1 SAN JOSE CREEK

MULTI-USE BIKEWAY

PROJECT
Steven Frieson, Project Manager
Alta Planning + Design
Attachment 1

• Adds 3.5 miles of new trail to the
San Jose Creek Bikeway
• Provides easy cycling connections to
John F . Kennedy Park
• Creates neighborhood greening at trailheads
• Uses native and drought tolerant trees
and plants
• Includes seating, shade, and other
park amenities

PROJECT BENEFITS

MURCHISON AVENUE (MURCHISON TRAILHEAD
Existing Conditions Proposed Design
TEMPLE AVENUE + SOUTH CAMPUS DRIVE (TEMPLE TRAILHEAD)
Existing Conditions Proposed Design

• Estimated Construction Cost is
$10.5 million
• Anticipated CEQA Approval by
December 31, 2025
• Anticipated Start of Construction
by June 2026
• Anticipated Construction
Completion by June 2027
PROJECT STATISTICS + DATES

Steven Frieson, Project Manager
[email protected]
10/27/2025 FOOTER GOES HERE 7
San Jose Creek Multi-Use Bikeway Project

← All documents from this meeting