CITY COUNCIL MEETING DATE: 09/15/2026
AGENDA REPORT AGENDA HEADING: Regular Business
AGENDA TITLE:

Consider updates on the Greater Portuguese Bend-Ancient Altamira Landslide Complex.

RECOMMENDED COUNCIL ACTION:
(1) Receive and file an update on the Greater Portuguese Bend-Ancient Altamira Landslide Complex (Landslide Complex) conditions, activities, and financials; (2) Receive and file an update on the status of the City’s preparation for the rainy season in relation to forecasted strong El Niño conditions; (3) Receive and file an update on the status of the grants related to the City’s response to the Landslide Complex;
(4) Adopt Resolution No. 2026-__, A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF RANCHO PALOS VERDES, CALIFORNIA, EXTENDING FOR A TERM OF 60 DAYS THE TEMPORARY PROHIBITION ON TRAVEL BY UNICYCLES, BICYCLES, MOTORCYCLES, AND OTHER ONE-, TWO- AND THREEWHEELED VEHICLES ON PALOS VERDES DRIVE SOUTH WITHIN THE LANDSLIDE COMPLEX DUE TO CONTINUED ROADWAY CONDITIONS;
(5) Adopt Resolution No. 2026-__, A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF RANCHO PALOS VERDES, CALIFORNIA, CONTINUING THE LOCAL EMERGENCY DECLARATION AS ESTABLISHED BY RESOLUTION NO. 2023- 47 ADOPTED ON OCTOBER 3, 2023 FOR AN ADDITIONAL 60 DAY PERIOD; and,
(6) Adopt Resolution No. 2026-__, A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF RANCHO PALOS VERDES, CALIFORNIA, EXTENDING THE STATE

OF LOCAL EMERGENCY WITHIN THE GEOGRAPHIC BOUNDARIES OF THE

PORTUGUESE BEND COMMUNITY ASSOCIATION, PORTUGUESE BEND

BEACH CLUB, AND SEAVIEW NEIGHBORHOODS BASED ON SUDDEN

ENERGY SHORTAGES, PLANNED DEENERGIZING EVENTS, AND INTERNET SERVICE SHUT OFFS AS ESTABLISHED BY RESOLUTION NOS. 2024-52 AND 2024-57 FOR AN ADDITIONAL 60 DAYS.

FISCAL IMPACT:

Cost to Date:

The total estimated cost for the Greater Portuguese Bend–Ancient Altamira Landslide Complex (Landslide Complex) from 2022 through June 30, 2027, is projected to reach close to $75 million ($74.8 million). Compared with prior 60-day report, this amount increased to include $1.75 million for the Abalone Cove Sewer Repair Program and $0.9 million in Tax Assessments, even though these costs are presented separately 1 in the budget. This cost is funded through multiple sources, mainly funded from the CIP Fund, General Fund, Metro Funds, ARPA, Gas Tax, Federal Grants, Supervisor Hahn’s Social Program Grant, Los Angeles County Sanitation District No. 2, and Los Angeles Flood Control District.

Fiscal Year (FY) 2025-26 Draft Year-End:

The City is currently closing its financials for FY 2025-26. In accordance with accounting requirements, prior-year transactions may continue to be recorded for up to 60 days after the fiscal year-end, through August 31. Based on draft year-end expenditures, FY 2025– 26 expenditures for the landslide projects are approximately $12.9 million, which is $4.95 million, or 28% below the revised budget of $17.9 million, as summarized in the table below. Of this amount, Staff anticipates approximately $2.3 million in carryover for landslide projects that were started but not completed by June 30, 2026.

As part of year-end closing process, Staff will continue to review and audit transactions in accordance with accounting requirements. Subsequently, CLA, the City’s independent certified public accounting firm, is expected to begin its audit in October. Any material changes will be reported to the City Council.

FY 2026-27 Budget:

Starting July 1, 2026, the FY 2026-27 Adopted Budget includes $10.6 million for landslide-related expenditures, $1.75 million for Abalone Cove Sanitary Sewer Repair Program, and $0.9 million of Tax Assessments to be paid to the Abalone Cove Landslide Abatement District (ACLAD) and Klondike Canyon Landslide Abatement District (KCLAD) for a total of $13.2 million.

BALANCE
$4.95M
CIP
Program
Project Title/ Cost Category Revised
Budget
Spent Committed Used % Balance
8307 Emergency Stabilization Measures $7.64M $5.46M $0.44M 77% $1.74M 8202 Abalone Cove Sanitary Sewer Repair $3.00M $1.78M $0.05M 61% $1.17M 8302 Palos Verdes Drive South Landslide Repair $2.50M $1.79M $0.71M 100% $0.00M 8308 Deep Dewatering Wells 1–6 – Permanent
Power
$2.10M - $0.06M 3% $2.04M
8309 Hydrology & Hydraulics Study $1.27M $0.85M $0.42M 100% $0.00M 3150 Property Tax Assessments $0.86M $0.86M - 100% $0.00M 8304 Portuguese Bend Landslide Remediation $0.53M $0.31M $0.22M 100% $0.00M Overall Budget Utilization (Spent + Committed): 72%
■■■■■■■■■■■■■■■■■■■■■■■■■■■■■□□□□□□□□□□□
FY 2025–26 Landslide Complex Project Budget Status
All Funding Sources • Project Summary as of August 31, 2026

REVISED BUDGET SPENT COMMITTED
$17.89M $11.05M $1.89M
2 The breakdown for each fund is shown below:

ORIGINATED BY: David Copp, PE, Interim Director of Public Works Vina Ramos, Director of Finance VR
Katie Lozano, Open Space and Trails Manager
REVIEWED BY: Catherine Jun, Deputy City Manager CJ
APPROVED BY: Ara Mihranian, AICP, City Manager
FY 2026-27 ADOPTED BUDGET $13.2M

CIP FUND
Program # Project / Cost Category Adopted Budget
8202 Abalone Cove Sanitary Sewer Repair $1,750,000
8304 Portuguese Bend Landslide Remediation $91,420
8307 Emergency Stabilization (Construction) $4,247,500
8307 Emergency Stabilization (Non-Construction) $1,452,500 8308 Deep Dewatering Wells 1–6
Permanent Power (Federal Match) $470,000
TOTAL – FY 2026-27 CIP FUND $8,011,420

SPECIAL REVENUE (RESTRICTED) FUNDS
Program # Project/Fund Source Adopted Budget
8302 Palos Verdes Drive South Landslide Repair
SB-1 Gas Tax (Fund 204) $1,830,000
8302 Palos Verdes Drive South Landslide Repair
Prop C (Fund 215) $825,000
8304 Portuguese Bend Landslide Remediation
Federal Grant (Fund 331) $274,265
8308 Deep Dewatering Wells 1–6 Permanent Power
Federal Grant (Fund 331) $1,410,000
TOTAL – FY 2026-27 SPECIAL REVENUE FUNDS $4,339,265

GENERAL FUND (TAX ASSESSMENTS)
Program # Assessment Adopted Budget
3150 KCLAD Property Tax Assessments $480,814
3150 ACLAD Property Tax Assessments $407,266
TOTAL – FY 2026-27 GENERAL FUND $888,080
3 ATTACHED SUPPORTING DOCUMENTS:

A. Resolution No. 2026-__ Continuing Temporary Prohibition of One-, Twoand Three-Wheeled Vehicles on Palos Verdes Drive South for 60 Days (Page A-1)
B. Resolution No. 2026-__ Continuing Local Emergency (Page B-1) C. Resolution No. 2026-__ Continuing Local De-energization Emergency (Page C-1)
D. Displacement Rate Contour Map: August 4, 2026 (Page D-1) E. Landslide GPS Survey Report: August 4, 2026 (Page E-1) F. December 16, 2025 City Council Staff Report (linked) G. November 4, 2025 City Council Staff Report (linked)
H. August 19, 2025 City Council Staff Report (linked)
I. June 16, 2026 City Council Staff Report (linked)
J. August 4, 2026 City Council Staff Report (linked)
EXECUTIVE SUMMARY:

Tonight, the City Council is being asked to receive and file an update on the Landside Complex conditions, activities, and financials. The City Council is also being asked to extend the temporary prohibition of one-, two-, and three-wheeled vehicles on Palos Verdes Drive South, continue the local emergency declaration, and continue the local deenergization emergency declaration for 60 days due to continuing landslide conditions. • Following are key rainfall updates:
o As of September 8, 2026, 15.57 inches of rain have fallen in the 2025-26 rainy season, which is about 114% of average seasonal rainfall. This total includes 0.97 inches, which recently fell on September 5-8, 2026, related to Tropical Storm Marie in the Eastern Pacific Ocean.
• Following are key landslide movement rate updates as of August 4, 2026:
o The average movement rate for all points still moving within the active landslide boundary is approximately 0.99 inches/week, an approximately 9.8% decrease since July 6, 2026 and 25.3% decrease for the approximate three-month period since May 5, 2026. This is the first time since October 2023 that the average horizontal movement velocity of all actively moving GPS monitoring points within the landslide has dropped below 1 inch per week.
o The Landslide Complex is moving about 49% slower than it was about one year ago (August 5, 2025), despite an above-average rainy season. o The Abalone Cove Landslide (ACL) decelerated an average of about 7.7% since July 6, 2026 to an average rate of movement of approximately 1.29 inches/week. o The Portuguese Bend Landslide (PBL) decelerated an average of about 13.9% since July 6, 2026 to an average rate of movement of approximately 0.81 inches/week.
4 o The Altamira Landslide located above or outside the historical ACL and PBL boundaries decelerated an average of about 7.1% since July 6, 2026, to an average rate of movement of approximately 1.22 inches/week. o The Klondike Canyon Landslide (KCL) generally continues to show no measurable horizontal or vertical movement.
• Following are key dewatering program updates:
o The City originally drilled 11 Deep Dewatering Wells (DDWS) in 2024, two of which have been permanently removed from service. The 9 remaining DDWs pumped approximately 17.6 million gallons in July 2026 and 18.7 million gallons in August 2026. As of early September 2026, 6 of the 9 remaining DDWs are operational.

The remaining 3 DDWs have all sheared and are offline pending redrilling. The first redrill is underway. The two remaining redrills will follow in sequence immediately afterward.
• The Abalone Cove Landslide Abatement District (ACLAD) currently has 14 operational wells (a combination of original wells and new DDWs). Approximately

5.7 million gallons of water were pumped in July 2026 and 5.1 million gallons in August 2026.
• The Klondike Canyon Landslide Abatement District (KCLAD) currently has 3 operational wells. Approximately 5.7 million gallons of water were pumped in July 2026 and 5.1 million gallons in August 2026.
• Following are key winterization program updates:
• The City began implementing its FY 2026-27 winterization program on August 20, 2026. Winterization measures include securing canyon liners, replacing sandbags, filling fissures, and drainage improvements (sump pumps, etc.) in areas prone to flooding such as along Palos Verdes Drive South. All work will be completed by October 15, 2026.
• ACLAD began their FY 2026-27 winterization program in August 2026. Measures include drainage improvements for upper Narcissa Drive at Ginger Root Lane, Narcissa Drive at lower Ginger Root Lane, and at the Narcissa Drive curve; and repair of the Kelvin Canyon culvert. All work will be completed by October 15, 2026. • KCLAD began their FY 2026-27 winterization program in August 2026. Measures include replacement of the 48-inch storm drain under Palos Verdes Drive South which was damaged during the 2023-24 storm season. All work will be completed by October 15, 2026.
• Palos Verdes Drive South (PVDS) historical rates of movement at six nearby survey points within the landslide area were compared to current rates of movement.

Although current rates are well below the peak movement rates of July 2024, they are an average of over four times greater than rates before major acceleration (generally considered to be before October 2022).
• Following are key financial updates:
o FY 2026–27 Adopted Budget includes $13.2 million for landslide-related costs, consisting of $10.6 million for landslide expenditures, $1.75 million for the Abalone Cove Sanitary Sewer Repair Program, and $0.9 million for ACLAD and KCLAD tax assessments.
5 o As of August 31, 2026, FY 2026-27 expenditures and commitments totaled approximately $4.7 million, or 35% of the $13.2 million budget. o As of August 31, 2026, preliminary FY 2025-26 year-end expenditures are $12.9 million, which is approximately $4.95 or 28% less than budget of $17.9 million. Of this amount, Staff anticipates approximately $2.3 million in carryover for landslide projects that were started but not completed by June 30, 2026. o The City fully disbursed $3.5 million in loans to ACLAD and KCLAD. Repayment begins in December 2026 under 12-year terms at 2.5% interest. o As of August 31, 2026, ACLAD had fully expended its $1.6 million loan, while KCLAD had spent approximately $1.5 million, or 78%, of its $1.9 million loan. o Payments to the City of $156,954 from ACLAD and $186,932 from KCLAD are scheduled for December 2026. These loan payments are an important revenue source for the CIP Fund as its available balance continues to decline and helps fund ongoing capital and maintenance projects throughout the City that have not been able to be completed due primarily to funding limitations. • Following is a summary of grants related to the Landslide Complex:
o The City is pursuing 8 grants for the voluntary buyout program and mitigation projects in the Landslide Complex, totaling $136,244,490 with a required nonfederal match of $36,900,079 (total grant project amount of $173,144,569). o At this time, the City does not have funds in its budget nor reserves for all the match funds.
o CalOES and FEMA have indicated a willingness to work with the City to identify options on how the matching funds can be reached without reducing the budget for each project.
o The City intends to continue to pursue these grants with the understanding that funds will not be accepted until the City Council formally accepts the terms and funds of each grant at a future meeting.

BACKGROUND:

The Greater Portuguese Bend Landslide Complex, sometimes called the Ancient Altamira Landslide Complex (Landslide Complex), encompasses four historically active landslide areas in the City: the Portuguese Bend Landslide (PBL), the Abalone Cove Landslide (ACL), the Klondike Canyon Landslide (KCL), and the Beach Club Landslide (BCL) and includes areas uphill from the PBL and ACL, within the Landslide Complex as mapped by various agencies.

On October 3, 2023, the City Council conducted a discussion regarding the conditions of the Landslide Complex. After considering information presented that evening, including public testimony, the City Council unanimously adopted Resolution No. 2023-47 declaring the existence of a local emergency within the geographic boundaries of the Landslide Complex and adopted Urgency Ordinance No. 674U to establish a 45-day moratorium on the acceptance or processing of applications, issuance of permits, and construction of all structures within the Landslide Complex (Moratorium). The City Council has extended the local emergency on multiple occasions, and it remains in effect until November 14, unless extended again this evening.
6 On August 20, 2024, the City Council authorized the emergency installation of immediate stabilization and protection measures consisting of deep dewatering wells (DDWs) in response to exponential acceleration of the Landslide Complex as a result of historic rainfall during the 2022-23 and 2023-24 rainy seasons.

On October 1, 2024, the City Council authorized an expansion of the DDW program to the Abalone Cove area, on City-owned property. Additionally, the City Council authorized a winterization program on City-owned property in the Landslide Complex without waiving ACLAD and KCLAD responsibilities as identified in their respective Plans of Control.

On February 18, 2025, the City Council affirmed only using the $1.6 million City loan to implement ACLAD’s DDW Plan including two monitoring wells and instrumentation that would be installed, maintained, and operated by ACLAD within their jurisdictional boundaries. A sum of $100,000 was also approved to provide ACLAD with professional services (i.e. project management and geologist).

On May 6, 2025, the City Council received a summary of the status of the DDWs and winterization programs.

On September 16, 2025, the City Council modified the FY 2025-26 landslide emergency response budget for several projects/activities resulting in an overall reduction of $2,168,000, to preserve funding for future year operations and maintenance of landslide measures due to the diminishing CIP fund balance and the City’s limited ability to complete other capital projects throughout the City. Additionally, the City Council authorized the use of the City’s winterization contingency of $200,000 to pay for 50% of the cost of repairing the culvert under Palos Verdes Drive South (PVDS) and 100% of the cost of Lower Altamira Canyon winterization by ACLAD.

This report will serve as the 60-day standing report on the current conditions of the Landslide Complex, to receive a status update on the City’s preparation for the rainy season in relation to forecasted strong El Niño conditions, to receive a status update on the grants related to the City’s response to the Landslide Complex, and consideration to extend the local state of emergencies and prohibition of one-, two-, and three-wheeled vehicles along PVDS through the Landslide Complex.

DISCUSSION:

1. Greater Portuguese Bend Landslide Complex Update
The City Council is being asked to receive and file an update on the Landslide Complex conditions, activities, and financials.

Geologic Conditions
A summary of the 2022-23 and 2023-24 rainy seasons can be found in the May 7, 2024 staff report at the following link:
https://rpv.granicus.com/MetaViewer.php?view_id=5&clip_id=4522&meta_id=118930 7 A summary of the 2024-25 rainy season can be found in the May 6, 2025 staff report at the following link:
https://rpv.granicus.com/MetaViewer.php?view_id=5&clip_id=4791&meta_id=127446 For the 2025-26 rainy season, 15.57 inches of rain have fallen at Rolling Hills Fire Station 56 near the crest of the Palos Verdes Peninsula as of September 8, 2026 (This total includes 0.97 inches, which recently fell on September 5-8, 2026, related to Tropical Storm Marie in the Eastern Pacific Ocean). This represents about 114% of the annual average for the entire season. About 89% of the season total rain fell in five storm periods:

October 14-15, 2025 (1.19”), November 13-21, 2025 (5.52”), December 23-26, 2025 (3.11”), December 31-January 6, 2026 (1.78”), and February 15-21, 2026 (2.18”). The November and December 2025 storms, which occurred after the November 4, 2025 Global Positioning System (GPS) monitoring and before the January 8, 2026 GPS monitoring, had a measurable impact on the rate of landslide movement, contributing to landslide reacceleration following a prolonged period of deceleration. The landslide complex (except for the KCL which is not moving) accelerated for three months, from November through January but has been decelerating since the February 2026 monitoring readings. For comparison, a similar phenomenon was observed during the much drier 2024-25 rainy season; however, the landslide acceleration only lasted for one month and appeared to be in response to a single 9-day storm period from February 5- 14, 2025, when 3.25 inches of rain fell. The rainfall and land movement data will continue to be evaluated in an effort to understand the relationships between the timing, severity and quantity of seasonal rainfall and changes in land movement velocity. This information may provide further insights into the effectiveness of winterization measures and the impacts on land movement notwithstanding the current deep dewatering systems operated by the City, ACLAD and KCLAD.

Recent GPS survey data published by McGee Surveying Consulting for the approximately “monthly” monitoring period ending August 4, 2026 were reviewed and analyzed (Attachment E). Figure 1 presents scaled displacement rates (i.e., movement velocities), movement vectors, and contours (aka “heat maps”) of displacement rates for the August 4, 2026 monitoring period. (Attachment D)
To summarize the data depicted in Figure 1 on the following page, the dark blue area representing displacement rates of 1 to 2 inches per week, which continue to shrink in a general westerly direction, simultaneously replaced by the purple area representing displacement rates of less than 1 inch per week.
8 Figure 1: Scaled Displacement Rates for August 4, 2026 Monitoring Period Figure 2 on the following page provides contours of landslide displacement rate change from March 9, 2025 to August 4, 2026; which provides perspective on which areas of the landslide complex are decelerating the fastest within a specified period of time. [continued on next page]
9 Figure 2: March 9, 2025 to August 4, 2026 Displacement Rate Change Contour Map Table 1 below provides a summary of movement rates for each sub-slide over time, including a comparison of the pre-emergency declaration, acceleration peak, last deceleration, and current status.

Table 1: Sub-Slide Movement Rates as of July 7, 2026
Sub-Slide Oct 2022 Oct 2023* July 2024** Nov 2025 Aug 2026 Average Movement (Inches/Week)
KCL 0.06 0.33 4.34 0.0 0.0
PBL 0.17 0.91 11.02 1.16 0.81
ACL 0.13 0.72 10.25 1.82 1.29
Upper Altamira 0.08 0.52 9.17 1.74 1.22
Factor of Movement
KCL 1 5.5 72.3 0 0
PBL 1 5.4 64.8 6.8 4.7
ACL 1 5.1 72.3 13.0 10.1
Upper Altamira 1 6.5 114.6 21.8 15.1
*Month of emergency declaration
**Month of peak movement rate
For all points monitored across the entire Landslide Complex, the following are the key conclusions for the monitoring period ending August 4, 2026:
o The average movement rate for all points still moving within the active landslide boundary as of August 4, 2026 is 0.99 inches/week, a 9.8% decrease since July 7, 2026. To provide another perspective, the Landslide Complex is moving 49% 10 slower than it was one year ago (July 1, 2025) despite an above-average rainy season.
o The ACL movement, within its historical boundary, has decelerated an average of about 7.7% since July 7, 2026. The average rate of movement for these points was approximately 1.29 inches/week in the most recent monitoring period from July 7, 2026 through August 4, 2026. The ACL has decelerated about 86% since the City’s deep dewatering program commenced in mid-September 2024 (using September 4, 2024 monitoring rates as a benchmark). The ACL has also decelerated about 70% since ACLAD’s deep dewatering well program commenced in the spring of 2025 (using March 9, 2025 monitoring rates as a benchmark), despite a three-month period of acceleration from November 2025- January 2026 which was in response to atypical high early season rainfall. The fastest moving areas are the upper portion of the ACL (i.e., monitoring point AB24 within the historical Abalone Cove Landslide boundary) and the middle ACL (i.e., monitoring point AB60), both of which are moving at approximately 1.44 inches/week. As can be seen in Figure 2, despite the 3-month period when movement accelerated, the ACL continues to exhibit the highest reduction in landslide velocity between March 9, 2025 and August 4, 2026, which is a direct effect of the deep dewatering program implemented by ACLAD. o The PBL, within its historical boundary, has decelerated about 13.9% since July 7, 2026. The average rate of movement was approximately 0.81 inches/week in the most recent monitoring period from July 7, 2026 through August 4, 2026. As of November 4, 2025, the PBL movement had decelerated an average of 88.3% since the deep dewatering (DDW) program commenced in mid-September 2024; however, unusually high early-season rainfall and normal mid-season rainfall contributed to a 3-month period of acceleration from November 4, 2025 through February 3, 2026. The PBL movement deceleration relative to movement rate just prior to the DDW program implementation is now 92%. The area of the PBL within its historical boundary that is moving less than 1 inch per week is approximately 74%. Staff will continue to track and report this metric with future readings. o In the staff report for the August 4, 2026 City Council meeting, staff noted that there had been no measurable movement of the KCL since mid-October 2024. An exception to this was identified with regard to GPS Monitoring Point KC30 which is located along Yacht Harbor Drive very close to the KCL/PBL boundary. KC30 moved 0.07 ft. between the June 2, 2026 and July 7, 2026 monitoring period. This movement was slightly above instrument precision (stated as 0.04 ft. at the 95% confidence level) and also in a direction consistent with past historical movements.

The City Geologist postulated that this movement might be a manifestation of the PBL “pushing” on the KCL, a phenomenon that occurred historically prior to the major, deeper movements in 2023 and 2024. In the July 7, 2026 to August 4, 2026 monitoring period, KC30 moved horizontally 0.01 ft. on an upslope vector, which is well below instrument precision and is considered survey “noise” rather a signal of movement. It also moved 0.09 ft. vertically, which is very close to instrument precision limits for vertical movement. The City Geologist will continue evaluating 11 this area; however, an additional month of movement data is needed to assess longer-term patterns.
o Analyses of vertical survey data of the KCL concluded that no vertical movement of the GPS monuments within the KCL has occurred since the survey period ending October 8, 2024, within the instrument and monitoring method precision limits which are typically 0.10 ft. for vertical movement. o The movement rate of the Altamira Landslide Complex GPS monitoring points outside of the historical boundaries of the ACL and PBL has, on average, decelerated about 7.1% in the monitoring period from July 7, 2026 through August 4, 2026. The average rate of movement for these points was approximately 1.22 inches/week as of August 4,2026. The Altamira Landslide Complex points have decelerated an average of about 87% since the deep dewatering program commenced in mid-September 2024.
o There continues to be no measurable movement of points along the Burma Road switchbacks since December 3, 2024. Vector analysis performed on the GPS points in this area confirms that the reported data represent GPS instrument “noise” rather than actual movement.
o There continues to be no measurable movement of points along Burma Road, located just north of the mapped boundary of major landslide movement (2023- 2025) and downslope from the 2024-2025 movement occurring in Rolling Hills in the Flying Triangle Landslide and the areas of Cinchring Road and Quail Ridge Road. This lack of measurable movement continues to support the hypothesis that the Altamira Complex and the landslide(s) further north-northeast in Rolling Hills, are not directly structurally connected.
o There continues to be no measurable movement of GPS points located outside of the mapped Landslide Complex, including at Abalone Shoreline Park, in the Island View tract, at the top of Burma Road, at the west end of the former Livingston Quarry area (Forrestal), and in the Seaview Tract.

Open Space, Palos Verdes Nature Preserve, Trails, and Beach Conditions Current trail and beach closures continue to exist within the Portuguese Bend, Filiorum, and Abalone Cove Reserves. Approximately 12.5 miles of trails within these Reserves remain closed, as well as the open space area around the Archery Range, due to landslide-related damage and/or abatement work. For the same reasons, three public beaches (Abalone Cove Beach, Sacred Cove Beach, and the beach below the Archery Club) remain closed. The City Manager temporarily closed these areas in close coordination with the City Geologist, L.A. County Fire Department and Lifeguards, California Coastal Commission, and Public Safety agencies. The City continues to monitor these areas closely with managing partners and subject experts for opportunities to reopen.

At the September 16, 2025 City Council meeting, members of the Portuguese Bend Community expressed the significant detrimental impact to their community of having so 12 many trails closed adjacent to their community. They spoke of the specific impact to equestrians and voiced their need for trail access. They additionally expressed their desire to use the trails located within the 96-acre Wildlife Corridor acquired in 2022.

Detailed information on these topics was provided in the “Additional Information” section of the November 4, 2025 City Council Staff Report (Attachment G).

The City was recently awarded a $500,000 competitive grant from the L.A. County Regional Park and Open Space District to explore the design of a multiuse trail connecting the Three Sisters and Filiorum Reserves. Constructing this trail would significantly increase trails available to the Portuguese Bend equestrian community. The planning process for this trail has begun and involves coordination with the U.S. Fish and Wildlife Service and Palos Verdes Peninsula Land Conservancy, because this trail will be located in the Preserve and may have potential impacts to biological resources. Once designed, the City will seek funding opportunities to build the trail which will likely take more than two years.

Deep Dewatering Well Program Status
The DDW component of the emergency stabilization activities is complete. The August 19, 2025 City Council staff report shows the locations of the DDWs and monitoring wells (Attachment H). Table 2 on the following page provides the current DDW program statistics. Following are key observations on the current status of DDW operations:
• The City originally drilled 11 DDWS in 2024, two of which have been permanently removed from service due to low production levels. The 9 remaining DDWs pumped approximately 17.6 million gallons in July 2026 and 18.7 million gallons in August 2026. Since the start of the DDW program in September 2024, approximately 561 million gallons, or 1,719 acre-feet of water have been extracted. • As of early September 2026, 6 of the 9 remaining DDWs are operational. The remaining 3 DDWs have all sheared and are offline, pending redrilling. The first redrill is underway. The two remaining redrills will follow in sequence immediately afterward.

[continued on next page]
13 Table 2 - DDW Current Water Extraction Rates as of August 31, 2026 DDW
No.

Date
Operational
Current Approximate Water Extraction Rate
(Gallons Per Minute)
Total Water
Extraction to Date
Acre-Ft Million
Gallons
1 9/13/2024 70 (re-drilled 3/21/25, 9/25/25, redrilled 6/3/26) 230 75 2 9/17/2024 90 (re-drilled 5/29/25) 239 78
3 9/21/2024 40 (re-drilled 3/24/25) 191 62
4 9/21/2024 N/A, Decommissioned 3/27/25
131 43
4A 3/29/2025 0 (re-drilled 2/24/26), redrill in progress 5 9/25/2024 90 (re-drilled 3/26/25, 9/18/2025, and 5/23/26) 204 66 6 9/28/2024 60 (re-drilled 12/29/24, 5/23/25, and 2/26/26) 171 56 7 10/15/2024 N/A, Decommissioned 6/3/25 15 5
8 10/17/2024 0 (re-drilled 8/14/25 and 2/20/26), redrill pending 153 50 9 10/25/2024 0 Decommissioned 11/07/24
120 39
9A 11/16/2024 25 (re-drilled 12/29/24, 5/10/25, 8/22/25) 10 10/24/2024 0 (re-drilled 5/11/25), redrill pending 263 86 11 12/3/2024 N/A, Decommissioned 3/14/25 2 1
Totals 375 1,719 561
Underground water pressure measuring instruments, called vibrating wire piezometers (piezometers) were installed to assist in determining the effects of DDWs on reducing high water pressures, including locally artesian pressures, that might be contributing to accelerated landslide movement. Five monitoring wells with piezometers were installed under the deep slip plane, as well as under the shallow slip plane to measure uplift pressure on each slip plane. The locations of the piezometers can be found in the August 19, 2025 City Council Staff Report (Attachment H).

Chart 1 on the following page shows water pressures from the piezometers installed under the deep slip plane and Chart 2, on the following page, shows water pressures from the piezometers installed above the deep slip plane and below the shallower slip plane. The charts show water pressure from the time the piezometers were installed until the present time, or until they stopped functioning due to landslide shearing. Pressure on the plots has been converted to equivalent feet of water pressure. [continued on next page]
14 Chart 1: PBL Deep Slip Plane Water Pressure
Chart 2: PBL Mid-Deep Slip Plane Water Pressure
15 For those piezometers near the DDWs in the PBL (P-1, P-2, and P-3), the plots show a marked decrease in pressure immediately following the start of the DDW program (SeptOct 2024). The surviving piezometer, P-2, continued to show a relatively constant decrease to more of a somewhat current steady state pressure drop over time at different levels, which correlated to reduced surface movement in nearby GPS survey points. Then, in the July to August 2025 timeframe, there was an increase in pressure which correlated to reduced operation of DDWs for re-drilling and other maintenance.

Once the DDWs were back to regular operation, there was a continued reduction in pressure. However, from November 2025 to March 2026, there was a slight increase in pressure in both the deep and mid-deep piezometers, which may be reflective of the early season rainfall events and in combination of periodic shut down and re-drilling of DDWs in the area. Dating back to October 2025, pore pressures are on an overall steady state trend with time; however, there was a slight increase between March and June 2026 in the deep piezometer as two wells had reduced production and sheared. Now that wells are back on-line, pore pressures are continuing to decrease again on a slight gradient through Auguust 2026.

The piezometers far away from DDWs (E-2-2 and E-2-5) show slight decreases to relatively constant pressures over the last year. In general, E-2-2 and E-2- 5 do not show any marked increase in pressure through time that can be correlated to the winter rains. However, these piezometers do seem to have nearly constant or very gradual drops in pressure over time, which may indicate that the pumping wells at the toe of the slide, even though not in close proximity, do have a regional effect to prevent buildup of pressures in this portion of the landslide. The deep piezometer sensor in E-2-2 has now malfunctioned, most likely do to shearing above that level in the borehole casing.

ACLAD Update
ACLAD Dewatering Well Program Status
The following is a summary status of ACLAD’s dewatering activities for September 2026.

The locations of ACLAD dewatering wells can be found in the August 19, 2025 City Council Staff Report (Attachment H).
• ACLAD currently has 14 operational wells (a combination of original wells and new DDWs).
• Approximately 5.7 million gallons of water were pumped in July 2026 and 5.1 million gallons in August 2026.
• Groundwater elevations have dropped from an average of 85' to 148' over the past year since the DDWs were installed
• Dewatering well pumping rates and water levels are generally consistent with prior months. Well readings are uploaded to the ACLAD website at ACLAD.ca.gov ACLAD installed piezometers in the vicinity of their DDWs to collect data on the impact of the DDWs on high water pressures, including local artesian pressures, that might be contributing to accelerated landslide movement. The locations of the piezometers can be found in the August 19, 2025 City Council Staff Report (Attachment H). The piezometers 16 were installed under the deep slip plane, as well as under the shallow slip plane to measure uplift pressure on each slip plane.

The City’s consultant engineering geologists, in coordination with ACLAD, reviewed the data from the piezometers and prepared charts to show water pressure over time. Charts 3 and 4 show water pressure from the time the piezometers were installed until the present time. Pressure on the plots has been converted to equivalent feet of water pressure.

Chart 3: ACLAD Deep Slip Plane Water Pressure
[continued on next page]
17 Chart 4: ACLAD Mid-Deep Slip Plane Water Pressure
The plots for those piezometers near the DDWs in the ACL (Alta 8 and Alta 9), show a marked decrease in pressure immediately following the start of the DDW program. The direct correlation between pumping rates/volumes and pressure decrease is pronounced.

While there was a continuous decreasing trend with the initiation and continuance of pumping on nearby wells, reciprocally there was a sharp rise in water pressure measurements when nearby wells ceased operation due to maintenance issues (some of which resulted in cessation of pumping for 3 weeks or more). Sharp pressure rises are evident on the ACL plots during this time period. Alta 8 shows a continuous decrease in pressure within the deep piezometer and the mid-deep piezometer until March 2026; at which point there is a slight increase. This could be due to breaks within the casing of the piezometer creating interconnectivity of pressure, making pressure from one piezometer additive to the pressure of the next piezometer. No obvious change in pressures were noted within the last three months. Alta 9 is no longer functional as it has been sheared.

Chart 5 on the following page provides a comparison of piezometric surfaces in monitoring well Alta-8 with average movement velocities of the 12 GPS monitoring points closest to Alta-8.
• An abrupt decline in pressure for the middle piezometer in Alta-8 occurred around May 1, 2025, after DDW's 24, 26, 27 and 28 came online (with DDW-16B and 25 already online), and there was an accompanying decrease in movement velocity as of the May 1st GPS readings. Similarly, there is a strong correlation observed between the decline in pressure for the shallow piezometer, and decrease in movement velocity, particularly notable around the middle of March, 18 2025 but then significantly dropping around the beginning of July, 2025 when DDW 29 came online. DDW 29 went offline on October 10, 2025 due to a generator issue, and there is an immediate response seen, with rising pressure for both the shallow and middle piezometers in Alta 8, until the pumping was restarted on October 22, 2025, after which piezometric levels began to fall again. This is a clear indication that DDW 29 is reducing groundwater levels (expressed as pressure) in multiple aquifers that do not appear to be hydraulically connected, but are both penetrated by the monitoring well as well as the dewatering well. This has slowed the movement of the ACL and upper Altamira Landslide by about 70% since March, 2025.
o Based upon review of Chart 5, the piezometric surfaces for all three piezometers show generally declining water pressures at the commencement of the ACLAD DDW program and an accompanying significant decline in land movement rate until November 2025. After November 2025, the shallowest piezometer has shown a continuing pressure decline while the middle and middle-deep piezometers have shown varying response to the five main rainstorms of the 2025-26 season to date, including slight uptrends in pressure since March 2026 which could be related to additive pressure from one piezometer to the next due to breaking of the casing. The middle and middle-deep piezometers appear to have reached a steady state since the middle of May 2026 (i.e., no further pressure reduction). The red line on the graph also illustrates the threemonth period of movement acceleration (Nov 2025 through Jan 2026) followed by recent 6-month deceleration through August 4, 2026, relative to piezometric levels. This would appear to indicate that the current land movement is more tied to pressures from the shallow piezometer, which continue to decline.
o The City’s consultants continue to review these important data to evaluate dewatering effectiveness and pumping program refinements. [continued on next page]
19 Chart 5: Piezometric Levels in Monitoring Well Alta-8 vs. Landslide Movement Rate for 12 Closest GPS monitoring points
ACLAD Winterization Program Status
The following is a summary status of ACLAD’s winterization activities for the 2026-27 rainy season.
• Current winterization activities include:
o Regrading upper Narcissa Drive at Ginger Root Lane (completed); o Regrading Narcissa Drive at lower Ginger Root Lane to allow drainage from the upper area of the Portuguese Bend Community Association; o Construction of a berm at Narcissa Drive curve to keep water out of fissures; and
o Repairing Kelvin Canyon Culvert
• Work started in mid-August and should be completed by October 15,2026.

KCLAD Update
Following is the status of KCLAD’s activities for September 2026.

KCLAD Dewatering Well Program Status
• KCLAD currently has three operational wells.
• Approximately 10.0 million gallons of water were pumped in July 2026 and 6.0 million gallons in August 2026.
• Dewatering well pumping water levels are generally consistent with prior months.

Pumping rates are currently lower due to two wells being offline for service. The following summarizes the operational status of KCLAD wells:
20 o KCLAD Wells #3 (shallow): not operational; water depth at 52 feet. o KCLAD Well #4 (shallow): water depth at 25 feet; temporarily offline. o KCLAD Well #5: pump depth at 144 feet; water depth at 105 feet. Well currently offline; suspected clog, pump scheduled to be pulled. o KCLAD Well #6: pump depth at 154 feet; and a water depth of 123 feet.

Well currently offline; preparing for operational test. o KCLAD Well #7: pump depth at 175 feet; water depth at 140 feet; pumping rate at 151 gallons per minute.
• The locations of KCLAD dewatering wells can be found in the August 19, 2025 City Council Staff Report (Attachment H).
• Weekly well readings are uploaded to the KCLAD website at KCGHAD.org.

KCLAD Winterization Program Status
The following is a summary status of KCLAD’s winterization activities for the 2026-27 rainy season.
• Current winterization activities include the following:
o Rehabilitation of the culvert under Palos Verdes Drive South at the intersection with Klondike Canyon.
o Work started in August 2026 and should be completed by October 15, 2026.

Utility Updates
Southern California Gas Company (SoCalGas)
Following are SoCalGas updates since the December 16, 2025 staff report (Attachment F):
• There are no new updates from the last report. All homes in Seaview and PBBC that have taken the necessary steps to receive gas service may make a request to SoCalGas for restoration of service. At this time, there is no indication when gas service will be restored in the PBCA.

Southern California Edison (SCE)
Following are SCE updates since the December 16, 2025 City Council Staff Report (Attachment F):
• SCE has re-energized 84 homes (PBBC and Seaview) and 2 KCLAD meters for dewatering wells in the PBBC. There are 7 homes in the PBBC and Seaview communities that remain without power.
• In the PBBC and Seaview neighborhoods, SCE will re-energize the remaining homes upon successful completion of electrical inspection or issuance of their NEM-PTO from SCE.
• At this time, there is no indication when power will be restored in the PBCA.

However, the City Manager sent a letter in August 2026 to SCE President and Chief Executive Officer, Steven Powell, requesting to meet in person to discuss 21 the latest City-documented movement measurements in order to reconsider the threshold for reinstating power in the PBCA. One of two meetings is tentatively scheduled to occur on September 14. More information will be reported at the September 15 meeting.

Sanitary Sewer – Portuguese Bend Community Association
The City has completed a systemwide closed-circuit television (CCTV) inspection of the City-owned Abalone Cove sanitary sewer system within the PBCA. Public Works staff are currently reviewing and evaluating the inspection data. The collected CCTV data will be used to prioritize, program, and schedule repairs to the system accordingly.

Sanitary Sewer – Seaview Neighborhood
There are currently no activities related to the Seaview Sanitary sewer as there has been no detectable land movement for many months.

Sanitary Sewer – Portuguese Bend Beach Club (PBBC)
There are currently no activities to report for the privately owned PBBC sanitary sewer.

Sanitary Sewer – PVDS Trunk Lines
There are currently no activities related to the PVDS sanitary sewer trunk lines.

California Water Service (Cal Water)
Following are Cal Water updates since the December 16, 2025 City Council Staff Report (Attachment F):
• Smart Meters Program
o All Smart Meters have been installed excluding those that have opted out of the program.
o Roughly half the meters have been activated to date, with the remaining to be activated within 30 days.
o Cal Water has stated that it intends to charge customers who opt-out a onetime administrative charge of $75 to be set up in an opt-out database and a reoccurring monthly fee of $10 to have Cal Water employees come to their homes to manually read their meters.
o Residents with questions about smart meters or how to opt-out of the program can contact Cal Water at (310) 257-1400 or
[email protected].
• Infrastructure Project at Yacht Harbor Drive and Palos Verdes Drive South o Project Purpose: Enhance system redundancy and strengthen overall water distribution network reliability.
o Project Scope: Installation of approximately 410 feet of 8-inch aboveground water main. 22 o Project Schedule: Start date has not yet been established; pre-construction site walks are currently underway, with construction anticipated in Q4 2026.

Communications
There are no new Communications updates since the December 16, 2025 City Council Staff Report (Attachment F).

Financial Update
Cost of FY 2025-26 DDW and Winterization Emergency Stabilization Measures Table 3 below provides a detailed breakdown of costs relative to emergency stabilization measures implemented in FY 2025-26, including location, scope, and the associated professional services required to accomplish the work. The figures represent reconciled amounts and include all work completed through June 30, 2025 under previously appropriated budgets.

Table 3 – Summary of FY 2025-26 Emergency Stabilization Costs for FY2025-26 (rounded) Deep Dewatering Well Program
Operations, Monitoring, General Maintenance $ 372,000
Generator Rental Service $ 390,000
Generator Fueling Service $ 251,000
Re-Drilling (9 total) $ 871,000
Site Security (Fencing, Cameras and Fire Protection) $ 18,000 Total $ 1,902,000
Winterization Program
Upper Altamira Canyon $ 1,408,000
Lower Altamira Canyon $ 157,000
Portuguese Canyon $ 273,000
Klondike Canyon $ 47,000
Seaview Neighborhood $ 21,000
Kelvin Canyon $ 17,000
Total $ 1,923,000
Professional Services
Geology and Engineering Support $ 524,000
Construction Management, Project Management and
Inspection $ 306,000
Independent Cost Estimating and Cost Validation $ 67,000 Environmental Compliance Monitoring $ 604,000
Landslide Monitoring Surveying $ 239,000
FEMA Grant Application and Administration Support $ 80,000 Total $ 1,820,000
Total Expenditures – Emergency Stabilization
Measures, FY 2025-26 $ 5,645,000*
23 *As part of the FY 2025-26 year-end closing process, approximately $0.3 million of purchase orders are being reconciled and verified for budget allocation. An update will be provided in the next report.

FY 2026-27 Budget – Expenditures
Starting July 1, 2026, the FY 2026-27 Adopted Budget includes $10.6 million for landslide-related expenditures, $1.75 million for Abalone Cove Sanitary Sewer Repair Program, and $0.9 million of Tax Assessments paid to the Abalone Cove Landslide Abatement District (ACLAD) and Klondike Canyon Landslide Abatement District (KCLAD) for a total of $13.2 million.

As of August 31, 2026, the following expenditures and commitments of approximately $4.7 million or 35% of the $13.2 million budget are summarized below and on the following page in Tables 4a through 4d:

Table 4a: PB Landslide - FY 2026-27 Budget Status Summary – All Funds Table 4b: PB Landslide - FY 2026-27 Budget Status – CIP Fund [continued on next page]
35%

BALANCE
$8.58M
Overall Budget Utilization (Spent + Committed - as of August 31,2026)

ADOPTED BUDGET
$13.24M
SPENT
$1.18M

COMMITTED
$3.48M Overall Budget Utilization (Spent + Committed as of August 31, 2026) 34% Program Project / Cost Category Adopted
Budget Spent Committed Used % Balance
8202 Abalone Cove Sanitary Sewer Repair $1,750,000 $13,164 $295,376 18% $1,441,460 8304 Portuguese Bend Landslide Remediation $91,420 $0 $0 0% $91,420 8307 Emergency Stabilization (Construction) $4,247,500 $165,425 $907,149 25% $3,174,926 8307 Emergency Stabilization (Non-Construction) $1,452,500 $105,511 $1,197,439 90% $149,550 8308 Deep Dewatering Wells 1–6
Permanent Power (Federal Match) $470,000 $0 $14,303 3% $455,697 $8,011,420 $284,100 $2,414,267 34% $5,313,053
FY 2026-27 CIP Fund Budget Status
Landslide Complex Expenditures • CIP Fund 330

ADOPTED
BUDGET

SPENT COMMITTED BALANCE
TOTAL – FY 2026-27 CIP FUND
$8.01M $0.28M $2.41M $5.31M
24 Table 4c: PB Landslide - FY 2026-27 Budget Status – Special Revenue Funds Table 4d: PB Landslide - FY 2026-27 Budget Status – General Fund ACLAD/KCLAD Loans $3,527,500
On August 20, 2024, the City received signed loan agreements from ACLAD and KCLAD in the amounts of $1.6 million and $1.9 million, respectively. As of April 3, 2025, both loans have been fully disbursed, totaling $3.52 million, in accordance with the loan agreements. The loans have a 12-year term at a 2.5% interest rate, with the first payments to the City of $156,954 from ACLAD and $186,932 from KCLAD scheduled for December 2026. These payments are an important revenue source for the CIP Fund as its available balance continues to decline and help fund ongoing capital and maintenance projects.

Per the agreements, the funds will be used to stabilize land movement, including the installation of dewatering and monitoring wells, system improvements, surface drainage enhancements, grading, and infilling of fractures. Tables 5a and 5b on the following page Overall Budget Utilization (Spent + Committed as of August 31, 2026) 25% Program # Project/Fund Source Adopted
Budget
Spent Committed Used % Balance
8302 Palos Verdes Drive South Landslide Repair
SB-1 Gas Tax (Fund 204) $1,830,000 $8,414 $1,066,586 59% $755,000 8302 Palos Verdes Drive South Landslide Repair
Prop C (Fund 215) $825,000 $0 $0 0% $825,000
8304 Portuguese Bend Landslide Remediation
Federal Grant (Fund 331) $274,265 $0 $0 0% $274,265
8308 Deep Dewatering Wells 1–6 Permanent Power
Federal Grant (Fund 331) $1,410,000 $0 $0 0% $1,410,000 TOTAL – FY 2026-27 SPECIAL REVENUE FUNDS $4,339,265 $8,414 $1,066,586 25% $3,264,265 FY 2026-27 Budget Status
Landslide Complex Expenditures • Special Revenue (Restricted) Funds

ADOPTED
BUDGET
$4.34M
SPENT
$0.01M

COMMITTED
$1.07M

BALANCE
$3.26M
Overall Budget Utilization (Spent + Committed as of August 31, 2026) 100% Program Assessment
Adopted
Budget
Spent Committed Used % Balan
ce
3150 KCLAD Property Tax Assessments $480,814 $480,814 $0 100% $0 3150 ACLAD Property Tax Assessments $407,266 $407,266 $0 100% $0 TOTAL – FY 2026-27 GENERAL FUND $888,080 $888,080 $0 100% $0 FY 2026-27 Budget Status
Landslide Complex - Property Tax Assessments • General Fund

ADOPTED
BUDGET
$0.89M
SPENT
$0.89M

COMMITTED
$0M

BALANCE
$0M
25 are a summary of deposits and expenditures that were used for the loan ending July 2025.

Financial information was provided by ACLAD and KCLAD.

As of August 31, 2026, there are no new updates since the June report for ACLAD (Table 5a). ACLAD has fully expended its $1.6 million loan.

For KCLAD (Table 5b), total spent as of August 31, 2026, is approximately $1.5 million (78%) of its $1.9 million loan. All expenditures continue to be consistent with the approved loan purposes.

Table 5a: ACLAD – Summary of Deposits and Expenditures for the City Loan of $1,610,000 Table 5b: KCLAD – Summary of Deposits and Expenditures for the City Loan of $1,917,500 ACLAD
City Loan $1,610,000
Total by Category
August 31, 2026
Category of Stabilization Program Deposits Payments
ReimbursementsSpent by
Category (%)
City Loan 1,610,000 0
Surface Drainage Reimbursement (City) 0 94,500 0%
Admin: Office Supplies 156 0%
Bank Fees & Service Charges 5 0%
Power Utilities, Propane, SCE, Diesel, Generators, Parts 70,648 4% Surface Drainage 43,360 -94,500 3%
Well Drilling and Pumps 1,141,196 71%
Well Maintenance - Service & Parts 354,176 22%
Grand Total $1,610,000 1,609,541
Total Spent (%) 100%
Loan Balance $459
*The above expenses are in addition to the KCLAD's regular annual maintenance and operational costs* KCLAD
City Loan $1,917,500
Total by Category
August 31, 2026
Category of Stabilization Program Deposits Payments Spent by City Loan $1,917,500
Admin: Board Expenses $132 0%
Admin: Consulting $18,961 1%
Admin: Geology Consulting $25,698 2%
Bank Charges & Fees $159 0%
Channel Maint $265,430 18%
Extraordinary Repair $88,000 6%
Utilities - SCE, Cal Water, Generator $90,523 6%
Well Drilling Expense $102,324 7%
Well Maint - Pipeline Maint $2,000 0%
Well Maintenance - Pipeline Maint. $899,171 60%
Grand Total $1,917,500 $1,492,399
Total Spent (%) 78%
Loan Balance $425,101
*The above expenses are in addition to the KCLAD's regular annual maintenance and operational costs*
26 2. City’s preparation for the rainy season in relation to forecasted strong El Niño conditions
City Emergency Winterization Measures Status
Staff, in consultation with the project engineering geologist and City geologist, are progressing winterization measures with an approach similar to last year, and ahead of the 2026-2027 rainy season and forecasted powerful El Niño conditions. This work is being undertaken to minimize runoff from recharging the groundwater table at the most vulnerable points. An update of ongoing and completed City-led winterization work is described in Table No. 6 below, with new improvements noted in bold when compared to what was completed last rainy season.

Table 6: Status of FY2026-27 City Emergency Winterization Measures Winterization
Site Description
Upper Altamira
Canyon
Fill new fissures and localized depressions, clear rockfall and debris from existing culvert pipe inlet and outlet, install bollards and grizzly at culvert inlet, replace section of liner at culvert inlet, add straw waddles on hillside for erosion control, track walk surface, construct west wing wall for rock slope protection, install boulders for speed dissipator at culvert outlet, reset/replace/repair liner and sandbags in the area as necessary.

Anticipated Completion: Early October
Seaview Graben
Re-flatten and weld existing liner, clean debris and around sump pumps, restore Chevron, clean and adjust catch basin, replace/reset liner and sandbags as necessary.

Anticipated Completion: September 11, 2026
Klondike Canyon
(COMPLETE)
Flatten and reset liner, clean, grub, upsize PVC outlet pipe and add screens, raise sandbags at the bottom of the system, weld existing sheeting 80-ft linear feet from the bottom and replace sandbags as necessary.

Kelvin Canyon
Clear debris and interfering vegetation, flatten existing sheet liner, clean pipe inlet, and replace sandbags as necessary.

Anticipated Completion: September 11, 2026
Portuguese
Canyon
Perform minor adjustments to canyon grading near existing outlet pipe. Adjust outlet pipe to ensure positive drainage.

Anticipated Completion: Early October
Staff are mobilizing a contractor to install additional passive drainage measures for floodprone areas along Palos Verdes Drive South within the Landslide Complex. The work is anticipated to be completed by early October.
27 Status of City’s Preparations for the Rainy Season
The National Oceanic and Atmospheric Administration (NOAA) forecasts a greater than 90% chance that the ongoing El Niño conditions will grow into a very strong “super” event during the fall and winter of 2026-27. Staff have proactively responded by implementing protective measures across the landslide. The following details the scope of these protective measures, all of which are scheduled to be completed by or before the end of September 2026:
• Winterization Measures
o Staff mobilized contractors several weeks earlier than the two previous fiscal years to carry out maintenance and improvements to previously winterized areas.
o Sections of pond liner systems are being welded together at the most critical areas to withstand land movement, rockfall, windy conditions, and further reduce permeability when conveying surface water.
o Additional debris and erosion protection measures are being implemented at winterized canyons.
• Deep Dewatering Wells
o Electrical cabinets and appurtenant equipment serving the DDWs that are located close to the coastline will be elevated where possible to withstand elevated swell conditions.
o Enclosures will be installed over wells to withstand elevated rainfall and surf conditions.
o Access to the DDWs will be improved to provide adequate access for operations, monitoring, maintenance and drilling crews. • Palos Verdes Drive South (PVDS)
o Additional passive drainage measures are being developed and installed to reduce the city’s reliance on pumping operations to minimize necessary road closures
o Staff have standardized last year’s storm monitoring and response program, including lines of communication, assignment of staffing (management and on-site crews), traffic control, and public notification protocols.
o Measures will be implemented (i.e. reinforced chains, surveillance cameras, etc.) to harden generators used to power sump pumps along PVDS.

3. Landslide Complex Grants Update
The City Council is being asked to receive and file an update on the status of the grants related to the City’s response to the Landslide Complex. 28 A detailed report on the status of the Landslide Complex Grants Update was provided as part of the June 16, 2026 staff report (Attachment I). Table 7 below provides a summary of the status of the grants currently being pursued (does not include Round No. 3 of the Voluntary Buyout Program that is pending):

Table 7 – Summary of Landslide Complex Federal Grants
Program Project Scope Estimated Total
Cost Grant Amount Match Amount Status
BRIC 2022
KCL Remediation
& ACL
Remediation:

Altamira Canyon
to PBL Boundary
$34,915,147 $23,329,850 $11,585,297
Awarded:

Pending ReScope Approval
LPDM 2023 DDW1-6
Permanent Power $2,586,085 $1,939,564 $646,521 Congressionally Earmarked HMGP
Buyout 1 Voluntary Buyouts $42,000,000 $42,000,000 Seller Requirement Under FEMA
Review
HMGP
Buyout 2 Voluntary Buyouts $10,145,417 $10,145,417 Seller Requirement Under FEMA
Review
HMGP
2025 PBL Remediation $48,719,185 $36,539,371 $12,179,814 Waitlisted BRIC 2025
ACL Remediation:

West of Altamira
Canyon
$31,725,017 $20,000,000 $11,725,017 Submitted to
FEMA

CDS PDM
ACLAD
Design of BRIC
2022 $1,526,859 $1,145,144 $381,715 Congressionally Earmarked

CDS PDM
KCLAD
Design of BRIC
2022 $1,526,859 $1,145,144 $381,715 Congressionally Earmarked Total $173,144,569 $136,244,490 $36,900,079

4. Bicycle, Motorcycle, Unicycle and Other Similar Wheeled Vehicle Prohibition The City Council is being asked to extend the existing resolution prohibiting one-, twoand three-wheeled vehicles on PVDS for an additional 60 days (Attachment A).

PVDS within the Landslide Complex has experienced ongoing and significant land subsidence and surface deformation since the acceleration of landslide movement, resulting in persistent and severe bumps, dips, elevation changes, cracking, and uneven patch transitions. Despite repeated maintenance efforts, roadway conditions remain unstable and continue to evolve, indicating that the underlying geotechnical movement is ongoing and is anticipated to persist for the near term. 29 These conditions exceed what motorcyclists, bicyclists, unicyclists, scooters, e-bikes and the like; traveling at lawful speeds can reasonably anticipate and/or navigate. Of particular concern is the disproportionate safety risk posed to these modes of transportation, which have limited tolerance for sudden grade changes, narrow contact patches, and pavement cracking. Additionally, there is reduced ability for these modes of transportation to recover from surface anomalies.

In order to quantitatively demonstrate the movement along PVDS, historical rates of movement at six survey point locations are included below. Figure 3 below shows the location of six survey points along PVDS between Peppertree Drive and the eastern edge of the Landslide Complex. Table 8 below shows a comparison of historic movement rates for these six survey points as reported by City consultants.

Figure 3 – Location of Selected PVDS Survey Points
Table 8 - Historical Survey Point Monthly Movement Rates (inches / week) Survey Point Oct 2022 Oct 2023* July 2024** August 2026 Current Rate
/ Oct 2022
Rate
PB06 0.14 0.78 9.42 0.76 5.42x
PB07 0.17 0.89 10.91 0.80 4.71x
PB08 0.14 0.83 10.00 0.76 5.42x
PB09 0.14 0.80 9.06 0.69 4.92x
PB12 0.22 1.08 12.10 0.75 3.40x
PB13 0.17 0.89 8.95 0.32 1.88x
Average 0.16 0.88 10.07 0.68 4.25x
*Month of emergency declaration
**Month of peak movement rate
30 The monthly movement rates in Table 8 show that current rates are well below the peak movement rates of July 2024; however, the rates are an average of over four times greater than the rates before major acceleration (generally considered to be before October 2022).

Based on professional engineering judgment of City staff, the PVDS roadway segment within the Landslide Complex is best characterized as continuing to deform and is not yet stable. In this condition, even in the absence of documented crashes, it is advised that these modes of transportation continue to be precluded from accessing designated portions of PVDS. The lack of stability also limits the effectiveness of short-term repairs.

The City Council has extended the local prohibition on multiple occasions within the 60- day window and it remains in effect until October 3, 2026, unless extended again this evening. At this time, the City Council is being asked to extend the local emergency declaration an additional 60 days through November 14, 2026, which does not require a public hearing. If extended this evening, the Council would consider renewing the local emergency declaration again during the next landslide update on November 4, 2026.

5. Extension of the Local Emergency Declaration
The City Council is being asked to adopt the attached resolution thereby extending the Declaration of Local Emergency by 60 days (Attachment B).

On October 3, 2023, the City Council adopted Resolution No. 2023-47 declaring a local emergency. The emergency declaration is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance.

The City Council has extended the local emergency on multiple occasions within the 60- day window, and it remains in effect until October 3, 2026, unless extended again this evening. At this time, the City Council is being asked to extend the local emergency declaration an additional 60 days through November 14, 2026, which does not require a public hearing. If extended this evening, the Council would consider renewing the local emergency declaration again during the next landslide update on November 4, 2026.

6. Extension of the Local Emergency Declaration for Utility Shutoffs The City Council is being asked to adopt the attached resolution thereby extending the Declaration of Local Emergency due to a severe and sudden energy shortage by 60 days (Attachment C).

On August 6, 2024, the City Council adopted Resolution No. 2024-52 declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off natural gas service to approximately 135 homes in the PBCA due to safety concerns. 31 On September 3, 2024, the City Council adopted Resolution No. 2024-57, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned de-energization events, and internet shut-offs in the PBCA, Seaview, and PBBC neighborhoods. The emergency declaration is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency because of a severe energy shortage has been abated or mitigated to insignificance.

The City Council has extended the local emergency on multiple occasions within the 60- day window, and it remains in effect until October 3, 2026, unless extended again this evening. At this time, the City Council is being asked to extend the local emergency declaration an additional 60 days through November 14, 2026, which does not require a public hearing. If extended this evening, the Council would consider renewing the local emergency declaration again during the next landslide update on November 4, 2026.

ADDITIONAL INFORMATION:

Continuing the Emergency Work and Emergency Contract
As a separate item on tonight’s agenda, the City Council is being provided with an update on the Portuguese Bend Landslide Emergency construction contracting and being asked to reconfirm the need to continue the emergency work. This is a recurring agenda matter and requires a 4/5th vote.

Hydrology & Hydraulics Study Update
On October 13, 2025, the City’s consultant, Geosyntec Consultants, Inc. (Geosyntec), started work on a comprehensive hydrology and hydraulics study of the Landslide Complex.

The general scope of the study is the following:
• Develop a Hydrology and Hydraulics (H&H) model for the entire Landslide Complex watershed (including the City of Rolling Hills) that incorporates storm patterns from the last ten years, with future rainfall data collection to field validate the model.
• Prepare planning level concepts for alternatives to reduce stormwater infiltration into the Landslide Complex including schematic layouts, cost opinions, real estate needs, utility impacts, and permit requirements.
• Conduct a subsurface conditions study of the PBL to characterize primary groundwater flow paths and geologic conduits.

Geosyntec has completed a draft preliminary watershed demarcation, including assessing contributing areas upstream of the Landslide Complex, and processing historical rainfall data for inclusion in the study model. Draft concept plans for alternatives 32 to reduce stormwater infiltration have been prepared and are undergoing quality control review. Subsurface data collection is complete, and the data is being synthesized into exhibits displaying sub-surface features.

A draft of the Hydrology and Hydraulics Study is anticipated to be completed by late fall, followed by its presentation by Staff to the City Council.

Disaster Cost Recovery Applications Update (FEMA and CalOES) Obligated Funds from FEMA ($574,335 as of January 2026):

In July 2025, FEMA informed staff that the reimbursement request for protective measures and debris removal, totaling approximately $596,000, has been approved and forwarded to CalOES to initiate the funding process. Staff continued to coordinate with both FEMA and CalOES to expedite the payments. Subsequently on October 10, 2025, FEMA notified the City that approximately $574,400 has been obligated and forwarded to CalOES for the reimbursement process.

On January 5, 2026, CalOES sent the City a Notification of Obligation and Payment for Public Assistance and CDAA Grants Program FEMA-4769. On January 26, 2026, the City received the first payment of $447,044, as shown below and the amount of $574,400 has been appropriated by the City Council on February 3, 2026. Staff continue to work with CalOES to receive reimbursement for the remaining balance of the grant.

A summary of obligated funds from FEMA is provided in Table 9 on the following page. [continued on next page]
33 Table 9 - Obligated Funds from FEMA – Public Assistance from Winter Storms (Jan. 31, 2024 - Feb. 9, 2024)
Projects Denied from FEMA ($37,775,258 as of January 2026) As previously noted in the prior reports, in response to the declared federal disaster for the winter storms that occurred between January 31 and February 9, 2024, and the Governor’s state of emergency for the indefinite de-energization of power, the City tabulated the costs it incurred through September 12, 2024 for reimbursement consideration by FEMA and CalOES, which total $61.4 million. Of this amount, $39.4 million is public assistance (City) and $22 million of individual assistance (residents).

According to FEMA and CalOES, natural disaster recovery funds will not be provided for landslide remediation efforts because it is considered “pre-existing.” Out of the $39.4 million application for public assistance (City), Staff is projecting only approximately $1.5 million in potential disaster recovery funds from the Winter Storm and Energy Shutoff. If deemed eligible, the reimbursement process could take anywhere from one to three years before the City receives the funds.

In January 2025, the City received seven denial letters from FEMA, followed by an additional denial letter on February 25, 2025, for a total of $37.9 million. For the $22 million individual assistance (IA) application that the City submitted on behalf of the residents, the City has been notified that these funds will not become available.

On March 17, 2025, pursuant to the Stafford Act and Code of Federal Regulations, the City filed appeals of the first seven denial letters, and on April 25, 2025, the City filed a remaining eighth appeal letter. The appeals are heard by FEMA’s District 9 Administrator, Robert Fenton, and his decision is then appealable to FEMA’s Headquarters in Washington D.C. AGENCY COST RECOVERY TYPE CATEGORY DESCRIPTION REQUESTED AMOUNT

APPROVED AMOUNT
(75% FEDERAL SHARE) PAYMENT STATUS
FEMA
Public Assistance (City)
#753367
(Damage #1386237)
Category B -
Emergency
Protective Measures
Emergency protective measures - tarps,
security by means of signage indicating
flooded and closed streets, flood fighting
through emergency pumping and
sandbagging, emergency Repairs of
damaged roofs and broken pipes, and mold remediation. Amount approved is is 75% of $465,902 minus insurance
reduction of $24K.
$465,902 $330,911 Received payment of
$330,911 on 1/26/26
FEMA
Public Assistance (City)
#750192
(Damage # 1380157)
Category A -
Debris Removal
The debris included vegetative, mud and
dirt debris, in storm drains and on
improved public property and public
rights-of way, throughout the City of
Rancho Palos Verdes.
$148,619 $111,464 Received payment of
$111,464 on 1/26/26
FEMA
(partially
approved for
$102,157.16)
Public Assistance (City)
#754844
(Damage # 1385919)
Category C- Road
and Bridges
Facility 4 (intersection of Rue De La Fleur
and Rue De La Pierre) is eligible for
$102,157.16 and demonstrated the
claimed work is a result of the declared
incident.
$136,210 $102,157
FEMA Management Costs
Category 2 - Management
Costs
Approved Administration Costs (5%) $29,803
Received partial of
$4,668.74 payment on
1/26/26

TOTAL COST RECOVERY -

APPROVED
$750,730 $574,335 $447,044
34 Projects Denied from FEMA ($37,775,258 as of January 2026) On October 10, 2025 (dated October 3, 2025), the City received a response to the appeal letters from FEMA Regional Administrator Robert Fenton, denying the City’s appeals for $37.77 million. The denial was based on the following determinations:
• Applicant did not demonstrate the claimed work required as a result of the declared disaster.
• Due to pre-existing instability, permanent repairs are not eligible. • Applicant did not demonstrate there was an immediate threat that required emergency protective measures.
• Several facilities are ineligible for public assistance funding. • Applicant did not demonstrate the claimed work required as a result of the declared disaster.
• Due to pre-existing instability, permanent repairs are not eligible. • Facility 1 (PVDS between Schooner Dr and Seacove Dr), Facilities 2 and 3 (two locations on Hawthorne Blvd.) are under the authority of another Federal agency.

On December 1, 2025, the City filed an appeal of District No. 9 Administrator Mr. Robert Fenton’s denial to FEMA Headquarters. A copy of the appeal is available on the City website at the following link:
https://www.rpvca.gov/DocumentCenter/View/24009/December-1-2025-FEMA-AppealLetter-PDF On January 16, 2026, Cal OES responded to the City’s appeal letters by forwarding a recommendation to FEMA indicating that it does not support the City’s appeal, following its review and analysis under applicable laws and regulations. FEMA has 120 days to render a final decision (with no direct consequences if more time is taken).

Table 10 on the following page summarizes the project denied from FEMA associated with the Winter Storms between January 31, 2024 and February 9, 2024. [continued on next page]
35 Table 10 Projects Denied from FEMA – Public Assistance from Winter Storms (Jan. 31, 2024 - Feb. 9, 2024)
AGENCY

COST RECOVERY

TYPE CATEGORY
DESCRIPTION DENIAL REASON FROM FEMA
Dated January 17 & 24, 2025

DENIAL REASON FROM FEMA
Dated October 3, 2025 for the City's
First Appeal submitted on April 25,
2025

REQUESTED
AMOUNT
FEMA
Public Assistance
(City)
#754845
Category D - Water Control
Facilities
Lanslide -
Drainage
(1) Damage not directly caused
by the severe winter storms;
(2) Facilities were unstable
based on pre-disaster evidence.
(1) Applicant did not demonstrate
the claimed work was required as a
result of the declared disaster;
(2) Due to pre-existing instability,
permanent repairs are not eligible;
(3) Applicant did not demonstrate
there was an immediate threat that
required emergency protective measures; and
(4) Several facilities are ineligible for
public assistance funding.
$200,000
FEMA
Public Assistance
(City)
#754846
Category F -
Utilities
Landslide
Utilities
(1) Damage not directly caused
by the severe winter storms;
(2) Facilities were unstable
based on pre-disaster evidence.
same as above $3,000,000
FEMA
Public Assistance
(City)
#753361
Category B -
Emergency
Protective Measures
PVDS
Temporary
Civil
Repairs
(1) Damage not directly caused
by the severe winter storms;
(2) Roads ineligible because
another Federal Agency is
legally responsible for the
repairs and maintenance of the
roads;
(3) Emergency work claimed is
due to an existing unstable
landslide.
same as above $5,375,000
FEMA
Public Assistance
(City)
#753364
Category B -
Emergency
Protective Measures
PB
Landslide
Stabilizati
on and Monitorin
g
(1) Work claimed is not
required as a result of the
declared disaster;
(2) Facility (slopes, canyons,
hilldsides) is an ineligible
unimproved natural feature;
(3) Existing unstable landslide.
same as above $9,000,000
FEMA
Public Assistance
(City)
#754843
Category C -
Utilities
Landslide
Roads
(1) Work claimed is not
required as a result of the
declared disaster;
(2) Facility were unstable based
on pre-disaster evidence.
same as above $11,635,000
FEMA
Public Assistance
(City)
#754842
Category G -
Parks,
Recreational
Facilities, and
Other Items
Damages
at
Portugues
e Bend
Trails,
(1) Work claimed is not
required as a result of the
declared disaster;
(2) Facility were unstable based
on pre-disaster evidence.
same as above $3,231,000
FEMA
Public Assistance
(City)
#730185
Category G -
Parks,
Recreational
Facilities, and
Other Items
Peppertre
e, Burma
Road X
Rim Trails
(1) Work claimed is not
required as a result of the
declared disaster;
(2) Facility were unstable based
on pre-disaster evidence.
(1) Applicant did not demonstrate
the claimed work was required as a
result of the declared disaster; and
(2) Due to pre-existing instability,
permanent repairs are not eligible.
$11,415
FEMA
(partially
approved for
$102,157.16)
Public Assistance
(City)
#754844
Category C- Road
and Bridges
Palos
Verde
Drive
South -
Schooner
and
Seacove
(1) Work claimed has not been
demonstrated that the repair is
a result of the declared
disaster; (2) Roads ineligible
because another Federal
Agency is legally responsible for
the repairs and maintenance of
the roads;
(1) Facility 1 (PVDS between
Schooner Dr and Seacove Dr),
Facilities 2 & 3 (two locations on
Hawthorne Blvd.) are under the
authority of another Federal agency;
and
(2) Facility 4 (intersection of Rue De
La Fleur and Rue De La Pierre) is
eligible for $102,157.16 and
demonstrated the claimed work is a
result of the declared incident.
*Original request is for $5,425,000
and only partially approved for
$102,157.16.
$5,322,843
TOTAL COST RECOVERY - DENIED $37,775,258
36 It should be noted that both ACLAD and KCLAD filed appeals as well for the denials they received for disaster recovery assistance. Both ACLAD and KCLAD received similar notifications that their appeals were denied by District No. 9 Administrator Mr. Bob Fenton (who is currently serving as the Interim FEMA Administrator). ACLAD and KCLAD collaborated with the City and filed a second and final appeal to FEMA Headquarters which are pending review similar to the City.

CONCLUSION:

The City’s dewatering well program is currently operating nine dewatering wells and pumped at a rate of approximately 17.6 million gallons in July 2026 and 18.7 million gallons in August 2026. ACLAD has 14 operational wells and pumped at a rate of 5.7 million gallons of water in July 2026 and 5.1 million gallons in August 2026. KCLAD has three operational wells and pumped at a rate of approximately 10 million gallons of water in July 2026 and 6 million gallons in June 2026.

The City’s winterization program is currently underway and implements improvements beyond what was accomplished in FY 2025-26. Winterization measures include securing canyon liners, replacing sandbags, filling fissures, and drainage improvements in areas prone to flooding such as along Palos Verdes Drive South. ACLAD is also implementing its winterization program including drainage measures at multiple points on Narcissa Drive and repairs to the culvert in the Kelvin Canyon area. KCLAD’s winterization measures are focused on repairs to the culvert under Palos Verdes Drive South at its intersection with Klondike Canyon. All winterization work done by the City, ACLAD, and KCLAD will be completed by October 15, 2026.

As of August 4, 2026, the Landslide Complex continues to decelerate following the threemonth period of acceleration from November 2025 to January 2026 to an average rate of movement of 0.99 inches per week, which is a decrease of 9.8% since July 6, 2026. More specifically, the ACL decelerated an average of about 7.7% to an average rate of approximately 1.29 inches/week; the PBL decelerated an average of about 13.9% to an average rate of approximately 0.81 inches/week; and the KCL generally continues to show no measurable movement.

The rates of movement at six survey points near PVDS within the landslide are an average of over four times greater than rates before October 2022.

As of August 31, 2026, preliminary FY 2025–26 year-end landslide expenditures totaled approximately $12.9 million, or $4.95 million (28%) below the $17.9 million budget, before carryover. For FY 2026–27, the Adopted Budget includes $13.2 million for landsliderelated costs, of which approximately $4.7 million, or 35%, was spent or committed.

Staff recommend extending the local state of emergency, the de-energization emergency, and the temporary prohibition of one-, two- and three-wheeled vehicles along PVDS through the Landslide Complex.
37 ALTERNATIVES:

In addition to Staff recommendation, the following alternative action is available for the City Council’s consideration:

1. Take no action and receive and file this report.

2. Do not extend the temporary prohibition of one-, two- or three-wheeled vehicles on PVDS and allow one-, two- and three-wheeled to begin using PVDS again.

3. Do not adopt one, or both, of the resolutions continuing the local emergency declarations.
38 01203.0023 2172377.1
RESOLUTION NO. 2026-__

A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF RANCHO PALOS VERDES, EXTENDING
FOR A TERM OF SIXTY (60) DAYS THE

TEMPORARY PROHIBITION ON TRAVEL BY

UNICYCLES, BICYCLES, MOTORCYCLES, AND

OTHER ONE-, TWO- OR THREE-WHEELED

VEHICLES ON PALOS VERDES DRIVE SOUTH

WITHIN THE LANDSLIDE COMPLEX DUE TO

CONTINUED ROADWAY CONDITIONS
WHEREAS, the Greater Portuguese Bend Landslide Complex (the Landslide Complex) encompasses four historically active landslide areas in the City: the Portuguese Bend Landslide (“PBL”), the Abalone Cove Landslide (“ACL”), the Klondike Canyon Landslide (“KCL”), and the Beach Club Landslide (“BCL”). It also includes the Flying Triangle Landslide (“FTL”) in the City of Rolling Hills as mapped by various agencies (i.e., U.S. Geological Survey, California Geological Survey) and other researchers; and
WHEREAS, following the 2022-23 rainy season, the Landslide Complex’s movement has accelerated exponentially. Therefore, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-047 based on its authority pursuant to Section 8610 et seq. and Section 8630 et seq. of the Government Code, and Chapter 2.23 of the Rancho Palos Verdes Municipal Code, declaring a state of local emergency for the Landslide Complex based on the accelerated movement of the land. The declaration of emergency has been renewed as required by law and currently applies; and
WHEREAS, following the City Council’s declaration of a local emergency, the City experienced another record-setting rainy season during the winter of 2023- 24; and
WHEREAS, since the City Council’s declaration of a local emergency, the City Geologist, Mike Phipps of Cotton, Shires, and Associates, Inc. (“CSA”), has been regularly conducting field mapping throughout the Landslide Complex, observing conditions at various locations, and reviewing survey and rainfall data; and
WHEREAS, the City Geologist most recently reported to the City Council on May 7, 2024, in summary, that the Landslide Complex continues moving at unprecedented rates, predominantly in response to the two consecutive seasons of significantly above average rainfall; and
WHEREAS, the City Geologist stated that land movement continued to manifest at the ground surface in the form of landslide scarps, fissures, grabens/sinkholes, tensional cracking, shear zones and thrust features; and that due to the continued acceleration, the ground movement features have continued to enlarge, expand, widen, or grow depending on the type of feature and location, A-1
Resolution No. 2026-__

Page 2 of 4 ends

01203.0023 2172377.1
which also affects Palos Verdes Drive South (“PVDS”) as it traverses the Landslide Complex area; and
WHEREAS, the City Geologist summarized that road conditions on PVDS continue to be adversely impacted due to differential rates of land movement ranging from about 5 to 8 inches per week, at the time of the report to the City Council on May 7, 2024; and
WHEREAS, traffic signs on PVDS in the landslide area include various signs warning of the landslide conditions, with some specifically directed at bicyclists and motorcyclists. Out of an abundance of caution, Staff (through a consultant), conducted a review of signs on PVDS. As a result, additional signs were installed, including signs installed on June 1, 2024 specifically directed at bicyclists and motorcyclists; and
WHEREAS, despite the existing bicycle warning signs, Staff has been anecdotally informed of bicycle crashes, and at least one claim has been filed against the City (which was prior to the additional bicycle and motorcycle signs installed on June 1) and at least two claims for injury to persons or property have been filed with the City; and
WHEREAS, Section 8610 of the Government Code provides the local disaster council with broad powers to “develop plans for meeting any condition constituting a local emergency or state of emergency, including, but not limited to, earthquakes, natural or manmade disasters specific to that jurisdiction, or state of war emergency….”; and
WHEREAS, Rancho Palos Verdes Municipal Code Chapter 2.24 designates the City Council, the director of emergency services, the assistant director of emergency services, and the chiefs of emergency services as the City’s Disaster Council; and
WHEREAS, the director of emergency services (the city manager), “[i]n the event of the proclamation of a local emergency […], the director [of emergency services] is empowered: a. To make and issue rules and regulations on matters reasonably related to the protection of life and property as affected by such emergency….”; and
WHEREAS, the City Council finds that despite consistent and recently increased signage, riders of bicycles and motorcycles continue to use PVDS, and that the land movement is creating frequent localized deviations in the road, which can be navigated safely in cars and trucks, but that are more dangerous for one-, two-, or three-wheeled vehicles such as bicycles and motorcycles; and WHEREAS, the City Council finds that the safety of bicycle, motorcycle and other one-, two-, or three-wheeled riders is a compelling interest; and A-2
Resolution No. 2026-__

Page 3 of 4 ends

01203.0023 2172377.1
WHEREAS, the City Council finds that in order to further the City’s compelling interest in the safety of riders, it is appropriate to temporarily route bicycles, motorcycles and other similar vehicles away from the portion of PVDS within the Landslide Complex, until such time as the City may be able to slow the land movement sufficiently to reduce the frequency and severity of road deviations to minimize the risk of injury to persons or property; and WHEREAS, on June 18, 2024, the City Council duly adopted Resolution No. 2024-39 prohibiting, for a period of six (6) months, bicycles, motorcycles, and other two-wheeled vehicles from traversing PVDS with the Landslide Complex; and WHEREAS, the City Council has, since that date and at various City Council meetings, duly adopted resolutions prohibiting for specified periods set forth therein, unicycles, bicycles, motorcycles, and other one- or two-wheeled vehicles from traversing PVDS with the Landslide Complex; and
WHEREAS, on August 4, 2026, the City Council identified the safety of three-wheeled riders to be a compelling interest and further approved a motion to include three-wheeled vehicles in this prohibition.

WHEREAS, staff and the Office of the City attorney are of the opinion that conditions on PVDS have not stabilized to the point that this prohibition should be allowed to terminate and is of the further opinion the existing prohibition should be extended for an additional sixty (60) day period.

NOW, THEREFORE THE CITY COUNCIL OF THE CITY OF RANCHO

PALOS VERDES DOES HEREBY FIND, DETERMINE AND RESOLVE AS FOLLOWS:

Section 1: The above recitals are true and correct and incorporated herein by reference.

Section 2: For a period of sixty (60) calendar days from and after the date of this resolution, the portion of PVDS within the Landslide Complex shall be closed to unicycle, bicycle, motorcycle, and other one-,two-, and three-wheeled vehicle traffic.

Section 3: Updates on the rate of movement and repair of PVDS will be provided at City Council meetings where the City Council is considering extending the local state of emergency, including an assessment of the relative safety of traveling on PVDS by unicycles, bicycles, motorcycles, tricycles, autocycles, and other one-, two-, and three-wheeled vehicles through the Landslide Complex, with the purpose of lifting the prohibition as soon as possible.

Section 4: This Resolution shall be effective immediately upon adoption by the City Council upon a majority vote.

A-3
01203.0023 2172377.1
Resolution No. 2026-__

Page 4 of 4 ends

PASSED, APPROVED, AND ADOPTED at a regular meeting of the City Council of the City of Rancho Palos Verdes, California, on this 15th day of September, 2026.

Paul Seo, Mayor
ATTEST:

Teresa Takaoka, City Clerk

STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss

CITY OF RANCHO PALOS VERDES )
I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, do hereby certify that the foregoing Resolution No. 2026-__ was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on September 15, 2026
Teresa Takaoka, City Clerk
A-4
01203.0023 2172401.1
RESOLUTION NO. 2026-__

A RESOLUTION OF THE CITY COUNCIL OF THE

CITY OF RANCHO PALOS VERDES, CALIFORNIA,

CONTINUING THE LOCAL EMERGENCY

DECLARATION AS ESTABLISHED BY
RESOLUTION NO. 2023-47 ADOPTED ON
OCTOBER 3, 2023 FOR AN ADDITIONAL 60 DAY
PERIOD
WHEREAS, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-47, declaring a local state of emergency because of the alarming increase of land movement in the Greater Portuguese Bend Landslide Complex, as depicted in Resolution No. 2023-47 Exhibits “A” and “B.” Resolution No. 2023-47, and the exhibits thereto, are incorporated by reference; WHEREAS, on October 3, 2023, the City Council by a 4/5 vote also adopted Interim Urgency Ordinance No. 674U, establishing a moratorium on all construction in the Landslide Complex;
WHEREAS, on November 14, 2023, the City Council by a 4/5 vote adopted Resolution No. 2023-56, extending the state of emergency for an additional 60 days; WHEREAS, on December 19, 2023, the City Council by a 4/5 vote adopted Resolution No. 2023-61, extending the state of emergency for an additional 60 days; WHEREAS, on February 6, 2024, the City Council by a 4/5 vote adopted Resolution No. 2024-05, extending the state of emergency for an additional 60 days; WHEREAS, on March 19, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-13, extending the state of emergency for an additional 60 days; WHEREAS, on May 7, 2024, the City Council by a 4/5 vote adopted Resolution No. 2024-20, extending the state of emergency for an additional 60 days; WHEREAS, on July 2, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-44, extending the state of emergency for an additional 60 days; WHEREAS, on August 6, 2024, the City Council by a 4/5 vote adopted Resolution No. 2024-51, extending the state of emergency by an additional 60 days; WHEREAS, on October 1, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-50, extending the state of emergency by an additional 60 days; WHEREAS, on November 19, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-70, extending the state of emergency by an additional 60 days; and WHEREAS, on December 17, 2024, the City Council by a 5-0 vote adopted Resolution No. 2024-77, extending the state of emergency by an additional 60 days; and B-1
01203.0023 2172401.1
WHEREAS, on February 4, 2025, the City Council by a 4/5 vote adopted Resolution No. 2025-06, extending the state of emergency by an additional 60 days; and WHEREAS, on March 18, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-18, extending the state of emergency by an additional 60 days; and WHEREAS, on May 6, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-27, extending the state of emergency by an additional 60 days; and WHEREAS, on July 1, 2025, the City Council by a 4/5 vote adopted Resolution No. 2025-45, extending the state of emergency by an additional 60 days; and WHEREAS, on August 19, 2025, the City Council by a 4/5 vote adopted Resolution No. 2025-61, extending the state of emergency by an additional 60 days; and WHEREAS, on September 16, 2025, the City Council by a 4/5 vote adopted Resolution No. 2025-66, extending the state of emergency by an additional 60 days; and WHEREAS, on November 4, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-81, extending the state of emergency by an additional 60 days; and WHEREAS, on December 16, 2025, the City Council by a 5-0 vote adopted Resolution No. 2025-91, extending the state of emergency by an additional 60 days; and WHEREAS, on February 3, 2026, the City Council by a 5-0 vote adopted Resolution No. 2026-12, extending the state of emergency by an additional 60 days; and WHEREAS, on March 17, 2026, the City Council by a 5-0 vote adopted Resolution No. 2026-21, extending the state of emergency by an additional 60 days; and WHEREAS, on May 5, 2026, the City Council by a 5-0 vote adopted Resolution No. 2026-32, extending the state of emergency by an additional 60 days; and WHEREAS, the state of emergency is deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance; and,
WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex.

NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS

VERDES, CALIFORNIA, HEREBY FINDS, DETERMINES, AND RESOLVES AS FOLLOWS:

B-2
Resolution No. 2026-__

Page 3 of 4 ends

01203.0023 2172401.1
Section 1. Recitals. The City Council hereby determines that the above recitals are true and correct and incorporates the same as the findings of the City Council.

Section 2. Proclamation of Emergency. The City Council finds, pursuant to RPVMC Chapter 2.24 and Government Code §§ 8630 and 8680.9, there exists an actual condition of peril to the safety of persons and property exiting within the Greater Portuguese Bend Landslide, comprised of the Portuguese Bend Landslide, the Abalone Cove Landslide, and the Klondike Canyon Landslide, as depicted in Exhibits “A” and “B” of Resolution No. 2023-47, and based on the staff report and recommendations and public testimony, and hereby proclaims that a state of local emergency continues to exist throughout the same.

Section 3. Authority Granted. It is further proclaimed and ordered that during the existence of said local emergency, the powers, authority, functions and duties of the Disaster Council, Director, and the City’s emergency services organizations shall be those prescribed by State Law, City ordinances, Resolution No. 2023-47 and any other applicable resolutions, and approved plans of the City in order to mitigate the effects of the local emergency.

Section 4. Immunity Invoked. To the maximum extent permitted by law, and pursuant to Government Code § 866, the City Council hereby invokes the immunity afforded to the City of Rancho Palos Verds in adopting and implementing the declaration of local emergency within the Landslide Complex
Section 5. Duration. The local emergency shall be deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law.

Section 6. Continuing Declaration. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within Landslide Complex has been abated or mitigated to insignificance.

Section 7. Severability. If any subsection, sentence, clause, phrase, or word of this Resolution or any application of it to any person, structure, gathering, or circumstance is held to be invalid or unconstitutional by a decision of a court of competent jurisdiction, then such decision will not affect the validity of the remaining portions or applications of this Resolution.

Section 8. Effectiveness. This Resolution shall take effect immediately. A copy of the Proclamation and this Resolution shall be forwarded to the California Emergency Management Agency. The City Clerk shall certify to the passage and adoption of this resolution.

B-3
Resolution No. 2026-__

Page 4 of 4 ends

01203.0023 2172401.1
PASSED, APPROVED AND ADOPTED on this 15th day of September, 2026.

Paul Seo, Mayor
ATTEST:

Teresa Takaoka, City Clerk

STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss

CITY OF RANCHO PALOS VERDES )
I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, hereby certify that the above Resolution No. 2026-__ duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on September 15, 2026.

Teresa Takaoka, City Clerk
B-4
01203.0023 2172432.1
RESOLUTION NO. 2026-__

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

RANCHO PALOS VERDES, CALIFORNIA, EXTENDING

THE STATE OF LOCAL EMERGENCY WITHIN THE

GEOGRAPHIC BOUNDARIES OF THE PORTUGUESE

BEND COMMUNITY ASSOCIATION, PORTUGUESE BEND

BEACH CLUB, AND SEAVIEW NEIGHBORHOODS,

BASED ON SUDDEN ENERGY SHORTAGES, PLANNED

DEENERGIZING EVENTS, AND INTERNET SERVICE
SHUT OFFS AS ESTABLISHED BY RESOLUTION NOS.
2024-52 AND 2024-57 FOR AN ADDITIONAL 60 DAYS
WHEREAS, the City of Rancho Palos Verdes is home to four out of five sub-slides that comprise the Greater Portuguese Landslide Complex (“Landslide Complex”): the Portuguese Bend Landslide, Abalone Cove Landslide, Klondike Canyon Landslide, and Beach Club Landslide. The Portuguese Bend Landslide encompasses the Portuguese Bend Community Association (“PBCA”), the Seaview Neighborhood (“Seaview”), and the Portuguese Bend Beach Club (“PBBC”). The Landslide Complex has been active since the 1950s;
WHEREAS, the 2022-2023 rainy season brought exceptional amounts of rain to the region, dumping 20.9” of rain or 190% of the average annual rainfall in the region; WHEREAS, by April 26, 2024, total rainfall for the 2023-24 season (beginning Oct 1, 2023) was 23.01" or 169% of the historical 67-year average of 13.63" for this rain gauge. (All data based on Los Angeles County Department of Public Works Rainfall Gauge No. 1011B at Rolling Hills FS.);
WHEREAS, beginning in 2018, but particularly since May 2023, the land movement in the Landslide Complex has increased significantly due to increased rainfall in the last two rainy seasons, which caused the water table to rise dramatically and destabilize the landslides. The City has established, via repeated geologic studies, that a significant factor in the speed of land movement in the Landslide Complex is the amount of water in the soil; WHEREAS, on October 3, 2023, the City Council of the City of Rancho Palos Verdes adopted Resolution No. 2023-47, declaring a local state of emergency due to the alarming increase of land movement in the Landslide Complex. The state of emergency based on the land movement has been extended as required by law and is still active; WHEREAS, on August 6, 2024, the City Council by unanimous vote adopted Resolution No. 2024-52, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service to approximately 135 homes in the PBCA due to safety concerns;
WHEREAS, on September 3, 2024, the City Council by unanimous vote adopted Resolution No. 2024-57, declaring a local state of emergency because of a sudden and C-1
Resolution No. 2026-__

Page 2 of 5 ends

01203.0023 2172432.1
severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on October 1, 2024, the City Council by unanimous vote adopted Resolution No. 2024-61, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on November 19, 2024, the City Council by unanimous vote adopted Resolution No. 2024-71, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on December 17, 2024, the City Council by unanimous vote adopted Resolution No. 2024-78, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; WHEREAS, on February 4, 2025, the City Council by unanimous vote adopted Resolution No. 2025-07, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on March 18, 2025, the City Council by unanimous vote adopted Resolution No. 2025-16, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on May 6, 2025, the City Council by unanimous vote adopted Resolution No. 2025-28, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on July 1, 2025, the City Council by unanimous vote adopted Resolution No. 2025-45, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex; and
WHEREAS, on August 19, 2025, the City Council by unanimous vote adopted Resolution No. 2025-45, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and C-2
01203.0023 2172432.1
WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex; and
WHEREAS, on September 16, 2025, the City Council by unanimous vote adopted Resolution No. 2025-67, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex; and
WHEREAS, on November 4, 2025, the City Council by unanimous vote adopted Resolution No. 2025-82, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex.

WHEREAS, on February 3, 2026, the City Council by unanimous vote adopted Resolution No. 2026-13, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on March 17, 2026, the City Council by unanimous vote adopted Resolution No. 2026-22, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, on May 15, 2026, the City Council by unanimous vote adopted Resolution No. 2026-33, declaring a local state of emergency because of a sudden and severe energy shortage caused by shutting off of natural gas service, planned deenergization events, and internet shut-offs in the PBCA, Seaview, and PBBC; and WHEREAS, after consideration of all facts reasonably available the City Council now desires to extend the declaration of a state of local emergency within the Landslide Complex.

NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF RANCHO PALOS

VERDES, CALIFORNIA, HEREBY FINDS, DETERMINES, AND RESOLVES AS FOLLOWS:

Section 1. Recitals. The City Council hereby determines that the above recitals are true and correct and incorporates the same as the findings of the City Council.

Section 2. Extension of Local State of Emergency. The City Council finds, C-3
Resolution No. 2026-__

Page 4 of 5 ends

01203.0023 2172432.1
pursuant to RPVMC Chapter 2.24 and Government Code §§ 8630, 8680.9, and 8558 there exists an actual condition of peril to the safety of persons and property existing within the PBCA, Seaview, and PBBC, as established by Resolutions No. 2024-52 and 2024-57, and based on the staff report and recommendations and public testimony, and hereby proclaims that a state of local emergency continues to exist throughout the same.

Section 3. Authority Granted. It is further proclaimed and ordered that during the existence of said local emergency, the powers, authority, functions and duties of the Disaster Council, Director, and the City’s emergency services organizations shall be those prescribed by State Law, City ordinances, Resolution Nos. 2023-52 and 2024-57, and any other applicable resolutions, and approved plans of the City in order to mitigate the effects of the local emergency.

Section 4. Immunity Invoked. To the maximum extent permitted by law, and pursuant to Government Code § 866, the City Council hereby invokes the immunity afforded to the City of Rancho Palos Verds in adopting and implementing the declaration of local emergency within the Landslide Complex.

Section 5. Duration. The local emergency shall be deemed to continue to exist until its termination is proclaimed by the City Council in accordance with law. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the geographic boundaries of the Landslide Complex has been abated or mitigated to insignificance.

Section 6. Continuing Declaration. Government Code § 8630 requires the City Council to review of the need for continuing the local emergency at least once every 60 days until the City Council determines the local emergency within the PBCA has been abated or mitigated to insignificance.

Section 7. Severability. If any subsection, sentence, clause, phrase, or word of this Resolution or any application of it to any person, structure, gathering, or circumstance is held to be invalid or unconstitutional by a decision of a court of competent jurisdiction, then such decision will not affect the validity of the remaining portions or applications of this Resolution.

Section 8. CEQA. The City Council finds that this Resolution is proposed to allow the City to continue to address and mitigate an imminent threat to public health and safety and therefore is exempt from CEQA pursuant to Public Resources Code, Section 21080(b)(4) and CEQA Guidelines, Section 15269.

Section 9. Effectiveness. This Resolution shall take effect immediately. A copy of the Proclamation and this Resolution shall be forwarded to the California Office of Emergency Management. The City Clerk shall certify to the passage and adoption of this resolution.

C-4
Resolution No. 2026-__

Page 5 of 5 ends

01203.0023 2172432.1
PASSED, APPROVED AND ADOPTED on this 15th day of September, 2026.

Paul Seo, Mayor
ATTEST:

Teresa Takaoka, City Clerk

STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss

CITY OF RANCHO PALOS VERDES )
I, Teresa Takaoka, City Clerk of the City of Rancho Palos Verdes, hereby certify that the above Resolution No. 2026-__ was duly and regularly passed and adopted by the said City Council at a regular meeting thereof held on September 15, 2026.

Teresa Takaoka, City Clerk
C-5
North 0 250 500 1000 (feet) PONY TRAIL PORTUGUESE BEND LANDSLIDE FLYING TRIANGLE LANDSLIDE KLONDIKE CANYON LANDSLIDE ABALONE COVE LANDSLIDE ABALONE COVE PORTUGUESE POINT INSPIRATION POINT SACRED COVE PALOS VERDES DRIVE SOUTH BURMA ROAD EXPLANATION Limits of the Ancient Portuguese Bend Landslide Complex Limits of Historically Mapped Landslides 2023/2024 Landslide Features (based on CSA field mapping) SEAVIEW TRACT Limits of 2023-2024 Major Landslide Movement (based on CSA field mapping and bathymetry survey) LIMITS OF 2023-2024 MAJOR LANDSLIDE MOVEMENT GPS Monument Displacement Rate (July 7, 2026 to August 4, 2026) Displacement Vector Scale 1"= 8"/week Displacement Rate Table Minimum Rate (inch/week) 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 Maximum Rate (inch/week) 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 Color 10.00 11.00 11.00 12.00 1.00 2.00 12.00 13.00 0.00 1.00 APPROXIMATE BOUNDARY OF ANCIENT PORTUGUESE BEND LANDSLIDE COMPLEX BEACH CLUB LANSDSLIDE DDW-10 DDW-9ADDW-9DDW-11 DDW-8 DDW-7 DDW-5 DDW-4DDW-6 DDW-1 DDW-2 DDW-3 WW-3 MW-18 WW-12 WW-13 WW-30 WW-1 WW-6 WW-7 WW-17 WW-11WW-15 WW-21 UDW-ACLAD-1 KC-1 KC-3 KC-4KC-6 KC-5 KC-2 KC-7 KC-4A ACLAD 25 ACLAD 24 ACLAD 28 ACLAD 27 ACLAD 16 ACLAD 26 ACLAD 29 ACLAD 8 ACLAD 21ACLAD 22 1.0 1.0 1.0 1.0 1.0 1.0 1.0 KC22 0.01 KC31 0.02 KC07 0.02 RP02 0.02 CR50 0.02 AB79 0.02 CW06 0.02 AB17 0.03 KC28 0.03 AB80 0.03 KC06 0.03 KC18 0.04 KC30 0.04 RP01 0.04 KC20 0.04 KC25 0.04 KC26 0.05 FT09 0.05 KC29 0.05 AB64 0.05 KC37 0.05 KC21 0.05 FT10 0.06 FT08 0.06 KC15 0.07 KC38RP 0.07 KC05 0.07 KC34 0.07 CR59 0.07 AB78 0.07 KC35 0.07 AB76 0.08 RP03 0.09 KC17 0.09 KC36 0.09 KC16 0.09 CR57 0.09 KC23 0.09 KC39 0.10 KC14 0.10 CR56 0.10 CW05 0.10 CW08 0.11 AB77 0.11 AB01 0.11 KC19 0.12 CW01 0.12 CR53 0.14 CR60 0.20 RP05 0.03 CR51 0.16 CR58 0.20 PB26 0.29 PB13 0.32 PB79 0.44 PB29 0.49 PB76 0.50 UB02 0.57 AB50 0.57 PB09 0.69 PB12 0.75 PB67 0.75 PB08 0.76 PB06 0.76 AB85 0.78 PB77 0.80 PB07 0.80 AB16 0.84 PB78 0.89 PB21 0.89 PB20 0.89 PB27 0.90 AB67 0.90 PB69 0.94 PB70 0.95 AB73 0.96 PB55 1.03 PB59 1.04 PB72 1.07 PB75 1.09 PB18 1.10 AB84 1.11 AB51 1.13 PB54 1.14 PB04 1.15 AB65 1.15 AB04 1.16 AB62 1.16 AB68 1.19 AB63 1.22 AB81 1.25 AB83 1.26 AB66 1.26 AB21 1.27 AB53 1.28 AB75 1.29 AB58 1.36 AB13 1.39AB86 1.39 AB57 1.40 CR54 1.42 AB60 1.43 AB24 1.44 AB59 1.49 COTTON, SHIRES AND ASSOCIATES, INC. CONSULTING ENGINEERS AND GEOLOGISTS RANCHO PALOS VERDES, CALIFORNIASC6163 POS MP August 31, 2026 1"=500' FIGURE NO. PROJECT NO. DATE SCALE APPROVED BY GEO/ENG BY GPS MONITORING DISPLACEMENT RATE CONTOUR MAP (8/4/26 DATA) 1 Abalone Cove, Portuguese Bend, Klondike Canyon Hillshade basemap produced from publicly available LiDAR: "2015 - 2016 LARIAC Lidar DEM: Los Angeles Region, CA" D-1
Notes:

An average month is 30.42 days
* = Indicates no horizontal movement detected in the Period at the 95% level of confidence $ = Overall Movement is Relative to the Date of Origin which varies, see Page 1 for Date 1 = Probable Error of the Indicated Movement, not of the Rate/Month 2 = Periodic Movement Time Intervals are as indicated and reflected in the Rates 3 = PB80: New point, Replaces PB71RP; No movement data available this period.

NAVD88 Rate/Mo
Point North (ft) East (ft) Elev(ft) North East Height Azim.º 2D Dist. North East Height Azim.º 2D Dist. 95%Err(1) Rate/Mo. Note % Chg AB01 1729427.53 6445709.65 178.61 -0.05 0.04 -0.02 140 0.06 0.02 0.03 0.02 60 0.04 0.04 * AB04 1728348.87 6447079.35 61.34 -43.13 -44.00 -6.23 226 61.61 -0.26 -0.29 -0.02 227 0.39 0.04 0.42 -13 AB13 1729870.03 6448220.75 353.20 -58.87 -15.29 -11.84 195 60.82 -0.46 -0.06 -0.15 187 0.46 0.04 0.50 -6 AB16 1730317.90 6447524.45 373.84 -40.98 -7.68 -2.78 191 41.70 -0.28 -0.04 0.03 189 0.28 0.04 0.30 -19 AB17 1731420.95 6446727.78 442.69 -0.17 0.01 -0.11 178 0.17 -0.01 0.01 -0.01 135 0.01 0.04 * AB21 1729295.56 6449659.89 393.48 -59.51 -15.13 -1.46 194 61.40 -0.41 -0.10 -0.03 194 0.42 0.04 0.46 -9 AB24 1729767.58 6447743.81 332.47 -62.78 -16.15 -3.45 194 64.82 -0.47 -0.10 -0.04 192 0.48 0.04 0.52 -7 AB50 1728064.57 6448222.04 185.08 -20.43 -26.14 3.10 232 33.18 -0.13 -0.14 0.03 228 0.19 0.04 0.21 -7 AB51 1729568.95 6447289.56 303.36 -48.06 -16.98 -2.06 199 50.97 -0.36 -0.10 -0.02 196 0.38 0.04 0.41 -13 AB53 1730371.34 6449702.16 347.05 -59.77 -10.21 -6.08 190 60.63 -0.42 -0.07 -0.03 189 0.43 0.04 0.46 -7 AB57 1731881.34 6449742.94 551.19 -45.56 -16.42 -13.74 200 48.43 -0.39 -0.25 -0.10 213 0.47 0.04 0.51 -5 AB58 1731058.19 6449070.91 394.76 -59.83 -4.02 -10.91 184 59.97 -0.45 -0.04 -0.08 185 0.45 0.04 0.49 -11 AB59 1730784.96 6450205.29 416.91 -65.90 -7.26 -17.46 186 66.30 -0.49 -0.06 -0.09 187 0.50 0.04 0.54 0 AB60 1729036.92 6447962.56 175.57 -52.79 -25.00 -3.88 205 58.41 -0.43 -0.21 0.01 206 0.48 0.04 0.52 -4 AB62 1728869.36 6446900.78 138.56 -40.99 -24.68 -4.45 211 47.85 -0.33 -0.21 -0.03 213 0.39 0.04 0.42 -7 AB63 1729011.72 6447278.83 166.13 -47.58 -28.20 -14.72 211 55.31 -0.32 -0.25 -0.16 218 0.41 0.04 0.44 -10 AB64 1731829.22 6447374.40 531.60 -1.47 1.32 -0.66 138 1.97 0.01 0.01 0.01 47 0.02 0.04 * AB65 1731657.24 6448269.14 444.09 -48.44 5.07 -14.45 174 48.70 -0.38 0.04 -0.10 174 0.38 0.04 0.42 -10 AB66 1729992.98 6448477.51 366.37 -54.30 -13.02 -7.92 193 55.84 -0.41 -0.09 -0.07 193 0.42 0.04 0.46 -5 AB67 1731141.17 6447738.77 396.36 -39.24 -2.99 -8.97 184 39.35 -0.30 -0.03 -0.08 185 0.30 0.04 0.33 -11 AB68 1730205.72 6448044.29 383.80 -53.13 -11.07 -9.64 192 54.27 -0.39 -0.06 -0.07 189 0.40 0.04 0.43 -6 AB73 1728409.92 6448377.48 302.75 -46.12 -16.55 -3.96 200 49.00 -0.31 -0.09 -0.02 196 0.32 0.04 0.35 -3 AB75 1729577.50 6449326.14 347.24 -42.67 -10.21 -1.78 193 43.87 -0.42 -0.07 -0.03 190 0.43 0.04 0.47 -2 AB76 1730022.68 6446807.09 385.69 -0.45 0.45 -0.59 135 0.63 0.03 0.01 -0.04 11 0.03 0.04 * AB77 1733161.89 6446514.86 895.13 -0.03 0.01 -0.19 160 0.03 0.02 0.03 -0.02 66 0.04 0.04 * AB78 1732238.60 6448523.57 568.63 -2.56 0.69 -1.11 165 2.65 -0.01 0.02 0.01 126 0.02 0.04 * AB79 1734784.19 6448718.99 1169.68 -0.01 -0.01 -0.09 215 0.02 0.01 0.00 0.04 27 0.01 0.04 * AB80 1734692.15 6447838.28 1165.43 0.00 -0.02 -0.13 282 0.02 0.01 0.00 0.02 338 0.01 0.04 * AB81 1731120.36 6448786.58 392.26 -20.03 -1.86 -4.05 185 20.12 -0.42 -0.04 -0.11 186 0.42 0.04 0.45 -7 AB83 1729265.89 6446949.93 214.65 -8.37 -3.66 -0.04 204 9.13 -0.40 -0.13 0.01 199 0.42 0.04 0.46 -6 AB84 1732177.05 6448637.50 552.77 -6.03 0.56 -2.65 175 6.05 -0.37 0.04 -0.06 174 0.37 0.04 0.40 -6 AB85 1729588.83 6446857.58 267.56 -3.49 -1.82 -0.92 208 3.93 -0.22 -0.13 -0.05 211 0.26 0.04 0.28 AB86 1729225.16 6448329.20 247.67 -3.70 -1.02 -0.57 195 3.84 -0.45 -0.13 -0.09 196 0.46 0.04 0.50 -4 CR50 1733012.98 6451036.21 872.15 -0.64 -1.17 -0.51 241 1.33 0.00 -0.01 -0.01 309 0.01 0.04 * CR51 1733061.19 6452360.60 975.80 -0.84 -1.26 -0.45 236 1.52 -0.04 -0.03 -0.03 218 0.05 0.04 0.06 CR53 1732779.33 6450222.60 780.19 -0.95 -1.59 -0.54 239 1.85 0.03 -0.03 -0.01 320 0.05 0.04 * CR54 1731192.14 6450979.68 515.87 -53.10 -12.15 -11.67 193 54.47 -0.45 -0.14 -0.18 197 0.47 0.04 0.51 -10 CR55A 1735437.62 6450188.39 1157.23 -0.05 -0.02 -0.05 201 0.05 -0.01 0.01 -0.07 137 0.02 0.04 * CR56 1733194.36 6449201.90 782.55 -0.05 0.01 -0.03 171 0.05 -0.01 0.03 0.00 100 0.03 0.04 * CR57 1731568.80 6451323.43 619.38 -0.07 -0.10 0.44 236 0.12 0.03 0.01 -0.09 15 0.03 0.04 * CR58 1732680.27 6452989.14 916.87 -0.34 -0.41 -0.13 231 0.53 0.00 -0.06 0.02 269 0.07 0.04 ??? CR59 1731860.83 6453394.59 878.01 -0.14 -0.16 -0.08 229 0.21 0.00 -0.02 0.00 275 0.02 0.04 * CR60 1732970.65 6452807.33 921.77 -0.18 -0.26 -0.08 235 0.32 0.04 -0.05 -0.07 314 0.07 0.04 * CW01 1734174.31 6450266.32 1175.38 0.00 -0.01 0.03 254 0.01 0.01 -0.04 0.04 292 0.04 0.04 * CW05 1732067.10 6450634.28 701.83 -1.26 -1.23 -0.10 224 1.76 0.02 -0.03 -0.01 314 0.03 0.04 * CW06 1730906.24 6452118.19 529.75 0.00 0.02 -0.01 80 0.02 0.01 0.00 -0.10 333 0.01 0.04 * CW08 1729146.30 6453119.76 607.57 0.01 -0.03 0.11 299 0.03 0.00 -0.04 0.06 263 0.04 0.04 * FT08 1729388.65 6453350.50 658.41 -0.03 0.00 -0.04 0 0.03 0.00 -0.02 0.04 276 0.02 0.04 * FT09 1729052.85 6454289.21 590.84 -0.05 -0.08 0.01 240 0.10 0.00 0.02 0.02 107 0.02 0.04 * FT10 1730454.56 6452471.93 482.23 -0.01 0.01 -0.12 118 0.01 0.02 0.00 -0.10 344 0.02 0.04 * KC05 1727077.16 6453174.07 226.77 -4.84 -5.02 -1.09 226 6.97 0.02 0.00 0.03 8 0.02 0.04 * KC06 1727782.47 6453384.91 295.68 -2.44 -11.75 -4.67 258 12.00 0.00 0.01 0.00 63 0.01 0.04 * KC07 1727759.37 6453683.86 313.47 0.00 0.01 -0.04 90 0.01 0.00 0.00 -0.01 45 0.01 0.04 * KC14 1726742.29 6453805.52 259.98 -0.15 -0.54 0.04 254 0.56 0.03 0.01 -0.02 27 0.03 0.04 * KC15 1727584.34 6453111.42 284.02 -6.11 -9.67 -3.08 238 11.44 0.02 0.01 -0.06 30 0.02 0.04 * KC16 1727602.24 6454098.22 327.24 -0.01 -0.01 0.34 238 0.01 0.03 0.02 0.01 33 0.03 0.04 * KC17 1727295.80 6453019.47 212.65 -6.97 -6.96 -2.60 225 9.85 -0.02 -0.02 0.02 224 0.03 0.04 * KC18 1727979.31 6452613.57 289.13 -21.19 -8.60 -2.04 202 22.87 -0.01 0.00 0.04 194 0.01 0.04 * KC19 1727780.04 6453488.54 302.73 -0.37 -8.68 -3.60 268 8.69 0.03 0.02 -0.05 38 0.04 0.04 * KC20 1727695.34 6453561.57 303.72 0.18 -7.98 -3.57 271 7.98 0.00 -0.01 -0.07 266 0.01 0.04 * KC21 1728095.82 6453495.12 383.66 0.00 0.03 0.06 90 0.03 0.02 0.00 0.00 3 0.02 0.04 * KC22 1728008.13 6453287.32 329.11 -2.03 -10.57 -5.25 259 10.76 0.00 0.00 0.01 76 0.00 0.04 * KC23 1727348.72 6453321.56 267.53 -2.70 -5.45 -1.78 244 6.09 0.00 0.03 0.01 84 0.03 0.04 * KC25 1726304.88 6452805.42 19.78 -0.41 -0.19 -0.02 205 0.45 0.01 0.00 0.04 20 0.01 0.04 * KC26 1726723.06 6452425.78 31.07 -6.46 -1.34 6.33 192 6.60 0.02 0.00 0.01 349 0.02 0.04 * KC28 1726768.60 6451998.87 26.25 -9.19 -1.04 6.31 186 9.25 0.01 -0.01 0.04 323 0.01 0.04 * KC29 1726923.89 6451934.52 19.84 -10.54 -3.12 1.94 196 10.99 0.01 -0.01 0.03 324 0.02 0.04 * KC30 1727529.33 6452141.94 97.64 -14.72 -4.58 -2.61 197 15.41 0.01 -0.01 -0.09 337 0.01 0.04 * KC31 1727910.90 6452353.12 206.79 -14.03 -5.08 -0.70 200 14.93 0.00 0.00 0.01 169 0.01 0.04 * KC34 1726698.41 6454866.44 325.36 0.01 0.00 -0.01 22 0.01 0.02 0.02 -0.02 45 0.02 0.04 * KC35 1726861.64 6454504.97 313.28 -0.02 0.01 -0.02 162 0.02 0.00 0.02 0.00 90 0.02 0.04 * KC36 1726390.09 6454165.10 254.98 0.02 -0.05 -0.03 289 0.05 0.03 0.00 -0.02 358 0.03 0.04 * KC37 1726109.82 6454779.83 280.31 0.00 -0.02 -0.01 285 0.02 0.01 0.01 0.01 47 0.02 0.04 * KC38RP 1726875.53 6451660.95 14.36 0.00 -0.02 0.01 265 0.02 0.00 -0.02 0.01 265 0.02 0.04 * KC39 1726579.06 6453069.26 192.34 -0.05 -0.03 -0.09 205 0.06 0.00 -0.03 0.01 270 0.03 0.04 * PB04 1727610.73 6448829.22 163.96 -65.21 -22.52 -6.56 199 68.99 -0.37 -0.09 -0.05 193 0.38 0.04 0.42 0 PB06 1727888.04 6449747.01 173.34 -80.40 -14.83 -9.72 190 81.76 -0.25 -0.05 0.01 193 0.25 0.04 0.27 -16 PB07 1728081.30 6450196.73 195.44 -94.62 -23.03 -4.77 194 97.39 -0.27 -0.02 -0.02 185 0.27 0.04 0.29 -26 PB08 1728150.16 6450449.92 196.91 -87.35 -19.88 3.23 193 89.58 -0.25 -0.02 0.05 184 0.25 0.04 0.27 -16 PB09 1728197.63 6450841.34 189.20 -90.95 -9.69 -3.32 186 91.46 -0.23 0.02 0.03 176 0.23 0.04 0.25 -21 PB12 1728196.33 6451565.42 177.19 -134.16 -39.15 -16.10 196 139.76 -0.25 0.00 -0.02 181 0.25 0.04 0.27 -18 PB13 1728002.52 6452131.87 205.55 -83.45 -32.47 -4.99 201 89.55 -0.11 -0.03 0.03 193 0.11 0.04 0.12 -16 PB18 1730371.77 6450713.37 354.98 -75.12 2.38 -12.60 178 75.15 -0.36 -0.06 -0.12 189 0.37 0.04 0.40 -20 PB20 1728682.52 6451110.28 224.28 -130.25 -25.39 -19.26 191 132.70 -0.29 -0.05 -0.01 189 0.30 0.04 0.32 -4 PB21 1729186.85 6451171.33 265.48 -111.37 -0.73 -14.55 180 111.37 -0.30 0.00 0.00 181 0.30 0.04 0.32 -3 PB26 1729501.41 6452246.46 279.88 -61.23 -3.10 -5.46 183 61.31 -0.09 0.02 0.04 169 0.10 0.04 0.10 -7 PB27 1729181.58 6451834.28 259.86 -157.76 -1.78 -24.56 181 157.77 -0.30 -0.02 -0.03 185 0.30 0.04 0.33 -13 PB29 1728800.26 6452074.86 159.36 -88.69 -45.63 -26.58 207 99.74 -0.14 -0.08 0.02 210 0.16 0.04 0.18 0 PB54 1729632.45 6450437.13 355.31 -62.45 -11.55 -3.31 190 63.51 -0.38 -0.06 -0.01 190 0.38 0.04 0.41 -12 PB55 1728718.11 6450789.50 230.14 -94.18 -14.54 -16.19 189 95.29 -0.34 -0.01 -0.01 181 0.34 0.04 0.37 7 PB59 1727698.58 6448640.34 150.99 -67.79 -21.33 -12.40 197 71.06 -0.33 -0.10 -0.06 198 0.35 0.04 0.38 -9 PB67 1727542.72 6450840.79 63.16 -96.01 -17.39 -12.85 190 97.58 -0.25 -0.03 -0.02 187 0.25 0.04 0.27 -12 PB68 Not a viable point, Replaced by PB78
PB69 1727730.50 6448759.54 161.91 -52.55 -19.04 -2.77 200 55.89 -0.30 -0.09 -0.03 197 0.31 0.04 0.34 -14 PB70 1727802.13 6448600.27 148.98 -52.78 -19.32 -7.26 200 56.20 -0.30 -0.09 -0.05 197 0.32 0.04 0.35 -18 PB71RP Point destroyed, Replaced by PB80
PB72 1727606.38 6449323.37 199.00 -43.95 -18.05 3.12 202 47.51 -0.33 -0.13 -0.01 201 0.36 0.04 0.39 -5 PB75 1729034.62 6450344.56 267.05 -49.23 -7.34 -4.85 188 49.78 -0.36 0.02 -0.12 177 0.36 0.04 0.40 -6 PB76 1729962.91 6451646.16 290.20 -10.19 0.29 -1.59 178 10.19 -0.17 0.02 -0.07 174 0.17 0.04 0.18 -26 PB77 1727511.71 6451675.02 98.11 -8.92 -1.01 -0.94 186 8.97 -0.27 -0.03 0.03 186 0.27 0.04 0.29 -10 PB78 1727651.46 6449009.30 173.67 -1.47 -0.50 0.01 199 1.56 -0.28 -0.11 -0.03 201 0.30 0.04 0.32 PB79 1727050.53 6451765.61 67.62 -0.15 0.00 0.04 -0.15 0.00 0.04 182 0.15 0.04 0.16 PB80 1728405.58 6449657.48 282.59 New Pt Replaces PB71RP 3 UB02 1727467.74 6450141.61 65.72 -113.37 7.82 -1.43 176 113.64 -0.19 0.03 0.03 170 0.19 0.04 0.21 21 PVE3RP 1729195.88 6438764.68 346.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Fixed * RP01 1725591.74 6455633.55 292.70 0.00 0.00 0.03 0.00 -0.01 0.00 -0.02 0.01 0.02 * RP02 1730832.99 6445586.60 480.62 0.00 -0.01 0.00 0.01 0.00 0.00 0.01 0.01 0.02 * RP03 1730848.53 6445628.19 479.98 0.04 -0.02 0.00 0.05 0.03 0.01 0.01 0.03 0.02 * RP05 1730809.64 6445502.00 474.21 -0.02 0.01 -0.05 0.03 0.01 0.01 0.00 0.01 0.02 Fixed Av. 0.36 Av. -9
NAD83 CA SPC Zone 5 Original Position to August 04, 2026 July 07,2026 to August 04, 2026 (28 days / 0.920 Mo.) PORTUGUESE BEND LANDSLIDE MONITORING - MOVEMENT at August 04, 2026 Page 17/17 Prepared by McGee Surveying Consulting - Document Date: August 11, 2026 Monitoring Point Movements
FULL PVDS MONITORING #97 (M97)
August 04, 2026 Positions $ Overall Movements (US Feet) Periodic Movements M96 to M97 (US Feet) E-1