South Bay Bicycle Master Plan
Implementation Update
CITY COUNCIL MEETING
SEPTEMBER 6, 2022
BACKGROUND AND HISTORY
The SBBMP adopted by City Council in 2011
38.6 miles of proposed routes
3.3 miles (8.5%) completed
Dedicated bike facility projects
Roadway resurfacing projects
COMPLETED AND CURRENT PROJECTS
Projects Implementing Bicycle Master
Plan Facilities
Bike Facility Miles Expected
Implementation
Pending Construction Projects
• Call for Projects - CMAQ Grant 11.1 2022
• Residential Rehab 0.5 2022
• Beryl St 0.3 2022
• Torrance Blvd 0.9 2023
• Striping FY22-23 9.7 2023
Subtotal 22.5 67%
Projects in Planning and Design
• Traffic Calming 0.7 2023
• Manhattan Beach Blvd 1 2023
• BCHD Measure M 0.2 2024
• Kingsdale Widening 0.5 2025
• MAT Grant 3.5 2025
Subtotal 5.9 82%
Total Active Projects 28.4
CFP PROJECT BICYCLE CORRIDORS
Challenging Corridors
Corridor Bike Facility
Miles
Issue
Inglewood Ave – Marine to Ripley 1.8 Insufficient ROW, excessive vehicle speeds for unbuffered CL2 Artesia Blvd – West limits to Hawthorne 2.3 Competing interest for parking, AACAP development recommendations
Marine Ave – Aviation to Inglewood 1.0 Portions in other jurisdictions, Insufficient ROW No. Catalina – Gertruda to PCH 0.2 No facility on PCH
Aviation Blvd. - Marine to Harper 1.7 Haven’t obtained buy in from all Beach Cities 182nd St. - Firmona to Hawthorne 0.4 Jurisdiction, ROW limitations Total 7.4 18%