Exhibit A - Community Development
Fee Description New Fee
Amount Prior Fee Amount Unit Fee
Last Modified Estimated Add'l Annual
Revenue
Planning Division Planning
Administrative Design Review
1. Single-Family, Additions, Commercial Remodels, Signs, Etc. No Charge No Charge Each 2020
2. New Development Containing 2-3 Units on a Lot 2,250.00 Plus 675.00 Per Unit 2,185.00 Plus 655.00 Per Unit Each 2020
3. Multi-Family Residential 2,250.00 Plus 675.00 Per Unit 2,185.00 Plus 655.00 Per Unit Each 2020
4. Non-Residential Under 10,000 Square Foot Floor Area 5295 5140 Each 2020
5. Non-Residential Over 10,000 Square Foot Floor Area 13300 12915 Each 2020
6. Review of Additions, Overlap Parking and/or Signs1 1110 1090 Each 2020
Appeals
7. Appeal of Decision by Director to Planning Commission2 540 525 Each 2020
8. Appeal of Administrative Design Review/Decision by Director to Planning Commission 540 525 Each 2020
9. Appeal of Administrative Design Review to Planning Commission for New Development Containing 2-3 Units on a Lot 720.00 Plus 720.00 Per Unit (To be Paid by Applicant) 700.00 Plus 700.00 Per Unit (To be Paid by Applicant) Each 2020
10. Appeal of Planning Commission Decision to City Council 25% of Original Application Fee to a Max of 500.00 25% of Original Application Fee to a Max of 500.00 Each 2020
11. Business License Administrative Appeal 540 525 Each 2020
Change of Land Use District/Zoning Map Amendment
12. Property Outside City's Coastal Zone 5400 5245 Each 2020
13. Property Within City's Coastal Zone 7885 7655 Each 2020
Coastal Development Permit
14. Public Hearing Waiver3 335 325 Each 2020
15. Public Hearing 1575 1530 Each 2020
Conditional Use Permit
16. Category 1 - All Uses Except Multi-Family Residential 3145 3055 Each 2020
17. Category 2 - Multi-Family Residential and Condominium Projects 3,147.00 Plus 1,318.00 Per Unit 3,055.00 Plus 1,280.00 Per Unit Each 2020
18. Category 3 - Condominium Conversion 3,147.00 Plus 1,318.00 Per Unit 3,055.00 Plus 1,280.00 Per Unit Each 2020
19. Development Agreement Actual Cost Actual Cost Each 2020 Planning Environmental Review Fees
20. Initial Study and Negative Declaration 2,030.00 plus Contract Cost 1,970.00 plus Contract Cost Each 2020
21. Initial Study and Mitigated Negative Declaration 2,255.00 plus Contract Cost 2,190.00 plus Contract Cost Each 2020
22. Environmental Impact Report (EIR) Actual Cost plus 2,255 adminstrative cost Actual Cost Each 2020
23. Contract Administration Charge for EIR Consultant Actual Cost Actual Cost Each 2020
24. Supplemental Fee for Environmental Analysis Based on Prior EIR or Master/Program EIR 1800 1750 Each 2020
Plan Check Fees4
25. New Development 50% of Building Permit Fee 50% of Building Permit Fee Each 2020
26. Additions of Floor Area to Existing Development 50% of Building Permit Fee 50% of Building Permit Fee Each 2020
27. Commercial Tenant Improvements 10% of Building Permit Fee 110 Each 2020
28. Structures Other Than Buildings (e.g., Fences, Walls, Signs) 110 110 Each 2020
Planned Development Review
29. In Conjunction With Establishment of Overlay Zone5 5400 5245 Each 2020
30. In Conjunction With Establishment of Overlay Zone Within the City's Coastal Zone5 7885 7655 Each 2020
31. Addition/Substantial Alteration to an Existing Development6 1575 1530 Each 2020
Planning Commission Design Review
Review of New Construction
32. Multi-Family Residential 3150 3060 Each 2020
33. Non-Residential Under 10,000 Square Foot Floor Area 3150 3060 Each 2020
34. Non-Residential 10,000 - 49,999 Square Foot Floor Area 12600 12300 Each 2020
35. Non-Residential 50,000 Square Foot or More Floor Area 25300 24600 Each 2020
36. Planning Re-Inspection Fee 225 220 Each 2020
37. Pre-Application Fee8 No Change 695 Each 2020
Prior Discretionary Approval
38. Amendment 1575 1530 Each 2020 Planning
39. Extensions9 675 655 Each 2020
Subdivisions
40. Parcel Map 1575 1530 Each 2020
41. Tract Map 2440 2370 Each 2020
42. Lot Line Adjustment 1575 1530 Each 2020
Other Planning Fees
43. Variance 3150 3060 Each 2020
44. Modification 900 875 Each 2020
45. Administrative Use Permit (AUP) Fee for Personal Improvement Services 1650 1530 Each 2020
46. Wireless Telecommunications Facilities Supplemental Application 3,150.00 Plus 1,310.00 Per Supplemental Application 3,060.00 Plus 1,275.00 Per Supplemental Application Each 2020
47. Zoning Compliance Report 225 220 Each 2020
48. Planning/Zoning Code W/Cover 0.17 0.16 Each 2020
49. Planning/Zoning Code Yearly Supplements 0.17 0.16 Each 2020
50. General Plan 53 52 Each 2020
51. Harbor/Civic Center Specific Plan 17 16 Each 2020
52. Temporary Use Permit 225 220 Each 2020
53. Temporary Use Permit for Watersport Instruction and Equipment Rental No change 1000 Each/Per Month 2020
54. Temporary Banners - Private Property 70 68.00 Plus 200.00 Refundable Deposit Each 2020
Massage Permit Application Fee
55. Business Location 275 265 Each 2020
Entertainment Permit
56. Level I 360 350 Each 2020
57. Level II 790 765 Each 2020
58. Renewal - Level I and Level II 200 195 Each 2020
Tobacco Retail Permits
59. Tobacco Retail Permit No Change 250 Each 2020
Planning
Preservation Fees
60. Landmark Designation or District Addition No Change No Fee Each 2020
61. Certificate of Appropriateness- Restoration or Addition No Change No Fee Each 2020
62. Mills Act Contracts No Change No Fee Each 2020
63. Historic Variance 2500 2445 Each 2020
64. Certificate of Appropriateness - Demolition or List Removal 5000 4930 Each 2020
Plan and Data Maintenance Fees
65. General Plan No Change 100,000.00 Per Year - 1.70 Per 1,000.00 Valuation Each 2020
1. Building Division Building
Miscellaneous Fees/Charges
1. Address Change No change 995 Each 2020
2. Certificate of Occupancy Included in Permit Fee Included in Permit Fee Each 2020
3. Certificate of Occupancy (Temporary) Included in Permit Fee Included in Permit Fee Each 2020
4. Appeals of Administrative Decision Board of Appeals "Uniform Codes, Disabled Access Appeals Board" 600 580 Each 2020
5. Deputy Inspector Certification Registration 170 165 Each 2020
6. Grading Refundable Bond Each 2020
7. Job Card Replacement 108 105 Each 2020
8. Report of Residential 135 130 Each 2020
9. Report of Residential - Expedited Additional Fee 210 205 Each 2020
10. State Energy Plan Check Fee No change 25% of Building Check Fee as Allowed by Section 25402.0 of Public Resources Code Each 2020
11. Construction Site Sign 88 85 Each 2020
Inspection Fees
12. Inspection Outside Normal Business Hours (Minimum 2 - Hour Charge) 125 120 Per Hour 2020 Building
13. Re-Inspection Fees Assessed Under Provisions of Section 305(G) 195 190 Flat Rate 2020
14. Inspections for Which No Fee is Indicated (Minimum 1 - Hour Charge) 180 175 Per Hour 2020 Plan Check/Review Fees1
15. Plan Review Fee/Plan Review Revision Fee 100% of Building Permit Fee and for Revisions 133.00 Per Hour 100% of Building Permit Fee and for Revisions 130.00 Per Hour Each 2020
16. Plan and Permit Retention Fee No change 1.2 Per Page 2020
17. Accelerated Plan Review No change 50% of Plan Check Fee Each 2020
18. Disability Plan Review and Permit Fees No change 10% of Building Permit Fee Each 2020
19. 50 Cubic Yards or Less 139 135 Each 2020
20. 51 to 100 Cubic Yards 210 205 Each 2020
21. 101 to 1,000 Cubic Yards 350 340 Each 2020
22. 1,001 to 10,000 Cubic Yards 445 430 Each 2020
23. 10,001 to 100,000 Cubic Yards 445.00 for the First 10,000 Cubic Yards Plus 139.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof 430.00 for the First 10,000 Cubic Yards Plus 135.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof Each 2020
24. 100,001 to 200,000 Cubic Yards 1,696.00 for the First 100,000 Cubic Yards Plus 95.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof 1,665.00 for the First 100,000 Cubic Yards Plus 92.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof Each 2020
25. 200,001 Cubic Yards or More 2,646.00 for the First 200,000 Cubic Yards Plus 95.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof 2,500.00 for the First 200,000 Cubic Yards Plus 92.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof Each 2020 Plan Check Fees
26. Electrical Plan Check Fee (1 Hour Minimum) 100% of Electrical Permit Fee or 133.00/Hour 100% of Electrical Permit Fee or 130.00/Hour Each 2020
27. Mechanical Plan Check Fee (1 Hour Minimum) 100% of Mechanical Permit Fee or 133.00/Hour 100% of Mechanical Permit Fee or 130.00/Hour Each 2020
28. Plumbing Plan Check Fee (1 Hour Minimum) 100% of Plumbing Permit Fee or 133.00/Hour 100% of Plumbing Permit Fee or 130.00/Hour Each 2020 Building
Permits
Miscellaneous Permits
29. After Hours Permit 80 78 Each Day 2020
30. Building Moving Permit (Within City, to City or From City) 925 897 Each 2020
Demolition Permit
31. Single Family Building 140 135 Each 2020
32. Accessory Building to Single Family Building 113 110 Each 2020
33. All Other Buildings 195 189 Each 2020
34. Transfer Fee Permit (In Addition to Issuance Fee) 27 26 Each 2020 Building Permits
Total Valuation
35. $ 1 to 500 54 52 Each 2020
36. $ 501 to 2,000 54.00 for First 500 + 8.25 for Each Addl 100 or Fraction Thereof 52.00 for First 500 + 8.00 for Each Addl 100 or Fraction Thereof Each 2020
37. $ 2,001 to 25,000 178.00 for First 2,000 + 23.69 for Each Addl 1,000 or Fraction Thereof 160.00 for First 2,000 + 23.00 for Each Addl 1,000 or Fraction Thereof Each 2020
38. $ 25,001 to 50,000 723.00 for First 25,000 + 18.50 for Each Addl 1,000 or Fraction Thereof 685.00 for First 25,000 + 18.00 for Each Addl 1,000 or Fraction Thereof Each 2020
39. $ 50,001 to 100,000 1,186.00 for First 50,000 + 13.50 for Each Addl 1,000 or Fraction Thereof 1,113.00 for First 50,000 + 13.00 for Each Addl 1,000 or Fraction Thereof Each 2020
40. $ 100,001 to 500,000 1,861.00 for First 100,000 + 11.50 for Each Addl 1,000 or Fraction Thereof 1,715.00 for First 100,000 + 11.00 for Each Addl 1,000 or Fraction Thereof Each 2020
41. $ 500,001 and Up 6,461.00 for First 500,000 + 8.25 for Each Addl 1,000 or Fraction Thereof 5,800.00 for First 500,000 + 8.00 for Each Addl 1,000 or Fraction Thereof Each 2020
42. Combination Permit for Residential Owner/Builder When Valuation Is Less Than $20,000.002 No Issuance Fee for Plumbing, Electrical and Mechanical Permits No Issuance Fee for Plumbing, Electrical and Mechanical Permits Permit 2020 Building
Electrical Permits
43. Issuance Fee 54 52 Each 2020
System Fee Schedule
New Residential Buildings
44. Multi-Family (Apts and Condos) - If Building Has Three or More Living Units, Not Including Garage, Carports and Other Non-Commercial Auto Storage Areas Constructed at the Same Time. 0.19 0.18 Per Sq. Ft. 2020
45. Single and Two-Family - If Building Has One or Two Living Units, Not Including Garage, Carport and Other Minor Accessory Constructed at the Same Time. 0.19 0.18 Per Sq. Ft. 2020
46. Others - Other Types of Residential Occupancies and Alterations, Additions and Modifications to Existing Residential Structures. 0.23 0.22 Per Sq. Ft. 2020 Private Swimming Pools
47. For New Private, Residential (Single and Multi-Family) In-Ground Pools, Including a Complete System of Necessary Branch Circuit Wiring, Bonding, Grounding, Underwater Lighting, Water Pumping and Related Electrical Equipment. 116 113 Each 2020
48. For Other Types of Swimming Pools, Therapeutic Whirlpools, Spas and Alterations to Existing Swimming Pools. See Unit Fee Schedule See Unit Fee Schedule See Unit Fee Schedule 2020
49. Solar Electric Panel - Residential 295 286 Each 2020
50. Solar Electric Panel - Commercial 890 866 Each 2020 Carnivals and Circuses3 2020
51. Electric Generators and Electrically Driven Rides 72 70 Each 2020
52. Electrical Lighting for Mechanically Driven Rides and Walk - Through Attractions 16.5 16 Each 2020
53. Area and Booth Lighting System 16.5 16 Each 2020 Building
Temporary Power Service
54. Temporary Power Service Pole or Pedestal, Including All Pole or Pedestal Mounted Receptacle Outlets and Appurtenances 46 45 Each 2020
55. Temporary Distribution System and Temporary Lighting and Receptacle Outlets for Construction Sites, Decorative Light, Christmas Tree Sale Lots, Firework Stands, Etc. 23 22 Each 2020
Electrical Permits (Continued)
Power Apparatus4
Items Rating in HP/ KW
56. Up to 1 16.5 16 Each 2020
57. Over 1 and Not Over 10 41 40 Each 2020
58. Over 11 and Not Over 50 70 68 Each 2020
59. Over 51 and Not Over 100 139 135 Each 2020
60. Over 101 205 200 Each 2020
Items Rating In KVA/KVAR
61. E53 Transformer < 75 KVA 41 40 Each 2020
62. E54 Transformer > 75 KVA 70 68 Each 2020
63. Busways - for Trolley and Plug-in Type Busways5 16.5 16 Each 2020
Signs, Outline Lighting and Marquees
64. Supplied From One Branch Circuit 45 44 Each 2020
65. Additional Branch Circuits W/I the Same Sign, Outline Lighting System or Marquee Services 16.5 16 Each 2020 Services 2020
66. 600 Volts or Less and Not Over 200 Amperes in Rating 54 52 Each 2020
67. 600 Volts or Less and Over 200 Amperes to 1,000 Amperes in Rating 155 150 Each 2020
68. Over 600 Volts or Over 1,000 Amperes in Rating 293 285 Each 2020
69. Miscellaneous Apparatus, Conduits and Conductors for Which a Permit is Required But No Fee is Set Forth. (This Fee is Not Applicable When a Fee is Paid for One or More Services, Outlets, Fixtures, Appliances, Power Apparatus, Busways, Signs or Other Equipment) 35 34 Each 2020 Building
Elevator Permits
New Installations6
Passenger or Freight Elevator, Escalator, Moving Walk
70. Up to and Including $40,000 Valuation 540 525 Each 2020
71. Over $40,000 Valuation 540.00 Plus 9.50 for Each 1,000.00 or Fraction Thereof Over 40,000.00 525.00 Plus 9.00 for Each 1,000.00 or Fraction Thereof Over 40,000.00 Each 2020
Dumbwaiter or Private Residence Elevator
72. Up to and Including $10,000 of Valuation 70 68 Each 2020
73. Over $10,001 Valuation 70.00 Plus 9.50 for Each 1,000.00 or Fraction Thereof Over 10,000.00 68.00 Plus 9.00 for Each 1,000.00 or Fraction Thereof Over 10,000.00 Each 2020
Unit Fee Schedule (The Following Do Not Include Permit Issuance Fees) Lighting Fixtures, Sockets or Other Lamp-Holding Device
74. First 20 3.25 3 Each 2020
75. Additional Fixtures 1.6 1.5 Each 2020
76. Pole or Platform-Mounted Lighting Fixtures 3.25 3 Each 2020
77. Theatrical-Type Lighting Fixtures or Assemblies Each 2020 Receptacle, Switch and Lighting Outlets at Which Current is Used or Controlled- Except Service Feeders and Meters
78. First 20 3.25 3 Each 2020
79. Additional Outlets 7,8 1.6 1.5 Each 2020
80. Residential Appliances or Receptacle Outlets for Same, Including Wall-Mounted Electric Ovens, Ranges, Console or Through-Wall Air Conditioners, Space Heaters, Food Waste Grinders, Dishwashers, Washing Machines, Water Heaters, Clothes Dryers, Etc. (Includes Motor Operated Appliances Not Exceeding 1HP Rating) 16.5 16 Each 2020
81. Non-Residential Appliances and Self-Contained Factory-Wired, Non-Residential Appliances Not Exceeding 1HP, Kilowatt, or Kilovolt-Ampere in Rating (Includes Medical and Dental Devices; Food, Beverage, and Ice Cream Cabinets; Illuminated Showcases; Drinking Fountains; Vending Machines, Laundry Machines or Other Similar Types of Equipment) 16.5 16 Each 2020 Building
Grading Permits9
82. 50 Cubic Yards or Less 145 140 Each 2020
83. 51 to 100 Cubic Yards 145 140 Each 2020
84. 101 to 1,000 Cubic Yards 145.00 for the First 100 Cubic Yards Plus 48.00 for Each Addl 100 Cubic Yards or Fraction Thereof 140.00 for the First 100 Cubic Yards Plus 47.00 for Each Addl 100 Cubic Yards or Fraction Thereof Each 2020
85. 1,001 to 10,000 Cubic Yards 577.00 for the First 1,000 Cubic Yards Plus 41.00 for Each Addl 1,000 Cubic Yards or Fraction Thereof 545.00 for the First 1,000 Cubic Yards Plus 40.00 for Each Addl 1,000 Cubic Yards or Fraction Thereof Each 2020
86. 10,001 to 100,000 Cubic Yards 946.00 for the First 10,000 Cubic Yards Plus 39.00 for Each Addl 10,000 Cubic Yards or Fraction Thereof 905.00 for the First 10,000 Cubic Yards Plus 38.00 for Each Addl 10,000 Cubic Yards for Fraction Thereof Each 2020
87. 100,001 or More Cubic Yards 1,297.00 for the first 100,000 cubic yards plus 36.00 for each addl 10,000 cubic yards or fraction thereof 1,247.00 for the first 100,000 cubic yards plus 35.00 for each addl 10,000 cubic yards or fraction thereof Each 2020 Mechanical Permits
88. Issuance Fee 56 55 Each 2020
System and Unit Schedule
89. Air-Handling Unit, Up to and Including 10,000 Cubic Feet Per Minute, Including Ducts Attached Thereto 27 26 Each 2020
90. Air-Handling Unit Over 10,000 CFM 35 34 Each 2020
91. Appliance Vent - Installation, Relocation or Replacement, Each and Not Included in an Appliance Permit 17.5 17 Each 2020 Building
92. Mechanical Exhaust Hood (Type I) 75 73 Each 2020
93. Mechanical Exhaust Hood (Type II) 33 32 Each 2020
94. Miscellaneous Appliances/Equipment/Electric/Gas 17.5 17 Each 2020
Boiler
95. 400,000 BTU/Hour or More 108 105 Each 2020
96. Less Than 400,000 BTU/Hour 67 65 Each 2020
97. FAU 100,000 BTU or Over 42 41 Each 2020
98. From 3 to 15 HP - 100,000 to 500,000 BTU 98 95 Each 2020
99. Boiler or Compressor13 Over 100,000 BTU/Hour and Including 500,000 BTU/Hour 103 100 Each 2020 100. Boiler or Compressor13 Over 15 HP to and Including 30 HP or Each Absorption System Over 500,000 BTU/Hour Up to and Including 1 Million BTU/Hour 111 108 Each 2020 101. Boiler or Compressor13 Over 30 HP to and Including 50 HP or Each Absorption System Over 1 Million BTU/Hour Up to and Including 1.75 Million BTU/Hour 142 138 Each 2020 102. Boiler or Compressor13 Over 50 HP or Each Absorption System Over 1.75 million BTU 209 203 Each 2020
103. Evaporation Cooler Other Than Portable Type 26 25 Each 2020
104. Furnace (Forced-Air or Gravity-Type)* Including Ducts and Vents Attached to Such Appliance, Up to and Including 100,000 BTU/Hour 48 47 Each 2020 105. Furnace (As Above) Over 100,000 BTU/Hour 67 65 Each 2020 106. Furnace - Including Vent 33 32 Each 2020
107. Heater (Suspended, Recessed Wall or Floor-Mounted Units) 33 32 Each 2020
108. Incinerator - Industrial Type 211 205 Each 2020
109. Repair of, or Alteration or Addition to Each Heating Appliance, Refrigeration Unit, Cooling Unit, Absorption Unit or Evaporative Cooling System, Including Installation of Controls Regulated by This Code 33 32 Each 2020 Building
110. Ventilation Fan Connected to a Single Duct 26 25 Each 2020 111. Ventilation System Which is Not a Portion of Any Heating or Air-Conditioning System Authorized by a Permit 26 25 Each 2020
112. Appliance or Equipment Not Regulated by This Code, But Not Classed in Other Appliance Categories, or for Which no Other Fee is Listed in This Code 26 25 Each 2020 113. New Multi-Family 0.2 0.19 Sq. Ft 2020
114. New One or Two Family 0.2 0.19 Sq. Ft 2020
115. Other Residential Addition, Alteration, Etc. 0.26 0.25 Sq. Ft 2020
Plumbing Permits
116. Issuance Fee 54 52 Each 2020
117. Abandoned Cesspool / Cap Sewer 154 150 Each 2020
118. Automatic Washer 23 22 Each 2020
119. Bar Sink 23 22 Each 2020
120. Bathtub 23 22 Each 2020
121. Bidet 23 22 Each 2020
122. Cesspool (Where Permitted) 116 113 Each 2020
123. Dishwasher (No Permit Required for Repair or Replacement) 23 22 Each 2020 124. Dishwasher - Commercial / Garbage Disposal 31 30 Each 2020 125. Drinking Fountain 23 22 Each 2020
126. Fixture/Trap/Set of Fixtures on One Trap (Including Water, Drainage Piping, and Backflow Protection) 26 25 Each 2020 127. Floor Drain / Floor Sink 23 22 Each 2020
128. Gas Piping System of One to Four Outlets 16.5 16 Per Outlet 2020 129. Gas Piping System of Five or More Outlets 14.5 14 Per Outlet 2020 130. Grease Trap / Interceptor / Clarifier 54 52 Each 2020 131. Kitchen Sink / Kitchen Sink With Garbage Disposal 23 22 Each 2020 132. Laundry Tub or Tray 23 22 Each 2020
133. Lavatory 23 22 Each 2020
134. Miscellaneous 23 22 Each 2020
135. Miscellaneous Electric 16.5 16 Each 2020
136. Pool / Spa / Heater / Filter System 62 60 Each 2020 137. Private Sewer Disposal System 152 149 Each 2020 Building 138. Rainwater Systems (Inside Building) 28 27 Per Drain 2020 139. Repair / Alter Vent Drain Sewer 23 22 Per Drain 2020 140. Repipe Per Fixture - First 10 (Each) 3.25 3 Per Drain 2020 141. Repipe Per Fixture - 11 and Over 1.75 1.5 Per Drain 2020
Sewer
142. Building and Trailer Park - Each 93 90 Per Drain 2020 143. Disposal System 209 203 Per Drain 2020
144. Ejector 58 56 Per Drain 2020
145. Capping 190 184 Per Drain 2020
146. Shower 23 22 Per Drain 2020
147. Solar Plumbing Fee 70 68 Per Drain 2020
148. Shower Pan Replacement 30 29 Per Drain 2020
149. Sink - Commercial 41 40 Per Drain 2020
150. Sprinkler (Lawn) on Any One Meter, Including Backflow Protection Devices 31 30 Per Drain 2020 151. Urinal 31 30 Per Drain 2020
Vac Breakers
152. Atmospheric - First 10 (Each) 3 2.9 Per Drain 2020 153. Atmospheric - 11 and Over (Each) 1.75 1.5 Per Drain 2020 154. Pressure Type - First 10 (Each) 8 7.5 Per Drain 2020 155. Pressure Type - 11 and Over (Each) 5 4.5 Per Drain 2020 156. Reduce Pressure Prin - First 10 (Each) 23 22 Per Drain 2020 157. Reduce Pressure Prin - 11 and Over (Each) 13.5 13 Per Drain 2020 158. Vent Piping and Drainage Repair or Alteration 16.5 16 Per Fixture 2020 159. Water Closet 23 22 Each 2020
160. Water Heater Replacement 23 22 Each 2020
161. Water Heater (New) 41 40 Each 2020
162. Water Piping and / or Water-Treating Equipment (Installation / Alteration / Repair) 23 22 Each 2020
New Residential Building
163. Multi-Family 0.19 0.18 Sq. Ft. 2020
164. Single Family and Two Family 0.19 0.18 Sq. Ft. 2020 Building 165. Other Residential Alterations, Additions, Etc. 0.22 0.21 Sq. Ft. 2020 Estimated Total Additional Annual Revenue - Community Development Department 122750 Planning Division
1 Fee Waived for Signs When in Conjunction With a Cup Application - No Longer Needs Planning Commission Review 2 Not Applicable to Appeal of New 2-3 Unit Residential Development 3 If a Public Hearing is Requested, Applicant Must Pay the Balance of the Public Hearing Fee 4 Fee Not Accessed for Minor Plan Checks Performed at the Public Counter That Require Less Than 15 Minutes of Planning Staff Review Time on an Applicant Initial Visit.
All Plan Check Reviews Requiring Submittal to the Planning Department's Formal Plan Check Review Process Will Require Payment of Fees Commensurate With the Scope and Complexity of the Project 5 Fee Waived for Zoning Map Amendment and for Planning Commission Design Review 6 Fee Waived for Planning Commission Design Review
8 Fee Credited Toward Other Application Fees If Project Application is Submitted. 9 No Additional Fee Charged for Extensions of Multiple Approvals in Conjunction With the Same Project.
Building Division
1 Additional Plan Review Required By Changes, Additions and/or Revisions to Approved Plans (1/2 Hour Minimum) 2 No Combination Permit Will Be Issued If Construction Starts Without Proper Permit 3 Applies to Carnivals, Circuses or Other Traveling Shows or Exhibitions Using Transportable-Type Rides, Booths, and/or Attractions. 4 Includes Motors Generators, Transformers, Rectifiers, Synchronous Converters, Capacitors, Industrial Heating, Air Conditioning and Heat Pumps, Cooking or Baking Equipment. • for Equipment or Appliances Having More Than One Motor, Transformer, Heater, Etc., the Sum of the Combined Ratings May Be Used. Fees Include Switches, Circuit Breakers Contacts, Thermostats, Relays and Other Directly Related Controls 5 An Additional Fee Will Be Charged for Lighting Fixtures, Motors and Other Appliances That are Connected to Trolley and Plug-In Type Busways. No Fee is Required for Portable Tools. 6 Installation Fees Include the First Year's Annual Inspection Fee and Charges for Electrical Equipment or Conveyance Side of Disconnect Switch 7 For Multi-Outlet Assemblies, Each 5 Feet or Fraction Thereof is Considered as One Outlet 8 For Other Types of Air Conditioners and Other Motor-Driven Appliances With Larger Electrical Ratings, See "Power Apparatus" 9 The Fee for a Grading Permit Authorizing Addional Work to That Under a Valid Permit Shall Be:
• The Difference Between the Fee Paid for the Original Permit and the Fee Shown for the Entire Project or • The Total Cost to the Jurisdiction, Whichever is Greater. • The Cost Shall Include Supervision, Overhead , Equipment, Hourly Wages and Fringe Benefits of the Employees Involved 12 This Fee Shall Not Apply to an Air Handling Unit Which is a Portion of a Factory-Assembled Appliance for Which a Permit is Required Elsewhere in This Code. 13 Installation or Relocation