WATER TREATMENT PLANT

SECURITY UPGRADES
MAY 2, 2023

Replace existing analog security system with latest networked surveillance technology.
Upgrade project includes:
•Removal of old analog cameras
•Network hardware & network cabling to new camera locations •Installation of 21 networked cameras
•Server and data storage hardware
•Genetec Enterprise Security Software
Water Treatment Plant Security Upgrades

Genetec Enterprise Security Software
•Unified security platform to manage cameras, access control and alarms
•Advanced surveillance technology
•Compliant with San Diego Sheriff’s Department and Safe Poway Initiative
•Future integration with other City Facilities
Water Treatment Plant Security Upgrades

Recommended Action
It is recommended the City Council award the contract for the Water Treatment Plant Security Upgrades project to Convergint Technologies, LLC. in the amount of $223,886.32 and authorize the City Manager to execute the agreement and related documents.

Water Treatment Plant Security Upgrades
Vendor
Convergint Technologies, LLC.
Cooperative Agreement
Sourcewell Contract #030421-CTL
Total Project Cost
$223,886.32