Battery Storage for
North County
Nighthawk Battery Storage Project
Poway, CA
February 15, 2022
A Proven Team
Falcon
Arevon is a leading renewable energy company with roots as one of the largest renewable asset managers in the United States.
• One of the largest owner operators of renewables in California • Several utility-scale battery storage projects in operation and construction Tenaska is an independent energy company with proven expertise developing generation assets and other energy solutions to meet dynamic customer and market needs. • Developed, managed and/or operated approximately 22 gigawatts of generation. • Known for developing and operating safe, efficient and environmentally responsible generating facilities.
• Committed to working closely with local communities.

Battery Storage – California
Portfolio
3 The Importance of Battery Storage
• Battery energy storage is proven, reliable and cost-effective • It works on a daily basis: it will be charged during the day when clean solar energy is abundant and it will discharge in the evenings when the sun sets • Nighthawk will be capable of supplying ~300,000 homes for 4 hours • Energy storage is different from traditional power generation: it is beneficial to be located close to the load
4 Nighthawk Project Site Location
5 Size: 300 MW
Point Of Interconnection:

Sycamore Canyon Substation
Schedule:

Construction Timeline - 10 to 12 months
Commercial Operations – Spring 2024

Nighthawk Preliminary Site Plan
• Ten-acre pad
• Grading and drainage plans in
process
• Site will be landscaped to
minimize viewshed issues

Preliminary Visual Representations
Landscaping to be added
Transmission line preliminary
details
• Preliminary design
underway
• Pole heights:
• ~60 to 70 feet tall
• Evaluating environmental
impacts of the design/route

• Preliminary Design Effort (on-going)
• Permit Application Submittal (March 2022)
• Permit Processing (March 2022 – Q3 2022)
• Start of Battery Project Construction (Q1 2023)
• Commercial Operations Date (Q2 2024)
• Expected Facility Life (20 years)
9 Nighthawk Project
Schedule
Nighthawk Project
• Invests ~$300 million in local economy.
• Has limited traffic impacts to nearby residents or businesses during construction, and no traffic impact when operating. • Creates approximately 100 well-paying construction jobs. • Strengthens existing electrical infrastructure.
• Improves electric grid resiliency and reliability, helps avoid blackouts.
• Is operationally quiet.
• Located within an existing industrial park.
• Maximizes the use and integration of renewable energy sources.
• Provides new capacity for growing businesses and residential communities.
• Looking to partner with/invest in local organizations to promote STEM-related education.

Community Benefits
10 Peregrine Project (San Diego) – Rendering
11 • 200 MW project located in Barrio Logan
• Project received unanimous approval
from Barrio Logan Community Planning
Group November 17, 2021
Condor Project (Grand Terrace, CA) – Rendering
12 • 200 MW project in Grand Terrace
• Located adjacent to High School
• Project received unanimous approval
from Grand Terrace Planning
Commission December 2, 2021
Thank You