CITY OF REDONDO BEACH
Budget Response Report #44
June 14, 2022
Question:

What is the annual cost and resource allocation for the City’s programs and services implemented in response to homelessness?
Response:

Programs funded by grant funding, other outside sources, and special funds In 2016, the Police Department established a full-time Quality of Life Officer to outreach to people experiencing homelessness and work closely with the Quality of Life Prosecutor to address issues that arise from the homelessness problem. The position costs roughly $215,000 per year. $200,000 of the cost is funded by the Housing Successor Agency and the balance, of approximately $15,000, is funded by the General Fund.

In 2016, the City Council approved a contract for services with PATH for $50,000 to address homelessness issues. The City Council renewed that agreement in 2017 for one year, and then approved two-year agreements in 2018 and 2020. The funding for the PATH contracts is also funded by the Housing Successor Agency, as it is an eligible expense.

In 2016, the Police Department acquired a Department of Mental Health (DMH) Mental Health Emergency Response Team (MET) clinician who covers the cities of Redondo Beach, Hermosa Beach, Manhattan Beach, and now El Segundo. The DMH clinician services are provided through a cooperative Memorandum of Understanding (MOU) between the LA County Department of Mental Health and the cities of El Segundo, Hermosa Beach, Manhattan Beach and Redondo Beach. There are no costs associated with the MOU for the DMH clinician. The County DMH clinicians’ availability is insufficient for the Police Department’s needs to respond to calls for service.

In 2017, the City Council approved an agreement for services with Harbor Interfaith for $58,000. The agreement was renewed in 2018 for one year, and then renewed again in two-year increments in 2019 and 2021. Funding for the first year of the agreement was provided through AB 109 supplemental funds, which were awarded to the City as a onetime funding source that the City used towards homelessness efforts. Since then, the agreement has been funded through a combination of AB 109 funds, Housing Successor Agency funds and General Funds, up until the current fiscal year. The agreement was amended in September 2019 to allow for the donation of a vehicle to Harbor Interfaith Service and to increase the annual reimbursable amount to $68,000. In 2020, a second amendment was approved to allow for additional COVID-19 expenses in the amount of BRR #44

Page 2 of 5 ends

$28,400 to be added, which is funded by the CDBG Cares Act. For Fiscal Year 2021- 2022, the City received CDBG grant funding from the County, which can be used to cover this agreement because Harbor Interfaith is involved with Redondo’s homeless court.

As part of the Fiscal Year 2019-20 budget, the Mayor and City Council appropriated $250,000 from available General Funds to fund the Police Department and City Attorney’s Office response to homeless issues. This became the Enhanced Response to Homelessness Pilot Program. This appropriation funded a new Police Captain position, police overtime and the promotion of two deputy city prosecutors to senior deputy city prosecutors. $100,000 of that appropriation was meant to be used for special services such as mental health and substance abuse programs. However, CLEAR Recovery Center donated these services to the City, so that allocation was never spent. The senior city prosecutors dedicate at least half of their time towards responding to homeless issues. Through this Pilot Program, the prosecutors were able to assist the City Attorney in creating Redondo Beach’s homeless court.

For Fiscal Year 2020-21, the South Bay Cities Council of Governments (SBCCOG) awarded the City $245,287 for the Enhanced Response to Homelessness Pilot Program from Measure H Innovative Funds. Part of the funding for special services was used for a census of Redondo’s homeless population conducted by City Net because the point in time count was cancelled in 2021. Again, CLEAR Recovery Center continued to donate services to the City, so $100,000 remained available for other purposes such as bridge housing. Due to the pandemic, the county extended the term for use of these funds to December 31, 2021.

In November, 2020, the City Council approved the construction and operation of a temporary emergency housing shelter on Kingsdale Avenue, known as the Pallet Shelters. The City currently pays the County $18,884.61 a month as the City’s share pursuant to the Letter of Agreement with Los Angeles County.

For Fiscal Year 2021-22, the City received $100,000 from Los Angeles County CDBG funds for Redondo Beach’s homeless court. In addition, the SBCCOG granted Redondo Beach a new Innovation Grant in the amount of $306,299 for the term of January 2022 to June 2023 to expand Redondo’s homeless court to add Hermosa Beach cases and for Hermosa Beach to host the homeless court for six out of the 18 sessions, special services (such as the services CLEAR Recovery is now billing the City for), and bridge housing.

In January 2021, the City Council approved the rental of five Single Room Occupancy (SROs) units in a city within Service Planning Area 8 to be used as bridge housing. At first, CDBG funds were used to pay the rent on these units. After the expiration of the CDBG funds, the unexpended funds from the first grant of Innovative Funds were used to continue renting these SROs. Now the SROs are funded by the most recent Innovation Grant from the SBCCOG as described above.

The Police Department also deploys Homeless Outreach Services Teams (HOST) composed of law enforcement officers who work closely with homeless service agencies BRR #44

Page 3 of 5 ends

to increase public safety while preserving the rights and dignity of people experiencing homelessness. The City receives funding from the County through Measure H. In Fiscal Year 2019-20, the City received $93,939; in Fiscal Year 2020-21, the City received $58,864.19; and for this fiscal year, the City has received $70,438 to date.

Services Funded by Grants, Other Outside Sources, and Special Funds Expenditures Relating to Homelessness Cost Funding Source Quality of Life Officer $200,000/yr. Housing Successor Agency PATH $50,000/yr. Housing Successor Agency
DMH MET team no costs
Harbor Interfaith $68,000/yr. County CDBG funds
Harbor Interfaith COVID related expenses $28,400 one time CDBG Cares Act Redondo Beach Homeless Court $42,000/1 yr. County CDBG funds Special Services (i.e. CLEAR recovery, etc.) $150,000/18 mos. SBCCOG Innovation Grant Wilmington SRO's $94,750/18 mos. SBCCOG Innovation Grant Expansion of Homeless Court to Hermosa
Beach $61,549/18 mos. SBCCOG Innovation Grant
Pallet Shelter $18,884/mo. CDBG funds
HOST $70,438 to-date in 2022 Measure H
TOTAL $784,021
City expenses funded by the General Fund
As part of the Fiscal Year 2021-22 budget, the City Council made the Enhanced Response to Homelessness Program permanent, which included extending City Net’s contract another year, another census of Redondo’s homeless population, hiring a fulltime Housing Navigator who needs a City vehicle, and hiring a part-time clerical assistant for homeless related administration. Lila Omura, the City’s Homeless Housing Navigator, was hired on January 3, 2022. Ms. Omura gets reports, calls and texts on a daily basis, including after hours and on weekends. Since then, she has received over 30 requests from the Mayor and City Council collectively. She receives at least four requests a week from the Police Department. She also gets requests for assistance from the Library, Code Enforcement, Ericka Gonzalez – the City’s Domestic Violence Advocacy Coordinator – for domestic violence victims, the Salvation Army, and Beach Cities Health District.

At midyear of the current fiscal year, the City Council approved ongoing appropriations for the rental of electrical poles and sanitation facilities at the Pallet Shelter in the amount of $21,781 a year to the General Fund.

Ongoing Expenditures Relating to Homelessness Cost Funding Source City Net Services, including Census $170,000/yr. General Fund Homeless Housing Navigator $126,500/yr. General Fund
Annual costs for City Vehicle $4,200/yr. General Fund
BRR #44

Page 4 of 5 ends

PT Clerical for homeless issues $33,586/yr. General Fund Shelter rental of electrical poles and sanitation $21,781/yr. General Fund Total $356,067
Public Works responds to miscellaneous removal of materials abandoned by people experiencing homelessness as well as cleanups of large encampments, trash and debris.

Miscellaneous materials removal requires one Maintenance Worker and takes approximately two hours for removal. Based on the Master Fee Hourly Rate of $103.48 an hour, one incident of miscellaneous materials removal costs the City about $206.96 per incident. Large cleanups of encampments, trash and debris may involve four maintenance workers and takes approximately four hours. Based on the Master Fee Hourly Rate of $413.92, one incident of a large cleanup costs the City about $1,655.69 per incident. A dispatch report for the last year shows about 222 total calls for service for Public Works, and about half of those calls are estimated to be related to homeless issues. Estimating the actual costs of Public Works Calls for Service is difficult given that Public Works Calls for Services are not coded or differentiated. The City might get an annual average of ten large cleanup calls for encampments, trash and debris for locations such as the 405 freeway on-ramp or the Harbor area. An annual estimate of costs for Public Works based on those assumptions would be approximately $39,529.36.

Public Works Call
Out Incident Type
Crew
Size
Needed
Master Fee
Hourly
Rate
Standard
Job
Length
Grand
Total per
Incident
Avg.

Incidents
Per Year
Est. PW
Expenditures -
Homelessness
Miscellaneous
Materials Removal 1 $103.48 2 $206.96 111 $22,972.56
Large
Encampment/
Trash/Debris
Cleanup
4 $413.92 4 $1,655.68 10 $16,556.80
Total $39,529.36
The Fire Department responds to both medical and public safety calls for service. The Fire Department started tracking patients experiencing homelessness on September 21, 2021 through screening questions. From September to December of 2021, there were a total of 176 patients with documentation answering “yes” to the homeless screening question. From January to June 13, 2022, there were a total of 275 patients with documents answering “yes” to the homeless screening question. Unfortunately, it will be impossible to collect accurate data prior to the implementation of this indicator in September 2021, but based on this data, it can be roughly estimated that the Fire Department responds to approximately 550 patients experiencing homelessness a year.

The Fire Department responded to a total of 4,456 calls for service in 2018, 4,398 in 2019, 4,014 in 2020 and 4,646 in 2021. 550 is approximately 12% of the total calls in 2021.

With 58 sworn personnel each working 2,912 hours a year, there is a total of 168,896 BRR #44

Page 5 of 5 ends

total sworn personnel hours a year. Twelve percent of that is 20,268 hours.

Hypothetically, that number multiplied by an average rate of $45.00 an hour is $912,038 for the 2021 calendar year.

Estimated Fire Department Expenditures
Relating to Homelessness Cost Funding Source
Fire Department Response to Calls for Service $912,038/yr. General Fund The Police Department takes a proactive approach in dealing with homelessness as evidenced by the number of calls for service related to homelessness. In 2021, there were 4,477 calls for service to the Police related to homeless issues, approximately 6% of the total calls for service. In 2020, there were 4,241 calls for service related to homeless issues, approximately 7% of the total calls for service. In 2019, there were 4,171 calls for service related to homeless issues, approximately 6% of the total calls for service. Please note these are only the calls that are initially tagged “Homeless” and do not capture every call for service that is related to homelessness.

Year
Month Total CFS
-
Homeless
Total
CFS
Homeless
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec CFS %
2021 393 371 367 328 378 347 447 393 344 383 400 326 4477 69596 6% 2020 343 280 287 338 328 294 371 437 400 442 386 335 4241 60721 7% 2019 383 290 264 328 355 405 480 351 349 367 311 288 4171 69596 6% Each year, as part of the budget process, a Police Captain reports an estimated time of total patrol hours under Performance Measures. For Fiscal Year 2020-21, there was an estimate of 118,000 total patrol hours, and 114,400 hours for Fiscal Years 2019-20 and 2018-19. Six percent (6%) of 118,000 is 7,080 hours of patrol time dedicated to homelessness in Fiscal Year 2020-21. Hypothetically, that number multiplied by an average hourly fully-loaded police officer rate of $89.00 is $630,120 for the 2021 calendar year.

Estimated Police Department Expenditures Relating
to Homelessness Cost Funding Source
Quality of Life Officer $15,000/yr. General Fund
Police Department Response to Calls for Service $630,120/yr. General Fund Total $645,120
BRR #45

Page 1 of 2 ends

CITY OF REDONDO BEACH
Budget Response Report #45
June 14, 2022
Question:

What is the total estimated cost to design and install drought tolerant landscaping, pathways, and a pollinator fountain on the SCE right-of-way property licensed by the City, west of Pacific Coast Highway?
Response:

The City’s current strategic plan includes an item to bring forward a conceptual plan for beautification and habitat restoration on the SCE right-of-way parcel, west of Pacific Coast Highway, recently licensed by the City. In preparation for that report, staff has engaged an on-call landscape architect and asked for some visioning documents regarding certain topics for future discussion such as grading and trails, planning scheme/palettes, accessibility, irrigation, signage, etc. While those plans have not been formally presented yet, the attachments include a portion of the Illustrative Site Analysis prepared by the consultant. Staff has also asked for high level budget numbers from the consultant (see attached).

The consultant’s overall price estimate for construction costs to improve the roughly five acre parcel is about $1.37M. That price includes material and construction costs (detailed on the attachment), as well as a 15% contingency and a 30% premium for prevailing wage, which the City is required to pay. The resulting cost is about $277,000 per acre, or $6.35 square foot. By comparison, the cost to install improvements to the two parcels of SCE right-of-way adjacent to Artesia Boulevard cost about $450,000 per acre. That work, however, included a parking area, solar lighting, and more decorative plant landscapes. An additional 5% is included in the grand total of $1.44M to include soft costs associated with design and construction administration.

An additional request was made to include pollinator fountains, which are small water features that function to allow water collection by various insects and birds. Anything large scale would likely not be permitted by SCE. The City’s license agreement with SCE prohibits installation of water storage tanks of any kind. However, there may be opportunity to add low profile water bubblers that could provide a similar function as part of the irrigation system and costs for these would be included in the general unit cost for irrigation included in the attached estimate.

BRR #45

Page 2 of 2 ends

Phased Approach
As an alternative, the City Council may wish to take a phased approach to completing the landscaping improvements on the right of way. For example, the Council may wish to initiate the work on the flatter eastern portion of the site, which is about 1.6 acres. Using the estimate provided by the consultant, improvements to this area could be performed for about $400,000 to $450,000. These figures include a scope of about 70,000 SF of planting area and temporary irrigation, and 12,000 SF of decomposed granite (DG) pathways. Currently there is about $138,000 available in the project account. Assuming the City Council wishes to proceed with the additional $312,000 appropriation needed to complete the work, staff would engage the consultant to prepare illustrative concepts to present to the City Council for preliminary consideration as part of the strategic planning objective and seek further direction on final design and follow up public outreach.

Funding for the additional $312,000 appropriation needed to fully install drought tolerant planting and pathways on the flatter, eastern portion of the SCE site is available in the Subdivision Park Trust (Quimby) Fund or from unallocated General Fund Balance.

Attachments
SCE ROW Improvements – Illustrative Site Analysis
SCE ROW Improvements – Cost Estimates
ATTACHMENT 45A

Page 1 of 4 ends

ARCHITERRA DESIGN GROUP

SCE COMMUNITY NATURE PARK

CITY OF REDONDO BEACH

OPINION OF PROBABLE CONSTRUCTION COSTS

ANDREW WINJE
Date: 06/09/2022
Created by: VALERIE ALEGRE

ITEM QUANTITY UNIT UNIT PRICE ITEM COST

LANDSCAPE CONSTRUCTION
•MOBILIZATION 1 ALLOW $35,000.00 $35,000.00
•DEMOLITION
Vegetation removal 126,000 S.F. $0.15 $18,900
Section Subtotal $18,900
•EARTHWORK/GRADING/SOIL PREPARATION
Soil Prep/Fine Grading 167,677 S.F. $0.60 $100,606
Section Subtotal $100,606
•SITE AMENITIES
Interpretive Display Signage with Supports 2 EA. $4,000.00 $8,000 Section Subtotal $8,000
LANDSCAPE CONSTRUCTION SUBTOTAL $162,506

LANDSCAPE PLANTING
•SHRUBS (167677sqft) 167,677
1 Gallon (80% at 1 per every 100sqft) 1,341 EA. $10.00 $13,414 5 Gallon (20% at 1 per every 100sqf) 335 EA. $28.00 $9,390 Hydroseed Areas 167,677 S.F. $0.14 $23,475
Section Subtotal $46,279
•MISCELLANEOUS
Decomposed Granite - 4" Compacted/Stabilized 30,090 S.F. $6.50 $195,585 Decomposed Granite - 6" On Roadside SCE Access 8,473 S.F. $8.50 $72,021 Cobble Swale Protection at toe of slopes 9,585 S.F. $18.00 $172,530 Section Subtotal $440,136
LANDSCAPE PLANTING SUBTOTAL $486,414

LANDSCAPE IRRIGATION UNIT UNIT PRICE
Automatic On-Grade Irrigation System Temp - Slope Are 98,404 S.F. $1.35 $132,845 Automatic On-Grade Irrigation System Temp - Flat Areas 69,273 S.F. $1.35 $93,519 Section Subtotal $226,364
LANDSCAPE IRRIGATION SUBTOTAL $226,364
10221-A Trademark Street, Rancho Cucamonga, CA 91730
(909) 484-2800 Fax (909) 484-2802 Page 1 of 2
ATTACHMENT 45B

Page 1 of 3 ends

ARCHITERRA DESIGN GROUP

LANDSCAPE MAINTENANCE
90 Day Maintenance Period 167,677 S.F. $0.25 $41,919
Section Subtotal $41,919
LANDSCAPE MAINTENANCE SUBTOTAL $41,919
TOTAL $917,204
15% CONTINGENCY $137,581
30% Prevailing Wage $316,435
GRAND TOTAL $1,371,220
Cost per Square Foot 215,825 S.F. $6.35
Cost per Acre 4.95 AC $276,754
DESIGN FEES (AERIAL SURVEY, CDS, CONSTRUCTION ADMIN.)
Design Plans for Bidding (Estimated at 5% of construction costs) $68,560.98 GRAND TOTAL $1,439,781
10221-A Trademark Street, Rancho Cucamonga, CA 91730
(909) 484-2800 Fax (909) 484-2802 Page 2 of 2
ATTACHMENT 45B

Page 2 of 3 ends

SCE ROW Costs (Reduce Scope Based on Architerra Estimate) Qty Unit Unit Cost Total
Earthwork
Mobilization 1 Allow 10,000.00$          10,000$
Demo/clear&grub      69,723 SF             0.15$        10,458$ Grading/Soil Prep      69,723 SF             0.60$        41,834$ Site Amenities 0 EA 4,000.00$     $             ‐
Landscape Planting
1 Gallon (80% @ 1 per 100 sf)           558 EA 10.00$                    5,578$ 5 Gallon (20% @ 1 per 100 sf)           139 EA 28.00$                    3,904$ Hydroseed ‐            SF             0.14$ $             ‐ 90‐day maint period      69,723 SF             0.25$        17,431$ Pathways
DG ‐ 4" compacted/stabilized 12000 SF             6.50$        78,000$ DG ‐ 6" roadside SCE Access 0 SF             8.50$ $             ‐ Cobble swale protection 0 SF 18.00$           $             ‐ Irrigation
Automatic On‐grade Temp System
Slope Area 0 SF             1.35$ $             ‐
Flat Area      69,723 SF             1.35$        94,126$ Subtotal     261,331$
15% Contingency        39,200$
30% Prevailing Wage        78,399$
Construcion Grand Total     378,930$
Design Fees (5% of Constr)       18,947$
Grand Total     397,877$
Improvement Area
Flat Area      69,723 SF
Slope Area ‐            SF
Total      69,723 SF

1.60 Acres
ATTACHMENT 45B

Page 3 of 3 ends