Street by Street Status of South Bay Bicycle Master Plan Implementation ‐ September 2022 Street From To
ProposedFacilityType
Likely /
ActualType
Proposed
Miles*
Com‐
pleted
Anticipated
Construction
this FY
Currently
Funded and
Active
Future Project
Harbor Dr Herondo St Existing Bike Path Class 4 Class 4 0.8 0.8 Harbor Gateway
Flagler Ln ‐
Alley
City Bndry Diamond St Class 1 Class 1 /
Class 3
0.1 0.1 BCHD
Measure M
Prospect Ave North City Limits PCH Class 2 Class 33 3 CFP ‐ CMAQ Knob Hill Ave Esplanade PCH Class 2 Class 2 0.4 0.4 CFP ‐ CMAQ Torrance Blvd West End East City Limits Class 2 Class 2 / Class 3
0.9 0.7 0.2 Torrance
Blvd
Resurfacing
Inglewood Ave Marine Ave Ripley Ave Class 2 1.8 1.8
Artesia Blvd West City Limits Hawthorne Blvd Class 2 2.3 2.3 So. Catalina Ave Torrance Blvd Knob Hill Ave Class 2 Class 3
0.6 0.6 Striping
So. Catalina Ave Knob Hill Ave Palos Verdes Blvd Class 2 Class 2 / Class 3
11 CFP ‐ CMAQ
Juanita Ave ‐
Del Amo Blvd
Diamond St East City Limits Class 2 Class 2 0.3 0.3 Previous Striping
Marine Ave Aviation Blvd Inglewood Ave Class 21 1
Ripley Ave Lilienthal Ln Inglewood Ave Class 2 Class 2 0.3 0.3 MAT Grant for RBB
Beryl St Harbor Dr PCH Class 2 Class 2 0.4 0.4 CFP ‐ CMAQ Beryl St PCH Prospect Class 2 Class 2 0.5 0.5 Residential Rehab '21
Beryl St Prospect Ave Flagler Class 2 Class 2 0.3 0.3 Beryl St ('22)
Street by Street Status of South Bay Bicycle Master Plan Implementation ‐ September 2022 Street From To
ProposedFacilityType
Likely /
ActualType
Proposed
Miles*
Com‐
pleted
Anticipated
Construction
this FY
Currently
Funded and
Active
Future Project
Beryl St Flagler 190th St Class 2 Class 2 0.3 0.3 Beryl St ('16) No. Catalina
Ave
Beryl St Gertruda Class 2 Class 2 0.3 0.3 CFP ‐ CMAQ
No. Catalina
Ave
Gertruda PCH Class 2 0.2 0.2
Camino Real Prospect Ave West City Limits Class 2 Class 3 0.3 0.3 CFP ‐ CMAQ Avenue I Esplanade Catalina Ave Class 2 Class 3 0.1 0.1 CFP ‐ CMAQ ManhattanBeach Blvd
Aviation Blvd Inglewood Ave Class 2 Class 21 1 Man Bch
Blvd Resurf
Herondo St Harbor Dr PCH Class 2 Class 2 0.4 0.4 Harbor Gateway
Lilienthal Ln Ripley Ave Fisk Ln Class 2 Class 2 0.4 0.4 MAT Grant for RBB
Aviation Blvd Marine Ave Harper Ave Class 2 1.7 1.7
190th St Blossom Ln East City Limits Class 2 1.3 1.3 MAT Grant for RBB
Redondo BeachBlvd
Artesia Blvd Hawthorne Blvd Class 2 Class 3 0.2 0.2 Lawndale Project
Esplanade Knob Hill Ave Catalina Ave Class 2 Class 2 0.6 0.6 Esplanade Resurf
Ripley Ave Flagler Ln Lilienthal Ln Class 3 Class 3 0.9 0.9 MAT Grant for RBB
Emerald St Catalina Ave Prospect Ave Class 3 Class 3 0.7 0.7 Emerald Traffic
Calming
Yacht Club Way West end Harbor Dr Class 3 Class 3 0.1 0.1 Striping Portofino Way West end Harbor Dr Class 3 Class 3 0.2 0.2 Striping
Street by Street Status of South Bay Bicycle Master Plan Implementation ‐ September 2022 Street From To
ProposedFacilityType
Likely /
ActualType
Proposed
Miles*
Com‐
pleted
Anticipated
Construction
this FY
Currently
Funded and
Active
Future Project
Ford Ave ‐ Herrin St ‐ Ormond Ln
Artesia Blvd Aviation Blvd Class 3 Class 3 0.5 0.5 CFP ‐ CMAQ Camino Real Torrance Blvd Prospect Ave Class 3 Class 3 0.7 0.7 CFP ‐ CMAQ 182nd St Felton Ave Firmona Class 3 Class 3 0.2 0.2 Striping 182nd St Firmona Hawthorne Blvd Class e 0.4 0.4
Kingsdale Ave Artesia Blvd 182nd St Class 3 Class 2 0.5 0.5 Kingsdale Resurfacing
Anita St PCH Blossom Ln Class 3 Class 3 0.9 0.9 Striping Francisca Ave Herondo St Catalina Ave Class 3 Class 3 0.3 0.3 Striping Palos VerdesBlvd
South City Limits Irena Class 3 Class 3 0.4 0.4 CFP ‐ CMAQ Palos VerdesBlvd
Irena East City Limits Class 3 Class 2 0.5 0.5 CFP ‐ CMAQ Knob Hill Ave PCH Camino Real Class 3 Class 2 0.5 0.5 CFP ‐ CMAQ Juanita Ave PCH Diamond St Class 3 Class 3 0.5 0.5 CFP ‐ CMAQ Flagler Ln Anita St Beryl St Class 3 Class 3 0.2 0.2 Slurry Project
Beland Bl ‐ Barkley Ln White Court Class 3 Class 3 0.1 0.1 Striping Diamond St Prospect Ave east end of
Diamond
BFS Class 3 0.1 0.1 BCHD
Measure M
Flagler Ln Artesia Blvd Anita St BFS Class 31 1 Striping Ave C ‐ Juanita
Ave ‐ Ave D ‐
Esplanade Prospect Ave BFS Class 3 0.9 0.9 CFP ‐ CMAQ
Warfield Ave Aviation Blvd Vail Ave BFS Class 3 0.5 0.5 Striping Vanderbilt Ln Flagler Ln Inglewood Ave BFS Class 31 1 striping Rindge Ln MBB Grant Ave BFS Class 3 1.2 1.2 CFP ‐ CMAQ
Rindge Ln Grant Ave 190th St BFS Class 3 0.7 0.7 Striping
Street by Street Status of South Bay Bicycle Master Plan Implementation ‐ September 2022 Street From To
ProposedFacilityType
Likely /
ActualType
Proposed
Miles*
Com‐
pleted
Anticipated
Construction
this FY
Currently
Funded and
Active
Future Project
Ralston Ln ‐
Firmona Ave
Meyer Ln Lilienthal Ln BFS Class 3 0.3 0.3 MAT Grant
for RBB
Mathews Av Aviation Way Inglewood Ave BFS 1.1 1.1 Striping Voorhees Ave Aviation Blvd Inglewood Ave BFS Class 3 1.1 1.1 Striping Robinson St Aviation Blvd Inglewood Ave BFS Class 3 1.1 1.1 Striping Meyer Ln Ripley Ave 190th St BFS Class 3 0.3 0.3 MAT Grant for RBB
Helberta Ave ‐
El Redondo
Vincent St Torrance Blvd BFS Class 3 0.5 0.5 Striping
Helberta Ave Avenue D Prospect Class 3 0.4 0.4 CFP ‐ CMAQ Farrell Ave Aviation Blvd Rindge Ln BFS Class 3 0.3 0.3 Striping Totals 38.6 3.3 22.3 5.6 7.4