H.13., File # 22-3713 Meeting Date: 2/15/2022
To: MAYOR AND CITY COUNCIL
From: TED SEMAAN, PUBLIC WORKS DIRECTOR
TITLE
INTRODUCE BY TITLE ONLY ORDINANCE NO. 3228-22, AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH, CALIFORNIA, AMENDING TITLE 3, CHAPTER 6
OF THE REDONDO BEACH MUNICIPAL CODE TO ESTABLISH A FEE TO USE PUBLIC
ELECTRIC VEHICLE CHARGING STATIONS, PERMIT THE ESTABLISHMENT OF
OVERSTAY CHARGES FOR PUBLIC ELECTRIC VEHICLE CHARGING STATIONS, AND
PROHIBIT NON-CHARGING VEHICLES FROM PARKING AT PUBLIC ELECTRIC VEHICLE CHARGING STATIONS. FOR FIRST READING AND INTRODUCTION.
EXECUTIVE SUMMARY
On January 18, 2022 the City Council accepted as complete Capital Improvement Project (CIP) Job No. 20770, Electric Vehicle Charging Infrastructure Project. The grant funded project added seven dual port level 2 chargers and one dual port DC fast charger at five different locations throughout the City. These locations include the Riviera Village Triangle Lot, Main Library Parking Structure, Performing Arts Center, North Branch Library Parking Lot, and Police Department Front Parking Lot.
These are the first publicly owned charging stations in the City and given the signification interest from the public and the Council, staff will look to expand the City’s electric vehicle charging station EVCS) footprint through future grant opportunities.
The EV charging stations are active and currently being offered at no cost to the user. The Public Works Department is proposing the attached Ordinance to establish the mechanism to apply fees for use of current and future EV charging stations. While the Ordinance creates the structure for the new proposed fees, the actual amounts will be set through updates to the Master Fee Schedule. A Public Hearing to consider changes to the Master Fee Schedule is also scheduled for the February 15, 2022 City Council Meeting. The City Council will need to approve the fee amount at the conclusion of the hearing for the new EVCS fees to be implemented.
Staff is proposing the new fees to recover the City costs incurred for public use of the stations. The recommended user fees are 30 cents per kWh for use of level 2 chargers and 40 cents per kWh for use of the DC Fast Charger, which is comparable to surrounding Cities. Furthermore, there is a proposed overstay fee of $1.50 per hour that will be assessed after a vehicle has been charging for more than four hours. Lastly, staff is proposing a parking violation of $50 for vehicles not plugged into the station while parked in an EV parking space, which mirrors the City’s expired meter violation penalty.
The purpose of the proposed fees is to recover electricity costs associated with the EV stations along
1 H.13., File # 22-3713 Meeting Date: 2/15/2022
The purpose of the proposed fees is to recover electricity costs associated with the EV stations along with promoting turnover in the EV parking spaces to allow for multiple users to utilize the stations each day. Staff is recommending the introduction and first reading of the ordinance to create the basis for fees and the violations associated with the use of EVCS parking spaces in the Municipal Code. The second reading and adoption of the Ordinance would occur on March 1, 2022, and if the City Council sets the amount of fees at the conclusion of the Public Hearing the EVCS fees would be implemented on April 1, 2022.
BACKGROUND
The City was awarded a grant from the MSRC that was executed in February 2019. The grant matched up to 50% of the total electric vehicle supply equipment/charging infrastructure (EVSE) cost for private access EVSE, which is for the dedicated use of the proposing entity; and up to 75% of the cost of publicly accessible EVSE up to a City total of $89,400.
The City Council approved the charging site locations that include one private use site ( City Hall Parking Lot), and five public use sites (Riviera Village Triangle Lot, Main Library Parking Structure, Performing Arts Center, North Branch Library Parking Lot, and Police Department Front Parking Lot), for a total of nine (9) EV charging stations including seven (7) dual port level II stations, one (1) single port level II station, and one (1) DC fast charger.
In addition, in November 2020 the City was notified of SCIP funds being reserved for the City as part of an application that was submitted in December 2019. The SCIP program is funded through the California Energy Commission and promotes easy access to zero-emission vehicle infrastructure by offering rebates for the purchase and installation of eligible public electric vehicle chargers. The EVCS project’s design scope was amended to incorporate a DC fast charger into the plans and specifications after SCIP funds were reserved for the City in the amount of up to $70,000 or 75% of the cost, whichever is less. The SCIP funds were appropriated in December 2020 for CIP No. 20770.
Subsequently, the plans and specifications for CIP No. 20770 were approved by the City Council on January 19, 2021. On February 25, 2021, five (5) bids were received and publicly opened in the City Clerk’s office. After reviewing the bids, Amtek Construction with a bid amount of $133,333 was found to be the lowest responsible bidder. Amtek Construction was awarded the contract through City Council approval on April 13, 2021. The agreement was finalized on May 18, 2021 and construction commenced on June 28, 2021.
The final inspection was approved and completed by the Building and Safety Division on December 20, 2021 and the City Council accepted the project as complete on January 18, 2022. Given that the stations are connected to existing City electric meters there is a need to recover the increased electrical costs from usage of the stations.
Public Electric Vehicle charging stations are new in the City. As such, the ability to recover costs associated with their use does not exist in the City’s Master Fee Schedule. Staff is proposing the attached Ordinance to establish the mechanism to collect fees for use of the recently activated and any future EVCS.
Charging Station User Fees and Non-Charging Violation
In order to optimize the use of the charging stations and allow multiple electric vehicles to use the charging equipment during a typical day, staff is proposing a pricing plan designed to cover energy
2 H.13., File # 22-3713 Meeting Date: 2/15/2022
charging equipment during a typical day, staff is proposing a pricing plan designed to cover energy costs and regular maintenance. Furthermore, in order to avoid non-charging vehicles from utilizing the EVCS spaces, staff is proposing a $50 violation for all vehicles parked in an EVCS space that are not charging their vehicles.
The cost for the use of the charger is calculated based on duration of stay and energy consumed kWh). ChargePoint, the station manufacturer, recommends using kWh pricing to cover electrical cost and provide revenue to cover ongoing operating costs, then encourages establishing “graduated pricing based on duration of stay” where the use fees are raised after a charging period to encourage turnover of the parking space. The proposal, which will be formally considered as part of the public hearing on the master fee schedule, is to set charging rates at:
Level 2 Charger (CT 4000) Rate Per
Kilowatt
Hour
Over-Stay
Rate After 4
Hours
0.30 $ 1.50/ Hour
Fast Charging (CPE250 50kW) Rate Per
Kilowatt
Hour
Over-Stay
Rate After 4
Hour
0.40 $ 1.50/ Hour
Staff is recommending that the City set a fee for use of the charging stations of $0.30/kWh for Level 2 and $0.40/kWh for the DC Fast charger. After 4 hours of charging the vehicle would begin to be charged an overstay fee of $1.50/hour for both the Level 2 and DC Fast Charger. These fees are consistent and comparable with the fees established by other communities with similar EV infrastructure. Staff will monitor demand and use of the charging stations during the first year to determine if any adjustments to the use fees are needed. On-going costs to be incurred by the City for the charging stations will consist of station maintenance, annual ChargePoint network fees, and the cost of the electricity used, which will vary based on station usage.
These ongoing revenue and expenditures will be tracked by site utilizing ChargePoint’s software, and pricing will also be set within the system. Users of the stations will pay for the use of the stations directly with ChargePoint. Specifically, users of the stations will need to establish an account with ChargePoint, Inc. to access the electric charging services.
The adoption of this ordinance codifies and creates the mechanism that allows for charging users a fee, as well as issue violations to those non-charging vehicles parked in current EVCS spaces along with future EVCS spaces.
COORDINATION
Staff coordinated this report with the Finance Department, the Police Department, and the City Attorney’s Office.
FISCAL IMPACT
The City projects expenses and (offsetting) revenue to be approximately $28,000 per year for the use
3 H.13., File # 22-3713 Meeting Date: 2/15/2022
of the stations.
APPROVED BY:
Mike Witzansky, City Manager
ATTACHMENTS
Ordinance
4 ORDINANCE NO. 3228-22
EV OVERSTAY & VIOLATION
PAGE NO. 1
ORDINANCE NO. 3228-22
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF
REDONDO BEACH, CALIFORNIA, AMENDING TITLE 3, CHAPTER 6
OF THE REDONDO BEACH MUNICIPAL CODE TO ESTABLISH A
FEE TO USE THE PUBLIC ELECTRIC VEHICLE CHARGING
STATION, PERMIT THE ESTABLISHMENT OF OVERSTAY
CHARGES FOR PUBLIC ELECTRIC VEHICLE CHARGING
STATIONS, AND PROHIBIT NON-CHARGING VEHICLES FROM
PARKING AT PUBLIC ELECTRIC VEHICLE CHARGING STATIONS
WHEREAS, the State of California has set a goal for the construction and installation of 250,000 electric vehicle charging stations by 2025 ; and WHEREAS, the City Council of the City of Redondo Beach accepted as complete Capital Improvement Project ( CIP) No. 20770, Electric Vehicle Charging Infrastructure, which added seven dual port electric vehicle charging stations and one DC fast charger station at five different locations throughout the City of Redondo Beach (City); and WHEREAS, the number of electric vehicle owners continues to grow and demand for public electric vehicle charging stations continues to increase; and WHEREAS, parking spaces designated for use of public electric vehicle charging stations are intended to be used only while using the public electric vehicle charging station; and WHEREAS, encouraging turnover at parking spaces designated for use of public electric charging stations is necessary to maximize station access; and WHEREAS, the electric vehicle charging stations have the technology to automatically charge drivers an administrative charge for overstaying in a parking space designated for use of a public electric vehicle charging station beyond the maximum charging time; and WHEREAS, the City desires to establish a fee for use of public electric charging vehicle station and an overstay charge for electric vehicles that remain in parking spaces designated for use of public electric vehicle charging stations past the maximum posted time limit; and WHEREAS, the City desires to prohibit non-charging vehicles from parking in spaces designated for use of public electric vehicle charging stations.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF REDONDO BEACH, CALIFORNIA, DOES ORDAIN AS FOLLOWS:
SECTION 1. AMENDMENT OF CODE. Title 3, Chapter 6, Section 3-6.01 of the Redondo Beach Municipal Code, is hereby amended to add the following definitions:
3-6.01 Definitions.
5 ORDINANCE NO. 3228-22
EV OVERSTAY & VIOLATION
PAGE NO. 2
Electric Vehicle” means a vehicle which uses one or more electric motors for propulsion.
An EV is either fully or partially powered on electric power. This includes both battery electric vehicles as well as plug-in hybrid electric vehicles.
Electric Vehicle Charging Station” means an Electric Vehicle charging station with a minimum installed "Level 2 Electric Vehicle Service Equipment” capable of charging at 40- amp or higher at 208/240VAC. An Electric Vehicle charging station capable of simultaneously charging at 40-amp for each of two (2) vehicles shall be counted as two 2) Electric Vehicle chargers.
Non-Charging Vehicle” means any vehicle parked in a designated Electric Vehicle space that is not charging at any given time.
SECTION 2. AMENDMENT OF CODE. Title 3, Chapter 6, Section 3-6.03 of the Redondo Beach Municipal Code, is hereby amended to add the following:
3-6.03 Installation of parking meters—Rates for parking. h) Spaces Designated for Use of Public Electric Charging Stations. The rates for use of a public Electric Vehicle Charging Station shall be set forth by resolution of the City Council and may be changed, from time to time, by resolution.
SECTION 3. AMENDMENT OF CODE. Title 3, Chapter 6, Section 3-6.04 of the Redondo Beach Municipal Code, is hereby amended to read as follows:
3-6.04 Deposit of payment required.
c) Public Electric Vehicle Charging Station Parking Space Overstay Charge 1) If an Electric Vehicle remains parked in a public Electric Vehicle Charging Station after the maximum posted time permitted for charging, an overstay charge shall be applied, which shall be in increments of an hour. 2) The rates for overstay charges for spaces designated for use of public Electric Vehicle charging stations shall be set forth by resolution of the City Council and may be changed, from time to time, by resolution.
SECTION 4. AMENDMENT OF CODE. Title 3, Chapter 6, Section 3-6.05 of the Redondo Beach Municipal Code, is hereby amended to read as follows:
3-6.05 Overtime parking.
a) It is unlawful for any person to cause, allow, or permit any vehicle (except an Electric Vehicle subject to any overstay charge) to be parked overtime or beyond the lawful period of time as provided by this chapter or to remain parked in any parking space while a signal showing legal parking is not displayed by the parking meter associated with such space. b) It is unlawful for any person to cause, allow, or permit any vehicle to be parked in any public parking lot having a ticket device or pay machine without 6 ORDINANCE NO. 3228-22
EV OVERSTAY & VIOLATION
PAGE NO. 3
making payment as provided by the pay machine or displaying a valid City parking permit, or to cause, allow, or permit any vehicle remain parked in any of such lots after the displayed ticket or permit or payment has expired. c) It is unlawful to permit or allow any vehicle (except an Electric Vehicle subject to any overstay charge) to remain parked or left standing in or at the same location or parking space for a period longer than the posted maximum time limit whether or not payment is deposited or a valid permit is displayed. d) It is unlawful for any vehicle to park in any parking space designated for use of a public Electric Vehicle Charging Station if the vehicle is not using the public Electric Vehicle Charging Station to charge the vehicle.
SECTION 5. AMENDMENT OF CODE. Title 3, Chapter 6, Section 3-6.10 of the Redondo Beach Municipal Code, is hereby amended to read as follows:
3-6.10 Enforcement of provisions.
It shall be the duty of the enforcement officers of the City to report the following:
a) The number of each parking meter or pay machine which indicates that the vehicle occupying the parking space adjacent to such parking meter is or has been parking in violation of any of the provisions of this chapter; b) The State license number of such vehicle;
c) The time during which such vehicle is parking in violation of any of the provisions of this chapter;
d) The number of each public Electric Vehicle Charging Station, which indicates that the vehicle occupying the space of the public Electric Vehicle Charging Station is or has been parking in violation of any of the provisions of this chapter; and
e) Any other facts or knowledge which is necessary to a thorough understanding of the circumstances attending such violation.
The enforcement officer shall also attach to such vehicle a notice to the owner or operator thereof that such vehicle is parked contrary to the parking limitations or the parking permit provisions of this chapter and instructing such owner or operator that he or she is subject to a civil penalty in the amount set forth upon the notice. The civil penalty for such violation shall be set by resolution of the City Council.
SECTION 6. INCONSISTENT PROVISIONS. Any provisions of the Redondo Beach Municipal Code, or appendices thereto, or any other ordinances of the City inconsistent herewith, to the extent of such inconsistencies and no further, are hereby repealed.
SECTION 7. SEVERANCE. If any section, subsection, sentence, clause, or phrase of this ordinance is for any reason held to be invalid or unconstitutional by the decision of any court of 7 ORDINANCE NO. 3228-22
EV OVERSTAY & VIOLATION
PAGE NO. 4
competent jurisdiction, such decision shall not affect the validity of the remaining portions of the ordinance. The City Council hereby declares that it would have passed this ordinance and each section, subsection, sentence, clause, and phrase thereof, irrespective of the fact that any one or more sections, subsections, sentences, clauses, or phrases be declared invalid or unconstitutional.
SECTION 8. PUBLICATION AND EFFECTIVE DATE. This ordinance shall be published by one insertion in the official newspaper of said city, and same shall go into effect and be in full force and operation from and after thirty (30) days after its final passage and adoption.
PASSED, APPROVED AND ADOPTED this 15th day of February, 2022.
William C Brand, Mayor
APPROVED AS TO FORM: ATTEST:
Michael W. Webb, City Attorney Eleanor Manzano, CMC, City Clerk 8 ORDINANCE NO. 3228-22
EV OVERSTAY & VIOLATION
PAGE NO. 5
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss
CITY OF REDONDO BEACH )
I, Eleanor Manzano, City Clerk of the City of Redondo Beach, California, do hereby certify that Ordinance No. 3228-22 was passed and adopted by the City Council of the City of Redondo Beach, California, at a regular meeting of said City Council held on the 15th day of February 2022, and there after signed and approved by the Mayor and attested by the City Clerk, and that said ordinance was adopted by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Eleanor Manzano, CMC
City Clerk
9