TRANSPORTATION CONSULTING ENGINEERS
211 Imperial Highway, Suite 208, Fullerton, CA 92835
(714) 992-4592 FAX (714) 992-2883 E-Mail: [email protected] MEMORANDUM July 11, 2022
To: Andrew Winje, P.E., City Engineer, City of Redondo Beach From: Ignacio Sanchez, P.E., Senior Transportation Engineer, AGA Engineers, Inc.

Subject: Artesia Boulevard Intersections Safety Improvements – Conceptual Design Plans Via the City’s Capital Improvement Program, the City of Redondo Beach has funded a project to improve safety at various intersections along Artesia Boulevard by improving the line of sight conditions for drivers making the eastbound and westbound left-turn movements. The improved line of sight is accomplished by modifying the alignment of eastbound and westbound left-turning lanes at five signalized intersections along Artesia Boulevard. The five intersections are as follows. - Artesia Boulevard at Aviation Way
- Artesia Boulevard at Green Lane
- Artesia Boulevard at Rindge Lane
- Artesia Boulevard at Mackay Lane
- Artesia Boulevard at Felton Lane
The City of Redondo Beach requested AGA Engineers, Inc. to prepare conceptual plans and develop an estimate of probable construction cost for proposed improvements. The proposed improvements include reduced width of raised medians for eastbound and westbound approaches, asphalt repairs, realignment of left-turn and through lanes, addition of buffers next to left turn pockets, lowering or abandonment of existing pull boxes on medians, and other appurtenant work, including minor signing and striping and traffic signal improvements.

In addition to the five study intersections, two intersections (traffic signals) along Artesia Boulevard: at Slauson Lane and at Vail Avenue, are also included in this assessment, but will only include minor traffic signal equipment improvements as no median work is proposed at these two intersections. The figure on next page shows the project location map.

Mr. Andrew Winje, P.E
July 11, 2022

Page 2 of 16 ends

All project intersections along Arteria Boulevard are currently signalized. Artesia Boulevard is classified as a major arterial and is also a truck route. The posted speed limit on Artesia Boulevard is 35 mph.

Artesia Boulevard is a four lane facility and there is an existing raised median on Artesia Boulevard at the project intersections. Protected/permissive left-turn traffic signal operation is utilized at all study intersections with the exception of Artesia Boulevard/Aviation Way, that intersection utilizes permissive left-turn phasing.

Field reviews were conducted to identify specific improvements at each of the project intersections.

Typical improvements at the five intersections along Artesia Boulevard include:
• Raised median modifications: reducing the width of the raised median, and realigning the leftturn pocket with a 4-foot right side buffer to improve the left-turning line of sight for the eastbound and westbound approaches.
• Implementing roadway striping modifications.
• Relocating the existing No-U-Turn signs for the eastbound and westbound traffic from the raised median to traffic signal mast-arm.
• Replacing left-turn vehicle detection loops with new loops as necessary, adjacent to the reconstructed median.
• Upgrading vehicle signal head and back plates.
• Upgrading to ADA compliant pedestrian push buttons as appropriate. • Replacing faded signs to current standards.
1 2 3 6 4 5
7 Mr. Andrew Winje, P.E
July 11, 2022

Page 3 of 16 ends

Exhibits showing available sight distance under existing conditions and with proposed median modifications are attached. With the proposed realignment of left-turn lanes on Artesia Boulevard, all five intersections will exceed expected sight distance.

At the two additional locations, both of which are T-intersections – Artesia Blvd/Slauson and Artesia Blvd/Vail Avenue, no median modification work is proposed at these two locations as left-turn lane is provided in only one direction and there is no impact to sight distance as there is no opposing left turn movement. Minor traffic signal upgrades are recommended at the two intersections.

The following exhibits show photographs of existing conditions along with typical proposed improvements at each intersection. Conceptual plans of proposed improvements are included for the five intersections where left-turn pockets will be realigned via median modifications. A typical curb median modification is included in the attachments. An order of magnitude cost estimate of proposed improvements is $776,000. Preliminary cost estimates of proposed improvements at each intersection are included in the attachments.

Upon receipt of City approval of the proposed improvements identified in this memorandum, AGA team will conduct topographical survey for median modifications, and prepare detailed engineering plans for the proposed improvements.

Mr. Andrew Winje, P.E
July 11, 2022

Page 4 of 16 ends

Artesia Boulevard at Aviation Way, Proposed Improvements:
- Raised median modifications
- Roadway striping modifications
- Install “No U-Turn” signs for eastbound and westbound traffic - Replace faded traffic signs

Exhibit 1-1. Artesia Boulevard at Aviation Way
Photographs of Existing Conditions
Artesia Boulevard
Existing west-leg raised median
and signs
Artesia Boulevard
Existing east-leg raised median
and signs
Signal equipment to be upgraded Pedestrian push-button to be upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 5 of 16 ends

– Left Turn Pocket Realignment
Mr. Andrew Winje, P.E
July 11, 2022

Page 6 of 16 ends

Artesia Boulevard at Green Lane, Proposed Improvements:
- Raised median modifications
- Roadway striping modifications
- Install “No U-Turn” signs for eastbound and westbound traffic - Replace faded traffic signs
- Upgrade vehicle signal heads and backplates
- Remove unused equipment
Exhibit 2-1. Artesia Boulevard at Green Lane
Photographs of Existing Conditions
Artesia Boulevard
Existing west-leg raised median
and sign
Artesia Boulevard
Existing east-leg raised median
and signs
Unused equipment to be removed Pedestrian push-button to be upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 7 of 16 ends

2-2. Artesia Boulevard at Green Lane
Conceptual Plan
– Left Turn Pocket Realignment
Mr. Andrew Winje, P.E
July 11, 2022

Page 8 of 16 ends

Artesia Boulevard at Rindge Lane, Proposed Improvements:
- Raised median modifications
- Roadway striping modifications
- Install “No U-Turn” signs for eastbound and westbound traffic - Replace faded traffic signs
- Upgrade vehicle signal heads and backplates
Exhibit 3-1. Artesia Boulevard at Rindge Lane
Photographs of Existing Conditions
Artesia Boulevard
Existing west-leg raised median
Artesia Boulevard
Existing east-leg raised median
Existing equipment to be upgraded
– evaluated during design phase
Pedestrian push-button sign to be
upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 9 of 16 ends

3-2. Artesia Boulevard at Ridge Lane
Conceptual Plan
– Left Turn Pocket Realignment
Mr. Andrew Winje, P.E
July 11, 2022

Page 10 of 16 ends

Artesia Boulevard at Mackay Boulevard, Proposed Improvements:
- Raised median modifications
- Roadway striping modifications
- Install “No U-Turn” signs for eastbound and westbound traffic - Replace faded traffic signs
- Upgrade vehicle head backplates
Exhibit 4-1. Artesia Boulevard at Mackay Boulevard
Photographs of Existing Conditions
Artesia Boulevard
Existing west-leg raised median
Artesia Boulevard
Existing east-leg raised median
Existing faded mast-arm sign to be
upgraded to latest standard
Pedestrian push-button sign to be
upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 11 of 16 ends

4-2. Artesia Boulevard at Mackay Boulevard
Conceptual Plan
– Left Turn Pocket Realignment
Mr. Andrew Winje, P.E
July 11, 2022

Page 12 of 16 ends

Artesia Boulevard at Felton Lane, Proposed Improvements:
- Raised median modifications
- Roadway striping modifications
- Install “No U-Turn” signs for eastbound and westbound traffic - Replace faded traffic signs
- Upgrade vehicle head backplates
Exhibit 5-1. Artesia Boulevard at Felton Lane
Photographs of Existing Conditions
Artesia Boulevard
Existing west-leg raised median
Artesia Boulevard
Existing east-leg raised median
Existing faded mast-arm sign to be
upgraded to latest standard
Existing equipment to be upgraded
– evaluated during design phase
Mr. Andrew Winje, P.E
July 11, 2022

Page 13 of 16 ends

5-2. Artesia Boulevard at Felton Lane
Conceptual Plan
– Left Turn Pocket Realignment
Mr. Andrew Winje, P.E
July 11, 2022

Page 14 of 16 ends

Artesia Boulevard at Slauson Lane, Proposed Improvements:
- Install “No U-Turn” sign for westbound traffic
- Install “No Left-Turn/U-Turn” sign for eastbound traffic - Replace faded traffic signs
- Upgrade vehicle head backplates
Exhibit 6-1. Artesia Boulevard at Slauson Lane
Photographs of Existing Conditions
Existing faded mast-arm sign to be
upgraded to latest standard
Existing faded pole sign to be
upgraded to latest standard
Existing signal equipment to be
upgraded
Pedestrian push-button sign to be
upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 15 of 16 ends

Artesia Boulevard at Vail Avenue, Proposed Improvements:
- Install “No U-Turn” sign for eastbound traffic
- Install “No Left-Turn/U-Turn” sign for westbound traffic - Replace faded traffic signs
- Upgrade vehicle head backplates
Exhibit 7-1. Artesia Boulevard at Vail Lane
Photographs of Existing Conditions
Existing faded mast-arm sign to be
upgraded to latest standard
Existing faded pole sign to be
upgraded to latest standard
Existing signal equipment to be
upgraded
Pedestrian push-button sign to be
upgraded
Mr. Andrew Winje, P.E
July 11, 2022

Page 16 of 16 ends

Attachments:
- Sight Distance Assessment
- Typical Curb Median Modification
- Order of Magnitude Cost Estimates
Sight Distance Assessment
Attachment
Attachment 1A. Artesia Boulevard at Aviation Way
Sight Distance – Existing
Attachment 1B. Artesia Boulevard at Aviation Way
Sight Distance with Proposed Left Turn Pocket Realignment Attachment 2A. Artesia Boulevard at Green Lane
Sight Distance –Existing
Attachment 2B. Artesia Boulevard at Green Lane
Sight Distance with Proposed Left Turn Pocket Realignment Attachment 3A. Artesia Boulevard at Ridge Lane
Sight Distance – Existing
Attachment 3B. Artesia Boulevard at Ridge Lane
Sight Distance with Proposed Left Turn Pocket Realignment Attachment 4A. Artesia Boulevard at Mackay Boulevard
Sight Distance – Existing
Attachment 4B. Artesia Boulevard at Mackay Boulevard
Sight Distance with Proposed Left Turn Pocket Realignment Attachments 5A. Artesia Boulevard at Felton Lane
Sight Distance – Existing
Attachments 5B. Artesia Boulevard at Felton Lane
Sight Distance with Proposed Left Turn Pocket Realignment Typical Curb Median Modification
Attachment
CURB MEDIAN DETAIL PROTECT IN PLACE AS NOTED. CLEANING AND GRUBBING (INCLUDES REMOVAL OF SIGNS, SHRUBS, LANDSCAPE.) CONSTRUCTION NOTES REMOVE EXISTING AND CONSTRUCT 6-INCH THICK ASPHALT PAVEMENT B (PG-64-10) OVER 4-INCH CMB TO 90% RC CONSRUCT 6 INCH PCC CURB PER SPPWC STD. PLAN 120-2. A1-6 (150) REMOVE AND DISPOSE EXISTING MEDIAN CURB AND PAVEMENT. COLD MILL 2-INCH EXISTING AC PAVEMENT CONSTRUCT 2-INCH AC PAVEMENT ARHM-CG-C (PG-64-16) ADJUST EXISTING WATER/GAS VALVE CAN/IRRIGATION METER BOX/PULL BOX COVER TO GRADE. RELOCATE EXISTING SIGN AND POLE.

Order of Magnitude Cost Estimates
Attachment
No. UNIT QTY AMOUNT ($)
1 LS 1 0.00 3,000.00
2 LS 1 0.00 4,000.00
3 EA 2 800.00 1,600.00
4 EA 2 900.00 1,800.00
5 EA 2 300.00 600.00
6 EA 2 500.00 1,000.00
7 EA 11 500.00 5,500.00
8 LS 1 1,000.00 1,000.00
9 LS 1 3,000.00 3,000.00
10 EA 5 1,000.00 5,000.00
11 EA 2 1,800.00 3,600.00
12 EA 8 500.00 4,000.00
13 EA 11 1,200.00 13,200.00
14 EA 4 400.00 1,600.00
1 LS 1 25,000.00 25,000.00
2 SF 750 20.00 15,000.00
3 LF 275 80.00 22,000.00
4 Ton 28 160.00 4,480.00
5 Ton 18 140.00 2,520.00
6 SF 520 0.40 208.00
7 Ton 16 130.00 2,080.00
8 EA 5 250.00 1,250.00
9 EA 2 1,000.00 2,000.00
10 LS 1 8,255.00 8,255.00
Artesia Blvd at Aviation Wy SUB TOTAL: 132,000
15% CONTINGENCIES: 19,800
TOTAL: 151,800
CALL: $152,000
Adjust existing Pull Box/ meter box//pull box cover to
grade.

Median Inspection and Construction Management
Relocate Existing Sign and Pole.

Furnish and install new sign
Remove sign and post
Replace backplates with new backplates with 2" reflective tape
Cold Mill 2-feet wide of 2-inch existing AC Pavement
Construct 2-inch AC Pavement ARHM-CG-C (PG-64-16)
3-12" Head (LED)
Remove and dispose existing median curb and concrete.

Construct 6 inch pcc curb per sppwc std. plan 120-2. A1-6 (150)
Construct 6-inch thick Asphalt Pavement B (PG-64-10)
Construct 4-inch thick Crushed Misc Base (CMB)
Pedestrian Push Button
Clearing and Grubbing (includes removal of Signs,
Shrubs, Landscape.)
Raised Median Reconstruction
Table 1. Order of Magnitude Cost Estimate - Artesia Blvd at Aviation Wy Roadway striping
Remove existing pull box
Furnish and install new pull box
Type E Loop (6' Round)
Remove existing striping
DESCRIPTION PRICE ($)
Signal Equipment Mobilization
Traffic Control
Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign and post
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,500.00
2 LS 1 4,000.00 4,000.00
3 EA 2 800.00 1,600.00
4 EA 2 900.00 1,800.00
5 EA 2 300.00 600.00
6 EA 2 500.00 1,000.00
7 EA 13 500.00 6,500.00
8 LS 1 1,000.00 1,000.00
9 LS 1 2,000.00 2,000.00
10 EA 4 1,000.00 4,000.00
11 EA 2 1,800.00 3,600.00
1 LS 1 25,000.00 25,000.00
2 SF 875 20.00 17,500.00
3 LF 280 80.00 22,400.00
4 Ton 33 160.00 5,280.00
5 Ton 20 140.00 2,800.00
6 SF 580 0.40 232.00
7 Ton 18 130.00 2,340.00
8 EA 6 250.00 1,500.00
9 EA 2 1,000.00 2,000.00
10 LS 1 10,693.00 10,693.00
Artesia Blvd at Green Ln SUB TOTAL: 117,000
15% CONTINGENCIES: 17,550
TOTAL: 134,550
CALL: $135,000
Relocate Existing Sign and Pole.

Median Inspection and Construction Management
Remove existing striping
DESCRIPTION PRICE ($)
Signal Equipment Mobilization
Traffic Control
Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign and post
Furnish and install new sign
Remove sign and post
Table 2. Order of Magnitude Cost Estimate - Artesia Blvd at Green Ln Cold Mill 2-feet wide of 2-inch existing AC Pavement
Construct 2-inch AC Pavement ARHM-CG-C (PG-64-16)
Adjust existing Pull Box/ meter box//pull box cover to
grade.

Raised Median Reconstruction
Clearing and Grubbing (includes removal of Signs,
Shrubs, Landscape.)
Remove and dispose existing median curb and concrete.

Construct 6 inch pcc curb per sppwc std. plan 120-2. A1-6 (150)
Construct 6-inch thick Asphalt Pavement B (PG-64-10)
Replace backplates with new backplates with 2" reflective tape
Roadway striping
Remove existing pull box
Furnish and install new pull box
Construct 4-inch thick Crushed Misc Base (CMB)
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,200.00
2 LS 1 4,000.00 4,000.00
3 EA 2 800.00 1,600.00
4 EA 2 900.00 1,800.00
5 EA 2 300.00 600.00
6 EA 2 500.00 1,000.00
7 EA 12 500.00 6,000.00
8 LS 1 1,000.00 1,000.00
9 LS 1 3,000.00 3,000.00
10 EA 4 1,000.00 4,000.00
11 EA 2 1,800.00 3,600.00
1 LS 1 25,000.00 25,000.00
2 SF 1,140 20.00 22,800.00
3 LF 420 80.00 33,600.00
4 Ton 43 160.00 6,880.00
5 Ton 27 140.00 3,780.00
6 SF 850 0.40 340.00
7 Ton 25 130.00 3,250.00
8 EA 6 250.00 1,500.00
9 EA 2 1,000.00 2,000.00
10 LS 1 11,341.00 11,341.00
Artesia Blvd at Rindge Ln SUB TOTAL: 138,000
15% CONTINGENCIES: 20,700
TOTAL: 158,700
CALL: $159,000
Table 3. Order of Magnitude Cost Estimate - Artesia Blvd at Rindge Ln Relocate Existing Sign and Pole.

Median Inspection and Construction Management 10%
Construct 6-inch thick Asphalt Pavement B (PG-64-10)
Construct 4-inch thick Crushed Misc Base (CMB)
Cold Mill 2-feet wide of 2-inch existing AC Pavement
Construct 2-inch AC Pavement ARHM-CG-C (PG-64-16)
Adjust existing Pull Box/ meter box//pull box cover to
grade.

Remove existing striping
DESCRIPTION PRICE ($)
Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign and post
Furnish and install new sign
Remove sign and post
Replace backplates with new backplates with 2" reflective tape
Signal Equipment Mobilization
Traffic Control
Construct 6 inch pcc curb per sppwc std. plan 120-2. A1-6 (150)
Roadway striping
Remove existing pull box
Furnish and install new pull box
Clearing and Grubbing (includes removal of Signs,
Shrubs, Landscape.)
Remove and dispose existing median curb and concrete.

Raised Median Reconstruction
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,000.00
2 LS 1 4,000.00 4,000.00
1 EA 2 800.00 1,600.00
2 EA 2 900.00 1,800.00
3 EA 2 300.00 600.00
4 EA 2 500.00 1,000.00
5 EA 12 500.00 6,000.00
6 LS 1 1,100.00 1,100.00
7 LS 1 3,000.00 3,000.00
8 EA 3 1,000.00 3,000.00
9 EA 0 1,800.00 0.00
10 LS 1 0.00 0.00
11 LS 1 0.00 0.00
12 LS 1 0.00 0.00
13 LS 1 0.00 0.00
1 LS 1 25,000.00 25,000.00
2 SF 1,260 20.00 25,200.00
3 LF 420 80.00 33,600.00
4 Ton 47 160.00 7,520.00
5 Ton 29 140.00 4,060.00
6 SF 900 0.40 360.00
7 Ton 27 130.00 3,510.00
8 EA 7 250.00 1,750.00
9 EA 2 1,000.00 2,000.00
10 LS 1 8,702.00 8,702.00
Artesia Blvd at MacKay Ln SUB TOTAL: 135,000
15% CONTINGENCIES: 20,250
TOTAL: 155,250
CALL: $155,000
Table 4. Order of Magnitude Cost Estimate - Artesia Blvd at Mackay Ln Remove existing striping
DESCRIPTION PRICE ($)
Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign and post
Furnish and install new sign
Remove sign and post
Replace backplates with new backplates with 2" reflective tape Signal Equipment Mobilization
Traffic Control
Raised Median Reconstruction
NPDES, SWPPP Plan and Implementation
Traffic Control
Mobilization
Roadway striping
Remove existing pull box
Furnish and install new pull box
Raised median reconstruction
Construct 4-inch thick Crushed Misc Base (CMB)
Construct 6-inch thick Asphalt Pavement B (PG-64-10)
Construct 6 inch pcc curb per sppwc std. plan 120-2. A1-6 (150)
Remove and dispose existing median curb and concrete.

Clearing and Grubbing (includes removal of Signs, Shrubs, Landscape.)
Median Inspection and Construction Management 10%
Relocate Existing Sign and Pole.

Adjust existing Pull Box/ meter box//pull box cover to grade.

Construct 2-inch AC Pavement ARHM-CG-C (PG-64-16)
Cold Mill 2-feet wide of 2-inch existing AC Pavement
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,000.00
2 LS 1 4,000.00 4,000.00
1 EA 2 800.00 1,600.00
2 EA 2 900.00 1,800.00
3 EA 2 300.00 600.00
4 EA 2 500.00 1,000.00
5 EA 12 500.00 6,000.00
6 LS 1 1,000.00 1,000.00
7 LS 1 3,000.00 3,000.00
8 EA 3 1,000.00 3,000.00
9 EA 0 1,800.00 0.00
10 LS 1 0.00 0.00
11 LS 1 0.00 0.00
12 LS 1 0.00 0.00
13 LS 1 0.00 0.00
1 LS 1 25,000.00 25,000.00
2 SF 1,160 20.00 23,200.00
3 LF 400 80.00 32,000.00
4 Ton 44 160.00 7,040.00
5 Ton 27 140.00 3,780.00
6 SF 800 0.40 320.00
7 Ton 25 130.00 3,250.00
8 EA 3 250.00 750.00
9 EA 2 1,000.00 2,000.00
10 LS 1 9,721.00 9,721.00
Artesia Blvd at Felton Ln SUB TOTAL: 130,000
15% CONTINGENCIES: 19,500
TOTAL: 149,500
CALL: $150,000
Remove existing pull box
Furnish and install new sign
Replace backplates with new backplates with 2" reflective tape Traffic Control
Remove existing striping
Roadway striping
Raised median reconstruction
Mobilization
NPDES, SWPPP Plan and Implementation
Furnish and install new pull box
Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign and post
DESCRIPTION PRICE ($)
Signal Equipment Mobilization
Traffic Control
Table 5. Order of Magnitude Cost Estimate - Artesia Blvd at Felton Ln Median Inspection and Construction Management 10%
Relocate Existing Sign and Pole.

Adjust existing Pull Box/ meter box//pull box cover to grade.

Construct 2-inch AC Pavement ARHM-CG-C (PG-64-16)
Cold Mill 2-feet wide of 2-inch existing AC Pavement
Construct 4-inch thick Crushed Misc Base (CMB)
Construct 6-inch thick Asphalt Pavement B (PG-64-10)
Construct 6 inch pcc curb per sppwc std. plan 120-2. A1-6 (150)
Remove and dispose existing median curb and concrete.

Clearing and Grubbing (includes removal of Signs, Shrubs, Landscape.)
Raised Median Reconstruction
Remove sign and post
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,000.00
2 LS 1 4,000.00 500.00
3 EA 1 800.00 800.00
4 EA 1 800.00 800.00
5 EA 9 300.00 2,700.00
6 EA 6 300.00 1,800.00
7 EA 9 500.00 4,500.00
Artesia Blvd at Slauson Ln SUB TOTAL: 12,000
15% CONTINGENCIES: 1,800
TOTAL: 13,800
CALL: $14,000
Table 6. Order of Magnitude Cost Estimate - Artesia Blvd at Slauson Ln PRICE ($)
Replace backplates with new backplates with 2" reflective tape Furnish and install new "No Left Turn" sign on mast-arm

DESCRIPTION
Furnish and install new "No U-turn" sign on mast-arm
Replace existing sign
Furnish and install new sign
Signal Equipment Mobilization
Traffic Control
No. UNIT QTY AMOUNT ($)
1 LS 1 1,500.00 1,000.00
2 LS 1 4,000.00 500.00
1 LS 1 1,500.00 600.00
2 LS 1 4,000.00 500.00
1 EA 1 800.00 800.00
2 EA 1 800.00 800.00
3 EA 8 300.00 2,400.00
4 EA 9 500.00 4,500.00
Artesia Blvd at Vail Ave SUB TOTAL: 11,000
15% CONTINGENCIES: 1,650
TOTAL: 12,650
CALL: $13,000
Table 7. Order of Magnitude Cost Estimate - Artesia Blvd at Vail Ave DESCRIPTION PRICE ($)
Furnish and install new "No Left Turn" sign on mast-arm Furnish and install new "No U-turn" sign on mast-arm
Furnish and install new sign
Replace backplates with new backplates with 2" reflective tape Signal Equipment Mobilization
Traffic Control
Signal Equipment Mobilization
Traffic Control
Artesia Blvd Preliminary Cost Estimate_July 11_2022.xlsx

← All documents from this meeting