Exhibit A
400kW COMMUNITY CENTER SOW COST
400kW Diesel Generator with outdoor enclosure
and sub base fuel tank $139,250.00
Automatic Transfer Switch x2 $17,515.00
Electrical Scope $160,000.00
Civil (Trench for electrical, concrete pad and
fence) $114,000.00
Crane off load and set $6,200.00
Installation labor $12,660.00
On site fuel tank pressure testing $2,400.00
Factory Commissioning and Testing with
warranty submission $4,250.00
Engineering / Construction Drawings /
Permitting / Air Quality Permitting $18,173.00
Fuel fill $5,552.00
Total excluding any taxes or freight $480,000.00
100kW CITY HALL SOW COST
100kW Diesel Generator with outdoor enclosure
and sub base fuel tank $63,034.60
Automatic Transfer Switch $9,166.00
Electrical Scope $111,000.00
Civil (Trench for electrical, concrete pad and
fence) $79,000.00
Crane off load and set $9,600.00
Installation labor $14,660.00
On site fuel tank pressure testing $2,400.00
Factory Commissioning and Testing with
warranty submission $4,250.00
Engineering / Construction Drawings /
Permitting / Air Quality Permitting $50,577.00
Fuel fill $5,552.00
Total excluding any taxes or freight $349,239.60