Request Approval of the Amendment to the Agreement with IEC and
Approval of the Consultant Agreement with Butier Engineering May 16, 2023
Clearwell
Replacement Project
Treated Water
Facilities Projects
Water Infrastructure Improvement Program Components
Clearwell
Bypass Project
Clearwell Replacement Project
Replace the existing Clearwell floating cover structure with two concrete tanks Replace the original inlet, outlet and drain valves
Removal of the temporary bypass facilities and restoration of the softball field Status:
Design: Completed
Advertisement for Bids: May 11, 2023
Construction Start: Fall 2023
Construction Completion: Fall 2025
Total amount: $303,490
Summary of scope of services:
Review shop drawings, submittals and RFIs
Provide design clarifications and redesigns as-needed
Prepare Record Drawings
Provide inspection of the structural elements:
Footing
Columns
Circumferential prestressing
Wall sections
Approval of the Second Amendment to the Agreement with Infrastructure Engineering Corporation (IEC) for Engineering Services During the Bid and Construction Phases of the Clearwell Replacement Project
Total amount: $2,641,012
RFP posted: December 1, 2022
Six proposals received on February 1, 2023:
Butier Engineering
Capo Project Group
Dudek
Hoch Consulting
Kennedy/Jenks Consultants
Lee + Ro Engineers
Fee proposals: $1.9M to $3.8M
Interviews: March 22, 2023
Approval of the Consultant Agreement with Butier Engineering for Construction Management and Inspection Services of the Clearwell Replacement Project; RFP 23-010