Administrative
Report
H.7., File # 23-6344 Meeting Date: 7/11/2023
To: MAYOR AND CITY COUNCIL
From: TED SEMAAN, PUBLIC WORKS DIRECTOR
TITLE
ACCEPT AS COMPLETE THE WORK OF RESOURCE ENVIRONMENTAL, INC. FOR LEAD AND
ASBESTOS ABATEMENT AS PART OF THE REDONDO BEACH TRANSIT CENTER PROJECT -, JOB NO. 20120, AND AUTHORIZE THE CITY ENGINEER TO FILE A NOTICE OF COMPLETION
FOR THE WORK WITH THE LOS ANGELES COUNTY RECORDER AND RELEASE THE FINAL RETENTION PAYMENT OF $7,000 TO RESOURCE ENVIRONMENTAL, INC., UPON EXPIRATION OF THE 35-DAY LIEN PERIOD AFTER SAID RECORDATION AND NO CLAIMS BEING FILED
UPON THE ABATEMENT PROJECT
EXECUTIVE SUMMARY
The Redondo Beach Transit Center - Job No. 20120, one of the largest public works projects in the City's history, required the abatement of hazardous materials on both the new and former transit center sites. Lead and asbestos materials were determined to be present during the design process and were identified for removal from structures destined to be demolished and removed as part of the awarded Transit Center Project. This work can only be performed by strictly licensed contractors and was contracted separately from the main project.
The City Council awarded Resource Environmental, Inc. a public works contract for $128,000 for the Redondo Beach Transit Center - Lead and Asbestos Abatement Project, Job No. 20120. During construction, staff issued one change order totaling $12,000, increasing the final contract amount to $140,000.
The abatement project is now complete and ready for City Council acceptance and authorization to release the final retention amount of $7,000 to the contractor upon expiration of the 35-day lien period and there being no claims filed.
BACKGROUND
During the preliminary engineering and design of the new Redondo Beach Transit Center, hazardous materials we discovered on several of the structures that were to be demolished in preparation for the new bus facility and the demolition of the previous center. Lead based paint was found to exist on certain concrete curbs and columns, and asbestos was found in the mastic used to adhere floor tiles and the roofing material for the shade structure. A hazardous material abatement Workplan was developed as part of the investigation process. The Workplan was approved by the appropriate authorities and used as a basis for the scope of work for the specialty contractor.
On April 7, 2020 the City Council authorized advertisement for competitive bids for the Abatement Project to remove lead and asbestos known to exist on the structures destined for removal. On May
H.7., File # 23-6344 Meeting Date: 7/11/2023
Project to remove lead and asbestos known to exist on the structures destined for removal. On May 20, 2020, the City received and publicly opened three bids for the Abatement of Lead and Asbestos for the Redondo Beach Transit Center Project, Job No. 20120. After staff reviewed the bids, Resource Environmental, Inc., was found to be the responsible bidder with the lowest responsive bid.
Staff recommended awarding a public works contract to Resource Environmental, Inc., in the amount of $128,000. On July 21, 2020, the City Council awarded Resource Environmental, Inc. a public works contract for $128,000 for the Redondo Beach Transit Center - Lead and Asbestos Abatement Project, Job No. 20120.
The Abatement Project work consisted of two phases, one for each site under construction for the Transit Center Project. The first phase included hazardous material abatement at the new Transit Center site. The second phase was for lead abatement at the former transit center site. This Abatement Project was coordinated with the work being performed by MS Construction, the general contractor. The Abatement Project was performed according to the Workplan approved by Caltrans (the NEPA reviewing agency), as dictated by the National Environmental Policy Act (NEPA) approval process. During construction, staff issued one change order totaling $12,000, increasing the final contract amount to $140,000. The work is now finished and staff recommends the City Council accept the work as complete and authorize release of the retention, assuming no claims are filed in the next thirty days.
COORDINATION
The abatement workplan development was coordinated by the Public Works Department and the Community Development Department working under NEPA Guidelines. Implementation of the contract was coordinated within the Public Works Department.
FISCAL IMPACT
Funding for the Transit Center Project comes from a variety of restricted transportation sources. The contract for the abatement work was funded using the Project's local Measure M Funds.
Funding Expenditures
Local Measure M Funds $ 140,000 Resource Env Agreement $ 140,000 Total $ 140,000 Total $ 140,000