AG EN DA REPORT City of Pow ay
April 7, 2026
Honorable Mayor and Members of the City Council
Julie Procopio, Director of Development Services q
Cassandra Seaboch, Assistant Engineer
(858) 668-4625 or [email protected]
CITY COUNCIL
Acceptance of the FY 2024-25 Americans with Disabilities Act Barrier Removal - Buckley Street Phase I with A.B. Hashmi, Inc., as Complete On November 18, 2025, the City Council awarded the FY 2024-25 Americans with Disabilities Act (ADA) Barrier Removal -Buckley Street Phase I project contract to A.B. Hashmi, Inc., Bid No. 26-004, in the amount of $85,610.00. This action will accept the project as complete.
Recommended Action:
It is recommended the City Council:
1) Accept the FY 2024-25 ADA Barrier Removal -Buckley Street Phase I project, as complete; 2) Authorize the City Clerk to file and record the Notice of Completion; 3) Authorize the release of the retention in the amount of $4,480.51 if unencumbered, 45 days after City Council acceptance;
4) Release the Old Republic Surety Company for Material and Labor in the amount of $85,610.00 after the release of retention; and
5) Retain the Old Republic Surety Company Bond for Faithful Performance for a period of one (1) year.
Discussion:
The FY 2024-25 ADA Barrier Removal -Buckley Street Phase I project is fully funded through the Community Development Block Grant (CDBG) Program. The County of San Diego manages the program and allocates funds to the City. As a requirement of this grant, the City allocates and expends funds for the approved project, which are then submitted to the County for reimbursement. The General Fund (F1000) provides temporary loans to the CDBG Fund as applicable in the interim to pay for the project.
This project consisted of ADA upgrades at the Buckley Street entrance to Community Park in the City of Poway. The project included the construction of a new ADA compliant pathway as well as ADA 1 of 2
April 7, 2026, Item #3
compliant picnic and barbeque areas along the new pathway. Enhancing ADA accessibility and connectivity at Community Park was a recommendation of the Community Park Needs Assessment.
This action accepts the FY 2024-25 ADA Barrier Removal -Buckley Street Phase I project as complete.
AB. Hashmi, Inc. has completed all work in accordance with the contract plans and specifications. A single change order, in the amount of $4,000.19, included costs for materials and labor associated with overtime work not included in the initial project scope. Overtime was deemed necessary to complete portions of work prior to the City's Winter Festival event. The final contract amount is $89,610.19.
Environmental Review:
The action of acceptance of public improvements, which was the subject of a prior environmental determination, is not considered a Project as defined under Section 15378 of the California Environmental Quality Act (CEQA) State Guidelines; therefore, pursuant to the CEQA State Guidelines Section 15378(b)(5) no environmental review is required.
Fiscal Impact:
Sufficient funds are available in the project account (PK030) for the release of retention.
Public Notification:
None.
Attachments:
None.
Reviewed/Approved By:
Assistant City Manager