PETRO-ANALYTICAL, INC.

P.O. BOX 2301 ORINDA, CA 94563 PHONE: 925.253.0591 Email: [email protected] California Contractors License #843221 General Engineering A September 16, 2024
City of Pleasant Hill
Attn: Ann James
310 Civic Dr.

Pleasant Hill, CA 94523
Re. Police Dept. fueling system replacement COR detail
Dear Ann James:

Thank you for your inquiry re. the scope of work transition from UST removal to UST ‘closure in-place’ on the City of Pleasant Hill Police Dept. fuel system replacement project (Project).

We have prepared the following table detailing the original scope of work tasks which were completed associated with the UST removal, and any correlating financial offsets. Per below, the standby offsets were considered in the development of the change order request, effectively ‘crediting’ those costs against the minor remaining UST removal tasks.

SUMMARY
Costs associated with ‘Standby’ or ‘Delay” time awaiting regulatory approval for the closure in-place effectively offset minor remaining original scope of work tasks and associated costs. The existing UST was ~65% ready for disposal at the time of water line proximity observation. All work was placed on standby pending resolution.

These ‘net’ costs were calculated into the COR budget report presented on 8/30/24. (Similarly, only the ‘net’ costs for the piping run for the new UST were presented in the 8/30/24 report) Please see detail below).

All other costs presented represent additional work related to out-of-scope tasks:
 Dewatering
 Soils management
 Contamination evaluation
 Restoration
As of 9/16/24 we do not anticipate any further out-of-scope tasks or costs.

DETAIL
UST removal tasks Tasks
completed
Offset
Permitting  Work completed (no offset)
Permit Fees  Work completed (no offset)
Utility search  Work completed (no offset)
Mobilization  Work completed (no offset)
A/C removal  Work completed (no offset)
Canopy removal  Work completed (no offset)
UST excavation layout  Work completed (no offset)
Exhibit B
PETRO-ANALYTICAL, INC.

P.O. BOX 2301 ORINDA, CA 94563 PHONE: 925.253.0591 Email: [email protected] California Contractors License #843221 General Engineering A Excavation/Shoring/UST demo
and offhaul (partial)
65% 65% work completed

1. The associated costs with the above were offset
by the delay cost for on-site standby awaiting
regulatory approval for closure in-place rather
than removal.

2. These delay costs were not included in the
COR. Costs included:

2.1. Excavator /Skidsteer/Loader/Dump truck
standby

2.2. Operators (3) standby

2.3. Technicians (5) standby

3. Remaining UST removal task value $12,500.00

4. Delay cost value $17,750.00
Soil sampling (per scope)  Work completed (no offset)
Analytical (per scope) 1. Work completed (no offset)

1.1. Only additional analytical related to
contamination evaluation included in
COR)
UST cleaning  1. UST rinsing activities were completed per scope.

1.1. (Additional degassing required per
County for closure in-place was included
in COR)
Fuel piping None 1. No original scope of work fuel piping was performed.

2. The pipe run from the original UST location
was ~12’ to the dispenser.

3. The new pipe run from the new UST location
to the dispenser is ~45’.

4. Fuel pipe offset value is $4,500.00

5. Delay cost value (remaining) is $5,250.00
Thank you for the opportunity to provide this clarification. We look forward to completing this project with you. If you have any questions, please feel free to reach me directly @ 925.528.9998.

Best Regards,
Petro-Analytical, Inc.

K.W. ‘Bud’ McCuaig
KWM:rw