Client Pricing Summary
PROJECT NAME: Redondo Beach Performing Arts Center Loudspeaker Replacement-BOND QUOTE NUMBER: 51709 LOCATION: Redondo Beach, CA DATE: 1/26/2022
ADDENDUMS: BID DATE: 1/26/2022
BID BOND REQ'D?: BY: DL
OWNER: City of Redondo Beach CONSULTANT:

ADDRESS: 415 Diamond St, Door 1 ADDRESS:

CITY: Redondo Beach, CA 90277 CITY:

CONTACT: Jack Meyer CONTACT:

PHONE: 310-318-0643 FAX: PHONE: FAX:

CELL: CELL:

EMAIL: [email protected] EMAIL:

EQUIPMENT COSTS
SUPPLIERS' COST: $0.00
INCOMING FREIGHT: $0.00 TOTAL EQUIPMENT PRICE: $0.00
WAREHOUSING: $0.00 $0.00
MISCELLANEOUS HARDWARE and SMALL PARTS: $0.00
----------------------
EQUIPMENT TOTAL: $0.00 EQUIPMENT AND LABOR PRICE: $0.00 LABOR COSTS $2,181.34

RATE AMOUNT

0.0 hrs PROJECT MANAGER: $100.00 $0.00 ----------------------

0.0 hrs PROJECT ENGINEER: $100.00 $0.00 $2,181.34

0.0 hrs DRAFTING/LABELS: $65.00 $0.00

0.0 hrs DEMO $95.00 $0.00 ----------------------

0.0 hrs INSTALL LABOR: $95.00 $0.00 ----------------------

0.0 hrs INSTALL SUPERVISION: $105.00 $0.00

0.0 hrs DSP/IP PROGRAMMING: $110.00 $0.00 $2,181.34

0.0 hrs FINAL TESTING & TUNING: $100.00 $0.00

0.0 hrs PURCHASING/RECEIVING/HANDLING: $50.00 $0.00 9.50% n/a

0.0 hrs TRAVEL & LOSS: $50.00 $0.00 ---------------------- LABOR TOTAL: $0.00
$2,181.34
COST EXT Clarifications:
$335,590.89 PROJECT VALUE BOND 0.0065 $2,181.34
OTHER TOTAL: $2,181.34
SALES TAX (travel, inbound shipping,
and install/service labor excluded):

TOTAL LABOR COST:

DIRECT COSTS
TOTAL DIRECT COSTS:

TOTAL PRICE:

TOTAL PRICE WITH SALES TAX
TOTAL WITH DIRECT COSTS: