Attachment 5 Bid Protest Response - Redondo Beach

Redondo Beach City Council
April 5, 2022

Document
Attachment 5 Bid Protest Response - Redondo Beach
Meeting
April 5, 2022
Body
Redondo Beach City Council
Original file
236 KB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

From the desk of Don Mangan, President
PaveWest . 11700 166th Street, Artesia, CA 90701 . Cell (562) 824-2527 . Office (562) 694-3113 [email protected] . www.pavewest.com
03/01/2022
City of Redondo Beach
415 Diamond Street
Redondo Beach, CA 90277
Attn: Daniel Gruezo, Civil Engineer
Re: Beryl Street Drainage and Street Improvements Project from North Prospect Avenue to Flagger Lane – Job No. 41130
Subject: Bid Protest Response
Dear City of Redondo Beach,
Regarding the Bid Protest about self-performance requirements from Sully-Miller for Beryl Street Drainage and Street Improvements Project from North Prospect Avenue to Flagler Lane – Job No. 41130, PaveWest has made two clerical errors:

1. PaveWest listed the subcontractor proposal costs and included 5% profit to our estimated amounts. This was listed in the “Designation of Subcontractors” form and should have reflected an estimated amount for each subcontractor at 5% less (Exhibit A).

2. PaveWest included the concrete portion of work in TTS Engineering Inc’s total estimated amount. TTS will only be performing the storm drain scope of work. We are self-performing the concrete and traffic control scope of work. PaveWest is performing 51% of the total contract amount. The subcontractors listed are performing the remaining 49% of the work. If we considered the clerical errors, then the subcontractors would have been performing 82% of the work which is not per specification (Exhibit B).

Please review the attached exhibits for complete details of the clerical errors. PaveWest self-performs all aspects of our General Engineering Contractor’s license with our own asphalt, concrete, and striping divisions. PaveWest apologizes for the clerical errors and appreciates the opportunity to resolve the matter and we look forward to working with the City of Redondo Beach. Thank you.

Respectfully,
Exhibit A
With clerical error of proposal costs:

With correct proposal costs:

Listed including 5% Profit Actual Dollar Amount
No profit included
Individual %
for Subs
TTS Engineering Inc. $ 1,727,217.55 $ 1,644,206.09 72%
Global Road Sealing $ 18,585.00 $ 17,700.00 1%
Cedillo Landscaping $ 77,820.00 $ 74,113.91 3%
PCI $ 72,429.00 $ 68,980.00 3%
Total for Subs $ 1,896,051.55 $ 1,805,000.00

SUBCONTRACTORS
Actual Dollar Amount
No profit included
Individual %
for Subs
TTS Engineering Inc. $ 920,212.59 40%
Global Road Sealing $ 17,700.00 1%
Cedillo Landscaping $ 74,113.91 3%
PCI $ 68,980.00 3%
Total for Subs $ 1,081,006.50

SUBCONTRACTORS
Exhibit B
Highlighted amounts indicate TTS’s SOW
Item No. Total Cost
1 $ 94,255.00
2 $ 160,457.50
3 $ 8,500.00
4 $ 28,000.00
5 $ 58,950.00
6 $ 127,500.00
7 $ 48,750.00
8 $ 106,990.80
9 $ 65,533.00
10 $ 76,966.08
11 $ 46,277.54
12 $ 39,710.00
16 $ 35,441.80
17 $ 31,390.52
18 $ 10,191.30
21 $ 14,400.00
22 $ 13,200.00
26 $ 228,900.00
27 $ 18,110.40
Total $ 1,213,523.94
PAVEWEST, INC. SOW
1 $ 32,255.00
2 $ 87,457.50
8 $ 101,990.00
9 $ 62,400.00
10 $ 82,467.00
11 $ 44,074.00
12 $ 38,000.00
13 $ 608,264.10
14 $ 193,825.27
15 $ 69,994.95
16 $ 33,755.00
17 $ 28,896.00
18 $ 9,706.00
19 $ 11,684.72
20 $ 4,188.55
26 $ 218,000.00
27 $ 17,248.00
Total Proposal $ 1,644,206.09
Total cost of correct
SOW for TTS $ 920,212.59
TTS PROPOSAL MINUS 5% PROFIT
Total Cost including Profit $ 1,101,187.87
PCI
$ 932,353.87
$ 18,585.00
$ 77,820.00
$ 72,429.00
TTS Engineering Inc.

Global Road Sealing
Cedillo Landscaping
PaveWest
SOW Price and % $ 1,181,268.94
Total Contract $ 2,314,711.81
51% % of Subs 49%