Cities Index.
Item 6 - Acceptance of the FY 21-22 Water Valve Replacement Project; Bid No. 22-003, with M-Rae Engineering, Inc. as Complete

Poway City Council
August 16, 2022

Document
Item 6 - Acceptance of the FY 21-22 Water Valve Replacement Project; Bid No. 22-003, with M-Rae Engineering, Inc. as Complete
Meeting
August 16, 2022
Body
Poway City Council
Original file
222 KB
Text extracted from the city's file for reading and search. Open the original on portal.laserfiche.com. That file is the official record.

August 16, 2022, Item #6
AGENDA REPORT CityofPoway
DATE:

TO;
FROM:

CONTACT:

August16,2022
Honorable Mayor and Members of the City Council
Robert Manis, Director of Development Service~
Andrea Thomas, Associate Civil Engineer 1~f</
(858) 668-4605 or [email protected]

CITY COUNCIL
SUBJECT: Acceptance of the FY 21-22 Water Valve Replacement Project; Bid No. 22-003, with M­ Rae Engineering, Inc., as Complete
summary:

On February 15, 2022 the City Council awarded the contract for the FY 21-22 Water Valve Replacement project; Bid No. 22-003, to M-Rae Engineering, Inc., in the amount of $286;030.00. This action will accept the project as complete.

Recommended Action:

It is recommended the City Council:
(1) Accept the FY 21-22 Water Valve Replacement project as complete; (2) Authorize the City Clerk to file and record the Notice of Completion; (3) Authorize the release of the retention in the amount of $13,928.41 if unencumbered, 45 days after City Council acceptance;
(4) Release the Merchants Bonding Company Bond for Material and Labor in the amount of $286,030.00 after the release of retention; and
(5) Retain the Merchants Bonding Company Bond for Faithful Performance for a period of one year.

Discussion:

The Water Valve Replacement Project is an annual program for replacement of valves serving Poway's water distribution system. This project consisted of replacement of 19 valves in various locations determined to be at the end of their useful life or currently inoperable. Two valves required the shutdown of a large water main which was discovered to be essential to meeting the elevated demand of summer water use.

There was one change order for this project which decreased the contract amount by $7,461.74. One of the valves to be replaced was identified in record drawings as 18 inches in diameter, however once the valve was excavated the actual valve was found to be 10 inches in diameter. The smaller valve is significantly less expensive than the 18-inch valve and the City sought a credit for the difference in material cost. The project required localized shutdowns of the potable water distribution system for 1 of 2
August 16, 2022, Item #6
work to be performed. These shutdowns are occasionally unable to be completed on time due to unforeseen circumstances outside of the contractor's control. The contractor experienced a delay on two shutdowns and requested compensation which was reflected in the change order. The final contract amount is $278,568.26.

Environmental Review:

The matter of acceptance of public Improvements that have been completed, which were the subject of a prior environmental determination, is not subject to the California Environmental Quality Act.

Fiscal Impact:

Sufficient funds are available in the Water Valve Replacement Project account (WT002) for the release of retention. Funds remaining In the project at year end will remain in the account to be combined with future appropriations for this annual CIP program.

Public Notification:

None.

Attachments:

None.

Reviewed/Approved By:
w:ndy aserman
Assistant City Manager
2 of2
Reviewed By:

Alan Fenstermacher
City Attorney City Manager