 7:29 PM.
B. NEW ITEM: Approval to Form a Sub-Committee of the Authority Board to Develop the Countywide Transportation Plan 2050 (CTP2050)
Recommendation: Staff seeks approval to form a sub-committee of up to three members of the Authority Board to assist with the development of the CTP2050, and appointment of members to serve on the sub-committee.
ACTION: Vice Chair Arnerich moved to approve the formation of a Countywide Transportation Plan (CTP) 2050 Sub-Committee of up to three members of the Authority Board to assist with the development of the CTP2050, and nominated and appointed Commissioners Carlson, Kelley and Sos to serve on the CTP Sub-Committee, seconded by Commissioner Noack. The motion was adopted by unanimous vote of the commissioners present, unless otherwise noted.
Authority Board Meeting MINUTES
December 20, 2023
Noes-Commissioner Thorpe
Absent-Commissioner Carlson
Abstain-None
DISCUSSION: John Hoang, Director, Planning, provided a background and overview of the CTP 2050, need for a sub-committee to assist with the development of the CTP 2050, and appointment of up to three Authority Board members to serve on the sub-committee.
Vice Chair Arnerich nominated Commissioners Carlson, Kelley, and Sos to serve on the CTP 2050 Sub-Committee.
Commissioners provided comments. Commissioner Thorpe stated that there was a lack of representation from East Contra Costa County.
10. CORRESPONDENCE AND COMMUNICATIONS
11. ASSOCIATED COMMITTEE REPORTS
A. Central County (TRANSPAC): Meeting Reports for the regular meetings on October 12, 2023, November 9, 2023, and December 14, 2023 (Attachment and meeting handout if available)
B. East County (TRANSPLAN): Meeting Report for the regular meeting on December 14, 2023 (Meeting handout if available)
C. Southwest County (SWAT): Meeting Report for the regular meeting on December 4, 2023
D. West County (WCCTAC): Meeting Reports for the regular meeting on October 27, 2023 and a special meeting on December 8, 2023 (Attachment and meeting handout if available)
12. AUTHORITY BOARD AND STAFF COMMENTS
A. Chair's Comments and Reports
B. Commissioners' and Ex-Officio Representatives’ Comments and Reports on Activities and Meetings
Authority Board Meeting MINUTES
December 20, 2023
DISCUSSION: Commissioner Haskew provided a report from the California Association of Councils of Governments Board meeting and Retreat on December 7, 2023.
Commissioner Kelley thanked Reps. Glover and Noack for their comments at the Metropolitan Transportation Commission (MTC) Board meeting.
Rep. Foley thanked the commissioners for their support on the Bay Area Rapid Transit (BART) Next Generations Fare Gates project, provided an update on the fare gates project at the BART stations, and discussed improvements for payment processing for BART fares.
Rep. Noack provided an update from the MTC meeting on December 20, 2023, regarding the need for enabling legislation to pursue a ballot measure in 2026, MTC’s authority, public acceptance of a measure, and announced that in January 2024 they will review a proposal for potential legislation.
Rep. Glover discussed the concerns of the transit operators and efforts to work closely together to build a network that works for Contra Costa County. He announced that a meeting will be scheduled with the small transit operators.
C. Executive Staff Comments
DISCUSSION: Timothy Haile, Executive Director, discussed the regional transportation working group meetings, staying apprised of direction from the Metropolitan Transportation Commission (MTC) on transit coordination versus consolidation, announced that the authorizing legislation if approved by MTC in January will be authored by Senator Wiener, and that Authority staff is working closely with the transit operators to form a unified voice around the regional measure, and will keep the Authority Board apprised. Mr. Haile further discussed the 10-year anniversary of the Caldecott Tunnel, provided an update on the dynamic personal micro-transit project, and announced that the Authority won the legacy award for the East Bay Innovation Awards with the ceremony to be held on March 28, 2024 and the Redefining Mobility Summit confirmed for May 7, 2024.
13. CALENDAR
A. December 2023, and January, February, and March 2024 B. Calendar of Upcoming Events
14. ADJOURNMENT to the next regular meeting proposed for January 17, 2024 at 6:00 PM.
DISCUSSION: The meeting was adjourned at 7:47 PM.