PROJECT NUMBER: MK-001
DEPARTMENT: Public Works
ESTIMATED BUDGET: $16,092,205
ACCOUNT: 301-5063
PROJECT DESCRIPTION:
PROJECT SCOPE:
FY 2026-27 FY 2027-28 FY 2028-29 FY 2029-30 FY 2030-31 TOTALS 630034 Design $0
611010 Engineering Staff $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 620131 Project Admin. $0
800030 Construction $5,350,000 $3,055,205 $2,479,000 $2,479,000 $2,479,000 $15,842,205 630018 C. Management $0
TOTAL $5,400,000 $3,105,205 $2,529,000 $2,529,000 $2,529,000 $16,092,205 PROJECT FUNDING:
Gas Tax (301) $700,000 $500,000 $500,000 $500,000 $500,000 $2,700,000 SB1 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $5,000,000 Measure K $1,900,000 $1,605,205 $1,029,000 $1,029,000 $1,029,000 $6,592,205 Measure J $1,500,000
Other* $300,000 $300,000
TOTAL $5,400,000 $3,105,205 $2,529,000 $2,529,000 $2,529,000 $16,092,205 PROJECT BENEFIT:
Extends the life of the pavement and provides timely and cost effective maintenance and pothole repairs. *unspent allocated funds from FY25-26 rolled over to FY26-27
STREETS & ROADS
STREET RESURFACING PROGRAM
This program provides for on-going maintenance of the City's 110 miles of roadway pavement. Roadway pavement typically needs to be maintained every 10 years, which means the City would have to rehabilitate approximately 11 miles of streets each year before starting over, to consistently maintain the streets in good condition.
Currently the City's Pavement Management Program estimates that an annual allocation of $2.5 million is necessary in order to maintain the City's Pavement Condition Index (PCI) at its current value of 70 points (good overall street condition), and an annual allocation of $3.5M will increase and maintain the City's PCI at 72 points. Currently 50.1% of the City’s streets are in “good” condition. Reducing the expenditures of funds below $2.5M will increase the City's long term maintenance backlog and reduce the overall PCI and condition of city streets.
Capital Improvement Plan FY 2026-2031