Task Staff Hours Rate Markup Total
Geotechnical Investigations Landmark - 9,750 $ 15% 11,213 $ Geotechnical Construction Testing Landmark - 9,200 $ 15% 10,580 $ Geotechnical Shop Welding Inspection (if required) Landmark - 1,350 $ 15% 1,553 $ Civil Engineering - Schematic Design VCA - 5,430 $ 15% 6,245 $ Civil Engineering - Design Development VCA - 7,157 $ 15% 8,231 $ Civil Engineering - Construction Documents VCA - 8,638 $ 15% 9,934 $ Civil Engineering - Plan Check / Bidding VCA - 987 $ 15% 1,135 $ Civil Engineering - Construction Administration VCA - 2,468 $ 15% 2,838 $ Civil Engineering - Topographical Survey VCA - 16,000 $ 15% 18,400 $ Civil Engineering - Underground Utility Survey (GPR) VCA - 15,800 $ 15% 18,170 $ Landscape Architecture - Schematic Design CWDG - 1,280 $ 15% 1,472 $ Landscape Architecture - Meetings CWDG - 1,170 $ 15% 1,346 $ Landscape Architecture - Construction Documents CWDG - 1,680 $ 15% 1,932 $ Landscape Architecture - Plan Check / Construction Ad min CWDG - 1,480 $ 15% 1,702 $ Structural Engineering - Schematic Design Wiseman + Rohy - 2,700 $ 15% 3,105 $ Structural Engineering - Design Development Wiseman + Rohy - 3,600 $ 15% 4,140 $ Structural Engineering - Construction Documents / Pl an Check Wiseman + Rohy - 8,700 $ 15% 10,005 $ Structural Engineering - Construction Administration Wiseman + Rohy - 3,000 $ 15% 3,450 $ M/E/P Engineering - Schematic Design P2S - 5,948 $ 15% 6,840 $ M/E/P Engineering - Design Development P2S - 11,896 $ 15% 13,680 $ M/E/P Engineering - Construction Documents P2S - 19,331 $ 15% 22,231 $ M/E/P Engineering - Permit / Bidding P2S - 18,588 $ 15% 21,376 $ M/E/P Engineering - Construction Administration P2S - 19,331 $ 15% 22,231 $ Construction Management - Preconstruction ACM
Design Meetings 48 185 $ 15% 10,212 $ Constructability Review / Value Engineering Review 48 185 $ 15% 10,212 $ Bid Preparation / Solicitation 80 185 $ 15% 17,020 $ Bid Analysis / Award 48 185 $ 15% 10,212 $ Construction Management - Construction ACM
Project Manager (20 hrs/wk) 540 185 $ 15% 114,885 $ Project Administrator (4 hrs/wk) 108 92 $ 15% 11,426 $ Project Executive (2 hrs/wk) 54 210 $ 15% 13,041 $ 3rd-Party Cost Estimating HLMC - 30,000 $ 15% 34,500 $ Due Diligence / Preliminary Design Matt Acton 90 192 $ 17,280 $ Matt Acton 140 192 $ 26,880 $
Kristine Luong 60 92 $ 5,520 $
Matt Acton 168 192 $ 32,256 $
Kristine Luong 72 92 $ 6,624 $
Matt Acton 218 192 $ 41,933 $
Kristine Luong 94 92 $ 8,611 $
Matt Acton 44 192 $ 8,448 $
Kristine Luong 18 92 $ 1,656 $
Matt Acton 200 192 $ 38,400 $
Kristine Luong 80 92 $ 7,360 $
Matt Acton 20 192 $ 3,840 $
Kristine Luong 12 92 $ 1,104 $
Matt Acton 60 192 $ 11,520 $
Kristine Luong 20 92 $ 1,840 $
Base Services Fee Subtotal: 636,587 $
Reimbursements: 31,829 $
Base Services Fee Total: 668,416 $
Laser Scanning + Modeling Raincross - 9,210 $ 15% 10,592 $ CASp Peer Review Services CWDG - 2,820 $ 15% 3,243 $ Historical Building Consultant (if required) TBD Allowance 35,000 $ 15% 40,250 $ Environmental Consultant (if required) LSA Associates Allowance 70,000 $ 15% 80,500 $ Low-Voltage System Design P2S - 21,000 $ 15% 24,150 $ Optional Services Fee Total: 158,735 $
Fee Estimate
Acton Architecture
Design Development
Construction Documents + Technical Specifications
Plan Check / Bidding + Award
Schematic Design
Meetings (Design Phase)
Consultants
Architectural Services
Optional Services
Close-Out
Construction Administration