CITY OF REDONDO BEACH

DEPARTMENT OF PUBLIC WORKS
Residential Street Rehabilitation Project Cycle 2 Phase 3, Job No. 40190 CHANGE ORDER NO. 2
March 7, 2023
I. Description of Work Included in the Contract:

Asphalt and PCC removals; pavement construction; ADA ramp, curb and gutter, alley intersections, and cross-gutter reconstruction; utility adjustment; dry wells; and signing and striping per the Plans and Specifications on various residential streets within the City of Redondo Beach, California.

II. Changes Ordered
This change order provides for changes performed by the Contractor under this project. It covers construction response to City requested. The changes ordered were negotiated prices and agreed upon between the City and the Contractor. The following changes were directed, monitored, and documented over the course of the project:
• Item #1 – Grinding and paving 3 inches of AC,2 new sidewalk bulb-outs curb ramps, striping replacement in kind and adjust manholes and valve covers on the 200 block of Avenue I.

III. Reasons for the Changes
• Item #1 – City requests Resurfacing of Avenue I between South Catalina Ave and South Elena Ave, which is offsite work approximately 2.4 miles away from the nearest work area on the contract. The scope of work entails grinding and paving 3 inches of AC, 2 new sidewalk bulb-outs ramps, striping replacement in kind and adjust manholes and valves covers.

IV. Contract Bid Item Adjustments
• None
V. Contract Adjustment:

Work Authorized in Base Contract…………………...………………. $ 4,611,206.00 CCO #1 Fully Executed……………………………………………….…. $ 178,687.76 This Change Order not to exceed amount……............................... $ 358,306.00 Revised Contract Amount............................................................ $ 5,148,199.76 VI. Contract Time:

The above change and a schedule delay for the City to revise project curb ramp Plans increase the contract time by 15 Working Days.

VII. Compensation:

This change order constitutes full and complete payment for all costs associated with the above changes inclusive of consultant’s profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities. Total cost will be based on actual quantities used and contracted unit prices for grinding and paving, plus stand alone lump sum items including, but not limited to, striping, bulb outs, and manhole adjustments.

Sully - Miller Co.

By: Andres Acosta 02/06/23
Authorized Representative

CITY OF REDONDO BEACH
By:

Andrew Winje, PE City Engineer
Job No 40190, Change Order No. 2 Sully- March 7, 2023
Miller Page 2 of 2