RESOLUTION NO. - 25

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PLEASANT HILL ACCEPTING THE 2024 STORM DRAIN IMPROVEMENT PROJECT NO. 04-24 AS

COMPLETE AND AUTHORIZING THE PUBLIC WORKS DIRECTOR TO ISSUE AND

RECORD A NOTICE OF COMPLETION
WHEREAS, the 2024 Storm Drain Maintenance, Project No. 04-24 is an identified and approved project in the 2024-2029 Capital Improvement Plan; and WHEREAS, the 2024 Storm Drain Maintenance Project No. 04-24 provides for the repair of storm drain systems at 507 Masefield Drive and Boyd Road; and WHEREAS, the 2024 Storm Drain Maintenance Project No. 04-24 is categorically exempt from environmental review under the California Environmental Quality Act pursuant to California Code of Regulations Title 14, Chapter 3, Section 15301 as a Class 1 categorical exemption (operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the lead agency’s determination) and Section 15302 as a Class 2 categorical exemption (replacement or reconstruction of existing structures and facilities where the new structure will be located on the same site as the structure replaced and will have substantially the same purpose and capacity as the structure replaced such as the replacement or reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity); and WHEREAS, on March 20, 2025, the City Manager, under the powers authorized by the City Council in Resolution No. 38-14 (Capital Improvement Plan 2014-2019) and Ordinance No. 770 (Bidding on Public Projects), executed a contract with FJ&I Engineering, Inc. to perform work described in contract documents entitled 2024 Storm Drain Improvement Project No. 04-24; and WHEREAS, the work has been performed to the satisfaction of the City and FJ&I Engineering, Inc. is requesting final payment for the completed work; and WHEREAS, the California Public Contract Code requires the City to notify the public of acceptance of a project prior to making a final payment.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Pleasant Hill finds that the work performed as 2024 Storm Drain Improvement Project No. 04-24 is complete to the satisfaction of the City and is hereby accepted as complete.

BE IT FURTHER RESOLVED, that the Public Works Director is authorized to execute a Notice of Completion and record it with the Office of the Recorder of the County of Contra Costa, State of California, within 10 days from the date thereof. [Signatures on the Following Page]
ADOPTED by the City Council of the City of Pleasant Hill at a regular meeting held on the 8th day of September, 2025, by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:
________________________
SUE NOACK, Mayor
ATTEST:
___________________________
LYONE P. CONNER, City Clerk