CITY OF REDONDO BEACH RECEIVED BY:
PLANNING DIVISION AG
DATE RECEIVED:
APPLICATION FOR COASTAL DEVELOPMENT PERMIT
4/13/23
(or application for exemption or categorical exclusion) APPLICATION NO:
CDP-2023-02
PLEASE NOTE: Within 30 days of receipt of an application, the Planning Division will inform the applicant in writing if the application is incomplete, and what items must be submitted to complete the application. Processing of the application will not begin until it is complete, pursuant to Section 10-5.2210 of the Municipal Code.
Application is hereby made to the City of Redondo Beach, for a Coastal Development Permit, pursuant to Article 10 of Chapter 5, Title 10 of the Redondo Beach Municipal Code.
A APPLICANT INFORMATION
STREET ADDRESS OF PROPERTY:
233 Portofino Way - Sportfishing Pier
EXACT LEGAL DESCRIPTION OF THE PROPERTY: ZONING:
CC-3
LOT: BLOCK: TRACT:
RECORDED OWNER'S NAME: AUTHORIZED AGENT'S NAME:
City of Redondo Beach Moffatt & Nichol (Kimberly Garvey) MAILING ADDRESS: MAILING ADDRESS:
415 Diamond Street, 4225 E. Conant St. | Long Beach, CA 90808 Redondo Beach, CA 90277
TELEPHONE:
TELEPHONE: 310 318-0661 Office Direct 562-317-3527 | Office Main 562-590-6500 PROJECT DEVELOPER: PROJECT ARCHITECT/FIRM/PRINCIPAL:
MAILING ADDRESS: MAILING ADDRESS:
TELEPHONE: TELEPHONE: LICENSE NO.
TYPE OF APPLICATION (Consult with Planning Division staff) Exempt (Emergency Coastal Development Permit)
_x. Categorical Exclusion (PRC 30611)
Coastal Development Permit public hearing waiver
Coastal Development Permit public hearing required
AUGUST 2020
C PROJECT DESCRIPTION. (Provide a detailed description of the project.) Extension of emergency Coastal Development Permit.
The demolished of the Sportfishing Pier, including the pier deck, piles, buildings, utilities, and appurtenances is in process at the moment and requires a minimum of two more weeks worth of work The demolition plan includes: a) installation of structural bracing and repairs (jacketing) of the existing deteriorated piles in order for construction equipment (including a crane) to safely access the pier, b) abatement of the lead/asbestos in the existing buildings on the pier, c) demo/removal of the existing buildings, d) demo/removal of the deck, stringers, pile caps, utilities, and appurtenances, e) extraction of existing timber piles; if piles cannot be removed in their entirety, they will be cut off at or near the mudline, and f) removal of large fender piles via crane. The demolition duration is expected to be ~3 months.
D PROJECT INFORMATION: (Note: Please provide a detailed project description on a separate page.) Where questions do not apply to your project, indicate "NOT APPLICABLE" or N.A.
1. TYPE OF PROJECT
• New Sq. Ft.
Addition Sq. Ft.
Demolition _Approx. 9,600 Sq. Ft.
Change of use from _to
Grading Cu. Yds.
Fence Height _ Length
Paving Amount
Other
2. ADDITIONAL INFORMATION
Note: If yes to any of the items b through h, please explain on a separate sheet. a. Has any application for development on this site been submitted previously to the California Coastal Zone Conservation Commission or Coastal Commission? • YES ANO If yes, state previous Application Number:
b. Are any utility extensions necessary to serve the project? If yes, explain. • YES • NO c. Does the development involve diking, filling, dredging or placing structures in open coastal waters? If yes, explain and indicate whether the U.S. Army Corps of Engineers Permit has been applied for. • YES XNO
d. Will the development extend into or adjoin any beach, tidelands, submerged lands or public trust lands? X YES • NO
e. Is the development in or near:
• Sensitive habitat areas? • YES X NO
• 100 year floodplain? • YES & NO
• Park or recreation area? * YES • NO
f. Will the development harm existing lower-cost visitor and recreational facilities? X YES • NO Will the development provide public or private recreational opportunities? • YES X NO g. Does the site contain any:
• Historic resources? & YES •NO
• Archaeological Resources? • YES X NO
AUGUST 2020
h. Will the proposed development be visible from:
• Park, beach or recreation areas? X YES LINO
• Harbor area? X YES UNO
i. Is the project a "Priority Project" as defined by the City's NDES Permit pursuant to Section 5-7.103 of the Redondo Beach Municipal Code? • YES •NO
• If yes, are copies (2 or 25 copies, as applicable) of the Low Impact Development (LID) report attached? • YES X NO
j. Is the a project with "Planning priority project characteristics" as defined by the City's NPDES Permit pursuant to Section 5-7.103 of the Redondo Beach Municipal Code? • YES • NO • If yes, are copies (2 or 25 copies, as applicable) of the Low Impact Development (LID) report attached? •YES X NO
E SHOWINGS: Explain how the project is consistent with the Certified Local Coastal Program.
1. Is the project designed in full accordance with the development standards and other provisions of the Zoning Ordinance for the Coastal Zone? If not, explain.
The existing Sportfishing Pier, including the pier deck, piles, buildings, utilities, and appurtenances would be demolished. No replacement structures are proposed at this time.
2. If the proposed development is located between the sea and the first public road paralleling the sea, indicate how it is in conformity with the public access and public recreation policies of Chapter 3 of Division 20 of the California Public Resources Code.
Public access to the existing Sportfishing Pier is restricted because of the deteriorated condition. A replacement structure would be proposed as part of the Harbor and Pier Amenities Plan in the future that would provide access and recreational opportunities.
3. Will the project have an effect on public access to and along the shoreline, either directly or indirectly (e.g. removing parking used for access to the beach)? If yes, describe the effect.
The demolition will be completed using both a barge and landside crane and require a laydown and staging area at the foot of the pier in the Marina Parking Lot. Access to the walkway in front of the hand launch may also be limited during the construction period, which is expected to last eight to ten weeks AUGUST 2020
OWNER'S AFFIDAVIT
Project address: Sportfishing Pier, King Harbor (233 Portofino Way) Project description: Demoliton of pier and staging of equipment in the parking area.
Greg Kapovich
reuten it en is tamar riy under pany pear hat he forgong a mans and information presented herein are in all respects true and correct to the best of my (our) knowledge and belief.
Signature(s): _
Address: 415 Diamond Street
Redondo Beach, CA 90277
Phone No. (Res.)
(Bus.) 310 318-0631 x2246
Subscribed and sworn to (or affirmed) before me this _ 13_ day of _April 120_23_ by Antonio Gardea _ proved to me on the basis of
satisfactory
evidence to be the person(s) who appeared before me.
Mitoushe
FILING CLERK OR NOTARY PUBLIC
State of California )
County of Los Angeles ) sS Seal
AUGUST 2020